Sorik Marapi

Geothermal Project
Transmission Lines

Subject : GROUNDING RESISTANCE MEASUREMENT

Project : Transmission Line TA . Location : Mandailing Natal, Sumatera Utara

Client : Huadong Engineering Corporate Reference Drawing : INSM-66TL-013-021-1

No. Description

I. Preliminary:
- This measurement is carried out to measure the system grounding resistance. Maximum of
resistance the allowable is : 5 (five) ohm
- The timing of measuring system grounding in the event of not rain

II. Tools use :


1. Kyoritsu Digital Earth Testing Model 4105A

III. Method of Measurement


Measurement were made to the area around the base station, on both side of the location and the width
of the cable minimum 15 M and maksimum 20 M from point of to be measured.
IV Measurement :
No. Point the measurement Value() Remarks
1. Kwh Meter Grounding
2. Leg Tower A
3. Leg Tower C
IV. Conclusion
Based on the measurement of grounding data system installed it is concluded that
Grounding System is Accepted Grounding System is Not Accepted

Remarks :

CONTRACTOR OWNER
Print
Name

Signature

Date
Subcontractor Signature : Date :

Powerchina Huadong Signature : Date :

Employer Signature : Date :