PAPER III
CONTROL MEASURES
Prepared by
YATI AHMAD
(NS2567)
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Table of Contents
Acknowledgements v
1. Abstract 1
2. Introduction
3. Objective 9
4. Methodology
The Risks
ii
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Table of Contents
5. Results
6. Recommendation
6.3 Conclusion 26
7. References 27
8. Appendices 28
iii
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Table of Contents
Contents
iv
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Acknowledgements
Berhad for giving me an opportunity to attend the Certificate of Safety and Health Officer
Safety and Health in Sunway Construction Berhad for the advice, guidance and
The special thanks also dedicated to Mr Bernard Engineer of Pekat Technology Sdn
Bhd, Mr Selva Rajah and Mr Rusmin Abd Ghani Safety & Health Executives of Sunway
Construction Berhad, Mr Michael Tan and Mr Beh Yen Fei Planning Engineers of Sunway
Construction Berhad, Mr Hung Siang Wei Engineer of Sunway Engineering and the other
colleagues of Kuala Lumpur Convention Centre Project, Sunway Construction Berhad for
their support and encouragement throughout the preparation of this Workplace Assignment.
The last but not least, a warmest appreciation to my husband Mr Haidhir bin Kamarul
v
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
____________________________________________________________________________________________________
1. Abstract
This Workplace Assignment is a study to identify the hazards, assessing the risks and
recommending the control measures for Earthing Installation at Raft Foundation at Kuala
The study has identified several hazards while installing the earthing system at raft
foundation area in this project. Using the Risk Ranking Table, hazards for trip and fall was
The slippery and unstable surface of rebar may contribute to the trip and fall hazard.
To eliminate or minimise this hazard, the control measures recommended is to ensure good
housekeeping. Proper safety shoes will assist in minimising the trip and fall hazard.
1
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
2. Introduction
Way Quarry Sdn. Bhd in 1976. It was subsequently re- named Sungei Way
Quarry and Construction Sdn. Bhd in March 1981 to reflect its growing
Sdn. Bhd. In 1996, it was converted into public company, and it was listed in
the main board of the Kuala Lumpur Stock Exchange (KLSE) on 12 June
1997. In line with the change of the Sunway Group, SUNCON acquired its
infrastructure works, etc. This was realized through the application of creative
of the Sunway Group, undoubtedly one of Malaysias most dynamic and well-
diversified conglomerates.
2
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
creating a corporate culture for the overall well-being of the employees and
the community.
3
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
assessment and risk control measures in one of the latest building construction
to attract and conduct large international standard convention and related trade
PROJECT TITLE
LOCATION
Bounded by Jalan Pinang & Jalan Kia Peng, the KLCC Metropolitan Park,
4
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
The Convention Centre is build into 4 sections i.e West Wing, Center Core,
East Wing and Plenary Hall with 2 basement levels and 4 levels (GL L4)
above ground
CONTRACT DETAILS
(TECHNICAL ADVISORY)
5
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Organisation Chart
Organisation Chart
6
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Tendering
Processes
Yes
Design
and Build Design and
? Development
No
Pre Construction
and Planning
Procurement
Construction
Post Construction
Hand Over to
Clients
vary from project to project. The details of work activities and schedule for the
7
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
one of the current active jobs is Raft Foundation, which cover the activity of
study the hazards identification, risk assessment and recommend the control
for the workers to do the tasks. Method Statement brief step by step the tasks
3. Objectives
8
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
a. To identify the hazards in the Earthing Installation at Raft Foundation area at Kuala
b. To assess the risks that might raise from the hazards identified in the Earthing
c. To recommend the control measures to minimise or eliminate the risks from the
4. Methodology
9
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Kuala Lumpur Convention Centre Project was done with the implementation
Job Safety Analysis is a tool to identify hazards, assess the risks and
recommend the control measures for the work activities that will be done. The
steps of JSA for identifying the hazards are by breaking down the job into its
identifying the hazards for each component. Then, the risks will be assessed
and evaluated. The risk ranking will give the guideline of the urgency of
Centre Project, the hazards identification steps were done by the discussion of
10
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
i. Identify location
ii. Drive in the copper bond earth electrode using hammer jet
iv. If earth resistance do not achieve desired value, insert rod coupling to
electrode planted.
i. Insert the graphite mould and place both electrode and cable and
11
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
ii. vertical earth cable is wire tie to column rebar at 1m interval after the
first welding point until the test point level or roof level interfacing
point.
Appendix VII describes photos for earthing installation at raft foundation area
With the break down of the job into its component parts, the hazards can easily
12
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
iii. Measure earth resistance and record Trip and fall Minor Injury
i. Identify location for laying cable Trip and fall Minor Injury
(horizontal)
ii. Lay cable along the routes Trip and fall Minor Injury
13
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
iii. Use flint gun to ignite the starting - Weld metal Major injury
powder spew out
i. tighten the vertical earth cable with wire - Trip and fall Minor injury
tie to the :
- raft foundations bottom horizontal rebar - Crushed in Minor Injury
- raft foundations upper horizontal rebar between
- columns vertical rebar
ii. vertical earth cable is wire tie to column - Trip and fall Major Injury
rebar at 1m interval after the first welding point
until the test point level or roof level interfacing - Crushed in Minor Injury
point. between
SUNCON has used the Risk Ranking Table to assess and evaluate the risks for
14
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
Probability 1 2 3 4 5
Once in 2 Once a Once in 6 Once a Once a
Consequence years year months month week
5 First Aid 5 10 15 20 25
10 Minor Injury 10 20 30 40 50
15 Diseases 15 30 45 60 75
Using this Risk Ranking Table, the risks for hazards identified in the earthing
15
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
x. If earth resistance
achieve desired value,
repeat step i to iv until
all electrode planted.
16
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
2. Installation of horizontal
earth cable (copper)
3. Exothermic Welding of
horizontal earth cable to
electrode
17
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
4. Installation of vertical
cable via column reinforcement
bar
18
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
foundation were prioritised with reference to the Risk Assessment done in part
4.2.
The highest risk ranking resulted from the assessment was given the first
number of prioritisation, followed with the second and third ranking. The list
of prioritisation is as below:
2. Crushed in between 20
4. Explosion 20
5. Hot material 20
6. Vibration 15
19
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
5.0 Results
From part 4.0, the hazards identified in the earthing installation at raft
foundation are :
No Hazards Category
20
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
5.2 Critical Hazard and Its Effect to the Safety and Health of the
Workers
After assessment and prioritisation, trip and fall hazards was found
Workers are exposed to the trip and fall hazards as they are walking on
the rebar. The rebars condition is quite slippery and is not a stable
Trip and fall hazard while walking or doing work on the rebar may
21
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
earthing installation were based on the Risk Tolerance Guide and Urgency of
Action Table.
22
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
From the part 4.3, the risk ranking for the hazards identified in earthing
Tolerance category.
The critical hazard i.e trip and fall is under Tolerance category and
1. Elimination N/A
2. Substitution N/A
3. Isolation N/A
23
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
The control measures for the other hazards are listed in the Appendix
for the workers. The training normally done in the Tool Box Briefing *
24
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
monitored through:
25
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
6.3 Conclusions
or reducing the risk that occur in the work place. Therefore, the
The minimum manhours loss due to the accident can assist SUNCON
goes to minimising the uninsured cost such as minimise staff turn over,
matters by the relevant personnel and others. This will totally benefits
26
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
7.0 References
Centre Project
27
Workplace Assignment Earthing Installation at Raft Foundation Area
Kuala Lumpur Convention Centre Project
8.0 Appendices
28