Você está na página 1de 7

SOIL CONDITIONING

Soil Conditioning
in EPB Tunnelling
Machines
Richard Lewis, YL
Associates Ltd, explains
in-depth the sometimes
overlooked yet vital issue of
soil conditioning in EPBMs Top: Foam testing in the and an area where cost savings can be
machine factory before made. However inadequate equipment and
shipping insufficient materials should not be a
means of saving a few pennies. This will
ONE OF THE MOST important activities in more malleable and able to be handled. often lead to blocked cutterheads, stuck
closed face EPB tunnelling, and one to This however resulted in difficulties with machines, slow progress and much more
which often too little attention is paid, is the handling and disposal of the material expenditure later. A stitch in time saved
the Soil Conditioning or Ground after it had left the TBM. Being wet and nine has never been a more appropriate
Conditioning. This is sometimes referred to sloppy made it difficult for conveying in the proverb.
as the GCS Ground Conditioning System. tunnel and on the surface, whilst bentonite So what are the purposes and benefits of
EPB tunnelling started originally in and chemicals made it unwelcome in Soil Conditioning and how is this achieved.
Japan in the 1970s as an extension of the disposal pits for environmental reasons.
simple blind shield, for use in soft clays And so the use of biodegradable foam, Purposes and benefits
and silts which would easily extrude later reinforced with strengthening a. When the ground is excavated and
through the machine. As they developed, polymers was developed. Again this was brought into the cutterhead chamber, its
not only did the benefits of this process pioneered in Japan, although one of the bulk density is naturally reduced as the
(as an alternative to the slurry shield first uses in Europe was on the Passante degree of consolidation is relaxed. This
which was developed earlier), become Ferroviario Milano in Italy, where Mitsubishi means that the increased spaces between
apparent but so did the difficulties of and Obayashi introduced it to the Italian the solid particles of the ground have to
extending the process into less benign contractor Torno for use on their EPB be filled with something. To prevent
ground conditions which did not flow or machine in about 1991. These days, it is water being drawn from the ground
extrude so easily. Initially the injection of considered an essential part of EPB ahead, these spaces are filled with the
water and then the use of a mud, tunnelling. conditioning agent be it fluid or foam.
consisting of bentonite, clay and/or Despite this it is too often treated with And so a degree of stability in the ground
polymers, was used to make the material little respect, as an unimportant ancillary, ahead of the TBM is maintained.

20 TUNNELLING JOURNAL
SOIL CONDITIONING

b.The conditioning agent also imparts a e. Whilst achieving these three main cutterhead. Figure 1 shows two types of
degree of improved consistency, making objectives of face stability, fluidity and rotary joint, though each manufacturer has
it flow more easily through the impermeability, various other benefits are his own design, and these are not the only
cutterhead, and thus preventing it derived from the soil conditioning. The ones.
becoming blocked and solid due to presence of foam and/or bentonite By the time the material has been
compaction and lack of fluidity. This is reduces the abrasivity of the spoil excavated and is already in the cutterhead,
particularly important with large resulting in less abrasive wear to the it may be too late to modify if it is too stiff.
diameter EPB machines (as has been cutterhead structure and to the cutters It must be conditioned before it gets to that
found out recently on more than one themselves. stage. Injection ports in the screw can be
project) because not only does the f. The fluidity of the material in the useful for reducing the impermeability of
material have to travel further through cutterhead enables the supporting the material if that has got out of hand,
the cutterhead to find the screw pressure applied from the thrust rams but again it is sometimes too late by then.
conveyor, the central area is large and through the TBM bulkhead to be applied However if the spoil in the screw is still too
with the slower movement of a slower evenly and more effectively to the stiff, care must be taken when injecting a
rotating cutterhead, the reduced mixing excavated face. conditioner through the casing, since this
action makes it more difficult to maintain g.The torque required to be applied by the will reduce the friction at the periphery and
the fluidity. This is why some cutterhead is reduced due to the may encourage the screw to rotate without
manufacturers have tried to use an increased fluidity and reduced internal conveying. It is better to inject at or close to
active centre cutter i.e. a smaller friction in the muck. The torque required the entrance of the screw so that it is well
separate cutterhead in the central area by the screw conveyor is similarly mixed in with the material across the full
which can rotate at a faster rate than the reduced. diameter of the screw.
peripheral section. However this is a h.There is a reduction in the tendency for The next aspect about the injections
complicated and expensive solution and granular material in the cutterhead to through the cutterhead is that every
the substantially increased costs are not segregate and form voids. injection port must have its own supply of
always justified. conditioning agent whether it is foam, or
c. When there is a substantial amount of How is all this achieved? The answer to a fluid such as bentonite or polymer (or
sticky clay in the ground there is a high this comes with the answers to three both). The reason for this is that if a single
risk of this clogging and hardening, further questions supply line is used and then divided
particularly in the central area. This is a Where do we inject the conditioning through a manifold to several injection
specific problem that has been addressed agent? ports, the fluid, be it foam or bentonite,
in specialist papers on the subject, such How much should we inject? will always take the path of least resistance
as that by Prof Marcus Thewes What should be injected? and flow through only one port.
see Ref. 1.
d.The conditioning
Figure 1: Two examples of a rotary coupling
agent is also
required to provide
some
impermeability to
the material. It is
essential that the
pressure inside the
chamber is the
same as the
surrounding
ground so that the
face can be
balanced and
supported. To
achieve this the
material in the
screw conveyor
must have
sufficient
impermeability to prevent water flowing Where to inject Subsequently the other ports will rapidly
straight through the screw conveyor as it The key is that the excavated material must get blocked with muck from the face. So
transports the muck and controls the be conditioned or modified as soon as it is each line must be independent and be kept
material flow. In very open gravels with excavated. Therefore the place to inject the flowing.
few fines this is difficult and will probably conditioning agent is at the face of the Finally there is the positioning of the
require the addition of fine material, e.g. cutterhead, immediately behind the cutting ports on the cutterhead. Often the
limestone dust with bentonite and tools that are doing the excavating. This positioning is determined by the space
polymers. Some people will know the means that the conditioning agent must be available after the cutters have been
rule of thumb that each pitch of the piped to the rotating cutterhead through a positioned. However it is important that
screw conveyor will withstand 0.2 bar of rotary coupling or rotary joint - situated at each injection port is expected to cover a
pressure differential. This is only true the centre of the cutterhead. Additional similar swept area of the face, so that
when there are sufficient fines in the injection lines to the bulkhead and to the roughly the same quantity is being injected
ground to make the material reasonably screw conveyor may also be fitted, but the through each port and a similar volume of
impermeable. crucial ones are those to the front of the excavated spoil is being conditioned by

TUNNELLING JOURNAL 21
www.normet.com

SOLUTIONS FOR TOUGH JOBS

HPC Products
Supplying Specialist Products to
Mining, Tunnelling and Industry

Alvenius Steel Pipe Systems ; Belloli Rockbolt Systems


CBE-APS Precast Concrete Moulds ; Cogemacoustic Tunnel Fans
Condat Lubricants, Greases and Oils ; LVC Knifegate Valves
Mat Hellas Ventilation Ducting
Metalliance Underground Vehicles
NFM Tunnel Boring Machines ; RBL-REI Conveyor Systems

Contact World Class Tunnel


Keith Prebble +44 (0) 1202 587750
www.hpcproducts.com Fire Protection
Hunter Personnel
Recruiting For Your Industry Promat are the worlds largest dedicated manufacturer of passive
re protection materials and global leaders in the Fire Protection
of Tunnels, providing re protection solutions to many of the
 Specialists in Tunnelling and Infrastructure worlds largest tunnel projects.
Recruitment over the past 30 years
Since the 1960s Promat materials have protected more than
 Supplying personnel of all nationalities for 190 tunnels using PROMATECT boards. More than 1.4 million m2 of
tunnel linings have been protected using our spray applied systems.
UK and International Projects
www.promat-tunnel.com
Contact
David Kellett +44 (0) 1202 298322
www.hunterpersonnel.com

22 TUNNELLING JOURNAL
SOIL CONDITIONING

each port. The exception to this is that it is solution, before having compressed air is usually necessary to use a bentonite,
sometimes advisable to have slightly more injected into it through a foam generator possibly with a filler material such as
conditioning agent being injected near the to create the foam. limestone dust or fine sand, together with
centre where there is an increased There are many proprietary suppliers of a polymer such as CMC (Carboxy Methyl
possibility of the material clogging and surfactant, such as Condat, Mapei, BASF, Cellulose ) a viscosity adjusting additive.
blocking the flow. Normet (TAM), Lamberti, etc. They vary In addition polymers are also added to
The number of injection ports on the not only in price but also in required assist in stabilising and strengthening foam
cutterhead is also a crucial decision and this dilution rates. So that in considering prices when it is used, or for the purpose of
is linked to how much injected agent is the required dilution must also be taken reducing clogging in heavy clays and to
required. This is dealt with separately later. into account. But a typical dilution rate assist in the action of the bentonite fillers.
may be 5%. In which case, for every litre The choice of polymer is a specialised
How much to inject of concentrated solution supplied to the subject and suppliers should be consulted
The answer to this, as well as to the next tunnel, 20 litres of foaming solution can about the benefits and applications of their
question, What to inject, can only be be mixed. particular polymer or product. Often the
determined ultimately by carrying out trials Using an FER of say 15, this 20 litres of stabilising polymer is already included
on each site with the preferred supplier of foam solution would create 300 litres of within the proprietary foaming agents.
the agent and samples of the ground to foam to be pumped into the cutterhead, Foams can be divided into three general
be excavated. However to initially design by the addition of 280 litres of types
the machine and the equipment some compressed air. However when calculating 1. High in stability and with anti-
assumptions have to be made and these the air flow required from the compressor segregation properties
then are subsequently refined by site trials. to create the required FER it must be 2. General purpose foams
To calculate the amount of foam that remembered that the air is compressible, 3. With high dispersant capability to break
might be required for a TBM, - and the face pressure must be allowed for clay bonds and reduce swelling.
The key parameters that must be known in computing the maximum FAD (Free Air Although there is no hard and fast rule for
or assumed are: Delivery) required. what to inject into each type of ground - the
a. The TBM Diameter and the design If an FIR of say 50% was being targeted, following table gives some very general
advance rate. Thus the rate that the this would be sufficient for 600 litres or guide lines, and a starting point for site trials.
muck is excavated will determine the 0.5 Cu mtrs of excavated spoil. This has been based on information and
quantity of foam required. So it can be seen that the volume of guidelines provided from various sources.
b.The FIR and FER. That is FIR - Foam foam, surfactant, water and air must be However it is no substitute for testing on
Injection Ratio and FER Foam calculated for each individual project and site using the ground expected and the
Expansion Ratio. geological situation considering the local water, whose pH and chemistry may
various condition and criteria that might well alter the performance of any particular
The FIR is the quantity of foam injected as be expected. chemical.
a proportion of the insitu ground
excavated.
Thus Foam volume flow = FIR(%) x insitu Ground FIR Range Type of Foam Possible Additional
volume rate of excavation. Gravels 40-80 Type 1 Bentonite, CMC, filler material,
The FIR may vary depending on the Sandy Gravels 30-70 Type 1 or 2 Polymer to control cohesiveness
ground being excavated between 10%
Sands 20-40 Type 1 or 2 Polymer to control cohesiveness and consistency
and 80%, but is generally between 30%
Silty sand 20-40 Type 2 Polymer to control consistency
and 60%
The FER defines the quality of the foam Silts 20-40 Type 2 or 3 Polymer to control consistency
being injected and represents the Silty clays 20-60 Type 2 or 3 Anti-clogging polymers
proportion of air to liquid in the foam. Clay 30 -80 Type 3 Anti-clogging polymers
Thus Foam volume flow = FER x Volume of
the liquid foaming solution.
It is expressed as a ratio and may vary What to inject Typical Equipment and Circuits
between 5 and 30. The higher the FER This is the crucial question and as always Although there are various detail
value, the drier is the foam created. One there is no fixed answer. The type of injected differences in the foam and bentonite
of the advantages of foam over a pure material must suit the ground conditions injection circuits between different TBMs,
liquid such as bentonite, is that the and trials and testing on site in each case is there are two basic alternatives for the
entrained air in the foam fills the voids always the best and correct way to proceed. foam circuit (Note that in these typical
and the bubbles of air provide lubricity to A foam is preferred in most cases but circuits only two seperate supply lines are
the muck, making it flow more easily. But one of the weaknesses of foam is that it is shown for clarity, but there would be as
after the muck has been removed from less efficient at creating impermeability. many as required for the size of machine.)
the face the foam degenerates and the air Although the permeability of the excavated One variation has a separate pump on
escapes into the atmosphere leaving a spoil in the chamber will be reduced as a each foam line, each pump being supplied
much drier material which is easier to result of the compressed air in the foam from a common supply of foam solution.
handle and dispose. filling the voids in the muck in the chamber, The circuit (with only two lines shown)
To create the foam solution a the lack of a fine filler material will mean would be as shown in Circuit 1 (p14).
concentrated foaming agent, more that very open ground with high Figure 2 shows a typical example of the
accurately called a surfactant (or permeability will not be made sufficiently use of separate pumps which can be seen
occasionally a tenside) and sometimes impermeable by foam alone. mounted on each supply line. In this
loosely referred to just as soap, is For this reason in very open gravel or example the foam generators with airflow
supplied to the tunnel where it is first when excavating through rock where the control valves, are mounted in the body of
diluted with water to create the foam fines created are expected to be very low, it the TBM and cannot be seen here on the

TUNNELLING JOURNAL 23
SOIL CONDITIONING

possible, to minimise any degeneration of


Circuit 1: With supply pumps on each individual supply line
the foam as it is piped into the cutterhead.
Foam concentrate tank
Controls
At the control panel there are usually either
TBM two or three modes of operation. Most
Bentonite Dosing pump
Water supply panels will have a manual control where all
Polymer Air
the pumps and valves are individually
Flow control
controlled. This is used for setting up,
testing and maintenance purposes.
Supply pumps In operation automatic or semi-automatic
Rotary Foam
coupling generator Polymer tank mode would normally be chosen. The
Supply pumps percent concentration of the surfactant is
selected, and this controls the dosing
Flow control Dosing pump pump. The operator can then select an FER
Water supply
Polymer Air and a fixed flow of foam for each injection
Bentonite line, and the system will control the
solution flow and air flow dependent on
the FER figure that has been selected.
Circuit 2: With a single supply pump and flow control valves on each supply line In semi-automatic mode this would give
a constant flow of foam independent from
Water the advance rate through each injection
supply Foam
TBM concentrate line.
tank
Bentonite Dosing pump In fully automatic mode the flow of foam
Polymer Air solution will be adjusted to the required FIR
Dosing/ rate dependent on the advance rate of the
supply pump TBM.
Flow
The control panels should display and
Rotary Foam control record both instantaneous flow rates and
coupling generator valves
the total amount of conditioning agent
injected, whether foam or other materials.
Dosing pump
Polymer tank Because of the importance of this process,
Polymer Air
the data should be included in the
Bentonite datalogging system incorporated on the
TBM for later analysis and review.

No of Injection ports
back up. pumps used are positive displacement One crucial aspect not discussed so far is
The second variation has a single supply pumps, normally screw type progressive the number of injection ports on the
pump, but with flow control valves on each cavity pumps, so that speed variation can cutterhead. Once again there is no hard
line so that each flow can be individually carefully control the flow of liquid. The and fast rule and consideration must be
controlled, as indicated in Circuit 2, (again tanks and pumps for the surfactant given to the type of ground being
only two lines shown). solution can be positioned on the backup excavated and the advance rate of the
The photo in Figure 3 clearly shows the some way back from the TBM, but the machine.
individual foam solution lines (purple) actual foam generators, where the air is One consideration is the passage of foam
passing through separate flow control injected into the solution and the foam is to the TBM through the pipework and the
valves and flow meters and each having a created, should be positioned as close to passages in the rotary coupling. From the
controlled air supply (yellow hoses) the point of injection on the TBM as Diameter, FIR and Advance rate, the total
supplying air before passing through the
separate foam generators and then forward
to the TBM. Figure 2: Foam Supply system with individual pumps (Type A)
Having fewer pumps, this system is less
expensive, whilst the first system with
individual pumps does provide for slightly
better control of the individual supply lines.
Flowmeters and control valves (not
shown on the circuit diagrams, but visible
in the photographs) are provided on the air,
water and foam solution lines so that the
mixing and control of the foam and
additive injection can be monitored and
controlled from a central control panel.
In both variations the surfactant
concentrate is mixed with a water supply
using a dosing pump so that the dilution
rate can be controlled, but the same
solution is provided for all supply lines. The

24 TUNNELLING JOURNAL
SOIL CONDITIONING

amount of foam required is calculated. spoil is removed from the cutterhead


small quantities of fines are expected, this
Each pipe to the machine is usually about would be the preferred type of chamber to enable the intervention, the face
1 i.e. 37mm and the recommended must be supported by compressed air. The
conditioning. Again progressive cavity
max velocity for the foam in the pipe is bentonite used in the previous conditioning,
pumps are provided, with variable speed
2.5m/sec. Thus the number of pipes to carry will form a cake or impregnate the ground
controls to ensure the correct quantity of
all the foam can be calculated. slightly, and this will inhibit the loss of
injection from bentonite storage tanks
The other criteria to consider is the swept housed on the backup gantries. compressed air during the intervention
area to be covered by each port. Approx 5 resulting in a safer situation.
When the TBM is expected to be stopped
8 sq m of swept face area per injection port Bentonite is also used in the AFS
for an extended period, bentonite should
is a reasonable figure, but this may be Auxiliary Face Support system. This is a
be used in preference to foam for a short
reduced near the central area. It should also provision to inject a quantity of bentonite
period before the stoppage. This is because
be consistent with the flow of foam from a storage tank on the backup gantries
the foam entrained in a static cutterhead
available through each injection port being into the cutterhead chamber if the face
will diffuse after a few hours and its
sufficient to provide the correct FIR for that pressure falls below a preset value, in order
effectiveness will disappear. Moreover the
area of face at the designed advance rate. to ensure face support. This injection is
air will probably rise to the crown and
One point of detail about the injection pressure controlled and will maintain the
diffuse into the surrounding ground. So the
ports on the cutterhead is that when not in face pressure at the desired value using a
spoil contained in a TBM which is to be
use they can tend to get blocked. For this pressure regulator.
stationary for any length of time is
reason some protection in the form of an preferably conditioned with a This is an emergency safety feature only
open sided steel cover, or a rubber non bentonite/polymer fluid. and is not intended to be used during the
return flap should be used to protect them. tunnelling process. This is because:
The facility to use bentonite as the
Various designs are available specifically for a. the volume of bentonite stored on the
conditioning agent is also required before an
this task. backup would be too small for this and
intervention for cutter changes. When the
b.If the face pressure is
maintained by the AFS
Figure 3: Foam Supply system using flow control valves from a single pump (Type B) pressure regulators
during tunnelling
there is no protection
against over excavation.
Under normal
operating situation
the face pressure is
maintained by the
speed of the screw
conveyor limiting the
volume of muck
removed. If face
pressure is maintained
by the AFS, this
control is lost and
there is high risk of
over-excavation.

Testing
It is important that both
the equipment and the
foam mix itself used in a
Soil Conditioning System
is tested prior to the TBM
being put into use. During
factory assembly the foam
circuits should be fully
tested to ensure correct
Bentonite It is important that functioning of the system.
EPB machines should ideally include a
facility for the injection of bentonite into both the equipment This is usually achieved by
first firing up each line
the cutterhead chamber. Normally this is
not provided on every injection line and in and the foam mix individually, and then
through them all together,
some machine separate injection ports are
provided. The details of how many
itself used in a Soil whilst the head is turning
(See Figure 4). Although
bentonite injection ports are provided will
vary according to the TBM manufacturers
Conditioning this make a bit of a mess
in the factory it is well
design and with the anticipated geology.
Injection of bentonite, with or without
System is tested worth doing as the
operation of plc and
polymer, as a ground conditioning agent
could be through the same ports as the
prior to the TBM controls can also be
checked.
foam and when very coarse ground with being put into use. But this is only intended

TUNNELLING JOURNAL 25
SOIL CONDITIONING

Figure 4: Foam testing in the factory

Figure 5: Typical good quality foam Conditioning of the


excavated spoil is an
essential component of
EPB tunnelling, and
although foam is the
agent used in the majority
of cases now, it is not the
only conditioning agent
to be considered.
to test the equipment. The actual foam the majority of cases now, it is not the versatility in the controls and equipment is
mix must be formulated and tested on site only conditioning agent to be considered. important to be able to deal with the
in conjunction with the chosen supplier to It should also be remembered that the use unexpected. The same rule applies with
ensure that a good strong foam can be of too much foam can also cause soil conditioning as with all other aspects
generated. Figure 5 shows what a good problems in the surrounding ground, so of tunnel construction Always expect
foam should look like this was generated having a good control system, and having the unexpected.
in a laboratory trial.
REFERENCES
Conclusions.
Conditioning of the excavated spoil is an Ref 1. Clogging of TBM drives in clay identification and mitigation of risks. - M. Thewes,
essential component of EPB tunnelling, (STUVA e.V., Cologne, Germany) and W. Burger, (Herrenknecht AG, Schwanau, Germany)
and although foam is the agent used in

26 TUNNELLING JOURNAL

Você também pode gostar