Escolar Documentos
Profissional Documentos
Cultura Documentos
Authors:
Cleo Batocail
Julie Mae Clarabal Instructor:
Glennie Lumampao Engr. Richard Aquino
Jethrine Claire Madarang
Edgardo Vargas Jr.
27 January 2013
Certification
This is to certify that part or parts of our work was not copied from some-
body else work. A proper and full referencing was included for all ideas
including plans, drawings, pictures and diagrams taken from the internet
and other sources. For the materials which is quoted essentially word-for-
word is given in quotation marks and referenced.
Signed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
Summary
3
Contents
1 Project Background 9
1.1 Project Description . . . . . . . . . . . . . . . . . . . . . . . . 9
1.2 Objectives of the Study . . . . . . . . . . . . . . . . . . . . . 9
1.3 Scope and Limitation . . . . . . . . . . . . . . . . . . . . . . 9
1.4 Project Outline/Workflow . . . . . . . . . . . . . . . . . . . . 10
3 Bridge Engineering 16
3.1 Design Parameters . . . . . . . . . . . . . . . . . . . . . . . . 17
3.2 Substructures . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.2.1 Wing wall . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.2.2 Abutment . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.2.3 Piles, Piers and Caissons . . . . . . . . . . . . . . . . 18
3.3 Superstructures . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.3.1 Bridge Deck . . . . . . . . . . . . . . . . . . . . . . . . 18
3.3.2 Girders . . . . . . . . . . . . . . . . . . . . . . . . . . 19
4
4.2 Loadings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
4.3 Prestress Losses . . . . . . . . . . . . . . . . . . . . . . . . . . 20
4.4 Design for Flexure . . . . . . . . . . . . . . . . . . . . . . . . 20
4.5 Shear and Diagonal Tension . . . . . . . . . . . . . . . . . . . 20
4.6 Deflection Calculations . . . . . . . . . . . . . . . . . . . . . . 20
4.7 Development, Splicing and Bar Cut-offs . . . . . . . . . . . . 20
5
List of Figures
6
List of Tables
7
Acknowledgements
8
Chapter 1
Project Background
9
1.4 Project Outline/Workflow
10
Chapter 2
2.1 Materials
This typical bridge is mainly a prestressed concrete material.
2.1.1 Concrete
”Concrete is an artificial engineering material made from a mixture of port-
land cement, water, fine and coarse aggregates, and a small amount of air.
It is the most widely used construction material in the world (Microsoft
Encarta 2009)”.
Concrete is the only major building material that can be delivered to the
job site in a plastic state. This unique quality makes concrete desirable as a
building material because it can be molded to virtually any form or shape.
Concrete provides a wide latitude in surface textures and colors and can be
used to construct a wide variety of structures, such as highways and streets,
bridges, dams, large buildings, airport runways, irrigation structures, break-
waters, piers and docks, sidewalks, silos and farm buildings, homes, and even
barges and ships.
The following are the main materials from which concrete is made:
11
Cement
”Cement, is any material that hardens and becomes strongly adhesive after
application in plastic form. The term cement is often used interchangeably
with glue and adhesive.In engineering and building construction, the term
usually refers to a finely powdered, manufactured substance consisting of
gypsum plaster or portland cement that hardens and adheres after being
mixed with water (Microsoft Encarta 2009).”
Aggregates
”Is a granular materaial, such as sand, gravel, crushed stone and iron blast
furnace slab, and when used with a cementing medium forms a hydraulic
cement concrete or mortar (NSCP,2010 6th Ed.).”
Water
”Water used in mixing concrete shall be clean, free from injurious amounts
of oils, acids, alkalis, salts, organic materials or other substances deleterious
to concrete or reinforcement(NSCP,2010 6th Ed.).”
Admixtures
”Is a material other than water, aggregate or hydraulic cement used as an
ingredient of concrete and added to concrete before or during its mixing to
modify its properties (NSCP,2010 6th Ed.).”
To increase the bond of concrete and steel, deformations are rooled unto
the surface of the bar and must conform in accordance to ASTM specifica-
tions inorder to be accepted as deformed bars or reinforcement.
12
2.1.3 Prestressing Tendons
Because of the high creep and shrinkage losses in concrete, effective pre-
stressing can be achieved by using very high strength steels in the range of
270,000 psi or more. Such high-stressed steels are able to counterbalance
these losses in the surrounding concrete and have adequate leftover stress
levels to sustain the required prestressing force.
Types of Prestressing
13
2.2.2 Pretensioning vs. Post-tensioning
The term ”pretensioning” means the pretensioing of the prestressing steel
not the beam itself. Steel is tensioned before casting of concrete mix. It is
normally performed at pre-casting plants where a precasting stressing bed,
of a long reinforced concrete slab is cast on the ground with vertical anchor
bulk heads or walls at its ends.
In Summary: Pre-tensioned
• Stress strands
• Cast concrete
• Cut strands
• Cast concrete
2.2.3 Anchorages
Anchorages is a prestressing system loacted at the end of a high tensile
strength section. After the wires are stressed, these anchor serves as lock at
both ends. Such anchorages are supported by large and stable bulkheads to
support the exceedingly high concentrated forces applied to the individual
tendons.
14
Figure 2.3: Type of Achorage
15
Chapter 3
Bridge Engineering
16
3.1 Design Parameters
3.2 Substructures
3.2.1 Wing wall
Wingwalls are a necessary component of most FIAB bridges to retain the fill
thatsupports the roadway. Currently, wingwalls do not get a lot of attention
from the designer, and are almost an afterthought to the overall design of
the structure. However, wingwall orientation and connection details can
have an impact on the forces induced in,and the distribution of, the forces
throughout the structure.
The following are types of Wingwall:
3.2.2 Abutment
In engineering, abutment refers to the substructure at the end of a bridge
span whereon the bridge’s superstructure rests. Single-span bridges have
abutments at each end which provide vertical and lateral support for the
bridge, as well as acting as retaining walls to resist lateral movement of the
earthen fill of the bridge approach.
Multi-span bridges require piers to support ends of spans unsupported
by abutments.The term may also refer to the structure supporting one side
of an arch, or masonry used to resist the lateral forces of a vault.The word
derives from the verb ”abut”, meaning to ”touch by means of a mutual
border”.
17
3.2.3 Piles, Piers and Caissons
Piles are a type of deep foundation that is drilled using a hydraulic drilling
machine below the earths surface unto a stable strata. Bridges are using
these piles to assure the stability because these are made from prestressed
concrete to withstand vertical forces.
A pier is a raised structure, including bridge and building supports and
walkways, typically supported by widely spread piles or pillars. The lighter
structure of a pier allows tides and currents to flow almost unhindered,
whereas the more solid foundations of a quay or the closely spaced piles of a
wharf can act as a breakwater, and are consequently more liable to silting.
In geotechnical engineering, a caisson is a watertight retaining struc-
ture[1] used, for example, to work on the foundations of a bridge pier, for
the construction of a concrete dam,[2] or for the repair of ships.[3] These are
constructed such that the water can be pumped out, keeping the working
environment dry. When piers are to be built using an open caisson and it
is not practical to reach suitable soil, friction pilings may be driven to form
a suitable sub-foundation.
3.3 Superstructures
3.3.1 Bridge Deck
A bridge deck or road bed is the roadway, or the pedestrian walkway, sur-
face of a bridge. The deck may be of concrete,wood which in turn may be
covered with asphalt concrete or other pavement.
The primary function of a bridge deck is to support the vehicular verti-
cal loads and distribute these loads to the steel superstructure. The deck is
typically continuous along the span of the bridge and continuous across the
width of the span.
In most applications, the bridge deck is made composite with the steel
superstructure through positive attachment to the girders, such as using
shear connecters to attach the concrete deck slabs to steel girders. In such
cases, the deck serves as part of the top flange in the composite section and
can be utilized for strength and stiffness. The deck is subjected to local flex-
ural bending of the slab spanning over the girders in the transverse direction
caused by the vehicle wheel loads. When the deck is made composite, it is
also subjected to longitudinal stresses caused by flexure along the span.
18
3.3.2 Girders
A girder bridge is perhaps the most common and most basic bridge. A
log across a creek is an example of a girder bridge in its simplest form.
In modern steel girder bridges, the two most common girders are I-beam
girders and box-girders.
19
Chapter 4
4.2 Loadings
20
21
Chapter 5
5.1 Plan
5.2 Elevations
22
.
23
Chapter 6
2. Midspan
3.Bar cut-offs
24
6.3.3 Prestressing Tendon and Profile
6.3.4 Shear Reinforcement
25
Chapter 7
Conclusion and
Recommendations
7.1 Conclusion
7.2 Recommendations
26