JINDAL POWER LIMITED

CHECKLISTS
Doc. No. TMD/CL/035
TITLE : CHECKLIST FOR PREVENTIVE MAINTENANCE OF EQUIPMENTS Issue No. /
01 / 01-09-2008
Date

TG & BOP MAINTENANCE DEPARTMENT Rev No. /


00 / 01-09-2008
Date
UNIT : EQUIPMENT NAME- FIRE WATER BOOSTER PUMP

WORK ORDER NO. : DATE :

PERMIT NO. : PTW ISSUE DATE : PTW CLOSING DATE :

Design Actual
Sl. No. Work Instructions Frequency Remarks
Value Value
Work to be done/carried out when the equipment is isolated
Take proper PTW and ensure all mechanical, electrical and C&I
1 Quarterly
isolations have been done.
Check the condition of the love joy coupling and spider if broken then
2 Quarterly
replace the same
Check the gland leakage if heavy then tightened or replace the gland
3 Quarterly
packing
4 Check the tightness of foundation bolt if loose then tighten the same Quarterly
Check the coupling in between engine and pump if found damaged then
5 Quarterly
replace and realignment to be done
6 Carry out pump bearing greasing Quarterly
7 House keeping / Clean the surrounding area Quarterly
Spill over oil / water / grease / cotton waste / etc in surrounding area
8 Quarterly
and floor to be cleaned and disposed
Return the PTW and trial run of the equipment. If any leakage persists
9 Quarterly
same is to be rectified.

Signature of Contractor Signature of JPL Engineer Signature of JPL Engineer in charge


Page No. : 01

Prepared By : Reviewed & Approved By :