Main Framing Coefficient(GCp) for Transverse Direction (MBMA 1996 , Table 5.4(a) , Page I-5-7)
Roof Angel Load Case End Zone Coefficient Interior Zone Coefficient
1E 2E 3E 4E 1 2
Enclosed 010 I 0.5 -1.4 -0.8 -0.7 0.25 -1
Building II 0.9 -1 -0.4 -0.3 0.65 -0.6
Main Framing Coefficient(GCp) for Longitudinal Direction (MBMA 1996 , Table 5.4(b) , Page I-5-7)
Building ty Load case End zone coefficient Interior Zone Coefficient
1E & 4E 2E 3E 5E 6E 1&4 2
Enclosed I -0.7 -1.4 -0.8 0.5 -0.7 -0.7 -1
II -0.3 -1 -0.4 0.9 -0.3 -0.3 -0.6
Load on Purlin
Purlin spacing= 1.5239 m
Bay spacing= 6 m
Bay spacing/3= 2 m
Effective purlin spacing= 2 m
Eff. Wind load area, A 12 m2 129.1008 ft2
4% of SD= 1.599816 ft
3 ft
From here, Z= 3 ft
one Coefficient
3 4
-0.65 -0.55
-0.25 -0.15
Load on Purlin
Purlin spacing= 1.5239 m
Bay spacing= 6 m
Bay spacing/3= 2 m
Effective purlin spacing= 2 m
Eff. Wind load area, A 12 m2 129.1008 ft2
4% of SD= 1.599816 ft
3 ft
From here, Z= 3 ft