3) Adequate illumination.
4) Adequate fire alarms, fire protection system and fire fighting facilities.
6) Design of floor shall be such that spilled oil / leakage oil, if any is collected
into drain pit and from there, arrangement shall be provided for collection and
disposal of leakage oil into oil barrels for reclamation purpose.
7) Emergency doors.
II Whatever Servo / Proportional Valves are used in the system, supplier shall
supply Servo Valve flushing facility and test kits for Servo and Proportional
Valves.
III For hydraulic systems with conventional valves, the supply voltage to various
controls shall be 24 V DC.
V Mineral oil shall be used in hydraulic systems until otherwise agreed upon by
BSP.
VI All the pipes and fittings used in hydraulic systems of critical production units
shall be stainless steel until otherwise agreed up on by BSP.
VII Filters shall be provided for continuous removal of contaminants from the
hydraulic fluid, which are likely to cause malfunction of pumps, valves and
actuators and maintain desired cleanliness level of hydraulic fluid. Adequate
filtration shall be provided for each system considering the ingress rate of
contaminants in each applications.
VIII All the pressure line, return line and circulation filters shall be of absolute filtration
design with B(x) ratio greater than or equal to 200. Total delta p across filters
shall not exceed 0.5 bar with filter element in clean condition. (Total p means
pressure drop across clean filter element plus pressure drop filter housing).
IX All the hydraulic system shall be provided with dedicated oil purifier. The oil
purifier (vacuum dehydrator type) shall be capable to remove undissolved as well
as dissolved water and solid containments from the hydraulic oil of the system in
a reasonable time to the desired level.
X Portable oil transfer unit with built in filtration facility shall be provided for transfer
ol from barrels to oil reservoir of the system.
XI Calibration and Testing Facilities for the Hydraulic Components installed in the
hydraulic systems shall be provided as detailed below.
A) Power pack for Test Rigs of conventional control valves, pumps, motors and
hydraulic cylinders.
E) Test rig and Power pack for Servo and Proportional valves (if Servo /
Proportional valves are used / installed in the hydraulic systems).
The scope of supply shall also include all components and accessories as
required to render the system complete in all respect.
The Test Rigs shall have facilities for on-line acquisition of test parameters of the
components while testing and shall be transferred to the main computer for
records and references.
XII Plate Type Heat Exchangers of adequate capacity shall be provided in the
Hydraulic Systems.
XIII The hydraulic system shall have facility for on-line Pressure measurement in P,
T, A and B lines at suitable locations of the circuit. Necessary instruments,
conditions monitoring system and facilities shall be provided by the supplier.
Hydraulic pipe work shall be assembled, pressure tested, pickled, flushed and
commissioned as per piping instructions given by the system designer /
consultant.
Provision of pipe line pickling and flushing facility shall be in the scope of work
(provision of separate tank, pumps filters elements, pickling and flushing fluids
shall be in the suppliers scope).
Supply of minimum 50 nos. of spare filter elements of each type along with the
hydraulic system at the time of Erection, Testing and Commissioning shall be in
the suppliers scope of supply.
Oil cleanliness shall be checked during commissioning and facilities for checking
and monitoring oil cleanliness shall be in the bidders scope of supply.
XVI All pipelines shall be of seamless type clamped with polypropylene heavy series
clamps. However, in the hot zone heavy series aluminum clamps shall be used.
XVII All hydraulic pipe lines shall be painted as per the standard color mode.