SAFETY AND HEALTH OFFICER EXAMINATION

3/2003

PAPER III

PART 2 : WORKPLACE ASSIGMENT

HAZARDS IDENTIFICATION, RISK ASSESSMENT AND RISK

CONTROL MEASURES

KUALA LUMPUR CONVENTION CENTRE PROJECT

SUNWAY CONSTRUCTION BERHAD

Prepared by

YATI AHMAD

(NS2567)
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Table of Contents

Contents Page Number

Acknowledgements v

1. Abstract 1

2. Introduction

2.1 The Company 2 3

2.2 The Selected Project 4-5

2.3 Organization Chart 6

2.4 Activities and Work Processes 7

2.5 Work Environment 8

2.6 Job and Tasks 8

3. Objective 9

4. Methodology

4.1 Identifying Hazards 10 - 14

4.2 Technique Used to Assess and Evaluate 15 18

The Risks

4.3 Hazards Prioritisation 19

ii
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Table of Contents

Contents Page Number

5. Results

5.1 Hazards Listing 20

5.2 Critical Hazard and Its Effect to the Safety 21

and Health of Workers

6. Recommendation

6.1 Control Measures 24

6.2 Programme Review 25

6.3 Conclusion 26

7. References 27

8. Appendices 28

Appendix I Project Site Location

Appendix II Built-up Area Plan

Appendix III Companys organisation chart.

Appendix IV Kuala Lumpur Convention Centre Project

Team Organisation Chart

iii
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Table of Contents

Contents

Appendix V Kuala Lumpur Convention Centre Site

OSH Organisation Chart

Appendix VI Summary of Master Work Programme

for Kuala Lumpur Convention Center Project

Appendix VII Photos for earthing installation at raft foundation area

Appendix VIII Job Safety Analysis for Earthing Installation.

iv
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Acknowledgements

I would like to express my sincere appreciation and gratitude to Sunway Construction

Berhad for giving me an opportunity to attend the Certificate of Safety and Health Officer

Course organized by National Institute of Occupational Safety and Health (NIOSH).

I also wish to extend my thanks to Mr Phillip Varughese, Sr. Manager of Occupational

Safety and Health in Sunway Construction Berhad for the advice, guidance and

encouragement throughout my career in Occupational Safety and Health.

The special thanks also dedicated to Mr Bernard Engineer of Pekat Technology Sdn

Bhd, Mr Selva Rajah and Mr Rusmin Abd Ghani Safety & Health Executives of Sunway

Construction Berhad, Mr Michael Tan and Mr Beh Yen Fei Planning Engineers of Sunway

Construction Berhad, Mr Hung Siang Wei Engineer of Sunway Engineering and the other

colleagues of Kuala Lumpur Convention Centre Project, Sunway Construction Berhad for

their support and encouragement throughout the preparation of this Workplace Assignment.

The last but not least, a warmest appreciation to my husband Mr Haidhir bin Kamarul

Bahrin for the invaluable love, encouragement, caring and support.

v
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
____________________________________________________________________________________________________

1. Abstract

This Workplace Assignment is a study to identify the hazards, assessing the risks and

recommending the control measures for Earthing Installation at Raft Foundation at Kuala

Lumpur Convention Centre Project, a project awarded to Sunway Construction Berhad.

The study has identified several hazards while installing the earthing system at raft

foundation area in this project. Using the Risk Ranking Table, hazards for trip and fall was

found as critical. This hazard may lead to an injury to the workers.

The slippery and unstable surface of rebar may contribute to the trip and fall hazard.

To eliminate or minimise this hazard, the control measures recommended is to ensure good

housekeeping. Proper safety shoes will assist in minimising the trip and fall hazard.

1
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

2. Introduction

2.1 The Company

Sunway Construction Berhad (SUNCON) was first incorporated as Sungei

Way Quarry Sdn. Bhd in 1976. It was subsequently re- named Sungei Way

Quarry and Construction Sdn. Bhd in March 1981 to reflect its growing

involvement in the construction industry. During the Groups corporate

exercise in 1984, SUNCON changed its name to Sungei Way Construction

Sdn. Bhd. In 1996, it was converted into public company, and it was listed in

the main board of the Kuala Lumpur Stock Exchange (KLSE) on 12 June

1997. In line with the change of the Sunway Group, SUNCON acquired its

present name on 13 December 1999.

SUNCON has, over the years, established itself as a reputable contracting

concern having undertaken a wide range of turnkey building and civil

engineering projects. Its track record features of buildings, roads, bridges,

infrastructure works, etc. This was realized through the application of creative

thinking, innovative methodology coupled with the synergistic diversification

of the Sunway Group, undoubtedly one of Malaysias most dynamic and well-

diversified conglomerates.

SUNCON is registered Class A Contractor with Pusat Khidmat Kontraktor. It

is also registered as a Grade 7 entity with the Construction Industry

2
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Development Board of Malaysia. The Companys clients range from

governmental sectors to private organizations and individuals.

SUNCON aspires to be a progressive construction company both in the

regional and international arena. The management of Occupational Safety and

Health has been considered as an important key performance to the company.

As an OHSAS 18001 certified company, SUNCON is committed to ensure the

providing and maintaining a safe and healthy working environment by

creating a corporate culture for the overall well-being of the employees and

the community.

2.2 The Selected Project

3
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

This Workplace Assignment will study the hazard identification, risk

assessment and risk control measures in one of the latest building construction

activities done by SUNCON. The selected project worth RM 550 million,

named as Kuala Lumpur Convention Centre Project is located in the Kuala

Lumpur City Centre area.

The project is to be an international exhibition and convention centre

to attract and conduct large international standard convention and related trade

shows and exhibition.

The details of project :

PROJECT TITLE

Kuala Lumpur Convention Centre at Kuala Lumpur City Centre, Kuala

Lumpur, Wilayah Persekutuan Design, Construction and Completion of

the Main Building Works

LOCATION

Bounded by Jalan Pinang & Jalan Kia Peng, the KLCC Metropolitan Park,

the Mandarin Oriental Kuala Lumpur and the Menara Exxon-Mobil

(Appendix I Project Site Location)

4
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

BUILT-UP AREA & CAPACITY

The Convention Centre is build into 4 sections i.e West Wing, Center Core,

East Wing and Plenary Hall with 2 basement levels and 4 levels (GL L4)

above ground

(Appendix II Built-up Area Plan)

CONTRACT DETAILS

Contract Sum : RM 549.3 million


Contract Award : 16th September 2002
Site Possession Date : 17th September 2002
Contract Period : 131 weeks
Sectional Completion : 24th December 2004 (East Wing, West

Wing & Centre Core)


Final Contract Completion : 21st March 2005 (Plenary Hall)

EMPLOYER : Kuala Lumpur Convention Centre Sdn Bhd

PROJECT MANAGER : KLCC Projeks Berhad

MAIN CONTRACTOR : Sunway Construction Berhad

KEY TEAM MEMBER : Taisei Corporation Japan

(TECHNICAL ADVISORY)

2.3 Organisation Chart

5
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Appendix III describes the companys organisation chart.

Appendix IV describes the Kuala Lumpur Convention Centre Project Team

Organisation Chart

Appendix V describes the Kuala Lumpur Convention Centre Site OSH

Organisation Chart

2.4 Activities and Work Processes

6
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Below is the common flow chart for SUNCONs work processes

Tendering
Processes

Yes
Design
and Build Design and
? Development
No

Pre Construction
and Planning

Procurement

Construction

Post Construction

Hand Over to
Clients

Ref : SUNCON Quality System Product Realization

As a construction company, details of work activities and schedule are

vary from project to project. The details of work activities and schedule for the

project also known as a Master Work Programme. This Master Work

7
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Programme will be planned by Planning Department and acts as a guidance

for the project implementation.

Appendix VI describes the Summary of Master Work Programme for

Kuala Lumpur Convention Center Project. With reference to this Summary,

one of the current active jobs is Raft Foundation, which cover the activity of

earthing installation. This Workplace Assignment had selected this activity to

study the hazards identification, risk assessment and recommend the control

measures for eliminating or minimising the risks.

2.5 Work Environment

Kuala Lumpur Convention Center is a building construction works

with 2 levels underground and 4 levels above ground.

2.6 Job and tasks

For each job activity, Method Statement was established as guidance

for the workers to do the tasks. Method Statement brief step by step the tasks

and will be read together with Job Safety Analysis.

3. Objectives

This Workplace Assignment objectives are

8
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

a. To identify the hazards in the Earthing Installation at Raft Foundation area at Kuala

Lumpur Convention Centre Project .

b. To assess the risks that might raise from the hazards identified in the Earthing

Installation at Raft Foundation area at Kuala Lumpur Convention Centre Project .

c. To recommend the control measures to minimise or eliminate the risks from the

identified hazards in the Earthing Installation at Raft Foundation area at Kuala

Lumpur Convention Centre Project .

4. Methodology

4.1 Identifying Hazards

9
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Hazards identification in the Earthing Installation at Raft Foundation area at

Kuala Lumpur Convention Centre Project was done with the implementation

of Job Safety Analysis (JSA).

Job Safety Analysis is a tool to identify hazards, assess the risks and

recommend the control measures for the work activities that will be done. The

steps of JSA for identifying the hazards are by breaking down the job into its

components parts in an orderly and chronological job sequences followed by

identifying the hazards for each component. Then, the risks will be assessed

and evaluated. The risk ranking will give the guideline of the urgency of

action and control measures.

For Earthing Installation at Raft Foundation area at Kuala Lumpur Convention

Centre Project, the hazards identification steps were done by the discussion of

sub contractor personnel (Operations), M&E Engineer and OSH personnel.

With reference to the Method Statement of Earthing Installation at Raft

Foundation area, the jobs sequence for this activity are :

1. Installation of earth electrode (copper)

10
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

i. Identify location

ii. Drive in the copper bond earth electrode using hammer jet

iii. Measure earth resistance and record

iv. If earth resistance do not achieve desired value, insert rod coupling to

joint first electrode to second electrode and drive in second electrode.

Measure earth resistance again.

v. If earth resistance achieve desired value, repeat step i to iv until all

electrode planted.

2. Installation of horizontal earth cable (copper)

i. Identify location for laying cable (horizontal)

ii. Lay cable along the routes

iii. Repeat until all earth cable installed.

3. Exothermic Welding of horizontal earth cable to electrode

i. Insert the graphite mould and place both electrode and cable and

ensure no gap between the jointing part

ii. Place retaining disc and pour in welding powder

iii. Use flint gun to ignite the starting powder

4. Installation of vertical cable via column reinforcement bar

i. tighten the vertical earth cable with wire tie to the :

a. raft foundations bottom horizontal rebar

b. raft foundations upper horizontal rebar

11
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

c. columns vertical rebar

ii. vertical earth cable is wire tie to column rebar at 1m interval after the

first welding point until the test point level or roof level interfacing

point.

5. Installation of test point

Appendix VII describes photos for earthing installation at raft foundation area

in Kuala Lumpur Convention Centre Project.

With the break down of the job into its component parts, the hazards can easily

be identified as in this table:

Job Sequences Hazard Identification


Potential Hazard Potential Risk

12
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

1. Installation of earth electrode (copper)

i. Identify location Trip and fall Minor injury

ii. Drive in the copper bond earth Vibration Diseases


electrode using hammer jet

iii. Measure earth resistance and record Trip and fall Minor Injury

iv. If earth resistance do not achieve Vibration Diseases


desired value, insert rod coupling to
joint first electrode to second
electrode and drive in second
electrode. Measure earth resistance
again.

v. If earth resistance achieve desired


value, repeat step i to iv until all
electrode planted.

2. Installation of horizontal earth cable


(copper)

i. Identify location for laying cable Trip and fall Minor Injury
(horizontal)

ii. Lay cable along the routes Trip and fall Minor Injury

iii. Repeat until all earth cable installed.

3. Exothermic Welding of horizontal earth


cable to electrode

i. Insert the graphite mould and place Crushed in Minor injury


both electrode and cable and ensure between
no gap between the jointing part

ii. Place retaining disc and pour in - Smoke Diseases


welding powder hazardous to
health

13
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

iii. Use flint gun to ignite the starting - Weld metal Major injury
powder spew out

- Explosion Major injury

Hot material Minor Injury

4. Installation of vertical cable via column


reinforcement bar

i. tighten the vertical earth cable with wire - Trip and fall Minor injury
tie to the :
- raft foundations bottom horizontal rebar - Crushed in Minor Injury
- raft foundations upper horizontal rebar between
- columns vertical rebar

ii. vertical earth cable is wire tie to column - Trip and fall Major Injury
rebar at 1m interval after the first welding point
until the test point level or roof level interfacing - Crushed in Minor Injury
point. between

5. Installation of test point - Trip and fall Major Injury

- Crushed in Major Injury


between

Table 1 : Hazards Identification in the earthing installation at raft foundation


area

4.2 Techniques Used to Assess and Evaluate the Risks

SUNCON has used the Risk Ranking Table to assess and evaluate the risks for

the potential hazards that were identified in the job activities.

14
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Probability 1 2 3 4 5
Once in 2 Once a Once in 6 Once a Once a
Consequence years year months month week
5 First Aid 5 10 15 20 25

10 Minor Injury 10 20 30 40 50

15 Diseases 15 30 45 60 75

20 Major Injury / 20 40 60 80 100


Fracture
25 Fatality 25 50 75 100 125

Table 2 : Risk Ranking Table

Using this Risk Ranking Table, the risks for hazards identified in the earthing

installation at the raft foundation area were assessed as below :

15
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Job Sequences Hazard Identification Risk Assessment


Potential Hazard Potential Risk Probabilit Consequences Risk
y Ranking
1. Installation of earth
electrode (copper)

vi. Identify location Trip and fall Minor injury 3 10 30

vii. Drive in the copper Vibration Diseases 1 15 15


bond earth electrode
using hammer jet

viii. Measure earth Trip and fall Minor Injury 3 10 30


resistance and record

ix. If earth resistance do Vibration Diseases 1 15 15


not achieve desired
value, insert rod
coupling to joint first
electrode to second
electrode and drive in
second electrode.
Measure earth
resistance again.

x. If earth resistance
achieve desired value,
repeat step i to iv until
all electrode planted.

16
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

2. Installation of horizontal
earth cable (copper)

iv. Identify location for Trip and fall Minor Injury 3 10 30


laying cable
(horizontal)

v. Lay cable along the Trip and fall Minor Injury 3 10 30


routes

vi. Repeat until all earth


cable installed.

3. Exothermic Welding of
horizontal earth cable to
electrode

iv. Insert the graphite Crushed in Minor injury 2 10 20


mould and place both between
electrode and cable and
ensure no gap between
the jointing part

v. Place retaining disc and - Smoke Diseases 1 15 15


pour in welding powder hazardous to
health

vi. Use flint gun to ignite - weld metal Major injury 1 20 20


the starting powder spew out

- explosion Major injury 1 20 20

17
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

Hot material Minor Injury 2 10 20

4. Installation of vertical
cable via column reinforcement
bar

i. tighten the vertical earth - Trip and Minor injury 3 10 30


cable with wire tie to the : fall
- raft foundations bottom
horizontal rebar - crushed in Minor Injury 2 10 20
- raft foundations upper between
horizontal rebar
- columns vertical rebar

ii. vertical earth cable is wire - Trip and Minor Injury 3 20 60


tie to column rebar at 1m interval fall
after the first welding point until
the test point level or roof level - crushed in Minor Injury 2 10 20
interfacing point. between

5. Installation of test point - Trip and Minor Injury 3 10 30


fall

- crushed in Minor Injury 2 10 20


between

Table 3 : Risk Assessment for Earthing Installation at Raft Foundation

18
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

4.3 Hazards Prioritisation

The hazards identified in the job sequences of earthing installation at raft

foundation were prioritised with reference to the Risk Assessment done in part

4.2.

The highest risk ranking resulted from the assessment was given the first

number of prioritisation, followed with the second and third ranking. The list

of prioritisation is as below:

No Hazards Risk Ranking

1. Trip and fall 30

2. Crushed in between 20

3. Weld metal spew out 20

4. Explosion 20

5. Hot material 20

6. Vibration 15

7. Smoke hazardous to health 15

19
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

5.0 Results

5.1 Hazards Listing

From part 4.0, the hazards identified in the earthing installation at raft

foundation are :

No Hazards Category

1. Trip and fall Physical hazard

2. Crushed in between Physical hazard

3. Weld metal spew out Physical hazard

4. Explosion Physical hazard

5. Hot material Physical hazard

6. Vibration Health hazard

7. Smoke hazardous to health Health hazard

20
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

5.2 Critical Hazard and Its Effect to the Safety and Health of the

Workers

After assessment and prioritisation, trip and fall hazards was found

as a critical hazard while doing earthing installation at raft foundation

in Kuala Lumpur Convention Centre Project. This hazard score 30

points as a result of the risk ranking.

Workers are exposed to the trip and fall hazards as they are walking on

the rebar. The rebars condition is quite slippery and is not a stable

surface for walking.

Trip and fall hazard while walking or doing work on the rebar may

lead to injury of the workers.

21
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

6.0 Recommendation and Review

6.1 Control Measures

The recommended control measures for hazards identified in the

earthing installation were based on the Risk Tolerance Guide and Urgency of

Action Table.

Risk Description Action Times Scale &


Ranking Urgency
0 25 Trival Relevant action is required Within 2 weeks
and records need to be kept
26 50 Tolerance Controls are required. Within 1 week
Consideration need to be
given for an effective
solution or improvement.
Monitoring is required to
ensure that the controls are
maintained
51 75 Moderate Efforts should be made to Within 4 days
reduce the risk. Risk control
measures should be
implemented within a
defined time period. Where
the moderate risk is
associated with extremely
harmful consequences,
further assessment may be
necessary to establish more
precisely the likelihood of
harm as a basis for
determining the need for
improved control measures
76 100 Substantial Work should not be started Within 1 day
until the risk has been
reduced. Measures shall be
allocated to reduce the risk.
Where the risk involves work
in progress, urgent action
shall be taken

22
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

101 125 Hazardous Work shall be stopped Immediately


immediately until all
measures taken is
satisfactory

Table 4 : Risk Tolerance Guide and Urgency of Action

From the part 4.3, the risk ranking for the hazards identified in earthing

installation at raft foundation activity were ranked in the Trival and

Tolerance category.

The critical hazard i.e trip and fall is under Tolerance category and

need an effective control measures and monitoring.

The recommended control measures for this hazard are:

No Hierarchy Control Measures Description

1. Elimination N/A

2. Substitution N/A

3. Isolation N/A

4. Engineering Control N/A

5. Administrative Control - Ensure housekeeping

6. PPE - Wear safety shoes

23
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

The control measures for the other hazards are listed in the Appendix

VIII Job Safety Analysis for Earthing Installation.

These recommended control measures will be used as training material

for the workers. The training normally done in the Tool Box Briefing *

session by the respective Supervisor.

* Tool Box Briefing : a short briefing session to workers of individual

trades lead by their respective Supervisors.

24
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

5.2 Program Review

The effectiveness of control measures implemented will be

monitored through:

a. Inspection or Audit result

b. Incident and Accident.

Inspection or Audit may identify the inadequate or improper

control measures. Some of the recommended control measures

may not environmental-free or may produce uncomfortably to

the workers. With the Inspection or Audit, the feedback or

responses may be considered.

While there is any incident or accident, the control measures

will be review to ensure its adequacy. The inadequate control

measures may lead to an accident.

The review and revision of control measures will be done

together of OSH personnel and respective Operational

personnel (SUNCON staff or Sub Contractor Staff or both).

The revised control measures once again will be brief to the

workers through their Tool Box Briefing.

25
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

6.3 Conclusions

In the earthing installation activity at raft foundation in Kuala Lumpur

Convention Center Project, the most critical hazard identified is trip

and fall. The control measures recommended will assist in eliminating

or reducing the risk that occur in the work place. Therefore, the

workers could do their works without or with a minimum risk to their

safety and health.

The minimum manhours loss due to the accident can assist SUNCON

much in ensuring on-time project hand-over to client. The benefits also

goes to minimising the uninsured cost such as minimise staff turn over,

minimise legal fees, minimise the loss time due to administrative

matters by the relevant personnel and others. This will totally benefits

SUNCON in ensuring its status as a reputable construction company.

26
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

7.0 References

a. Sunway Construction Berhad, 2000, OSH Manual and Procedures

b. Sunway Construction Berhad, 2002, Quality System Manual

c. Sunway Construction Berhad, 2002, Project Occupational Safety

and Health Programme Kuala Lumpur Convention Centre Project

d. Sunway Construction Berhad, 2002, Contractors Overall Schedule

Kuala Lumpur Convention Centre Project

e. Sunway Construction Berhad, 2003, Method Statement for

Earthing Installation (Electrical) - Kuala Lumpur Convention

Centre Project

f. Sunway Construction Berhad, 2002, Document Management

System Database - Kuala Lumpur Convention Centre Project

g. National Institute of Occupational Safety and Health, 1997, Safety

and Health Officer Course Book.

27
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project

8.0 Appendices

28