1.5 No need to add the strong point structure No need to add the new platform for operation during Load
to arrange the pulling Padeye out if using the airbag
1.6 No need to add the new platform for operation during Load
out if using the airbag
2 Disadvantage
2.1 Removing 02 caissons of LOB, adding new Removing 02 caissons of LOB, adding new Fabricating new Cofferdam (L42m x B2.4m x H5m, Area Removing 02 caissons of LOB, adding new
structure IWO there to blank off (Area: 210 m2) structure IWO there to blank off (Area: 210 m2) 280m2) to join two parts underwater structure IWO there to blank off (Area: 210 m2)
2.2 Ballasting/Stability concern during Load out Overhang too much (50 m) Lacking of experience during joining two parts underwater Ballasting/Stability concern during Load out
due to C.L of FD to be offseted (Design & Installation Cofferdam, Welding & Paiting due to C.L of FD to be offseted
underwater (inside Cofferdam))
2.3 Ballasting/Stability concern during Float off Ballasting/Stability concern during Float off Ballasting/Stability concern during Float off
due to removed 02 caissons of LOB (lost due to removed 02 caissons of LOB (lost due to removed 02 caissons of LOB (lost buoyance)
buoyance) buoyance)
2.4 Need to rent the airbag for Load out or Need to rent the airbag for Load out or Crane lifting limiation during blocks erection and big
need to invest 180m new Launching rolller need to investigate the Launching rolller equipment installation
(our one is not enough)-03 lines x 96m (our one is not enough)
2.5 Need to add the strong point structure Basic design should be always ready to build the blocks by
to arrange the pulling Padeye sequence from AFT to Fwd (or from Fwd to AFT) to solve Crane
lifting limitation problem during blocks erection
2.6 Need to add the new platform for operation Big equipment should be always ready to install to follow the
during Load out if using the airbag blocks building sequence from AFT to Fwd (or from Fwd to
AFT) to solve Crane lifting limitation problem
2.7 All the Old Jetty to be locked during FD construction building
(5.5 months)
Note:
1- Airbag Launching : 25USD/ton Total Cost : 5600 tons x 25$ = 140,000$
2- Investment Cost for Launching roller: 1200USD/m Total Cost : 180 m x 1200$ = 216,000$
3- Launching roller available: 108m