V100
Installation Guide
Issue 03
Date 2010-05-04
Website: http://www.huawei.com
Email: support@huawei.com
and other Huawei trademarks are the property of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or representations
of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute the warranty of any kind, express or implied.
Contents
4 Installation Procedure...............................................................................................................4-1
5 Unpacking the Equipment.......................................................................................................5-1
6 Checking the Installed Modules and Cables........................................................................6-1
7 Installing the Base......................................................................................................................7-1
7.1 Installing the Base on the Concrete Floor.......................................................................................................7-2
7.2 Installing the Base on the ESD Floor..............................................................................................................7-5
10.3.3 Installing the Input Power Cable for the 220 V Cabinet....................................................................10-7
10.4 Installing the Transmission Cables.............................................................................................................10-9
10.4.1 Installing the E1/T1 Cables..............................................................................................................10-10
10.4.2 Installing the FE/GE Cable or FE/GE Optical Cable.......................................................................10-11
10.5 Installing the CPRI Cables Between the Cabinets....................................................................................10-13
10.6 Installing the RF Jumper...........................................................................................................................10-14
10.7 Installing the Monitoring Signal Cable for the EMU................................................................................10-16
11 Installation Checklist............................................................................................................11-1
12 Performing the Power-On Check........................................................................................12-1
13 Obtaining the ESN.................................................................................................................13-1
Figures
Tables
Purpose
This document describes installation of the BTS3900 cabinet, boards, modules, and cables. It
also provides checklists for hardware installation.
Product Version
The following table lists the product version related to this document.
BTS3900 V100R001
V100R002
V100R003
Intended Audience
l Base station installers
Organization
1 Changes in the BTS3900 Installation Guide
This chapter describes the changes in the BTS3900 Installation Guide.
2 Preparing for Installation
This topic describes the tools and meters that need to be available before the installation. It also
describes the skills that the installation engineers must possess, and the requirements that the
installation engineers must meet.
3 Information About the Installation
BTS3900 cabinets can be classified into -48 V cabinet, +24 V cabinet, and +220 V cabinet. You
need to familiarize yourself with the related information and clearance requirements before the
cabinet installation.
4 Installation Procedure
The BTS3900 cabinets are delivered with boards are installed. The installation procedure
involves installing the base, cabinets, and cables on site. In addition, some optional components
can be installed on site as required.
You need to unpack and check the delivered equipment and ensure that all the materials are
included and intact.
The internal modules and cables are installed in the cabinet before delivery. You need to check
that the modules and cables are securely connected.
The BTS3900 cabinet must be installed on the base. The base can be installed on the concrete
floor or ESD floor according to the equipment room conditions and customer requirements.
The BTS3900 cabinets can be flexibly installed. In different scenarios, a single cabinet can be
separately installed and two cabinets can be installed side-by-side or stacked.
The mandatory modules in the cabinet are already installed. The optional modules can be
installed on site according to different field requirements.
The BTS3900 cabinet is delivered with boards installed, and the internal cables are already
installed. Therefore, only the external cables and cables for the optional modules need to be
installed on site.
11 Installation Checklist
After the cabinets and devices are all installed, you need to check the installation items,
installation environment, and cable-related items.
Before the cabinets are powered on and work, you need to check the power-on status of the
cabinets.
The Electronic Serial Number (ESN) is unique to a Network Element (NE) for identification.
The ESN is used during the commissioning of the base station.
Conventions
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol Description
General Conventions
The general conventions that may be found in this document are defined as follows.
Convention Description
Command Conventions
The command conventions that may be found in this document are defined as follows.
Convention Description
Convention Description
GUI Conventions
The GUI conventions that may be found in this document are defined as follows.
Convention Description
Keyboard Operations
The keyboard operations that may be found in this document are defined as follows.
Format Description
Key Press the key. For example, press Enter and press Tab.
Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt
+A means the three keys should be pressed concurrently.
Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A means
the two keys should be pressed in turn.
Mouse Operations
The mouse operations that may be found in this document are defined as follows.
Action Description
Click Select and release the primary mouse button without moving
the pointer.
Drag Press and hold the primary mouse button and move the
pointer to a certain position.
03 (2010-05-04)
This is the second commercial release.
Compared with issue 02 (2009-12-28), this issue incorporates the following changes:
l There are some editorial changes.
l The context of 8.3 Stacking Two Cabinets is modified.
02 (2009-12-28)
This is the first commercial release.
Compared with issue 01 (2009-10-15), this issue incorporates the following changes:
l 13 Obtaining the ESN is added.
l 7.1 Installing the Base on the Concrete Floor is modified.
l 7.2 Installing the Base on the ESD Floor is modified.
l 8.1 Installing a Single Cabinet Separately is modified.
01 (2009-10-15)
This is the initial release.
This topic describes the tools and meters that need to be available before the installation. It also
describes the skills that the installation engineers must possess, and the requirements that the
installation engineers must meet.
When arranging the installation engineers to perform this activity, the customer needs to pay
attention to the following points:
l The technical engineer of the customer must have received the basic training conducted by
Huawei Technologies Co., Ltd., and must understand the related methods of installation
and construction.
l The number of installation engineers should be based on the specific engineering schedule
and the installation environment. In general, arrange for three to five installation engineers.
BTS3900 cabinets can be classified into -48 V cabinet, +24 V cabinet, and +220 V cabinet. You
need to familiarize yourself with the related information and clearance requirements before the
cabinet installation.
The BTS3900 cabinet (-48 V) can house three RFUs in typical configuration or six RFUs in full
configuration. Figure 3-1 and Figure 3-2 show the BTS3900 cabinet (-48 V) in typical
configuration and in full configuration respectively.
The BTS3900 cabinet (+24 V) supports the 3RFU typical configuration and the 6RFU full
configuration. Figure 3-3 and Figure 3-4 show the BTS3900 cabinet (+24 V) in typical
configuration and in full configuration respectively.
Figure 3-7 shows the installation clearance requirements when a single cabinet is installed, two
cabinets are installed side-by-side, and two cabinets are stacked.
l No space is reserved between the cabinets and the customer equipment if they are installed
side-by-side.
Figure 3-8 shows the layout requirements (unit: mm) for the installation of the BTS3900
cabinets.
4 Installation Procedure
The BTS3900 cabinets are delivered with boards are installed. The installation procedure
involves installing the base, cabinets, and cables on site. In addition, some optional components
can be installed on site as required.
Figure 4-1 shows the installation procedure.
You need to unpack and check the delivered equipment and ensure that all the materials are
included and intact.
Context
NOTE
When transporting, moving, or installing the equipment, components, or parts, you must:
l Prevent them from colliding with doors, walls, shelves, or other objects.
l Wear clean gloves, and avoid touching the equipment, components, or parts with your bare hand,
sweat-soaked gloves, or dirty gloves.
Procedure
Step 1 Check whether the total number of goods in each case matches that in the packing list.
If... Then...
The total number does not match that in the Find out the cause and report it to the local
packing list Huawei office.
If... Then...
The outer packing is severely damaged or Find out the cause and report it to the local
soaked Huawei office.
Step 3 Check the type and quantity of the equipment in the cases according to the packing list.
If... Then...
Types and quantity of the goods are in Sign the packing list with the customer.
conformity with those on the packing list
There is wrong delivery or shortage of Fill in the Cargo Shortage and Miscarriage
goods Report and submit it.
WARNING
To protect the equipment and find out the cause in the future, you need to keep the unpacked
equipment and packing materials in indoor environment, take photos of the stocking
environment, rusted or eroded equipment, packing case or carton, and packing materials, and
then file the photos.
----End
The internal modules and cables are installed in the cabinet before delivery. You need to check
that the modules and cables are securely connected.
Module Checklist
The modules are securely connected to the cabinet, and the screws are tightened.
Cable Checklist
Check whether the power cables and screws are properly and securely fixed in the cabinet by
referring to Figure 6-1 and Table 6-1.
Check whether the signal cables and screws are properly and securely fixed in the cabinet by
referring to Figure 6-2 and Table 6-2.
Check and ensure the secure connections of the CPRI cables, which are installed inside the
cabinets based on different configurations of the cabinets before delivery.
The BTS3900 cabinet must be installed on the base. The base can be installed on the concrete
floor or ESD floor according to the equipment room conditions and customer requirements.
Procedure
Step 1 Determine the position of the cabinet by referring to the marking template, as shown in Figure
7-1.
Step 2 Drill a hole at each anchor point, and then install the expansion bolt assembly, as shown in
Figure 7-2.
Ø16
1
2 90。
3
52-60mm
(1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Expansion tube
1. Use the percussion drill with bit 16 to drill holes at the anchor points, and ensure that the
depth of each hole ranges from 52 mm to 60 mm.
WARNING
Take proper safety measures to protect your eyes and respiratory tract against the dust
before drilling holes.
2. Use a vacuum cleaner to clear the dust inside and around the holes. If the inter-hole spacing
is too wide or too narrow, locate and drill holes again.
3. Slightly tighten the expansion bolt, and then put the expansion bolt assembly into the hole
vertically.
4. Use a rubber mallet to hammer the expansion bolt until the expansion tube is buried into
the hole.
5. Remove the M12x60 bolt, spring washer, and flat washer from each expansion bolt
assembly in sequence.
WARNING
After disassembling the expansion bolt assembly, ensure that the top of the expansion tube
is on the same level as the floor.
Place the level on the top plane of the base to check the base level, as shown in Figure
7-4. If the bubble is not in the middle of the level, adjust the base level through the adjusting
bolts.
Step 4 Test the insulation between the base and the expansion bolt.
1. Set the multimeter to the megohm position (MΩ).
2. Measure the resistance between the base and the four expansion bolts, as shown in Figure
7-5.
Figure 7-5 Measuring the resistance between the base and the expansion bolt
l If the resistance is less than five megohms, you can infer that the base is not insulated
from the floor. Go to Step 4.3.
l If the resistance is greater than or equal to five megohms, you can infer that the base is
insulated from the floor. End the test.
3. Dissemble the expansion bolt assembly, and check whether insulating washers are missed
or damaged.
l If insulating washers are missed or damaged, reinstall them, and then adjust the base
level.
l If no insulating washers are missed or damaged, check whether the multimeter is faulty
or whether the setting is correct.
----End
Context
Figure 7-6 shows the support for installing the ESD floor.
The support for installing the ESD floor on which the BTS3900 is installed is classified into two
types: support with fixed height and support with adjustable height. Table 7-1 lists the relations
between the two types of supports and the height of the ESD floor.
Table 7-1 Height of the support for installing the ESD floor
Type of the Support Height of the ESD Floor (Unit: mm)
Support with adjustable 120 at least; adjustable according to the height of the floor
height
NOTE
Height of the ESD floor refers to the spacing between the concrete floor and the upper surface of the ESD
floor.
Procedure
Step 1 Determine the installation position of the cabinet on the ESD floor by referring to Installing the
Cabinet on the Concrete Floor Step 1.
Step 2 Drill holes on the ESD floor.
1. Use a percussion drill with bit 16 to drill holes at the anchor points. The holes should
penetrate the ESD floor, as shown in Figure 7-7.
WARNING
Take proper safety measures to protect your eyes and respiratory tract against the dust
before drilling holes.
2. Use a vacuum cleaner to clear the dust inside and around the holes. If the inter-hole spacing
is too wide or too narrow, locate and drill holes again.
Step 3 Position the support.
1. Place the support under the ESD floor, and then use bolts to secure the ESD floor on the
support temporarily, as shown in Figure 7-8.
Figure 7-8 Positions of the access holes in the support and holes in the ESD floor
(1) Access holes (2) ESD floor (3) Mounting holes for the support
2. Mark the positions of the mounting holes on the concrete floor, as shown in Figure 7-9.
(1) Mounting holes for (2) Support for installing (3) Concrete floor (4) ESD floor
the support the ESD floor
3. Use a measuring tape to measure the inter-hole spacing, and ensure that the four holes serve
as the vertices of a rectangle.
Step 4 Drill holes at the anchor points on the concrete floor, and then install expansion bolt assemblies.
For details, see Installing the Cabinet on the Concrete Floor Step 2.
Step 5 Secure the support for installing the ESD floor.
Use M12x60 bolts, spring washers, and flat washers to secure the support for installing the ESD
floor on the concrete floor. Tighten the bolts until the fastening torque reaches 45 N·m. Figure
7-10 shows how to secure the support for installing the ESD floor.
Figure 7-10 Securing the supports for installing the ESD floor
Step 6 Remove the bolts that are used to temporarily secure the ESD floor on the support in Step 3.1.
Step 7 Refer to Installing the Cabinet on the Concrete Floor Step 3, Step 4.
----End
The BTS3900 cabinets can be flexibly installed. In different scenarios, a single cabinet can be
separately installed and two cabinets can be installed side-by-side or stacked.
Context
The cabinet door can be removed before the cabinet is installed for easy operations. When
removing the cabinet door, disconnect the equipotential cable from the lower part of the door,
and then rotate the spring pin 90° to the left and press the pin. Thus, the cabinet door can be
removed, as shown in Figure 8-1.
When installing the cabinet door, align the spring pin with the hole, rotate the pin to the right
until it is tightly pressed by the door, and then install the equipotential cable on the door, as
shown in Figure 8-2.
Procedure
Step 1 Lift the cabinet onto the base.
Step 2 Slide the cabinet along the base to ensure that the back of the cabinet is aligned with the back
of the base. Use a torque wrench to tighten the two M12x50 bolts in the front of the cabinet until
the fastening torque reaches 45 N·m, as shown in Figure 8-3.
CAUTION
Install the OT terminal in a correct way, as shown in Figure 8-4.
1. Use a PGND cable with a cross-sectional area of 25 mm2 to connect the ground point on
the -48 V cabinet to the external ground bar, as shown in Figure 8-5.
The procedure for grounding the 220 V cabinet is the same as that for grounding the -48 V
cabinet.
2. Use two PGND cables with a cross-sectional area of 25 mm2 to connect the ground point
on the +24 V cabinet to the external ground bar, as shown in Figure 8-6.
----End
Procedure
Step 1 Install a single cabinet by referring to 8.1 Installing a Single Cabinet Separately. Ensure that
the single cabinet is secure on the base.
Step 2 Remove the connecting pieces on the top of the cabinets, as shown in Figure 8-7.
Step 3 Install the two connecting pieces on the positions shown in Figure 8-8, and then tighten the
screws.
Step 4 Install the PGND cables (25 mm2) and equipotential cable (16 mm2).
1. Install the PGND cables and equipotential cable for the -48 V cabinet, as shown in Figure
8-9.
The procedures for installing the PGND cables and equipotential cable for the 220 V cabinet
and for the -48 V cabinet are the same.
Figure 8-9 Installing the PGND cables and equipotential cable for the -48 V cabinet
2. Install the PGND cable and equipotential cable for the +24 V cabinet, as shown in Figure
8-10.
Figure 8-10 Installing the PGND cables and equipotential cable for the +24 V cabinet
----End
Context
l The -48 V cabinet can be stacked.
l The +24 V cabinet cannot be stacked.
l Stacking 220 V cabinets are not recommended. If they have to be stacked, the cabinets can
bear the highest ambient temperature that is 5°C lower than normal.
Procedure
Step 1 Install a single cabinet by referring to 8.1 Installing a Single Cabinet Separately. Ensure that
the single cabinet is secure on the base.
Step 2 Remove the rubber screws and connecting pieces from the top of the lower cabinet, and then
install the installation blocks on the rear part of the cabinet top, as shown in Figure 8-11.
Step 3 Remove the cover plate from the top of the upper cabinet, as shown in Figure 8-12.
Step 4 Lift the upper cabinet onto the lower cabinet, slide the upper cabinet along the top of the lower
cabinet until the backs of two cabinets are aligned. Tighten the bolts to secure the cabinet, as
shown in Figure 8-13.
Step 5 Install the PGND cables (25 mm2) and equipotential cable (16 mm2) for the -48 V cabinet, as
shown in Figure 8-14.
NOTE
The procedure for installing the PGND cable and equipotential cable for the 220 V cabinet and for the -48
V cabinet are the same.
Figure 8-14 Installing the PGND cable and equipotential cable for the -48 V cabinet
----End
The mandatory modules in the cabinet are already installed. The optional modules can be
installed on site according to different field requirements.
9.1 Installing the GPS Surge Protector
This section describes the procedure and precautions for installing the GPS surge protector.
9.2 Installing the Optical-to-Electrical Conversion Module and Optical Module
This section describes the procedure and precautions for installing the optical-to-electrical
conversion module, optical module, and related cables.
Procedure
Step 1 Remove the connecting piece from the cabinet top, and then install the support for the GPS surge
protector in the original position of the connecting piece, as shown in Figure 9-1.
Figure 9-1 Installing the support for the GPS surge protector
Step 2 Link the SMA male connector of the GPS signal cable to the GPS surge protector on the USCU
and the N-type connector to the support for the GPS surge protector, as shown in Figure 9-2.
Step 3 Install the GPS surge protector to the support, and then connect cables, as shown in Figure
9-3.
Step 4 Route the cable by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 5 Attach labels to the installed cables. For details, see Labeling Signal Cables.
----End
Procedure
Step 1 Insert the optical-to-electrical conversion module into the FE/GE0 port on the UTRP.
Step 2 Connect one end of the FE/GE cable to the optical-to-electrical conversion module and the other
end to the FE0 port on the GTMU.
Step 3 Insert the optical module into the FE/GE1 port on the UTRP.
Step 4 Connect the FE/GE optical cable led from the cabinet to the optical module. Figure 9-4 shows
the cable connections.
Figure 9-4 Installing the optical-to-electrical conversion module and optical module
----End
The BTS3900 cabinet is delivered with boards installed, and the internal cables are already
installed. Therefore, only the external cables and cables for the optional modules need to be
installed on site.
l The PGND cables for the base station must be connected to the same ground bar.
l The PGND cables must be buried in the ground or routed indoors. They should not be
routed overhead before they are led into the equipment room.
l The exterior of the coaxial wire and shielding layer of the shielded cable must have proper
electrical contact with the metal surface of the connected equipment.
l The PGND cable and signal cable cannot be bound or entangled. A certain distance must
be reserved between them to prevent interference from each other.
l Fuses or switches cannot be installed on the PGND cables.
l Other devices cannot be used for the electrical connection of the PGND cables.
l All the metal parts in the housing of the equipment must be reliably connected to the ground
terminal.
l The E1 cable cannot cross the power cable, PGND cable, or RF cable when routed. If the
transmission cable is routed with the power cable, PGND cable, and RF cable in parallel,
the spacing between them must be greater than 30 mm.
l The E1 cables must be neatly and elegantly routed and securely bound with cable ties.
l Extra length of E1 cables must be reserved when they are curved.
l Do not stretch the optical cables, step on the cables, or place heavy objects on the cables.
Keep the cables away from sharp objects to prevent damage to the fibers.
l When the optical cables are routed, the extra length of the cables must be coiled around
special devices, such as a fiber coiler.
l When coiling the optical cables, apply the strength evenly. Do not bend the cables with
force, thus preventing any damage to the fibers.
l Cover the optical connectors that are not in use with dustproof caps.
(1) PGND cable (2) Jumper on the left (3) Input power cable
(1) PGND cable (2) Jumper on the left (3) Input power cable
(4) Jumpers in the upper cabinet (5) Jumper on the right (6) Transmission cable
10.3.1 Installing the Input Power Cable for the -48 V Cabinet
The input power cable for the -48 V cabinet connects the wiring terminals for the input power
cable on the DCDU-01 to the external power equipment. The cable feeds -48 V DC power into
the BTS3900 cabinet.
10.3.2 Installing the Input Power Cable for the +24 V Cabinet
The input power cable for the +24 V cabinet connects the power system (DC/DC) to the external
power equipment. The cable feeds +24 V DC power into the BTS3900 cabinet.
10.3.3 Installing the Input Power Cable for the 220 V Cabinet
The input power cable for the 220 V cabinet feeds external AC power into the BTS3900 cabinet.
10.3.1 Installing the Input Power Cable for the -48 V Cabinet
The input power cable for the -48 V cabinet connects the wiring terminals for the input power
cable on the DCDU-01 to the external power equipment. The cable feeds -48 V DC power into
the BTS3900 cabinet.
Context
The cross-section area of the -48 V power cable is 16 mm2.
Procedure
Step 1 Measure the distance between the DCDU-01 and the external power equipment according to the
actual cable route, and then prepare power cables of a proper length.
NOTE
Reserve an extra length of 300 mm when preparing the input power cables. Thus, the power cables can be
led out from the upper cabinet if two cabinets are stacked in the case of capacity expansion.
Step 2 Make an M6 OT terminal at each end of the power cable. For details, see Assembling the OT
Terminal and the Power Cable.
Step 3 Remove the protecting hood from the terminal block of the DCDU-01.
Step 4 Connect the blue cable to the wiring terminal labeled NEG(-) and black cable to the wiring
terminal labeled RTN(+).
NOTE
When two -48 V cabinets are stacked, the external power equipment supplies power to the upper and lower
cabinets.
Step 7 Route the cable by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 8 Attach labels to the installed cables. For details, see Attaching the Cable-Tying Label.
----End
10.3.2 Installing the Input Power Cable for the +24 V Cabinet
The input power cable for the +24 V cabinet connects the power system (DC/DC) to the external
power equipment. The cable feeds +24 V DC power into the BTS3900 cabinet.
Context
The cross-section area of the +24 V power cable is 25 mm2.
Procedure
Step 1 Measure the distance between the wiring terminal of the power subrack (DC/DC) and the
external power equipment according to the actual cable route, and then prepare power cables of
a proper length.
NOTE
Reserve an extra length of 300 mm when preparing the input power cables. Thus, the power cables can be
led out from the upper cabinet if two cabinets are stacked in the case of capacity expansion.
Step 2 Make an M6 OT terminal at each end of the power cable. For details, see Assembling the OT
Terminal and the Power Cable.
Step 3 Use a Phillips screwdriver to remove the screws from the protecting hood for the wiring terminals
of the power subrack (DC/DC), and then remove the protecting hood.
Step 4 Connect the two red cables to the wiring terminals labeled + and two black cables to the wiring
terminals labeled -.
Step 6 Install the protecting hood, and then use a screwdriver to tighten the screws. Figure 10-4 shows
the installation procedure.
Step 7 Route the cable by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 8 Attach labels to the installed cables. For details, see Attaching the Cable-Tying Label.
----End
10.3.3 Installing the Input Power Cable for the 220 V Cabinet
The input power cable for the 220 V cabinet feeds external AC power into the BTS3900 cabinet.
Context
l The 220 V cabinet supports three types of AC power input: 220 V AC single-phase, 220
V AC three-phase, and 110 V AC dual-live-wire.
l The cross-section area of the 220 V AC single-phase power cable is 6 mm2. The cross-
section area of the 220 V AC three-phase power cable is 2.5 mm2. The cross-section area
of the 110 V dual-live-wire power cable is 6 mm2.
Procedure
Step 1 Measure the distance between the wiring terminal of the power subrack (AC/DC) and the
external power equipment according to the actual cable route, and then prepare power cables of
a proper length.
NOTE
Reserve an extra length of 300 mm when preparing the input power cables. Thus, the power cables can be
led out from the upper cabinet if two cabinets are stacked in the case of capacity expansion.
Step 2 Make an M6 OT terminal at each end of the power cable. For details, see Assembling the OT
Terminal and the Power Cable.
DANGER
When adding OT terminals to the power cable, do not expose the metal wires, as shown in
Figure 10-5.
2. Install the 220 V AC three-phase input power cable. That is, remove the short-circuiting
cable from the wiring terminals of the power subrack (AC/DC), connect the three live wires
to the wiring terminals labeled L1, L2, and L3, and then connect the neutral wire to the
wiring terminal labeled N1, as shown in Figure 10-7.
3. Install the 110 V AC input power cable. That is, connect the live wire to the wiring terminal
labeled L1 in the power subrack (AC/DC) and neutral wire to the wiring terminal labeled
N1, as shown in Figure 10-8.
Step 4 Connect the other end of the power cable to the external power equipment.
Step 6 Route the cable by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 7 Attach labels to the installed cables. For details, see Attaching the Cable-Tying Label.
----End
Prerequisite
Ensure that both ends of the E1 cable are disconnected. Then, weld connectors to the bare wires
at one end of the E1 cable all at once.
Procedure
Step 1 Connect the E1/T1 cable to the port on the corresponding board.
If... Then...
The co-transmission mode is Link the DB26 male connector of the E1/T1 cable to the port
used labeled E1/T1 on the GTMU, and then tighten the screws, as
shown in Figure 10-9.
The separate transmission Link the DB26 male connectors of two E1/T1 cables to the
mode is used ports labeled E1/T1 on the GTMU and on the WMPT
respectively, as shown in Figure 10-10.
Step 2 Route the E1/T1 cable along the cable trough on the right of the cabinet, and then use cable ties
to bind the cable.
Step 3 Route the cable by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 4 Attach labels to the installed cables by referring to Attaching the L-Shaped Label.
----End
Procedure
Step 1 Connect the FE/GE cables or FE/GE optical cables to the port on the corresponding board.
If... Then...
The co-transmission mode l Connect the FE/GE cable to the port labeled FE0 on the
over the electrical port is used WMPT.
l Connect the two ends of the interconnection cable
between the FE optical ports to the ports labeled FE1 on
the GTMU and on the WMPT respectively, as shown in
Figure 10-11.
The co-transmission mode l Connect the FE/GE optical cable to the port labeled FE1
over the optical port is used on the WMPT.
l Connect the two ends of the interconnection cable
between the FE electrical ports to the ports labeled FE0
on the GTMU and on the WMPT respectively, as shown
in Figure 10-11.
NOTE
The FE/GE optical cable should be wrapped a winding pipe, as
shown in Figure 10-12.
If... Then...
The separate transmission Connect one FE/GE cable to the port labeled FE0 on the
mode is used WMPT and another FE/GE cable to the port labeled FE0 on
the GTMU, as shown in Figure 10-13.
Step 2 Route the FE/GE cable along the cable trough on the right of the cabinet, and then use cable ties
to bind the cable.
Step 3 Route the cables by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 4 Attach labels to the installed cables by referring to Attaching the L-Shaped Label.
----End
Procedure
Step 1 Install the CPRI cables between the cabinets installed side-by-side.
1. Install the cabinets side-by-side by referring to 8.2 Installing Two Cabinets Side-by-
Side.
2. The main cabinet is placed on the left, and the extension cabinet is placed on the right.
Figure 10-14 shows the CPRI cable connections between two cabinets.
Figure 10-14 CPRI cable connections between two cabinets installed side-by-side
Step 3 Route cables by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 4 Attach labels to the installed cables by referring to Attaching the L-Shaped Label.
----End
Procedure
Step 1 Lead the RF jumpers into the cabinet through the cable holes, and the route the jumpers by
referring to 10.2 Cable Routing Principles.
NOTE
Reserve an extra length of 300 mm when preparing the RF jumper according to the actual cable route. Thus, the
jumper can be led out from the upper cabinet if two cabinets are stacked during capacity expansion. For details
about how to add a DIN connector to the RF jumper, see Assembling the 7/16 Straight Male Coaxial DIN
Connector and the 1/2'' Feeder.
Step 2 Link the DIN connectors of the RF jumpers to the ports labeled ANT on the panels of the RFUs.
Figure 10-16 shows the RF jumper connections in a single cabinet, and Figure 10-17 shows
the RF jumper connections in stacked cabinets.
Step 3 Use a torque wrench to tighten the DIN connector until the fastening torque reaches 25 N·m to
35 N·m.
Step 4 Attach color rings by referring to Color Ring for the Antenna System and Attaching the Color
Ring.
NOTE
Check and ensure the secure connections of the Inter-RFU RF signal cables, which are installed inside the
cabinets based on different configurations of the cabinets before delivery.
----End
Procedure
Step 1 Insert the RJ-45 connector at one end of the monitoring signal cable for the EMU into the port
labeled MON1 on the UPEU in the BBU3900.
Step 2 Link the DB9 male connector at the other end of the monitoring signal cable for the EMU to the
port labeled RS485 on the EMU, and then tighten the screws.
Step 3 Route the cable by referring to 10.1 Cabling Requirements and 10.2 Cable Routing
Principles.
Step 4 Attach labels to the installed cables by referring to Attaching the L-Shaped Label.
----End
11 Installation Checklist
After the cabinets and devices are all installed, you need to check the installation items,
installation environment, and cable-related items.
2 All the bolts, especially those for electrical connections, are tightened. Both the
spring washer and the flat washer are installed in a correct sequence.
6 All labels, tags, and nameplates are correct, legible, and complete.
2 No tapes, tails of cable ties, paper, or packing bags are left inside or outside the
cabinet.
3 All the items around the cabinet are neat, clean, and intact.
2 The redundant part of the power cable or PGND cable is stripped off rather than
coiled.
3 The lugs at both ends of the power cable or PGND cable are securely soldered or
crimped.
4 The bare wires and the terminal handles at the wiring terminals are coated with
heat-shrinkable tubes.
5 The flat washer and the spring washer are well mounted on all OT terminals.
6 All cables are connected securely and reliably. Pay special attention to the cable
connections at the bottom of the cabinet.
7 The cables are neatly and tightly bound. The cable ties are evenly spaced and face
the same direction.
8 The power cable, PGND cable, feeder, optical cable and the E1/T1/FE signal cable
are bound separately with a spacing of larger than 30 mm.
9 The cable layout facilitates maintenance and future capacity expansion. And the
bending radius of the cables meet the requirements.
11 The extra length of each indoor cable tie is cut, and the cut surface is smooth
without sharp edges. An extra length of 3 mm to 5 mm is resereved for each
outdoor cable tie.
13 The connectors of the RF cables are fixed in position to avoid false connection
that may cause an abnormal voltage standing wave ratio (VSWR).
Before the cabinets are powered on and work, you need to check the power-on status of the
cabinets.
Figure 12-1 shows the power-on check procedure.
NOTE
For details about how to check the DIP switches on the boards, see the BTS3900 Hardware Description.
The Electronic Serial Number (ESN) is unique to a Network Element (NE) for identification.
The ESN is used during the commissioning of the base station.
Procedure
Step 1 Record the ESN shown on the label attached to the mounting ear of the BBU. Figure 13-1 shows
the position of the ESN.
Step 2 Report the ESN to the engineer for the commissioning of the base station.
Step 3 Close the cabinet door, and lock it.
----End