ABSTRACT ESTIMATE FOR : PROVN OF ADMIN BLDG FOR MCEME AND 80 SINGLE OFFFCIERS ACCN
MCEME, SECUNDERABAD (SPL WORK)
S.No Item No. Brief Description of item Qty Unit unit rate Amount
Remarks
1 1 Surface excavation, Earth work, PCC in Foundation,form
work,reinforcement and RCC in footings,columns up to plinth beams, RFR, Filling
under floors & Brick work up to FFL
(i) Excavation and Earth work details
a Surface excavation n-exc 30cm deep are 15cm and getting in artificial
soil 2999.75 m 24.00 71994.06
b Excavation over areas nexc 1.5m deep 2400.00 m 118.00
283200.00
c Excavation over but hexc 1.5m b. nexe 3.00m 1700.00 m 191.00
324700.00
d Earth required for return and filling 239.64 m 63.10
15121.28
e Earth required for filling under floors 471.29 m 79.00
37232.23
f Removal of surplus soil to a dist n.exe 50m 3860.36 m 147.00
567472.92
iii PCC 1:4:8 as in foundation
a PCC 1:4:8 as in foundation 119.73 m 3515.00 420850.95

iii Form work


a Form work for footings, pedastals and plinth beams 2927.56 m
205.00 600149.80
b Form work for columns 297.00 m 406.00 120582.00

iv TMT Rienforcement for RCC works 74.00


a 10mm dia and over up to 25mm dia TMT bars 54500 Kg 74.00 4033000.00

b -do- but 8mm dia TMT bars incl stirrups 23600 Kg 75.00
1770000.00
v RCC M-30 design mix for concrete items 1st to 4th floor

a RCC M-30 design mix for concrete for col footings, raft beams, PBS,
Pedastals etc 668.06 m 5569.00 3720426.14
b -do- for columns 28.00 m 6598.00 184744.00
Total of 1 Rs 12149473.38

c/o to yardstick sheet


2 2 ATT
a Treating back fill of floors @7.50 ltrs/m 299.57 m 194.00
58116.58
b Treating top of floors @5.00 ltrs/m 1047.32 m 123.00
128815.75
c Treating perimeter of bldg @2.25 ltrs/RM 261.20 RM 59.00
15410.80
Total of 2 Rs 202343.13

c/o to yardstick sheet


3 3 Form work, Reinforcement work & RCC columns, lintels, Chejjas, drops,
Fins, staircase, slabs for Ground floor
i Form work
a -do- for columns 819.49 m 406.00 332712.94
3277.96
b -do- for FB / RB/LB & Lintels 1063.93 m 349.00
371305.78 4255.70
c -do- for floor/roof slabs & Projections 1165.91 m 361.00
420892.43 4663.63
d -do- for Chajjas/ gutters 34.56 m 429.00 14826.24
138.24
e -do- for RCC walls/ drops/parapet/waist slab 545.01 m
433.00 235989.33 2180.38
ii TMT Rienforcement for RCC works for Ground floor

a 10mm dia and over up to 25mm dia TMT bars 34529.86 Kg 74.00
2555209.64 138119.44
b -do- but 8mm dia TMT bars incl stirrups 20052.47 Kg 75.00
1503935.25 80209.89
iii RCC M-30 design mix for concrete items for Ground floor

a -do- for columns 78.04 m 598.00 46667.92 312.16

b -do- for FB / RB/LB & Lintels 89.98 m 6365.00


572722.70 359.91
c -do- for floor/roof slabs & Projections 81.56 m 6005.00
489767.80 326.25
d -do- for Chajjas/ gutters 2.60 m 6562.00 17061.20
10.37
e -do- for RCC walls/ drops/parapet/waist slab 41.30 m
6577.00 271630.10 165.21
Total of 3 Rs 6832721.33 44548164.46

c/o to yardstick sheet


4 4 Form work, Reinforcement work & RCC columns, lintels, Chejjas, drops,
Fins, staircase, slabs for First floor
i Form work
a -do- for columns 819.49 m 406.00 332712.94
3277.96
b -do- for FB / RB/LB & Lintels 1063.93 m 349.00
371305.78 4255.70
c -do- for floor/roof slabs & Projections 1165.91 m 361.00
420892.43 4663.63
d -do- for Chajjas/ gutters 34.56 m 429.00 14826.24
138.24
e -do- for RCC walls/ drops/parapet/waist slab 545.01 m
433.00 235989.33 2180.38
ii TMT Rienforcement for RCC works for First floor

a 10mm dia and over up to 25mm dia TMT bars 34529.86 Kg 74.00
2555209.64 138119.44
b -do- but 8mm dia TMT bars incl stirrups 20052.47 Kg 75.00
1503935.25 80209.89
iii RCC M-30 design mix for concrete items for First floor

a -do- for columns 78.04 m 6598.00 514907.92 312.16

b -do- for FB / RB/LB & Lintels 89.98 m 6365.00


572722.70 359.91
c -do- for floor/roof slabs & Projections 81.56 m 6005.00
489767.80 326.25
d -do- for Chajjas/ gutters 2.60 m 6562.00 17061.20
10.37
e -do- for RCC walls/ drops/parapet/waist slab 41.30 m
6577.00 271630.10 165.21
Total of 4 Rs 7300961.33
c/o to yardstick sheet
5 5 Form work, Reinforcement work & RCC columns, lintels, Chejjas, drops,
Fins, staircase, slabs for Second floor
i Form work
a -do- for columns 819.49 m 406.00 332712.94
3277.96
b -do- for FB / RB/LB & Lintels 1063.93 m 349.00
371305.78 4255.70
c -do- for floor/roof slabs & Projections 1165.91 m 361.00
420892.43 4663.63
d -do- for Chajjas/ gutters 34.56 m 429.00 14826.24
138.24
e -do- for RCC walls/ drops/parapet/waist slab 545.01 m
433.00 235989.33 2180.38
ii TMT Rienforcement for RCC works for Second floor

a 10mm dia and over up to 25mm dia TMT bars 34529.86 Kg 74.00
2555209.64 138119.44
b -do- but 8mm dia TMT bars incl stirrups 20052.47 Kg 75.00
1503935.25 80209.89
iii RCC M-30 design mix for concrete items for Second floor

a -do- for columns 78.04 m 6598.00 514907.92 312.16

b -do- for FB / RB/LB & Lintels 89.98 m 6365.00


572722.70 359.91
c -do- for floor/roof slabs & Projections 81.56 m 6005.00
489767.80 326.25
d -do- for Chajjas/ gutters 2.60 m 6562.00 17061.20
10.37
e -do- for RCC walls/ drops/parapet/waist slab 41.30 m
6577.00 271630.10 165.21
Total of 5 Rs 7300961.33

c/o to yardstick sheet


6 6 Form work, Reinforcement work & RCC columns, lintels, Chejjas, drops,
Fins, staircase, slabs for Third floor
i Form work
a -do- for columns 819.49 m 406.00 332712.94
3277.96
b -do- for FB / RB/LB & Lintels 1063.93 m 349.00
371305.78 4255.70
c -do- for floor/roof slabs & Projections 1165.91 m 361.00
420892.43 4663.63
d -do- for Chajjas/ gutters 34.56 m 429.00 14826.24
138.24
e -do- for RCC walls/ drops/parapet/waist slab 545.01 m
433.00 235989.33 2180.38
ii TMT Rienforcement for RCC works for Third floor

a 10mm dia and over up to 25mm dia TMT bars 34529.86 Kg 74.00
2555209.64 138119.44
b -do- but 8mm dia TMT bars incl stirrups 20052.47 Kg 75.00
1503935.25 80209.89
iii RCC M-30 design mix for concrete items for Third floor

a -do- for columns 78.04 m 6598.00 514907.92 312.16


b -do- for FB / RB/LB & Lintels 89.98 m 6365.00
572722.70 359.91
c -do- for floor/roof slabs & Projections 81.56 m 6005.00
489767.80 326.25
d -do- for Chajjas/ gutters 2.60 m 6562.00 17061.20
10.37
e -do- for RCC walls/ drops/parapet/waist slab 41.30 m
6577.00 271630.10 165.21
Total of 6 Rs 7300961.33

c/o to yardstick sheet


7 7 Form work, Reinforcement work & RCC columns, lintels, Chejjas, drops,
Fins, staircase, slabs for 4th floor level
ii Form work for various cone for fourth floor

a -do- for columns 791.96 m 426.00 337372.83

b -do- for FB / RB/LB & Lintels 1075.35 m 366.00


393576.27
c -do- for floor/roof slabs & Projections 1160.22 m 379.00
439723.38
d -do- for Chajjas/ gutters 46.08 m 450.00 20736.00

e -do- for RCC walls/ drops/parapet/waist slab 1120.11 m


454.00 508529.94
iv TMT Rienforcement for RCC works for Fourth floor

a 10mm dia and over up to 25mm dia TMT bars 26141.15 Kg 80.00
2091292.00
b -do- but 8mm dia TMT bars incl stirrups 19622.01 Kg 81.00
1589382.81
vi RCC M-30 design mix for concrete items for Fourth floor

a -do- for columns 73.06 m 6928.00 506125.04 146.11

b -do- for FB / RB/LB & Lintels 115.73 m 6683.00


773423.59 231.46
c -do- for floor/roof slabs & Projections 104.29 m
6305.00 657548.45 208.58
d -do- for Chajjas/ gutters 6.91 m 6890.00 47609.90
6.91
e -do- for RCC walls/ drops/parapet/waist slab 78.31 m
6906.00 540808.86 156.62
Total of 7 Rs 7906129.07

c/o to yardstick sheet


8 8 Form work, Reinforcement work & RCC columns, lintels, Chejjas, drops,
Fins, staircase, slabs for 4th floor level
i Form work for various cone for fifth floor

a -do- for columns 791.96 m 426.00 337372.83

b -do- for FB / RB/LB & Lintels 1075.35 m 366.00


393576.27
c -do- for floor/roof slabs & Projections 1160.22 m 379.00
439723.38
d -do- for Chajjas/ gutters 46.08 m 450.00 20736.00

e -do- for RCC walls/ drops/parapet/waist slab 1120.11 m


454.00 508529.94
ii TMT Rienforcement for RCC works for Fifth floor

a 10mm dia and over up to 25mm dia TMT bars 26143.9 Kg 80.00
2091512.00
b -do- but 8mm dia TMT bars incl stirrups 19623.01 Kg 81.00
1589463.81
iii RCC M-30 design mix for concrete items for Fifth floor

a -do- for columns 73.06 m 6928.00 506125.04 146.11

b -do- for FB / RB/LB & Lintels 115.73 m 6683.00


773423.59 231.46
c -do- for floor/roof slabs & Projections 104.29 m
6305.00 657548.45 208.58
d -do- for Chajjas/ gutters 6.91 m 6890.00 47609.90
6.91
e -do- for RCC walls/ drops/parapet/waist slab 78.31 m
6906.00 540808.86 156.62
Total of 8 Rs 7906430.07

c/o to yardstick sheet


9 i MASONRY First floor
a 200th Fly ash brick masonry built in cm (1 : 6) 272.66 m
3651.00 995481.66 817.98
b - do- but for 100th wall built in cm (1 : 4) 343.33 m 409.00
140421.97 1030.02
Total of 9 Rs 1135903.63

c/o to yardstick sheet


10 i MASONRY Second floor
a 200th Fly ash brick masonry built in cm (1 : 6) 272.66 m
3651.00 995481.66 817.98
b - do- but for 100th wall built in cm (1 : 4) 343.33 m 409.00
140421.97 1030.02
Total of 10 Rs 1135903.63

c/o to yardstick sheet


11 i MASONRY Third floor
a 200th Fly ash brick masonry built in cm (1 : 6) 272.66 m
3651.00 995481.66 817.98
b - do- but for 100th wall built in cm (1 : 4) 343.33 m 409.00
140421.97 1030.02
Total of 11 Rs 1135903.63

c/o to yardstick sheet


12 i MASONRY Fourth floor
a 200th Fly ash brick masonry built in cm (1 : 6) 250.65 m
3833.00 960741.45 501.30
b - do- but for 100th wall built in cm (1 : 4) 343.34 m 428.00
146949.52 686.68
Total of 12 Rs 1107690.97

c/o to yardstick sheet


13 i MASONRY Fourth floor
a 200th Fly ash brick masonry built in cm (1 : 6) 250.65 m
3833.00 960741.45 501.30
b - do- but for 100th wall built in cm (1 : 4) 343.34 m 428.00
146949.52 686.68
Total of 13 Rs 1107690.97

c/o to yardstick sheet


14 i Flooring items Ground floor
a 75mm th PCC (1:5:10) type E2 for sub base 11.41 m 3242.00
37002.57
b PCC (1:4:8) type D2 for sub base 126.85 m 3515.00
445860.18
d 100 mm th PCC (1:2:4) type B1 1268.45 m 496.00
629151.20
g -do do but 20mm th PCC 1:2:4 3265.58 m 116.00 378807.28

Total of 14 Rs 1490821.22

c/o to yardstick sheet


15 i Flooring items First floor
a 7mm th Non-skid ceramic tiles of size 300 x 300 (matt finish) over
10mmth scrced bed in cm (1:4) 70.08 m 1040.00 72883.20 210.24

b 7-8mm th Non-skid ceramic tiles area of each tile exc 0.18 and n.exc
0.36 over 10mmth screed bed in cm (1:4) 298.87 m 1158.00 346091.46
896.61
c 10mm th Non-skid vitrified tiles area of each tile n.exc 0.36 sqm over
10mm th screed bed in cm (1:4) 646.61 m 1364.00 881976.04
1939.83
d Green marble flooring over a screed bed of 20th in CM 1:6 72.97 m
978.00 71361.43 218.90
Total of 15 Rs 1372312.13

c/o to yardstick sheet


16 i Flooring items Second floor
a 7mm th Non-skid ceramic tiles of size 300 x 300 (matt finish) over
10mmth scrced bed in cm (1:4) 70.08 m 1040.00 72883.20 210.24

b 7-8mm th Non-skid ceramic tiles area of each tile exc 0.18 and n.exc
0.36 over 10mmth screed bed in cm (1:4) 298.87 m 1158.00 346091.46
896.61
c 10mm th Non-skid vitrified tiles area of each tile n.exc 0.36 sqm over
10mm th screed bed in cm (1:4) 646.61 m 1364.00 881976.04
1939.83
d Green marble flooring over a screed bed of 20th in CM 1:6 72.97 m
978.00 71361.43 218.90
Total of 16 Rs 1372312.13

c/o to yardstick sheet


17 i Flooring items Third floor
a 7mm th Non-skid ceramic tiles of size 300 x 300 (matt finish) over
10mmth scrced bed in cm (1:4) 70.08 m 1040.00 72883.20 210.24

b 7-8mm th Non-skid ceramic tiles area of each tile exc 0.18 and n.exc
0.36 over 10mmth screed bed in cm (1:4) 298.87 m 1158.00 346091.46
896.61
c 10mm th Non-skid vitrified tiles area of each tile n.exc 0.36 sqm over
10mm th screed bed in cm (1:4) 646.61 m 1364.00 881976.04
1939.83
d Green marble flooring over a screed bed of 20th in CM 1:6 72.97 m
978.00 71361.43 218.90
Total of 17 Rs 1372312.13
c/o to yardstick sheet
18 i Flooring items Fourth floor
a 7mm th Non-skid ceramic tiles of size 300 x 300 (matt finish) over
10mmth scrced bed in cm (1:4) 70.08 m 1092.00 76527.36 140.16

b 8mm th Non-skid ceramic tiles area of each tile exc 0.18 and n.exc 0.36
over 15mmth screed bed in cm (1:4) 298.87 m 1216.00 363425.92 597.74

c 10mm th Non-skid vitrified tiles area of each tile n.exc 0.36 sqm over
10mm th screed bed in cm (1:4) 646.61 m 1432.00 925945.52
1293.22
d 20 mm th PCC (1:2:4) type B1 1052.77 m 122.00 128437.94
2105.54
e Green marble flooring over a screed bed of 20th in CM 1:6 72.97 m
978.00 71364.66 74.42
Total of 18 Rs 1565701.40

c/o to yardstick sheet


19 i Flooring items Fifth floor
a 7mm th Non-skid ceramic tiles of size 300 x 300 (matt finish) over
10mmth scrced bed in cm (1:4) 70.08 m 1092.00 76527.36 140.16

b 8mm th Non-skid ceramic tiles area of each tile exc 0.18 and n.exc 0.36
over 15mmth screed bed in cm (1:4) 298.87 m 1216.00 363425.92 597.74

c 10mm th Non-skid vitrified tiles area of each tile n.exc 0.36 sqm over
10mm th screed bed in cm (1:4) 646.61 m 1432.00 925945.52
1293.22
d 20 mm th PCC (1:2:4) type B1 1052.77 m 122.00 128437.94
2105.54
e Green marble flooring over a screed bed of 20th in CM 1:6 72.97 m
978.00 71364.66 74.42
Total of 19 Rs 1565701.40

c/o to yardstick sheet


20 i Internal Plastering First floor
a 10mm th plastering in CM (1:6) above skirting & dado 2853.87 m
152.00 433788.24
Total of 20 Rs 433788.24

c/o to yardstick sheet


21 i Internal Plastering second floor
a 10mm th plastering in CM (1:6) above skirting & dado 2853.87 m
152.00 433788.24
Total of 21 Rs 433788.24

c/o to yardstick sheet


22 i Internal Plastering Third floor
a 10mm th plastering in CM (1:6) above skirting & dado 2853.87 m
152.00 433788.24
Total of 22 Rs 433788.24

c/o to yardstick sheet


23 i Internal Plastering Fourth floor
a 10mm th plastering in CM (1:6) above skirting & dado 2763.86 m
160.00 442217.60
Total of 23 Rs 442217.60

c/o to yardstick sheet


24 i Internal Plastering Fifth floor
a 10mm th plastering in CM (1:6) above skirting & dado 2763.86 m
160.00 442217.60
Total of 24 Rs 442217.60

c/o to yardstick sheet


25 i External plastering 1st to 4th
a 5mm th plastering in CM (1:4) using WPC over 10mm thick cm (1:6)
3351.83 m 240.00 804439.20
b Supply only 3% of IWPC 428.36 Kg 54.00 23131.65
ii External plastering 5th to 6th
a 5mm th plastering in CM (1:4) using WPC over 10mm thick cm (1:6)
1946.56 m 252.00 490533.12
b Supply only 3% of IWPC 248.77 Kg 56.00 13931.14
Total of 25 Rs 1332035.11

c/o to yardstick sheet


26 i Skirting and dado 1st to 4th
a 10mm th vitrified tiles 600 X 100 high to match the floor tiles over
10 th CM (1:3) 193.98 m 2031.00 393973.38
b 7 to 8mm th glazed ceramic tiles 400 X 300 high to match the floor
tiles over 10 th CM (1:3) 886.84 m 1099.00 974637.16
ii Skirting and dado 5th to 6th
a 10mm th vitrified tiles 600 X 100 high to match the floor tiles over
10 th CM (1:3) 129.32 m 2132.00 275710.24
b 7 to 8mm th glazed ceramic tiles 400 X 300 high to match the floor
tiles over 10 th CM (1:3) 591.23 m 1154.00 682279.42
Total of 26 Rs 2326600.20

c/o to yardstick sheet


27 i Ceiling plaster 1st to 4th
a 5mm ceiling plaster in CM (1:3) on exposed surface of conc 4243.76
m 135.00 572907.60
ii Ceiling plaster 5th to 6th
a 5mm ceiling plaster in CM (1:3) on exposed surface of conc 2061.06
m 142.00 292670.52
Total of 27 Rs 865578.12

c/o to yardstick sheet


28 i WPT on Roofs
a 5mmth cement plaster in CM (1:3) using WPC 1160.70 m 154.00
178747.80
b Apply HMHDPE polymeric water proof membrane 3kg / m wt over bitumen @
1.20 Kg / m over 0.20 lars / m of primer - after laying of w.p menbrane a coat of
bitumen be applied at 1.20 kg / m and finally with a coat of at a paint 0.10
Kg/m. 1160.70 m 873.00 1013291.10
c Supply only 3% of IWPC 175.15 kg 59.00 10333.83
Total of 28 Rs 1202372.73

c/o to yardstick sheet


29 i Rain water Pipes 1st to 4th
a 160mm dia UPVC rain water pipe 628.80 Rm 486.00
305596.80
b 160 mm dia shoe bend 576.00 Each 305.00 175680.00

c 20mm th polished kadapa slab stone 48.00 m 656.00 31488.00

ii Rain water Pipes 5th to 6th


a 160mm dia UPVC rain water pipe 307.20 Rm 511.00
156979.20
b 160mm dia dome grating 48.00 Each 401.00 19248.00
c 160 mm dia shoe bend 288.00 Each 291.00 83808.00

Total of 29 Rs 772800.00

c/o to yardstick sheet


30 i Panelled Doors First floor
a 1.25th pressed steel door frame 60 x 105mm profile for frames 248.00
Rm 382.00 94736.00 744.00
b 30mm tk factory made panelled door shutter 97.77 m 2416.00
236212.32 292.32
c builders hardware (9% cost of c&d) 21259.11

Total of 30 Rs 352207.43

c/o to yardstick sheet


31 i Panelled Doors Second floor
a 1.25th pressed steel door frame 60 x 105mm profile for frames 248.00
Rm 382.00 94736.00 744.00
b 30mm tk factory made panelled door shutter 97.77 m 2416.00
236212.32 292.32
c builders hardware (9% cost of c&d) 21259.11

Total of 31 Rs 352207.43

c/o to yardstick sheet


32 i Panelled Doors Third floor
a 1.25th pressed steel door frame 60 x 105mm profile for frames 248.00
Rm 382.00 94736.00 744.00
b 30mm tk factory made panelled door shutter 97.77 m 2416.00
236212.32 292.32
c builders hardware (9% cost of c&d) 21259.11

Total of 32 Rs 352207.43

c/o to yardstick sheet


33 i Panelled Doors fourth floor
a 1.25th pressed steel door frame 60 x 105mm profile for frames 248.00
Rm 401.00 99448.00
b 30mm tk factory made panelled door shutter 97.77 m 2536.00
247944.72
c builders hardware (9% cost of c&d) 22315.02

Total of 33 Rs 369707.74

c/o to yardstick sheet


34 i Panelled Doors fifth floor
a 1.25th pressed steel door frame 60 x 105mm profile for frames 248.00
Rm 401.00 99448.00
b 30mm tk factory made panelled door shutter 97.77 m 2536.00
247944.72
c builders hardware (9% cost of c&d) 22315.02

Total of 34 Rs 369707.74

c/o to yardstick sheet

35 i PVC Doors First floor


a PVC solid door frame 99.20 Rm 511.00 50691.20 297.60

b PVC solid door shutter 31.82 m 3242.00 103160.44 95.76


c builders hardware (7% cost of b) 7221.23

Total of 35 Rs 161072.87

c/o to yardstick sheet


36 i PVC Doors Second floor
a PVC solid door frame 99.20 Rm 511.00 50691.20 297.60

b PVC solid door shutter 31.82 m 3242.00 103160.44 95.76


c builders hardware (7% cost of b) 7221.23

Total of 36 Rs 161072.87

c/o to yardstick sheet


37 i PVC Doors Third floor
a PVC solid door frame 99.20 Rm 511.00 50691.20 297.60

b PVC solid door shutter 31.82 m 3242.00 103160.44 95.76


c builders hardware (7% cost of b) 7221.23

Total of 37 Rs 161072.87

c/o to yardstick sheet


38 i PVC Doors Fourth floor
a PVC solid door frame 99.20 Rm 537.00 53270.40 297.60

b PVC solid door shutter 31.82 m 3404.00 108315.28 95.76


c builders hardware (7% cost of b) 7582.07

Total of 38 Rs 169167.75

c/o to yardstick sheet


39 i PVC Doors Fifth floor
a PVC solid door frame 99.20 Rm 537.00 53270.40 297.60

b PVC solid door shutter 31.82 m 3404.00 108315.28 95.76


c builders hardware (7% cost of b) 7582.07

Total of 39 Rs 169167.75

c/o to yardstick sheet


40 i Steel windows and fixed glazing First floor

a 1.25th pressed steel /CRCA steel window frames with top fixed glazing
complete incl glazing 117.00 Sqm 3665.00 428805.00 351.00
b Stand sectioned and type top hung steel ventilators 21.87 Sqm
3055.00 66812.85 65.60
c 12mm dia MS bars for guard bars 1038.96 KG 102.00
105973.92 3116.88
Total of 40 Rs 601591.77

c/o to yardstick sheet


41 i Steel windows and fixed glazing Second floor

a 1.25th pressed steel /CRCA steel window frames with top fixed glazing
complete incl glazing 117.00 Sqm 3665.00 428805.00 351.00
b Stand sectioned and type top hung steel ventilators 21.87 Sqm
3055.00 66812.85 65.60
c 12mm dia MS bars for guard bars 1038.96 KG 102.00
105973.92 3116.88
Total of 41 Rs 601591.77

c/o to yardstick sheet


42 i Steel windows and fixed glazing Third floor

a 1.25th pressed steel /CRCA steel window frames with top fixed glazing
complete incl glazing 117.00 Sqm 3665.00 428805.00 351.00
b Stand sectioned and type top hung steel ventilators 21.87 Sqm
3055.00 66812.85 65.60
c 12mm dia MS bars for guard bars 1038.96 KG 102.00
105973.92 3116.88
Total of 42 Rs 601591.77

c/o to yardstick sheet


43 i Steel windows and fixed glazing Fourth Floor

a 1.25th pressed steel /CRCA steel window frames with top fixed glazing
complete incl glazing 117.00 Sqm 3848.00 450216.00
b Stand sectioned and type top hung steel ventilators 21.87 Sqm
3208.00 70158.96
c 12mm dia MS bars for guard bars 1038.96 KG 107.00
111168.72
Total of 43 Rs 631543.68

c/o to yardstick sheet


44 i Steel windows and fixed glazing Fifth Floor

a 1.25th pressed steel /CRCA steel window frames with top fixed glazing
complete incl glazing 117.00 Sqm 3848.00 450216.00
b Stand sectioned and type top hung steel ventilators 21.87 Sqm
3208.00 70158.96
c 12mm dia MS bars for guard bars 1038.96 KG 107.00
111168.72
Total of 44 Rs 631543.68

c/o to yardstick sheet


45 i Steel Ladders
a stnd section and type steel ladders at machine rooms 3.5m 1.00 Each
9919.00 9919.00
Total of 45 Rs 9919.00

c/o to yardstick sheet


46 i Cupboards 1st to 4th
a stnd section and type 18mm thk prelaminated particle board shutters and
shelves with second class hardwood frame work all as specified

CB1 of size 1.2x2.1 m 120.96 Sqm 6867.00 830632.32

ii Cupboards 5th to 6th


a stnd section and type 18mm thk prelaminated particle board shutters and
shelves with second class hardwood frame work all as specified

CB1 of size 1.2x2.1 m 80.64 Sqm 7210.00 581414.40


Total of 46 Rs 1412046.72
c/o to yardstick sheet
47 i Sanitary fittings & fixtures 1st to 4th

a Vit China White glazed pedasta pattern EWC 400 X 410 mm 48.00 each
2327.00 111696.00
b 10 ltrs cap HDPE LLFC. 48.00 each 1569.00 75312.00
c Flat back Wash Hand Basin 48.00 Each 1221.00 58608.00

d standard type 300mm stainless steel towel rail 48.00 Each 305.00
14640.00
e standard section type 5mm thick looking mirror with ply wood backing
600x900mm 48.00 each 3205.00 153840.00
f 75mm NHT PVC with grating 96.00 each 269.00 25824.00

g Toilet paper holder 24.00 each 458.00 10992.00


h Shower 48.00 each 763.00 36624.00
j 150 X 150 mm SGSW gullytrap 48.00 each 675.00 32400.00

k A peg set of 3 48.00 each 229.00 10992.00


ii Santry fittings & fixtures 5th to 6th

a Vit China White glazed pedasta pattern EWC 400 X 410 mm 32.00 each
2443.00 78176.00
b 10 ltrs cap HDPE LLFC. 32.00 each 1647.00 52704.00
c Flat back Wash Hand Basin 32.00 Each 1282.00 41024.00

d standard type 300mm stainless steel towel rail 32.00 Each 320.00
10240.00
e standard section type 5mm thick looking mirror with ply wood backing
600x900mm 32.00 each 3365.00 107680.00
f 75mm NHT PVC with grating 64.00 each 282.00 18048.00

g Toilet paper holder 16.00 each 481.00 7696.00


h Shower 32.00 each 801.00 25632.00
j 150 X 150 mm SGSW gullytrap 32.00 each 709.00 22688.00

k A peg set of 3 32.00 each 240.00 7680.00


Total of 47 Rs 902496.00

c/o to yardstick sheet


48 i Plumbing items:- 1st to 4th
a 75mm dia UPVC waste pipe/vp 17.40 RM 177.00 3079.80

b 75mm dia bends 5.00 each 116.00 580.00


c - do - 110 for sp 11.10 RM 323.00 3585.30
d do do bends 5.00 each 197.00 985.00
ii Plumbing items:- 5th to 8th
a 75mm dia UPVC waste pipe/vp 11.60 RM 186.00 2157.60

b 75mm dia bends 5.00 each 121.00 605.00


c - do - 110 for sp 7.40 RM 339.00 2508.60
d do do bends 5.00 each 206.00 1030.00
Total of 48 Rs 14531.30

c/o to yardstick sheet


49 i Plinth protection ground floor
a 75mm hard core of gange h-exe 63 mm agg 6.68 m 1366.00
9128.30
b 50mmth PCC (1:3:6) type C1 89.10 m 208.00 18532.80
Total of 49 Rs 27661.10

c/o to yardstick sheet


50 i Crumple Section
a 25mm thk bitumenous mastic pad 9.00 m 986.00 8874.00

b 1mm thk Al sheet to cover gaps 9.00 m 635.00 5715.00

Total of 50 Rs 14589.00

c/o to yardstick sheet


51 i Finishes 1st to 4th
a 3 coats of white wash on walls 8168.76 m 17.00 138868.92

b 3 coats of white wash on ceiling 4243.76 m 19.00 80631.44

c two coats of oil bound distemper over 1 coat of putty 6620.01 m


99.00 655380.99
d Two coats of cement base paint over a coat of primer 3351.83 m
74.00 248035.42
ii Finishes 5th to 6th
a 3 coats of white wash on walls 5445.84 m 18.00 98025.12

b 3 coats of white wash on ceiling 2061.06 m 20.00 41221.20

c two coats of oil bound distemper over 1 coat of putty 4413.34 m


104.00 458987.36
d Two coats of cement base paint over a coat of primer 1946.56 m
136.00 264732.16
Total of 51 Rs 1985882.61

c/o to yardstick sheet


TOTAL RS 90000000.58 -0.16