Method of Estimation:
1. Long and short wall method or separate method
2. Centre line method
Material analysis for 100 cft (10” wall) Brick work – Ratio: 1:4
Size of Brick without mortar – 9.5 X 4.5 X 2.75 inch = 117.65 cubic inch = 0.068 cft
Size of Brick with mortar – 10 X 5 X 3 inch = 150 cubic inch = 0.087 cft
100
No of bricks for 100 cft works – = 1150 nos
0.087
Volume of mortar = 1150 X 0.019 = 21.85 cft
Wastage for frog mark, bats, closer etc about 15% and increase in volume of mortar about 33%. So multiply the
hardened volume by 1.5.
32.775 1
Cement - = 6.55 cft = 4.5 bags
5
32.775 4
Sand - = 26.22 cft
5
Material analysis for 100 sft (5” wall) Brick work – Ratio: 1:4
Size of Brick without mortar – 9.5 X 2.75 inch = 26.125 square inch = 0.18 sft
100
No of bricks for 100 sft works – = 500 nos
0.2
14.25 1
Cement - = 2.85 cft = 1.95 bags
5
14.25 4
Sand - = 11.4 cft
5
Ratio = 1:2:4
Sum of Ratio = 7
154 1
Cement - = 22 cft = 15 bags
7
154 2
Sand - = 44 cft
7
154 4
Chips = = 88 Cft
7
0.5 100
Volume of work = = 4.16 cft
12
Dry Volume = 4.16 X 1.5 = 6.25 cft
6.25 1
Cement - = 1.25 cft = 0.85 bags
5
6.25 4
Sand - = 5 cft
5