Você está na página 1de 1

CRONOGRAMA VALORIZADO DE OBRA

PROYECTO:

Mes
Item Descripción Presupuesto
1 2 3
01 OBRAS PRELIMINARES 793.69
01.01 LIMPIEZA DEL TERRENO MANUAL 318.65 318.65
01.02 TRAZO, NIVELES Y REPLANTEO 475.04 475.04
02 MOVIMIENTO DE TIERRAS 3,292.08
02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS 3,292.08 3,292.08
03 ESTRUCTURAS 18,604.96
03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 + 30% P.M. 17,656.02 17,656.02
03.02 CONCRETO FALSO PISO e=4" 948.94 948.94
04 ARQUITECTURA 158,246.99
04.01 MURO LADRILLO DE ARCILLA (ADOBE) DE 0.20x0.25x0.40, JUNTA 1.5 cm. MORTERO
5,424.57
1:1:5 5,424.57
04.02 REVOQUES, ENLUCIDOS Y REVESTIMIENTO 31,137.98 31,137.98
04.03 PISO DE CEMENTO PULIDO 1,733.27 866.64 866.64
04.04 PISO VINILICO DE ALTO TRANSITO 8,459.94 8,459.94
04.05 PISO CERAMICO 0.30x0.30x0.002m 1,955.50 1,955.50
04.06 VEREDA DE CONCRETO A=2.00 h=0.15 f'c=210 kg/cm2 16,352.22 16,352.22
04.07 CARPINTERIA DE MADERA 38,000.00 38,000.00
04.08 CARPINTERIA DE METALICA 16,035.00 16,035.00
04.09 COBERTURA CON TEJA DE ARCILLA 21,518.30 21,518.30
04.10 CERRAJERIA 6,855.00 6,855.00
04.11 PINTURA EN INTERIORES 02 MANOS 5,962.82 5,962.82
04.12 PINTURA EN EXTERIORES 02 MANOS 2,853.03 2,853.03
04.13 APARATOS SANITARIOS 1,959.36 1,959.36
05 INSTALACIONES SANITARIAS 1,796.70
05.01 SALIDA DESAGUE DE PVC SAL 4" 235.60 235.60
05.02 SALIDA DESAGUE DE PVC SAL 2" 892.50 892.50
05.03 SALIDA DE AGUA FRIA TUBERIA PVC C-10 D=1/2" 377.16 377.16
05.04 CAJA DE REGISTRO DE 300 x 300 x 400 mm CON TAPA DE CONCRETO 291.44 291.44
06 INSTALACIONES ELECTRICAS 12,148.44
06.01 ACOMETIDA DOMICILIARIA CONFIGURACION LARGA 106.28 106.28
06.02 SALIDA DE ALUMBRADO EN TECHO 754.56 754.56
06.03 SALIDA PARA INTERRUPTOR SIMPLE 260.88 260.88
06.04 SALIDA PARA TOMACORRIENTE SIMPLE 552.24 552.24
06.05 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLOS 474.48 474.48
06.06 VARIOS 10,000.00
06.06.01 OBRAS NO IDENTIFICADAS 10,000.00 3,333.33 3,333.33 3,333.33

CD COSTO DIRECTO 194,882.86 30,499.69 98,500.97 65,882.20


GG GASTOS GENERALES 19,488.29 6,496.10 6,496.10 6,496.10
SUB TOTAL 214,371.15 36,995.79 104,997.07 72,378.30
ELABORACION DE EXPEDIENTE TECNICO 6,859.88 6,859.88
SUPERVISION 19,293.40 6,431.13 6,431.13 6,431.13
LIQUIDACION 5,359.28 0.00 0.00 5,359.28
MONITOREO ARQUEOLOGICO 0.00 0.00 0.00 0.00
TP TOTAL DE PRESUPUESTO 245,883.71 50,286.80 111,428.20 84,168.71
% AVANCE 100% 20.45% 45.32% 34.23%

Você também pode gostar