BATAAN NATIONAL HIGH SCHOOL

City of Balanga

SENIOR HIGH SCHOOL INDUSTRIAL ARTS

SHIELDED METAL ARC WELDING (SMAW) NC II

JOB PLAN NO. 1

SINGLE BUTT JOINT IN HORIZONTAL POSITION (2G)

Name: Section:

Date Began: Date Finished:

I.Objectives:

To develop our welding skills in shielded metal arc welding and enhance the straightness of bead.

II. Equipment Tools and Materials:

DC inverter/ DC Combination 200 AMP Welding Machine


Chipping Hammer
Steel Brush
Welding Tongs
PPE (Personal Protective Equipment)
III. Plan / Illustration: (Separate Sheet)

IV. Procedure:

1. Grind the edge of square bar 1/8 per edge.


2. Tack the square bar with 2.5mm gap.
3. Tack the square bar horizontal for root pass.
4. Start welding at left (If left handed start at right) use E7018 or E6010.
5. Chip and brush the weld.
6. When the weld is good, then fill the remaining space (Hotpass).
7. Complete hot pass or fill the space.
8. Chip and clean the finished weld.
V. Self Checked:

MARKING TABLE

Criteria Marks Subtracted


1.Straightness
2.Width of Bead
3.Height of Bead
4. Ripple
5. Plate Alignment

Total Mark Subtracted

Final Point:_________

Prepared by:

_______________