A Theoretical Review of the Causes and Effects


of Construction Projects Cost and Schedule
Overruns
Mukuka M.J, Aigbavboa C.O., and Thwala W.D.

I. INTRODUCTION
AbstractThis study examines previous literature on
construction projects cost and schedule overruns, with the specific
aim of identifying the causes and effects of cost schedule overruns in
construction projects. This is because the concept of construction
C OST and schedule overruns can occur for a wide variety
of reasons on various types of projects which has led to
the debate on how to minimise these construction projects
projects cost and schedule overruns has attracted much attention in cost and schedule overruns [1]. However, Memon, Rahman,
recent years and that researchers and research bodies, be it corporate Asmi, and Azis, [2] states that in order to find measures of
or government that try to formulate remedies to projects cost and
minimising these overruns, the very first and most important
schedule overruns should begin with an understanding of the causes
of these overruns and their effects to the construction industry as a step is to identify and understand the factors responsible for
whole. The study is conducted with reference to existing theoretical the overruns. Hence, this paper examines previous literature
literature, published and unpublished research. The study is mainly on causes and effects of construction projects cost and
a literature review/survey on the causes and effects of construction schedule overruns.
project cost and schedule overruns. The primary findings emanating
from the study revealed that empirical studies have identified a II. CONSTRUCTION PROJECTS COST OVERRUNS
number of important factors which cause projects cost overruns, Cost overruns are very common in the construction
such as fluctuation of prices of material, cash flow and financial industry. Hardly few projects get completed within original
difficulties faced by the contractor, poor site management and costs [3]. Al-Najjar [4] defines cost overruns as the change in
supervision, lack of experience and schedule delay. The study
contract amount divided by the original contract award
further revealed that poor site management, delay in progress
payments, poor communication and financial difficulties by the amount. However, Zhu and Lin [5] states that cost overrun
contractor are among the identified causes of construction projects can be defined as excess of actual cost over budget. Cost
schedule overruns by previous scholars. Literature also revealed that overrun is also sometimes called cost escalation, cost increase
extension of project, additional cost, budget short fall, adversarial or budget overrun. Memon, Rahman and Abdul Azis [2]
relationship between participants of the project, delayed payments to outlines that cost is among the major considerations
contractors, poor quality workmanship and dissatisfaction by project throughout the project management life cycle and can be
owners and consequently by end users as the major effects of cost regarded as one of the most important parameters of a project
overruns. Furthermore, it was observed that time overrun, cost and the driving force of project success. Olawale and Sun [6]
overrun, arbitration, litigation, disputes and total abandonment of
states that despite the availability of various control
projects were the effects of construction projects schedule overruns.
The study explores the causes and effects of construction projects techniques and project control software many construction
cost and schedule overruns and presents a robust background on the projects still do not achieve their cost objectives. Hence,
theories of construction project cost and schedule overruns. despite its proven importance it is not uncommon to see a
construction project failing to achieve its objectives within the
KeywordsCost overruns, Schedule overruns, Construction specified cost [2]. Park and Papadopoulou [7] states that
Industry, Causes and effect of cost and schedule overruns. construction cost overruns mean negative publicity for the
design team and loss of client confidence. The repercussions
for contractors are similar as they see their profit margins
shrink.
Mulenga. Mukuka is an MTech students with the Department of
Construction Management and Quantity Surveying, University of Johannesburg, III. CONSTRUCTION PROJECTS SCHEDULE OVERRUNS
Johannesburg, 2028 South Africa (corresponding author to provide phone:+27
(0) 11 559 6398; fax:+27 (0) 11 559 6630; e-mail: sirjoze2002@gmail.com). Projects or construction works that are not delivered on
Clinton. Aigbavboa is a Lecture with the Department of Construction
Management and Quantity Surveying, University of Johannesburg,
time to the client are referred to as projects that have
Johannesburg, 2028 South Africa (corresponding author to provide phone:+27 undergone schedule overruns. Hence, Mohamad [8] Defines
(0) 11 559 6398 ; fax:+27 (0) 11 559 6630; e- schedule overruns as an act or event that extends the time to
mail:caigbavboa@uj.ac.za). complete or perform an act under the contract. Also, Assaf
Wellington. Thwala is a Professor with the Department of Construction
Management and Quantity Surveying, University of Johannesburg, and Al-Hejji [9], defined schedule overruns as the time
Johannesburg, 2028 South Africa (corresponding author to provide phone:+27 overrun either beyond completion date specified in a contract,
(0) 11 559 6048; fax:+27 (0) 11 559 6630; e-mail: didibhukut@uj.ac.za).

112
International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

or beyond the date that the parties agreed upon for delivery of frequent design changes and poor financial control on site.
a project. It is basically a project slipping over its planned These results were not in agreement with the results of
schedule and is considered as common problem in Memon el al [15] where poor design and delays in design,
construction projects worldwide. Assaf and Al-Hejji [9] unrealistic contract duration and requirements imposed, lack
further illustrates that, to the owner, schedule overruns means of experience, late delivery of materials and equipment,
loss of revenue through lack of production facilities and rent- relationship between management and labour, delay in
able space or a dependence on present facilities. In some preparation and approval of drawings, inadequate planning
cases, to the contractor, schedule overruns means higher and scheduling, poor site management and supervision,
overhead costs because of longer working periods, higher mistakes during construction and changes in material
material costs through inflation, and due to labour cost specification and type were identified as the top causes of cost
increases. Alkhathami [10] states that schedule overruns can overruns. Kasimu [16] identified five categories of causes of
be defined as extra time required to finish a given cost overruns which include: financial related factors, factors
construction project beyond its original planned duration, related to construction parties, factors related to construction
whether compensated for or not. items, environmental related factors and politics related
factors.
IV. CAUSES OF CONSTRUCTION PROJECTS COST OVERRUNS
V. CAUSES OF CONSTRUCTION PROJECTS SCHEDULE OVERRUNS
Cost overruns do not just occur naturally, there are a
number of factors during the construction process that when Causes of schedule overruns are factors that lead to
not managed properly can lead to cost overruns. Al-Najjar [4] construction projects not being finished according to the
identified a total of 42 factors that cause cost overruns and planned scheduled time at the inception of project. Ade-ojo
ranked the top ten causes as follows: Technical incompetence, and Babalola [17] states that there are 6 major causes that
poor organizational structure, and failures of the enterprise, would lead to schedule overruns, the identified causes were
lack of cost reports during construction stage, inadequate ranked as follows: design error, poor site condition, delay in
project preparation, planning and implementation, delays in payment, financial incapability of client, financial
issuing information to the contractor during construction incapability of contractor and non-availability of
stage, lack of coordination at design phase, change in the subcontractor and supplier. Further, Akinsiku and Akinsulire
scope of the project or in Government policies, Some [18] show that, financial or cash flow difficulties, financial
tendering manoeuvres by contractors, such as front- loading difficulties faced by contractors and public agencies, frequent
of rates, incomplete design at the time of tender, bad change order and design, failure to pay for completed works,
allocation of labour inside the site and delays in decisions shortages of resources, considerable additional work,
making by government were ranked the top ten causes of cost escalations of material prices, increases in the scope of work,
overruns. delay in design work and late delivery of materials are the top
Eshofonie [11] revealed a total of 40 causes of cost ten causes of schedule overruns on construction projects.
overruns with the top ten causes being the following: cost of However, Ali, Smith, Pitt and Choon [19] shows that
materials, incorrect planning, wrong method of estimation, labour Shortage, contractors financial difficulties,
contract management, fluctuation of prices of materials, construction mistakes and defective works, coordination
previous experience of contractor, Absence of construction problem, material shortage and poor Site management are the
cost data, Additional cost and Project financing. However, the major factors that contribute to schedule overruns con
study of Ameh, Soyingbe and Odusami [12] identified factors construction projects in Malaysia. Furthermore, Memon et al.
that cause of cost overruns, these factors were then [20] revealed that design and documentation issues, financial
categorised in 5 categories namely: environmental factors, resource management, project management and contract
construction factors, construction Item Factors such as administration, contractors site management, information and
frequent design changes, Cost estimating factors and communication technology, material and machinery resource,
financing factors. Baloyi and Bekker [13] revealed that labour (human) resource and external factors as the major
increase in material cost, inaccurate material estimates, factors affecting time performance on construction projects.
shortage of skilled labour, clients late contract award, project The study of Pourrostam and Ismail [21] shows the following
complexity, increase in labour cost, inaccurate quantity take- as the top ten causes of schedule overruns: poor site
off, difference between selected bid and the consultants management, delay in progress payments by client, change
estimate, change orders by client during construction and orders by client during construction, ineffective planning and
shortage of manpower. scheduling of project by contractor, financial difficulties by
Rahman, Memon and Abd. Karim [14] identified the contractor, slowness in decision making process by client,
following as the top ten causes of cost overruns in large delays in producing design documents, late in reviewing and
construction projects: fluctuation of prices of material, cash approving design documents by client, poor contract
flow and financial difficulties faced by the contractor, poor management by consultant and problems with subcontractors.
site management and supervision, lack of experience,
schedule delay, inadequate planning and scheduling,
incompetent subcontractors, mistakes and errors in design,

113
International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

VI. EFFECTS OF COST OVERRUNS years and that researchers and research bodies, be it corporate
Effects are the consequences that will be encountered when or government that try to formulate remedies to construction
cost overruns occur on a construction project. Nega [22] states projects cost and schedule overruns should begin with an
that cost overruns have obvious effects for the key understanding of the causes and their effects. The current
stakeholders in particular, and on the construction industry in methodology falls within the qualitative research
general. To the client, cost overrun implies added costs over methodology.
and above those initially agreed upon at the onset, resulting in IX. LESSONS LEARNT FROM LITERATURE REVIEW
less returns on investment. To the end user, the added costs
Literature reviewed showed that the major causes of cost
are passed on as higher rental or lease costs or prices. To the
overruns include: cost of materials, incorrect planning, wrong
professionals, cost overrun implies inability to deliver value
method of estimation, contract management, and fluctuation
for money and could well tarnish their reputations and result
of prices of materials [11]. Other causes identified through
in loss of confidence reposed in them by clients. To the
literature include, environmental factors, construction factors,
contractor, it implies loss of profit for non-completion, and
construction Item Factors such as frequent design changes,
defamation that could jeopardize his or her chances of
Cost estimating factors and financing factors [12].
winning further jobs, if at fault. To the industry as a whole,
Furthermore, literature showed that the major causes of
cost overruns could bring about project abandonment and a
schedule overruns include: design error, poor site condition,
drop in building activities, bad reputation, and inability to
delay in payment, financial incapability of client, financial
secure project finance or securing it at higher costs due to
incapability of contractor and non-availability of
added risks [22].
subcontractor and supplier [17]. Other causes of schedule
The study of Nega [22] further identified the following
overruns included: financial or cash flow difficulties,
as the major effects of cost overruns: delays during
financial difficulties faced by contractors and public agencies,
construction, supplementary agreement, additional cost,
frequent change order and design, failure to pay for
budget short fall, adversarial relationship between
completed works, shortages of resources, considerable
participants of the project, loss of reputation to the consultant,
additional work, escalations of material prices, increases in
the consultant will be viewed as incompetent by project
the scope of work, delay in design work and late delivery of
owners, high cost of supervision and contract administration
materials [18].
for consultants, delayed payments to contractors, the
Literature further identified the following as the major
contractor will suffer from budget short fall of the client and
effects of cost overruns, delays during construction,
poor quality workmanship. However, Eshofonie [11]
supplementary agreement, additional cost, budget short fall,
identifies four effects of cost overruns as follows: company or
adversarial relationship between participants of the project,
firm liability to insolvency and liability of the companies or
loss of reputation to the consultant, the consultant will be
firms to bad debt, under-utilization of man-power resources,
viewed as incompetent by project owners, high cost of
plants and equipment, increased project cost due to extension
supervision and contract administration for consultants,
of time: Longer project duration means that more resources
delayed payments to contractors, the contractor will suffer
will need to be allocated to the project, which then increases
from budget short fall of the client and poor quality
the project costs and project abandonment.
workmanship [22]. Furthermore, literature showed the major
VII. EFFECTS OF SCHEDULE OVERRUNS effects of schedule overruns to be time overrun, cost overrun,
Effects of schedule overruns are the consequences that will dispute, arbitration, litigation, and total abandonment of
occur when the causes of these schedule overruns are not projects [21].
identified and worked on effectively. The study of Pourrostam X. CONCLUSION
and Ismail [21] identifies and ranks the effects of construction
This article has examined literature relating to construction
delays as follows, time overrun, cost overrun, dispute,
project cost and schedule overruns. Literature review showed
arbitration, litigation, and total abandonment of projects.
that the causes of cost and schedule overruns range from
These findings are in general agreement with other studies as
those caused by poor construction management to those that
carried out by Aibinu and Jagboro [23] and Motaleb and
are caused by other external factors like poor weather
Kishk [24]. However, the study of Baki [25] brings in the
conditions. Further, literature revealed that there are
aspect of claims as one of the effects of delays in construction
corresponding negative effects of construction project cost
projects.
and schedule overruns that can eventually lead to total project
VIII. RESEARCH METHODOLOGY abandonment.
The research was conducted with reference to existing REFERENCES
theoretical literature, published and unpublished literatures. [1] Alinaitwe, H., Apolot, R. and Tindiwensi, D. 2013, Investigation into the
The study is mainly a literature survey/review and looks at the Causes of Delays and Cost Overruns in Uganda's Public Sector
literatures relating to construction project cost and schedule Construction Projects: Journal of Construction in Developing Countries,
18(2), 3347, 2013.
overruns. This is because the concept of projects cost and [2] Memon, A.H., Rahman, I.A., Asmi, A. and Azis, A., 2010, Factors
schedule overruns has attracted much attention in recent Affecting Construction Cost in Mara Large Construction Project:

114
International Conference on Emerging Trends in Computer and Image Processing (ICETCIP'2014) Dec. 15-16, 2014 Pattaya (Thailand)

Perspective of Project Management Consultant: International Journal of [25] Baki, M.A. 1999, Delay Claims Management in Construction-A Step-By-
Sustainable Construction Engineering & Technology: Vol 1, No 2, Step Approach: ProQuest Dissertations & Theses Full Text: pg. 36-38.
December 2010.
[3] Subramani, T., Sruthi, P. S. and Kavitha, M. 2014, Causes of Cost
Overrun In Construction: IOSR Journal of Engineering (IOSRJEN): ISSN
(e): 2250-3021, ISSN (p): 2278-8719: Vol. 04, Issue 06 (June. 2014),
||V3|| PP 01-07.
[4] Al-Najjar, J.M., 2002, Factors Influencing Time and Cost Overruns on
Construction Projects in the Gaza Strip: Masters Thesis: The Islamic
University of Gaza.
[5] Zhu, K. and Lin, L., 2004, A stage by stage factor control frame work
for cost estimation of construction projects, Owners Driving Innovation:
International Conference. http:/ flybjerg. Plan.aau.dk / JAPAASPUBLISH.
[6] Olawale, Y. A, and Sun M., 2010, Cost and time control of construction
projects: Inhibiting factors and mitigating measures in practice.
Construction Management and Economics, 28 (5), 509 526.
[7] Park, Y-III and Papadopoulou, T. C. 2012, Causes of cost overruns in
transport infrastructure projects in Asia; Their significance and relationship
with project size: Built Environment Project and Asset Management, Vol.
2 No. 2, 2012: pp. 195-216: Emerald Group Publishing Limited.
Available at www.emeraldinsight.com/2044-124X.htm.
[8] Mohamad, M.R.B. 2010, The factors and effect of delay in government
Construction project, Case study in kuantan: University Malaysia Pahang.
[9] Assaf, S.A. & Al-Hejji, S. 2006, Causes of delay in large construction
projects: International Journal of Project Management, 24 (2006): 349
357.
[10] Alkhathami, M.M. 2004, Examination of the correlation of critical success
and delay Factors in construction projects in the kingdom of Saudi Arabia:
Doctor of Philosophy Thesis: University of Pittsburgh.
[11] Eshofonie, F.P., 2008, Factors affecting cost of construction in Nigeria:
Masters in construction management thesis: University of Lagos akoka,
Lagos.
[12] Ameh, O.J., Soyingbe, A.A. and Odusami, K.T., 2010, Significant Factors
Causing Cost Overruns in Telecommunication Projects in Nigeria: Journal
of Construction in Developing Countries, Vol. 15(2), 4967, 2010.
[13] Baloyi, L. and Bekker, M., 2011, Causes of construction cost and time
overruns: The 2010 FIFA World Cup stadia in South Africa: Acta
Structilia 2011: 18(1).
[14] Rahman, I.A., Memon, A.H and Abd. Karim, A. T., 2013, Significant
Factors Causing Cost Overruns in Large Construction Projects in
Malaysia: Journal of Applied Sciences 13 (2): 286-293, 2013.
[15] Memon, A. H., Rahman, I. A. and Abdul Azis, A. A. 2011, Preliminary
Study on Causative Factors Leading to Construction Cost Overrun:
International Journal of Sustainable Construction Engineering &
Technology Vol 2, Issue 1, June 201.
[16] Kasimu, M. A., 2012, Significant factors that causes cost overruns in
building construction project in Nigeria. Interdisciplinary journal of
contemporary research in business: March 2012, VOL 3, NO 11.
[17] Ade-Ojo, C. O. and Babalola, A. A. 2013, Cost and Time performance of
construction projects under the due process reform in Nigeria. Research
Inventy: International Journal Of Engineering And Science: Vol.3, Issue 6
(Aug 2013), PP 01-06: Issn(e): 2278-4721, Issn(p):2319-6483,
Www.Researchinventy.Com.
[18] Akinsiku, O. E and Akinsulire, A. 2012, Stakeholders Perception of the
Causes and Effects of Construction Delays on Project Delivery. KICEM
Journal of Construction Engineering and Project Management: Online
ISSN 2233-9582.
[19] Ali, A. S. Smith, A. Pitt, M. and Choon, C. H. 2012, Contractors
perception of factors contributing to project delay: case studies of
commercial projects in klang valley, Malaysia.
[20] Memon, A.H., Rahman, I.A. and Azis A.A.A. 2012, Time and Cost
Performance in Construction Projects in Southern and Central Regions of
Peninsular Malaysia: International Journal of Advances in Applied
Sciences (IJAAS): Vol.1, No.1, March 2012, pp. 45-52.
[21] Pourrostam, T. & Ismail, A. 2011, Significant Factors Causing and Effects
of Delay in Iranian Construction Projects: Australian Journal of Basic and
Applied Sciences, 5(7): 450-456.
[22] Nega, F., 2008, Causes and effects of cost overrun on public building
construction projects in Ethiopia: Master of Science thesis: Addis Ababa
University.
[23] Aibinu, A.A. & Jagboro, G.O. 2012, The effects of construction delays on
project delivery in Nigerian construction industry: International Journal of
Project Management, 20 (2002): 593599.
[24] Motaleb, O. & Kishk, M. 2010, An investigation into causes and effects of
construction delays in UAE: Robert Gordon University.