Escolar Documentos
Profissional Documentos
Cultura Documentos
by
ABSTRACT
This paper presents evidence from actual field tests performed in the
Middle East that the simultaneous measurements of pressure, rate,
density and temperature performed downhole by the Production Logging
Tool (PLT)*, are not only needed to reduce testing time by
incorporating the measured afterflow into the analysis, but also needed
to do the proper interpretation of test data. The paper presents
several interesting test examples, that would have been misinterpreted
completely if the downhole flow monitoring was not performed during
these tests. The theory for using these simultaneous PLT* measurements
is reviewed briefly in connection with this part of the paper.
The paper also shows a new use of the simultaneous PLT measurement of
pressure, rate and temperature to derive deliverability and turbulence
parameters of gas wells, without performing one of the conventional
deliverability multi-rate testing methods. This new approach uses the
PLT measured afterflow following the closing of the well at surface as a
variable rate schedule, from which deliverability and turbulence
parameters could be calculated. Results obtained from this approach
are compared to those obtained from conventional isochronal gas well
testing on several Middle East gas wells. The clear advantage of the
method is reducing gas well testing time, however, it is applicable
only for dry gas reservoirs.
The production logging and testing data given in the paper should be
very useful to extend the afterflow analysis to gas wells. Although the
examples given in this paper are from the Middle East, it is believed
that the new ideas presented are also applicable elsewhere.
* Mark of Schlumberger
-1-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
INTRODUCTION
It has been noticed from many actual field tests that the analysis of only
pressure-time data gathered during conventional well testing may lead to
erroneous results; due to the absence of the down-hole flow performance
picture during these tests. This absence normally leads to overlooking
serious violations of the basic assumptions inherent to the analysis models
and hence to test data misinterpretation.
A well test may also be performed with the Production Logging Tool
(PLT), which provides simultaneous down-hole measurements of pressure,
flow rate, temperature and density.
Al. BACKGROL~D
When a well is closed-in at surface for a pressure build-up (PBU), the sand
face flow rate does not go to zero immediately, the formation continues to
produce for sometime, and the additional production is accommodated by the
compression of the well-bore fluids. This phenomenon is called afterflow
or well-bore storage effect. Other types of afterflow behaviour are also
known.
-2-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
Rules to estimate the start of the correct straight line have been
developed, such as the famous 1$ log cycle rule.
Type-curve matching could also be used for the interpretation of test data.
This approach suffers from the non-uniqueness problem ; where the same set
of data could be matched to several models giving widely different
reservoir and well parameters.
The application of this technique to perform a PBU test calls for the PLT
to be positioned above the top perforations during the last part of the
drawdown and through to the end of the shut-in period. Pressure, spinner
(rate), temperature and gradiomanometer (density) are recorded
simultaneously versus time. The collected data may be analyzed in real
time to make the full use of testing a well this way. Figure-1 shows how
the PLT is positioned in the well during a test.
-3-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
(1)
Permeability andskin factor are calculated from the slope and intercept of
this line as in the conventional interpretation. Integral (1) is normally
approximated ly~a summation term as given by references 3 and 8.
For the purpose of this paper let us call the pressure and time functions
defined abovezlp(q,t) and F(q,t) respectively. We will also call the
resulting ~lot Incorporating the Measured ~fterflow (PIMA).
Figures 2 and 3 show the analysis plots for 2 PBU tests from the Middle
East, where downhole flow monitoring took place during the testing.
The measured afterflow in Well A lasted for about 6 minutes. MDH line may
be defined after one hour of shut-in time, while the line obtained from the
afterflow analysis (PIMA) is reached after only one minute. In Well-B,
afterflow lasted for two minutes, and the advantages of incorporating
afterflow in the PBU analysis over the conventional MDH approach are also
evident.
Very early time data points in Figures 2 and 3 are not on the defined PIMA
line. This may be reflecting a heterogeneous reservoir nature.
-4-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
B
B1. EXAMPLE C
Well-C was producing at a down-hole rate of 10175 RBPD, when it was closed
in for a PBU. MDH plot for the collected pressure/time data is shown on
Figure -4. This test was performed using the PLT, and the spinner
performance during the build-up portion of the test is given on Figure -5.
In fact, the perforated interval of this well never stopped production ;
the rate declined from 8.93 rps (corresponding to 10,175 RBPD) to 1.1 rps
(corresponding to 1250 RBPD) in 6 minutes and continued at the later value
for the rest of the build-up which lasted for approximately one hour. This
continued production is thought to be a crossflow to some upper formation
through a casing leak a few thousand feet above the perforated zone.
B2. EXAMPLE D
Well-D is another oil producer from the Middle East. The well was flowing
at a downhole rate of 8900 RBPD prior to its shut-in for a PBU. Figure -7
shows the MDH plot for this test. A line could be fitted through the last
portion of the data giving permeability, skin and reservoir pressure.
-5-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
Cl. BACKGROUND
The purpose of gas well deliverability tests is to predict the flow rate
decline with reservoir depletion. Some kind of a multi-rate test is
normally performed to calculate the deliverability of a gas well ; the
isochronal or modified isochronal tests are typical ones.
This new approach requires that the well is produced at a relatively high
rate for a period of time long enough to reach stabilization (this
corresponds to the extended flow period in an isochronal test). The well
is then shut in for build up. The flow rate prior to shut-in is monitored
at surface, and the PLT is used throughout the test to monitor downhole
pressure, spinner (rate), temperature and density.
-6-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 19S4
B
Figure -9 shows how the points are chosen. When the afterflow stops, ie.
~ws i . 0, q will be equal to q while P% keeps increasing as the well
pressure build% up until we eventually reach the stabilized point. In
practice the stabilized point is taken as the last point in the drawdown
preceding closing the well for build-up.
The rate ~si in standard cubic feet per day is calculated using spinner,
temperature and pressure readings at each point, with incorporating surface
measurement of the rate qo. A conversion factor C is calculated such that:
go Bgo
c= (Smv)o
(3)
where Bg is defined as :
c (smv)w,~
qw(li= ~
(5)
gwai
10
Alternatively the rate at standard conditions could be obtained
qwsi
using spinner, friction corrected gradionometer reading (density) along
with the rate q. and standard conditions gas density.
in this case :
qO(splN)w~iPWOi
!lwei= (0)
WWO(PO)
C3. EXAMPLE E
The new approach has been applied to several actual gas well tests from the
Middle East. The results have been compared to those obtained from modified
isochronal tests. The following example demonstrates the good agreement
obtained.
Figure -10 shows a modified isochronal test performed for well-E. The
measured afterflow associated with the last build up in figure -10 is shown
on figure -11. The well was flowed at 11.2, 19.95, 28.9 MMCFpD for 4
hourseach with each 2 rates seperated by a build up for 4 hours. An
extended flow period of 13.32 hours at a rate of 32.2 MMCFPD was performed
following PBU-3 and finally the well was shut in for build up for about 13
hours. The afterflow recorded at the beginning of the last PBU lasted for
about 10 minutes as could be seen on figure -11.
-7-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
Table 2 summarizes the modified isochronal test data used to establish the
conventional deliverability line shown on figure -12. Table 3 shows the
data perinent to the deliverability calculations from afterflow data.
Rates shown in this table are calculated using equation (5).
C4 . APPROACH VALIDITY
Several gas well tests have confirmed the validity of this approach. These
tests were performed in straight holes. Condensate production was
typically less than 10 BBLS/MMCF and afterflow lasted for about 10 minutes.
The new approach did not give satisfactory results in cases where the
spinner performance was far from perfect; such as in deviated holes
especially for wells characterized with condensate production of more than
20 BBLS/MMCF and short duration after flow of only 1-2 minutes or less.
More tests are being used to compare the conventional method to this new
approach. A gas well model is also being used to study the limitations and
opitimize the application. Findings from this simulation work along with
its application to other fi d examples will be the the subject of a
f!
forthcoming SPE Presentation.
-8-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
CONCLUSIONS B
ACKNOWLEDGEMENTS
The authors thank the operating companies of the Middle East who kindly
released the data presented in this paper. They also would like to thank
Schlumberger Middle East for permission to pu-blish the paper. Special
thanks are also due to J. P. Guerle who supervised the data acquisition of
most of the data presented in the paper.
NOMENCLATURE
-9-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
z Compressibility factor
T Temperature
P Pressure psia
gas density
REFERENCES
2. Matthews, C.S., and Russell, D.G. : Pressure Build-Up and Flow Tests
in Wells, SPE of AIME Monograph Volume 1, 1967.
6. Miller, C.C., Dyes, A.B., and Hutchinson, C.A., Jr.: The Estimation of
Permeability and Reservoir Pressure from Bottom-Hole Pressure Build-Up
Characteristics, Trans., AIME (1950) 189, 91-104. Also Reprint
Series, No. 9 - Pressure Analysis Methods, SPE of AIME, Dallas (1967)
11-24.
-1o-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
11. Abed, A.F., E1-Hadidi, S., and Awad, M.A. : short Duration Gas well
Deliverability Testing Using Simultaneous Downhole Flow and Pressure
Measurements , paper presented for the 59th SPE Annual Fall Meeting,
Houston, Texas, September 16-19, 1984.
. .
I PLT
PRESSURE,RATE,
TEMPERAUEcDENSITY
ARERECORDED
0/
SMJLTANEOUSLY
PERFORATIONS
-11-
TABLE 1 TABLE 3
tabilixed point
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
o
0
H
FTERFLOW
v
o
INCORPORATING MEASURED
AFTERFLOW
o MDH
1
:3 -2 -1 0 1
F(q, t)
1 I , , 1 , r, m , I I , ,, , , I I , d
o 001 0.01 0.1
At ( HOURS )
F(q, t)
-13-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10.13, 1984
3150
3100
P
2 3050
Y
E
3
kz 3000
2950
10
8
+
+
+
+
+
6 +
+
+
+
*)
4 *+
+
B
*
%
2 ++++
+e
+*++++*++++++ +
++
0 I r I IrTll( I I I ,r141,
o.io
1 0.01 1 10
bt t ;;Rs )
- 14 -
300 I I I 1 1 1 I 10
. 0.001
. 0.01
---- 0-1 1 10
At ( HOURS )
1
270 9
240 I PIMA 8
.-
: 210 7
n 1 \
1
6
u
5
1 an
UI
I
a
o
1204 VI ii!
m
z
-1
$
n
an 90 ii
-3 -1
x
>
z
z
c
60 -2 >
r
m
/
30 . -1
.
0 I I I n o
I 1 I
-3 -2 -1 0 1
F(q, t)
Figure 6 : Wel 1 - C PBU Analysis Incorporating Measured Down-hole Flow Rate Data
TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
2200-
2000-
n
g g
m 8
a.
w 1800- :
u :
a 8
3
co 8
UY
w 1600- 2
K 0
0
0
0
Ooo
1400-
80
00000
o 0 000 Ooooomoooooooooooo
m I 1 11111
1200 1 11911 1 1 I I 18ael v 1 # a #,811 I 1 n 1 # 1Iv
0.001 0.01 0.1 10 100
At( HOURS )
o 100 200 0 s
:
:
:
: 10800
,
,
1
:
I
:
y Dowhl
,
+ - UP I
t
, [
I
:
1:;
:
:,
,
1 ~ J
PERFCRATION:
i
-16-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
STABILIZED
w
a
= Pwsi ,----------------- - ----
co
u)
Lu
a
a Pwf ~ . .
9
9 ,
8 *
I *
a :
o .
TfME
qo
**
w
1- :
I8
2
~ qw~l -- --------------+ ---;
~ ,
u. *: I
1
*9 B
# *
# [
a *
to tl
TIME
32.2 MMCFPD
13.92 HOURS
28.9
4
19.96
4
11.2
PERFORATE
AC IDIZE-CLEAN 4
-17-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
15 +
lo-
1 +
+
+
+
+
+
+
+
+
+
5-
0
0.001 0.01 0.1 10 100
At ( HOURS)
Figure 11 : Well - E MeasuredAfterflowat the Beginningof PBU 4
o 20 40
q, MMCFPD
-18-
SPWLA TWENTY-FIFTH ANNUAL LOGGING SYMPOSIUM, JUNE 10-13, 1984
AWAD TERGIMAN
Jean Tergiman is the Marketing manager with Schlumberger Middle East in Abu
Dhabi. Before joining Schlumberger in December 1972, Mr. Tergiman worked
in the Centre d'etudes nucleaires de Grenoble. Mr. Tergiman graduated
from the University of Grenoble with a degree in Electronics and performed
Business Administration Studies for one year. He is a member of SPWLA and
SPE.
- 19 -