Project Amanuel Hospital Date Dec-05

Description Seismic Analysis of Structure By


Chkd

FLOOR LOADS
ROOF FLOOR(5TH FLOOR)
WR 1694 KN
X - BAR 5.60 m
Y - BAR 8.75 m
FOURTH FLOOR
W4 4076
X - BAR 12.36
Y - BAR 7.70
THIRD FLOOR
W3 4151
X - BAR 12.70
Y - BAR 7.41 TOTAL LOAD FOR
SECOND FLOOR SEISMIC BASE SHEAR
W2 4151 = ### KN
X - BAR 12.70
Y - BAR 7.41 27873 KN
FIRST FLOOR
W1 4151
X - BAR 12.70
Y - BAR 7.41
GROUND FLOOR
Wg 4151
X - BAR 12.70
Y - BAR 7.41
FIRST BASEMENT FLOOR
Wg 4151
X - BAR 12.70
Y - BAR 7.41
SECOND BASEMENT FLOOR
Wg 1348
X - BAR 12.36
Y - BAR 7.39

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

CALCULATE SEISMIC BASE SHEAR

Fb =
Sd(T1)W [EBCS 8 - 2.3.3.2.2]

W= 27873.00 KN
Sd(T1) = a b g [EBCS 8 - 1.4.2.2]
a = a oI [EBCS 8 - 1.4.2.2]
I = 1.4 [EBCS 8 - TABLE 2.4]
ao= 0.05 [EBCS 8 - TABLE 1.1]

a = 0.07

b = 1.2S <= 2.5 [EBCS 8 - 1.4.2.2]


T2/3
S= 1.2 [EBCS 8 - TABLE 1.2]
C
T= 1H3/4
[EBCS 8 - 2.3.3.2.2]
H= 24.9 m
C1 = 0.075

T = 0.84

b = 1.62 use 1.62

g = goKDKRKw <= 0.7 [EBCS 8 - 3.3.2.1]


go = 0.2
KD = 1
KR = 1
Kw = 1

g = 0.2 use 0.2

Sd(T1) = 0.02271695

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

Fb = 633.19 KN

* For Distribution of base shear to upper floor in accordance with:- EBCS 8, 2.3.3.2.3

Fb =
Fb + 0.07T1 Fb Equation 2.6

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

DISTRIBUTE BASE SHEAR TO THE FLOORS

ROOF(5th - FLOOR) 24.9

( F b ) W i hi
t
Fi = n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 1694
hi = 24.9
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
Wr = 1694
hr = 24.90

n
385135.30
W j h j=
j=1

= 102.34 KN

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

DISTRIBUTE BASE SHEAR TO THE FLOORS

4th - FLOOR 21.7

( F b ) W i hi
t
Fi = n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 4076
hi = 21.7
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
W5 = 1694
h5 = 24.90

n
385135.30
W j h j=
j=1

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

= 136.91 KN

DISTRIBUTE BASE SHEAR TO THE FLOORS

3rd - FLOOR 18.5

( F bt ) W i hi
Fi = n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 4151
hi = 18.5
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
W5 = 1694
h5 = 24.90

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

n
385135.30
W j h j=
j=1

= 118.87 KN

DISTRIBUTE BASE SHEAR TO THE FLOORS

2nd - FLOOR 15.3

( F bt ) W i hi
Fi = n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 4151
hi = 15.3
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

h4 = 21.70
W5 = 1694
h5 = 24.90

n
385135.30
W j h j=
j=1

= 98.30 KN

DISTRIBUTE BASE SHEAR TO THE FLOORS

1st - FLOOR 12.1

( F bt ) W i hi
Fi = n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 4151
hi = 12.1
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
W5 = 1694
h5 = 24.90

n
385135.30
W j h j=
j=1

= 77.74 KN

DISTRIBUTE BASE SHEAR TO THE FLOORS

Ground - FLOOR 8.9

( F b ) W i hi
t
Fi = n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 4151
hi = 8.9
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
W5 = 1694
h5 = 24.90

n
385135.30
W j h j=
j=1

= 57.18 KN

DISTRIBUTE BASE SHEAR TO THE FLOORS

1st basement - FLOOR 5.7

Fi =
( F bt ) W i hi
n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 4151
hi = 5.7
W2ba = 1348
h2ba = 2.50
W1 ba= 4151
h1ba = 5.70
Wg = 4151

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
W5 = 1694
h5 = 24.90

n
385135.30
W j h j=
j=1

= 36.62 KN

DISTRIBUTE BASE SHEAR TO THE FLOORS

2nd basement - FLOOR 2.5

Fi =
( F bt ) W i hi
n
W j hj
j=1

Ft =0. 07 T 1 Fb
T 1= 0.84 sec
Fb= 633.19 KN

= 37.05

W i= 1348
hi = 2.5
W2ba = 1348
h2ba = 2.50

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Project Amanuel Hospital Date Dec-05
Description Seismic Analysis of Structure By
Chkd

W1 ba= 4151
h1ba = 5.70
Wg = 4151
hg = 8.90
W1 = 4151
h1 = 12.10
W2 = 4151
h2 = 15.30
W3 = 4151
h3 = 18.50
W4 = 4076
h4 = 21.70
W5 = 1694
h5 = 24.90

n
385135.30
W j h j= 385135.30
j=1

= 5.22 KN

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
18.65 12.82
0.9325
0.641
ROOF FLOOR X Y
WR 1268 KN
X - BAR 7.54 m 6.6075 8.4725
Y - BAR 4.56 m 3.919 5.201
FOURTH FLOOR
W4 1462
X - BAR 7.58 6.6475 8.5125
Y - BAR 4.24 3.599 4.881
THIRD FLOOR
W3 1462
X - BAR 7.58 6.6475 8.5125
Y - BAR 4.24 3.599 4.881
SECOND FLOOR
W2 1462
X - BAR 7.58 6.6475 8.5125
Y - BAR 4.24 3.599 4.881
FIRST FLOOR
W1 1462
X - BAR 7.58 6.6475 8.5125
Y - BAR 4.24 3.599 4.881
GROUND FLOOR
Wg 1266
X - BAR 8.17 7.2375 9.1025
Y - BAR 3.37 2.729 4.011