how to calculate cable size, olr rating, contactor rating

and mccb rating,to below given details three phase motor

75 kw,415 v,.85 pf,50 hz?

Answers were Sorted based on User's Feedback

motor rating 75kw,so it taken full load p=1.732*v*I*cosfy

i= p/1.732*v*cosfy

=123 amp. so we requared a cable to carry 123 amp

contonious rating. so require to run motor in star delta

starter . in star delta connection load current is 58% of

line current. we require 58% of 123 amp carring capasity

cable.it is around 71 amp.generly copper cable taking 4

times current of cable rating and alluminium cable taken

1.5 times of cable ratting .so for 71 amp carring alu.

cable 50mm2 suffisent but due to high starting curent its

take 70 mm2 cable ib best.

its overload relay ratting is in range to 71 amp. it to be

60-80 amp,and mccb rating is 2.5 times of full load =200

amp

is best.
Is This Answer Correct ? 47 Yes 32 No

Answer / pvr.parthasarathi

75 Kw motor takes 134 amps full load current. But for

selecting its Cable, Contactor, OLR and MCCB, we have to

consider many other factors such as need of its operation.

Place of the Motor Control Centre and possibility of laying

the cable Wheter inside the duct, underground or in the

air. For selection of the Contactor enclosure of the

panel, its environments etc are to be taken into

consideration. So giving answer at a stretch basing on

some thumb rule is not technically qualified.

Other particulars are required.

Is This Answer Correct ? 17 Yes 4 No


Answer / mohamed-mohamed

i know> but my nglish not well> because of that i can not answer

Is This Answer Correct ? 1 Yes 1 No

Answer / v.raguvaran

THE MOTOR AMP IS 130AMP.THE CABLE(USE COPPER ) SIZE SHOULD BE 45sq.mm (delta
connection),35sq.mm(star delta)

OLR RATING IS (125-135) BUT STANDARD SIZE IS (130-175)ABB

CONTACTOR RATING IS 200A(DELTA),100(MAIN)-100(DELTA)-50(STAR)

MCCB RATING IS 250A

Is This Answer Correct ? 0 Yes 0 No


Answer / rsbangra

motor rating 75kw,so it taken full load p=1.732*v*I*cosfy

i= p/1.732*v*cosfy

=123 amp. so we requared a cable to carry 123 amp

contonious rating. so require to run motor in star delta

starter . in star delta connection load current is 58% of

line current. we require 58% of 123 amp carring capasity

cable.it is around 71 amp.generly copper cable taking 4

times current of cable rating and alluminium cable taken

1.5 times of cable ratting .so for 71 amp carring alu.

cable 50mm2 suffisent but due to high starting curent its

take 70 mm2 cable ib best.

its overload relay ratting is in range to 71 amp. it to be

60-80 amp,and mccb rating is 2.5 times of full load =300amp

is best.

Is This Answer Correct ? 47 Yes 55 No


Post New Answer

More Electrical Engineering Interview Questions

how to select overload-relay for perticular motor 1.for D.O.L. starter 2. for Star-delta starter ????

0 Answers

what will happen if any motor runs long time with star connection in400vA.C. system

5 Answers

which relay is used for both detection & correction?(there is only one relay)

2 Answers
Can anyone tell me how a 12v battery is transformed to

20,000v at the spark plug

6 Answers

why transformer not work in dc

16 Answers

please tell me when we start motor without load in star or delta connection whose current above
condition,pl write formula

0 Answers Foxconn,

why moisture formation found in XLPE Armoured cable outer sheath

0 Answers

sir , what happen if we decrease ( approx 3 inch ) the lenth of shaft in 110KW Induction , three phase
motor. actually a 110KW motor is couppled with star couplling to 120TR compressor. When we doing
maintenance in compressor it is required to skid the motor backword and resulting dis- alightnment . so
we want to change the tyre coupling in place of existing coupling. so it is required to cut off the rotor
aprox 3 inch form driving side.

2 Answers

What is the basic principal of Diesel genarator?

3 Answers MRF, Juniper Networks,

BRIEFLY EXPLAIN THE STORAGE CLASSES AND THEIR TYPES IN C

0 Answers

why open circuit test is conducted on hv side and short circuit test is conducted on lv side of a
transformer ?what is the reason for it ?

3 Answers NTPC, HCL,

What is phase in electrical engineering?

5 Answers

Você também pode gostar