CLASSES DE TREM TIPO EM PONTES
DETERMINAO DE CARGAS NORMAIS NOS PILARES DE
PONTES SOB INFLUENCIA DO TREM TIPO
PARA O CLCULO DE PLACAS, VIGAS E TRANSVERSINAS, JUNTO S BORDAS DO
ESTRADO, OBRIGATRIO ENCOSTAR A RODA AO GUARDA-RODAS.
EX.01: DETERMINE OS COEFICIENTES Y1,Y2,Y3,Y4,Y5 E Y6 PARA
CARREGAMENTO MVEL TREM TIPO 30
0,50 2,00 0,50
Y1=1,220
Y2=1,146
Y3=1,108
Y4=1,000
Y5=0,960
Y6=0,923
Eixo
do
pilar
y6 12,425m
y5 12,925m
13,45m
y3 y4
14,925m
y2
15,425m
y1
1 16,425m
Y1 = Y2 = Y3 = Y4 = Y5 = Y6
16,425 15,425 14,925 13,45 12,925 12,425
CARGA DE EIXO CARGA LATERAL
R+=Qe*(y1+y2+y3)+q*(y1*x/2)
Qe tf Qe tf Qe tf
R-=Qe*(y6+y7+y8)+q*(y8*x/2)
q dist. tfm
DETERMINAO DAS REAES DE APOIO PARA TREM TIPO 30
Carga de eixo= Qe=TT.y3+TT.y5 =
5x1,065+5x0,957 =10,11tf
1,0 Carga lateral= ql =0,5(rea)+0,3(rea) =
Y1 = Y2 = Y3 = Y4 = Y5 = Y6 0,5(17,2x0,929/2)+0,3(1,135+1,092)/2x0,8=4,26tfm
21,0 20,20 19,70 18,50 17,70 17,20 Carga de frente =qf=0,5(rea) =
0,5(1,092+0,929)x3/2=1,51tfm
Trem Tipo Homogeneizado=Qe-(qf-ql).2=
10,11-(1,51- 4,26)x2 = 15,61tf
Coef. Impacto =1,4-0,007. L da Ponte =
1,4-0,007x75,0 = 0,875
Correo
Qe = 15,61 x 0,875 = 13,66tf
qdist = 1,51 x 0,875 = 1,32tfm
(17,70-0,50)
(19,70-2,0)
(21,00-1,10-0,20-0,95-0,25) Y1 = 1,333
(21,00-1,10-0,20) Y2 = 1,300
(21,00-1,10-0,20+0,50) Y3 = 1,266
(1,10+0,20+0,95+0,50+9,00+9,0+0,25) Y4 = 1,000
15,00m 13,66tf 13,66tf 13,66tf
Y5 = 0,000
Y8
13,50m
Y7 Y6 = 0,266
12,00m
Y6
Y7 = 0,300 1,32tfm
0,00m
Y1=1,152
7,75
Y2=1,106
8,25
10,25 Y3=1,000
Y4=###
10,75
Y5=0,106
11,65 Y6=0,152
R(+)=76,773tf
R(- ) =3,09tf
10,00m 65,50m 10,00m
Y3
Y1 Y2
DETERMINAO DAS REAES DE APOIO PARA TREM TIPO 45
Carga de eixo= Qe=TT.y3+TT.y5 =
. 7,5x1,065+7,5x0,957 =15,165tf
Carga lateral= ql =0,3(rea)+0,5(rea) =
0,3(1,135+1,092)0,80/2 + 0,5 (0,929x17,2)/2= 4,26tf
Carga de frente =qf=0,5(rea) =
0,5( 1,092+0,929) 3 / 2 = 1,52tfm
Trem Tipo Homogeneizado=Qe-(qf-ql).2 =
15,165-(1,52-4,26)2 = 20,63tf
Coef. Impacto =1,4-0,007. 75,0 = 0,875
Correo
Qe = 18,06tf
qdist =1,33tfm
Y3 = 1,266
Y4 = 1,000
1,33tfm
1
Y5 = 0,000
CAR.LONGIT.
Y1 =Y2 = Y3 = Y4 = Y5 = Y6 = Y7 = Y8 Y8 Y6 = 0,266
60,0 58,5 57,0 45,0 ## 12,0 13,5 15,0 Y6 Y7 Y7 = 0,300
Y8 = 0,333
15,00m R+ =....... 45,00m R- =....... Y5 15,00m
R+=Qe*(y1+y2+y3)+q*(y1*x/2)
Y4 R+=18,06(1,33+1,30+1,266)+1,33(1,333*60/2)
Y3
R+= 123,48tf
Y2
R-=Qe*(y6+y7+y8)+q*(y8*x/2)
Y1
R-=18,06(0,266+0,300+0,333)+1,33(0,333*15/2)
R-= 19,57tf
EX.01 Determine o carregamento Carga de eixo= Qe=TT.y3+TT.y5
Qe= 5,0 * 1,160 + 5,0 * 0,918 = 10,390tf
mvel trem tipo 30 , vo 60,00m Carga lateral= ql =0,5(rea)+0,3(rea)
1 ql=0,5.(0,857.7,075)/2+0,3.(1,330+1,221)/2.0,90=1,881tfm
Y1 = Y2 = Y3 = Y4 = Y5 = Y6 Carga de frente tras =qf=0,5(rea)
10,975 10,075 9,575 8,250 7,575 7,075 qft= 0,5*[(1,221+0,857)/2]*3= 1,558tfm
Trem Tipo Homogeneizado=Qe-(qf-ql).2
Y1= 1,330 TTH =10,390 ( 1,558 1,881)*2 = 11,036tf
Y2= 1,221 Coef. Impacto =1,4-0,007.comp. da Ponte
CI = = 1,4 0,007* 60 = 0,98
Y3= 1,160
Y4= 1,000 Correo Qe.= Coef.Imp.* TTH =
Y5= 0,918 Qe.=0,98*11,036=10,81tf
Y6= 0,857 10,81tf 10,81tf
Qdist = Coef.Imp.* qft
10,81tf
qdist.= 0,98 *1,558 =1,526tfm
Eixo
1,526tfm do
pilar
7,075
7,575
8,250
9,575
10,075
10,975
EX:02 Determine os coeficientes do carregamento trem tipo 45 ,
vo 89,50m.
Y1 = Y2 = Y3 = Y4 = 1Y5 = Y6
9,85 9,60 9,10 7,30 7,10 6,60
Y1= 1,3493
Y2= 1,3150
Y3= 1,2465
Y4= 1,000
Y5= 0,9726
Y6= 0,9041
Eixo
do
pilar
7,10
7,30
9,10
9,60
9,85
EX.02 Determine o carregamento Carga de eixo= Qe=TT.y3+TT.y5
trem tipo 45 Qe= 7,5*1,11+7,5*0,960 = 15,525tf
Carga lateral= ql =0,5(rea)+0,3(rea)
vo 80,00m ql =0,5*(0,92*12,425)/2 +0,3*[(1,22+1,14)*1,00]/2=3,23TF
Carga de frente =qf=0,5(rea)
qf= 0,5*[(1,14+0,920)*(15,425-12,425)]/2 = 1,545tf
Trem Tipo Homogeneizado=Qe-(qf-ql).2
TTH =15,525 ( 1,545 3,23)*2 = 18,803tf
Coeficiente Impacto =1,4-0,007.comp. da Ponte
Y1=1,22 CI = = 1,4 0,007* 80,00 = 0,84
Y2=1,14 Correo
Qe. = CI* TTH =
Y3=1,11 Qe.= 0,84*18,803=15,79tf
Y4=1,00
Y5=0,96 qdist. = CI * qft
Y6=0,92 qdist = 0,84*1,545 =1,298tfm
Eixo
do
pilar
12,925
13,450
14,925
15,425
16,425
Carga de eixo= Qe=TT.y3+TT.y5 Qe=14,367tf
Carga lateral= ql =0,5(rea)+0,3(rea) ql=2,198tfm
tipo 45 Carga de frente =qf=0,5(rea) qf=1,436tfm
Trem Tipo Homogeneizado=Qe-(qf-ql).2 TT =15,896
Coeficiente Impacto =1,4-0,007.comp. da Ponte
CI = = 1,4 0,007* 87 = 0,791
Correo
Qe. = CI* TTH = Qe.=12,569 tf
qdist. = CI * qft qdist =1,135 tfm
3x 12,569 tf
1,135tfm
Eixo
do
pilar
9,275
9,775 Y1=1,167
11,250 Y2=1,091
Y3=1,047
11,775 Y4=1,00
Y5=0,869
12,275 Y6=0,824
13,125
EX:02 Determine os coeficientes do carregamento trem tipo 45 ,
vo 89,50m.
1
Y1 = Y2 = Y3 = Y4 = Y5
..... ..... ..... ...... ....
Y1=
Y2=
Y3=
Y4=
Y5=
Eixo
do
pilar
EX. 03Determine o carregamento Carga de eixo= Qe=TT.y3+TT.y5
Qe= 4,0*1,065+4,0*0,957 = 8,088tf
trem tipo 12 , vo 25,00m Carga lateral= ql =0,5(rea)+0,3(rea)
ql =0,5*(0,929*17,20)/2
+0,3*[(1,135+1,092)*0,80]/2=4,262tf
Y1=1,135 Carga de frente =qf=0,5(rea)
Y2=1,092
qf= 0,5*[(1,092+0,929)*(20,20-17,20)]/2 = 1,516tf
Y3=1,065
Trem Tipo Homogeneizado=Qe-(qf-ql).2
Y4= 1,000
Y5=0,957 TTH =8,088 ( 1,516 4,262)*2 = 13,584tf
Y6=0,929 Coeficiente Impacto =1,4-0,007.comp. da Ponte
CI = = 1,4 0,007* 25,00= 1,225
Correo
17,70
18,50
19,70 3x 16,60tf
20,20
1,857tfm
21,00
EX.04 determine o Carga de eixo= Qe=TT.y3+TT.y5 = Qe= 10,105tf
Carga lateral= ql =0,5(rea)+0,3(rea)=ql =4,262tfm
carregamento Carga de frente =qf=0,5(rea)=qf= 1,515tfm
Trem T. Homog.=Qe-(qf-ql).2=TTH = 15,600tf
trem tipo 30 , vo 55,00m. Coef. Impacto =1,4-0,007.comp. da Ponte
CI = 1,015
3x10,105.tf
17,20
1,10 0,20 0,95 0,50 9,00
17,70
18,5
3x 15,834tf
19,7
20,20 1,537tf
21,00 tfm
Carga de eixo= Qe=TT.y3+TT.y5 = Qe= 14,925TF
EX.05 Determine o carregamento Carga lateral= ql =0,5(rea)+0,3(rea) = ql = 3,79TFM
Carga de frente =qf=0,5(rea) = qf=1,49TFM
trem tipo 45 Trem Tipo Hom.=Qe-(qf-ql).2 = TTH = 19,525TF
Coeficiente Impacto =1,4-0,007.comp. da Ponte
CI = 1,046
Correo ==== Q =20,43TF
qdist.=1,56tfm
Y1=1,12
Y2=1,084
Y3=1,05
Y4=1,00
Y5=0,96
Y6=0,91
Eixo
do
pilar
16,25
17,3
0
18,25
18,75
19,40
EX.06 Determine o carregamento Carga de eixo= Qe=TT.y3+TT.y5 Qe= 16,44
Carga lateral= ql =0,5(rea)+0,3(rea) ql =1,545
para trem tipo 45. Carga de frente =qf=0,5(rea) qf= 1,643
Trem Tipo Homogeneizado=Qe-(qf-ql).2 TTH = 16,244
Coef. Impacto =1,4-0,007.comp. da Ponte CI =0,774
Correo
Qe. =
qdist. =
Y1=1,336
Y2=1,301
Y3=1,233
Y4=1,000
Y5=0,959
Y6=0,890
Eixo
do
pilar
7,00
7,30
9,00
9,50
9,75
EX.05 Determine o carregamento
Carga de eixo= Qe=TT.y3+TT.y5 = Qe=
Carga lateral= ql =0,5(rea)+0,3(rea) = ql =
trem tipo 45 com
Carga50,50m
de frente =qf=0,5(rea) = qf=
Trem Tipo Hom.=Qe-(qf-ql).2 = TTH =
Coeficiente Impacto =1,4-0,007.comp. da Ponte
CI =
Correo Q =
qdist.=
Y1=1,413
Y2=1,297
Y3=1,238
Y4=1,00
3x18,69 tf
Y5=0,934
7,725
8,22
5
10,22
5
10,725
11,62
5
EX.06 Determine o carregamento Carga de eixo= Qe=TT.y3+TT.y5 Qe= 16,44
Carga lateral= ql =0,5(rea)+0,3(rea) ql =1,545
para trem tipo 45. Carga de frente =qf=0,5(rea) qf= 1,643
Trem Tipo Homogeneizado=Qe-(qf-ql).2 TTH = 16,244
Coef. Impacto =1,4-0,007.comp. da Ponte CI =0,774
Correo
Qe. =
qdist. =
Y1=1,336
Y2=1,301
Y3=1,233
Y4=1,000
Y5=0,959
Y6=0,890
Eixo
do
pilar
7,00
7,30
9,00
9,50
9,75
EX: DETERMINAR R+ e R-
Y1=1,750
Y2=1,450
Y3=1,000
Y4= 0,000
Y5=0,045
Y6=0,075
R+ = 81,555tf
R- = 2,514tf
EX: DETERMINAR R+ e R-
DETERMINE AS REAES DE APOIO PELA LINHA DE
INFLUNCIA R(+)= 104,68tf
R(-) = - 39,034tf
6,63t 6,63t 6,63t
1,83tfm
15,20m
50,00m
DETERMINE AS REAES DE APOIO PELA LINHA DE
INFLUNCIA
R(+)= 74,19tf OK
R(-) = - 5,08tf OK
11,90t 11,90t 11,90t
1,965tfm
25,00m
34,00m
DETERMINE AS REAES DE APOIO PELA LINHA DE
INFLUNCIA
R(+)= 135,40tf OK
R(-) = 15,40 tf OK
2,00tfm
40,00m
60,00m
DETERMINE AS REAES DE APOIO PELA LINHA DE
INFLUNCIA
1,50tfm
18,25m
5,55
23,8
25,3 7,05
26,8
8,55
Y1 =Y2 = Y3 = Y4 = Y5 = Y6 = Y7 = Y8
26,8 25,30 23,80 18,25 ## 5,55 7,05 8,55
Y1=1,468 Y2=1,386 Y3=1,304 Y4= 1,000 Y5=#### Y6=0,304 Y7= 0,386 Y8= 0,468
1,22tfm
7,00m
40,00m
8,50m
47,00m
10,00m
48,50m
50,00m
60,00m