  S-CHEM / SENDAN

ICOM LINER INSTALLATION IN SUMP S 8416


Activity ID Activity Name BL Project Start Original BL Project Finish 2016
January
Duration February March
18 25 01 08 15 22 29 07 14 21 28
Liner Installation in Sump S 8416 25-Jan-16 08:00 PM 47d 12-Mar-16 08:00 AM 12-Mar-16 08:00 AM, Liner Installation in Sump S 8416

Award of Project 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM 26-Jan-16 08:00 PM, Award of Project
A1540 Final PO Receipt & Start of Project 25-Jan-16 08:00 PM 0d Final PO Receipt & Start of Project
Safety Trainings 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM 26-Jan-16 08:00 PM, Safety Trainings
A1000 Workers Safety Training 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM Workers Safety Training
A1010 PTW Receiver Training 25-Jan-16 08:00 PM 1d 26-Jan-16 08:00 PM PTW Receiver Training
Installation of Pumps /Pipe line 26-Jan-16 08:00 PM 7d 02-Feb-16 08:00 PM 02-Feb-16 08:00 PM, Installation of Pumps /Pipe line
A1020 Taking Measurements 26-Jan-16 08:00 PM 1d 27-Jan-16 08:00 PM Taking Measurements
A1025 Mobilization of Tools & Welding Equipments 26-Jan-16 08:00 PM 1d 27-Jan-16 08:00 PM Mobilization of Tools & Welding Equipments
A1030 Making ISO Hand Drgs 27-Jan-16 08:00 PM 1d 28-Jan-16 08:00 PM Making ISO Hand Drgs

A1040 ISO Drgs Approval 28-Jan-16 08:00 PM 1d 29-Jan-16 08:00 PM ISO Drgs Approval

A1060 Temp Piping Fabrication 29-Jan-16 08:00 PM 1d 30-Jan-16 08:00 PM Temp Piping Fabrication

A1070 Installlation of Pump 30-Jan-16 08:00 PM 1d 31-Jan-16 08:00 PM Installlation of Pump

A1080 Installation of Pipes & Valves 31-Jan-16 08:00 PM 1d 01-Feb-16 08:00 PM Installation of Pipes & Valves
A1090 Isolation by Valve Closure 01-Feb-16 08:00 PM 1d 02-Feb-16 08:00 PM Isolation by Valve Closure

ICOM Workshop Fabrication 27-Jan-16 09:00 AM 8d 04-Feb-16 09:00 AM 04-Feb-16 09:00 AM, ICOM Workshop Fabrication

A1260 Plates & Structural Materials Receiving by Sendan 27-Jan-16 09:00 AM 1d 28-Jan-16 09:00 AM Plates & Structural Materials Receiving by Sendan
A1270 Liner Plates Cutting,Drilling,Bevelling 28-Jan-16 09:00 AM 3d 31-Jan-16 09:00 AM Liner Plates Cutting,Drilling,Bevelling
A1280 Structural Members Cutting 28-Jan-16 09:00 AM 2d 30-Jan-16 09:00 AM Structural Members Cutting
A1290 Coating of Liner Plates (As Per Sendan Paint Code) 31-Jan-16 09:00 AM 2d 02-Feb-16 09:00 AM Coating of Liner Plates (As Per Sendan Paint Code)
A1550 Transport of Prefabricated Plates,Structural Items (From ICOM
02-Feb-16
to S-Chem)
09:00 AM 2d 04-Feb-16 09:00 AM Transport of Prefabricated Plates,Structural Items (From ICOM to S-Chem)
Decontamination of Sump 31-Jan-16 08:00 PM 8d 08-Feb-16 08:00 PM 08-Feb-16 08:00 PM, Decontamination of Sump
A1100 Mobilization of Super Sucker (By ICOM) 31-Jan-16 08:00 PM 1d 01-Feb-16 08:00 PM Mobilization of Super Sucker (By ICOM)
A1110 Arrangement of Fixing for Sucking (By ICOM) 01-Feb-16 08:00 PM 1d 02-Feb-16 08:00 PM Arrangement of Fixing for Sucking (By ICOM)
A1120 Sucking of Contaminated Water (By ICOM) 02-Feb-16 08:00 PM 1d 03-Feb-16 08:00 PM Sucking of Contaminated Water (By ICOM)
A1130 Transportation of Contaminated Water (By Sendan) 03-Feb-16 08:00 PM 1d 04-Feb-16 08:00 PM Transportation of Contaminated Water (By Sendan)
A1140 Steaming (By Sendan) 04-Feb-16 08:00 PM 1d 05-Feb-16 08:00 PM Steaming (By Sendan)
A1150 Chemical Decontamination (By Sendan) 05-Feb-16 08:00 PM 1d 06-Feb-16 08:00 PM Chemical Decontamination (By Sendan)
Sludge Removal (By Sendan) 06-Feb-16 08:00 PM 2d 08-Feb-16 08:00 PM 08-Feb-16 08:00 PM, Sludge Removal (By Sendan)
A1160 Destagging & Depropping 06-Feb-16 08:00 PM 1d 07-Feb-16 08:00 PM Destagging & Depropping
A1170 Final Cleaning & Sludge Removal 07-Feb-16 08:00 PM 1d 08-Feb-16 08:00 PM Final Cleaning & Sludge Removal
Uninstallation of instrument & Comp. Isolation 03-Feb-16 09:00 AM 1d 04-Feb-16 09:00 AM 04-Feb-16 09:00 AM, Uninstallation of instrument & Comp. Isolation

A1180 Pump S 8416 03-Feb-16 09:00 AM 1d 04-Feb-16 09:00 AM Pump S 8416


A1190 Charcoal Filter Y8416 04-Feb-16 09:00 AM 0d 04-Feb-16 09:00 AM Charcoal Filter Y8416
A1200 Level Transmitter LT 84104 & 1" Detector 04-Feb-16 09:00 AM 0d 04-Feb-16 09:00 AM Level Transmitter LT 84104 & 1" Detector
A1210 Plugging 04-Feb-16 09:00 AM 0d 04-Feb-16 09:00 AM Plugging
Demolition of Slab & Beam Installation 04-Feb-16 09:00 AM 10d 14-Feb-16 08:00 PM 14-Feb-16 08:00 PM, Demolition of Slab & Beam Installation

A1220 Stage-1 Cutting & Repair (By Sendan) 04-Feb-16 09:00 AM 3d 07-Feb-16 09:00 AM Stage-1 Cutting & Repair (By Sendan)
A1230 Fixing of Insert Plates with Anchor Fastners 07-Feb-16 09:00 AM 1d 08-Feb-16 09:00 AM Fixing of Insert Plates with Anchor Fastners
A1240 Welding of Main Beam to Insert Plates 08-Feb-16 09:00 AM 1d 09-Feb-16 09:00 AM Welding of Main Beam to Insert Plates
A1250 Stage-2 Cutting & Repair (By Sendan) 09-Feb-16 08:00 PM 2d 11-Feb-16 08:00 PM Stage-2 Cutting & Repair (By Sendan)
A1300 Fixing of Insert Plates with Anchor Fastners 11-Feb-16 08:00 PM 1d 12-Feb-16 08:00 PM Fixing of Insert Plates with Anchor Fastners
A1310 Welding of Secondary Beam to Insert Plates 12-Feb-16 08:00 PM 2d 14-Feb-16 08:00 PM Welding of Secondary Beam to Insert Plates
Insp. and repair of Existing wall (By Sendan) 14-Feb-16 08:00 PM 4d 18-Feb-16 08:00 PM 18-Feb-16 08:00 PM, Insp. and repair of Existing wall (By Sendan)
A1320 Inspection of Existing Wall 14-Feb-16 08:00 PM 1d 15-Feb-16 08:00 PM Inspection of Existing Wall
A1330 Finalization of Methodology of Repair 15-Feb-16 08:00 PM 0d 15-Feb-16 08:00 PM Finalization of Methodology of Repair
A1340 Repair of The Wall & Curing time 15-Feb-16 08:00 PM 2d 17-Feb-16 08:00 PM Repair of The Wall & Curing time

Page 1 of 2 TASK filter: All Activities


Actual Work Critical Remaining Work Summary
Remaining Work Milestone © Oracle Corporation
  S-CHEM / SENDAN
ICOM LINER INSTALLATION IN SUMP S 8416
Activity ID Activity Name BL Project Start Original BL Project Finish 2016
January
Duration February March
18 25 01 08 15 22 29 07 14 21 28
A1350 Floor Repair,Slope & Drainage 17-Feb-16 08:00 PM 1d 18-Feb-16 08:00 PM Floor Repair,Slope & Drainage
Liner installation 18-Feb-16 08:00 PM 13d 02-Mar-16 08:00 AM 02-Mar-16 08:00 AM, Liner installation
A1390 Fixing of Liners on Floor 18-Feb-16 08:00 PM 2d 20-Feb-16 08:00 AM Fixing of Liners on Floor
A1360 Fixing of Anchor Fastners in the Wall 19-Feb-16 08:00 PM 2d 21-Feb-16 08:00 PM Fixing of Anchor Fastners in the Wall
A1400 Welding Liners Floor 20-Feb-16 08:00 AM 7d 27-Feb-16 08:00 AM Welding Liners Floor
A1370 Fixing the Liners 21-Feb-16 08:00 PM 2d 23-Feb-16 08:00 AM Fixing the Liners
A1380 Welding the Liners on Wall 23-Feb-16 08:00 AM 7d 01-Mar-16 08:00 AM Welding the Liners on Wall
A1410 Coating (Touch Up) On Liners 27-Feb-16 08:00 AM 4d 02-Mar-16 08:00 AM Coating (Touch Up) On Liners
A1405 Inspection & Welding Repairs (If Any) 27-Feb-16 08:00 AM 2d 29-Feb-16 08:00 AM Inspection & Welding Repairs (If Any)
Leak Testing (By Sendan) 02-Mar-16 08:00 AM 2d 04-Mar-16 08:00 AM 04-Mar-16 08:00 AM, Leak Testing (By Sendan)

A1420 Fill Up the Tank 02-Mar-16 08:00 AM 1d 03-Mar-16 08:00 AM Fill Up the Tank

A1430 Holding the Water for 24Hrs 02-Mar-16 08:00 AM 1d 03-Mar-16 08:00 AM Holding the Water for 24Hrs
A1440 Check the Level Drop & Draining 02-Mar-16 08:00 AM 2d 04-Mar-16 08:00 AM Check the Level Drop & Draining

Completion of Frame work and top slab 04-Mar-16 08:00 AM 6d 10-Mar-16 08:00 AM 10-Mar-16 08:00 AM, Completion of Frame work and top slab

A1450 Installation of Angles 04-Mar-16 08:00 AM 1d 05-Mar-16 08:00 AM Installation of Angles


A1460 Installation of Top Liners (By Sendan) 05-Mar-16 08:00 AM 3d 08-Mar-16 08:00 AM Installation of Top Liners (By Sendan)
A1470 Installation of Precast Panels (By Sendan) 08-Mar-16 08:00 AM 2d 10-Mar-16 08:00 AM Installation of Precast Panels (By Sendan)
A1465 Fillet Welding of Top Liner to Seconday Beam 08-Mar-16 08:00 AM 1d 09-Mar-16 08:00 AM Fillet Welding of Top Liner to Seconday Beam
Reinstallation of Instruments & Isolation Removal 10-Mar-16 08:00 AM 1d 11-Mar-16 08:00 AM 11-Mar-16 08:00 AM, Reinstallation of Instruments & Isolation Remova
A1480 Pump S8416 10-Mar-16 08:00 AM 1d 11-Mar-16 08:00 AM Pump S8416
A1490 Charcoal Filter Y8416 10-Mar-16 08:00 AM 1d 11-Mar-16 08:00 AM Charcoal Filter Y8416
A1500 Level Transmitter LT84104 10-Mar-16 08:00 AM 1d 11-Mar-16 08:00 AM Level Transmitter LT84104
A1510 1" Leak Detector 10-Mar-16 08:00 AM 1d 11-Mar-16 08:00 AM 1" Leak Detector
Demobilisation 11-Mar-16 08:00 AM 1d 12-Mar-16 08:00 AM 12-Mar-16 08:00 AM, Demobilisation
A1520 Demobilizing of Manpower & Equipments 11-Mar-16 08:00 AM 1d 12-Mar-16 08:00 AM Demobilizing of Manpower & Equipments
A1530 Submission of QC Dossier 0d 11-Mar-16 08:00 AM Submission of QC Dossier

Page 2 of 2 TASK filter: All Activities


Actual Work Critical Remaining Work Summary
Remaining Work Milestone © Oracle Corporation