Você está na página 1de 6

Construction Management and Economics (2000) 18, 263± 268

NOTE

A systematic approach to the evaluation of indirect


costs of contract variations
DENISE BOWER
Centre for Research in the Management of Projects, University of Manchester Institute of Science and Technology,
P O Box 88, Manchester M60 1QD, UK

Received 21 June 1999; accepted 11 October 1999

A mechanism is proposed for the evaluation of compensation due in the event of a variation order under
contracts for construction work. It demonstrates how the indirect costs of a variation can be derived by the
use of in¯ uence curves. Commonly it is accepted that such costs are very dif® cult to evaluate systematically,
and hence the parties to the contract have been left to argue over the cost and time effects of a variation
and the compensation due. The technique suggested provides a simple solution to this problem.

Keywords: Contracts, changes, variations, costs

Introduction the valuation of interim payments and change. The


effects of time and of cost are considered separately.
Many industrial and public construction projects They may require two models, one for time and one
world-wide adopt `admeasurement’ contracts in which for cost, or they may not have a rational basis at all,
the contract price is accumulated from competitively causing con¯ ict and promoting distrust between the
tendered unit rates (Smith and Wearne, 1993; parties. Payments are based on a complex `shopping
Langford and Rowland, 1995; World Bank, 1995; list’ of rates, with the concept of a relationship between
Institution of Civil Engineers, 1996). The price ® nally time and cost non-existent. This is an unrealistic
paid is based on remeasurement of the actual quanti- assumption that causes problems for both parties,
ties of work completed. particularly in the event of a variation, so much so that
Commonly problems arise because unit rates do the cost model, when used to assess compensation in
not represent the way in which all costs are incurred. the event of change, gives a false measure. The results
Many signi® cant costs are related to both time and are claims and con¯ ict. The concept of method-related
the method of execution. A signi® cant part of a con- charges introduced in 1973 by N. M. L. Barnes in
tractor’ s costs are time related. These are most affected revising the UK Civil Engineering Standard Method of
by disruptions such as the effects of variation orders, and Measurement (Institution of Civil Engineers, 1973) goes
as such are a major source of claims and disputes part way to resolving this problem, but no systematic
(Merna et al., 1996). Variations are accepted as procedure has been established for the evaluation of
inevitable in much construction, as a project is usually variations involving disruption and delay. As a result,
only a means to an evolving end (Akinsola et al., 1997). there are many claims for additional payment and
Conditions of contract vary widely in their alloca- considerable effort is spent in their resolution. In many
tion of such risks and the relationship between time cases con¯ ict inhibits all collaboration between the
and cost. None provides a truly systematic basis for parties to the contract.
Construction Management and Economics
ISSN 0144± 6193 print/ISSN 1466-433X online € 2000 Taylor & Francis Ltd
264 Bower

The research project undertaken by the author was the speedy and fair evaluation of payments due to a
funded by the UK Engineering and Physical Sciences contractor, but the development of such systems,
Research Council and jointly managed by UMIST except in the case of cost-reimbursable contracts, has
and the University of Dundee. It was subject to the not addressed the problem of the evaluation of indi-
guidance of a steering group of clients, consultants and rect costs associated with change. Commonly it has
contractors. The results provide a new technique for been accepted that such costs are very dif® cult to eval-
the evaluation of indirect costs due to a variation, called uate systematically. Hence the parties to a contract
`in¯ uence curves’ by the author (Bower, 1996). Use have been left to argue over the cost and time effects
of this technique should reduce the scope for argu- of the variation and the compensation due. Generally,
ments, leading to better relationships between client the settlement of such costs has been left to the end
and contractor and more ef® ciently run projects. The of the contract period when all disruptive effects have
research concentrated on contracts for the construc- been `rolled up’ together, and the compensation to the
tion of bridges, roads and service reservoirs, that is, contractor has been bartered between the parties. The
relatively low risk, low technology projects. Projects effects of this are that the contractor has no certainty
unique in nature, because of the level of technological as to the outcome of the negotiations and hence has
development or high risks, were outside the scope of to allow high contingencies against the outcome. This
work as the nature of those projects might have biased causes contention between the parties as the contractor
the ® ndings of the research, but the approach adopted is continually pushing the client to settle the claim
for the development of the in¯ uence curves should be for additional costs while invariably feeling that the
relevant for any form of construction. reimbursement has been insuf® cient. This can be very
Thus the objective of the research was to develop a damaging to relationships between all parties’ repre-
mechanism that would allow the systematic evaluation sentatives. If partnering or alliancing is the policy for
of direct costs associated with contractual variations. a project, the preparatory workshop which this requires
provides a means of agreeing how to manage such
claims (McGowan et al., 1992). In this research we
The effects of a variation sought a means of avoiding the occurrence of claims.
The traditional method of settling claims for indi-
When the scope of a job is varied many tasks may be rect costs is a `horse trade’ in which one party, normally
affected both directly and indirectly. Additional costs the contractor, suggests a level of compensation for the
due to the direct effects of a variation, such as a change variation, and then the other argues for adjustment of
in resource requirements, are relatively easy to esti- that amount. This method in itself would be dif® cult
mate. The indirect effects which are dif® cult to quan- to justify if it related to individual variations, and
tify can include: normally it is undertaken for all of the changes at once
at the end of the contract, when it is impossible to
rework and lost effort on work already done;
separate out the effects of any one problem. No
time lost in stopping and restarting current tasks in
attempt is made to quantify and cost all of the effects
order to make the variation;
listed above. For example, additional management
change in cash ¯ ow, ® nancing costs, loss of earn-
time will simply be costed as a percentage of the direct
ings, etc;
costs associated with the variation, with no attempt
loss of productivity due to reprogramming, loss of
having been made to account for the fact that some-
rhythm, unbalanced gangs and acceleration;
times variations having only a small direct cost effect
revisions to project reports and documents; and
can have a large indirect effect.
loss of ¯ oat, therefore increased sensitivity to delay.
These strategies are not systematic and they are all
It is common for the contractor to work to a responsible for furthering the arguments between client
programme that is not contractual. This further and contractor and prolonging claims situations.
complicates the evaluation of compensation for the
indirect costs of a variation. The time effects translate
into a cost because either the contract duration will be Evaluating indirect costs
extended, which means that overheads and ® nancing
are increased, or the work has to be accelerated, leading A systematic approach to the assessment of indirect
to the inef® cient use of resources. costs associated with a change needs to take account
In 1993 Thomas and Napolitan stated that `there of those costs which arise due to a number of tasks
have been no de® nitive studies reporting in quanti- being performed at the same time, whether they are
tative terms the impact of changes’. Much attention logically linked or not, and the effects of `ripples’
has been given to payment mechanisms that allow for through the programme due to logic links. These could
Indirect costs of contract variations 265

be thought of as vertical and horizontal relationships 2. Recalculation of network, increased time-related


within a bar chart programme, vertical links taking charges and overheads.
account of the control needed for a number of tasks 3. Rework, standing time for subcontractors.
to be live at any one time, and horizontal links being 4. Timing effects, for example, winter working.
the more traditional logic links. 5. In¯ ation, change to cash ¯ ow, loss of earnings,
Thomas and Napolitan (1993) described a `factor etc.
model’ which provides a means for understanding 6. Management time, head of® ce and site.
and quantifying the effects of change on labour pro-
The more of these included as a direct cost, the lower
ductivity. The factor model does not take into account
should be the in¯ uence factor. For civil engineering
the `cumulative or ripple effect that occurs when project
it seems sensible to de® ne a direct cost as the change
conditions have deteriorated to the point where work on
in cost associated with tasks whose resource usage is
a task is adversely affected by another task or by the mere
changed due to the variation, that is, tasks whose dura-
nature of the site environment’. Thomas and Napolitan
tion is increased due to the variation. These affected
went on to say that `no research has been conducted on
tasks are apparent without recalculation of the network
the ripple effect, although it has been acknowledged
as long as the programme is clear.
quite often by construction professionals’.
In cases where a subcontractor is already on site and
Another systematic approach that has been taken
it is not possible for him to perform other work, an
in the assessment of these costs has been developed
allowance for standing time must be included as a
empirically by Fluor Daniel Ltd for use in process
direct cost. In effect the subcontractor will have to be
plant contracts (private communication). It is known
paid time-related charges as though he was working,
as `Impact’ . It is applied to the estimate of additional
therefore constituting an extension to the duration of
direct costs, cost being cost to the client due to the
the task.
variation.
The approach of establishing a standard `in¯ uence
curve’ from which a factor could be sought in the
The shape of the in¯ uence curve
event of a variation was believed by the author to be
a systematic, rapid and equitable technique for indi-
The author aimed to derive in¯ uence curves that
cating the indirect costs. In the research, curves were
could be used to evaluate the indirect costs of contract
developed recognizing that different types of work may
variation and that could be adopted as standard for
require different curves. Initially, research concentrated
certain types of work, such as road building. As many
on producing a curve for road building. A numerical
construction projects are unique by nature some
rather than an empirical approach was sought by which
clients may want to derive their own curves, so a simple
the curve could be derived. Further validation of the
derivation was sought that would allow users to verify
curves focuses on the establishment of a database of
for themselves the most appropriate shape of curve.
projects from which curves can be derived.
Two approaches have been taken in the derivation
It was important that the technique for curve devel-
of an in¯ uence curve. They have both developed from
opment should be simple enough to be used by clients
the philosophy that there are two major in¯ uences on
to derive their own curves for unique projects.
the shape of the curve: (i)the more live tasks at any
given time, the greater is the effect of a variation, and
(ii) the less the scope available for reworking the
Determining direct cost
programme, the greater is the effect of a variation.
For the ® rst approach a variation is introduced to a
In the use of in¯ uence curves cost is the cost to the
project at various points in time and then the direct
client. Therefore whenever possible, rates tendered
costs associated with that variation are assessed. The
by the contractor should be used to assess the direct
direct costs are then factored by the number of live
cost. If actual costs have to be used, an addition for
tasks at that point in time (to take account of the ripple
pro® t should be made after the in¯ uence adjustment,
effect) and summed for the project. For the second
according to the terms of the contract. The in¯ uence
approach the level of resourcing was assessed at various
curve is then used to assess the indirect part of the
points in time then combined with the rigidity of the
compensation when there is a variation.
programme (rigidity being the lack of ¯ oat).
The elements listed below, in order of increasing
The derivation of these curves is detailed below. It
subjectivity, make up the cost associated with change.
should be noted that once a satisfactory curve shape
1. Time and material related charges related to has been obtained it is used as a standard, and an
immediately affected tasks. in¯ uence curve need be derived from ® rst principles
266 Bower

only for projects that are out of the ordinary, as already hammock rather than a task (general overhead
stated. The simplicity of the technique means that if hammocks are excluded in this example).
a client were unsure whether his project suited the 5. Calculate the percentage change in budget, i.e.
criteria for a particular standard curve it would be (change in budget/original budget) ´ 100.
relatively easy to derive a unique curve. 6. Weight the percentage change in budget by a
A workshop for preparing for partnering on a project task multiplier de® ned as the number of other
would provide the opportunity to agree the value live tasks within the same category at the time
of in¯ uence factors appropriate to that project if the of the disruption. If a hammock is being used
parties felt that they needed review. Simulation of then the multiplier is the number of other
the effects of risks identi® ed at that workshop would hammocks in that category plus the number of
indicate the compensation for indirect costs before an other tasks live in that category which are not
event, so allowing client and contractor to assure them- spanned by the hammock.
selves that the results would be equitable.
These ® gures should then be summed to give the
weighted cumulative percentage change. This is plotted
Derivation of the in¯ uence curve against time to give the in¯ uence curve.
The change in cost was translated into a percentage
The derivation of the curve uses only the change in change from the original budget which was then
cost associated with tasks whose resource usage is factored by the number of other tasks in the same cate-
changed due to the variation, that is, tasks whose dura- gory that were live at the time of the disruption. This
tion is increased due to the variation. In cases where gave a weighted percentage change taking into account
a subcontractor is already on site and it is not possible the vertical links or `ripple’ effect. The cumulative
for him to perform other work, an allowance for percentage change was plotted against time to achieve
standing time must be included as a direct cost. In the effect of the in¯ uence curve increasing with time.
effect the subcontractor will have to be paid time- Once an in¯ uence curve has been plotted it is used in
related charges as though he was working, therefore the event of a variation by multiplying the direct costs
constituting an extension to the duration of the task. associated with the variation by the in¯ uence factor
These were the direct costs. The other costs listed and adding this amount to the direct cost to give the
earlier become the indirect costs that the in¯ uence total cost of the variation to the client. The shape of
factor takes account of. the curve was tested by using delays of differing dura-
tions and each time the shape remained constant. The
proposed in¯ uence curve is shown in Figure 1. The
Approach A shape of the curve was veri® ed using approach B.

1. De® ne intervals at which analysis will take place.


Shorter time periods are required from 20 to Approach B
65% of project completion time. In this case the curve is derived by summing ¯ oat and
2. At a given time examine the programme and resource usage days.
note all of the tasks that are live. Determine
how many logic links each of those tasks has 1. Count the maximum number of days ¯ oat at
and how many of the live tasks are in the same day 1.
category. The number of categories is deter- 2. At speci® ed time intervals count the number
mined according to the phasing of the work. of days of ¯ oat remaining. This is calculated
(For the purposes of this methodology a cate- by assuming that tasks prior to the assessment
gory is a work phase, and an example would date have actually occurred as late as possible
be: preliminary work, category 1; roadworks, without affecting the project end date and
category 2; and tie-ins, category 3.) counting how many days ¯ oat are left.
3. Apply the disruption to the task with the most 3. For the derivation of an in¯ uence curve it is the
logic links. In the ® rst instance a delay of ® ve inverse of this that is of interest, or the rigidity:
days was used, that is the duration of the task if the original number of days ¯ oat was F, then
with the most logic links was extended by ® ve the rigidity is F ± x, where x = F for the ® rst
days. In instances where there is more than one period and x = 0 for the ® nal period.
task with a large number of logic links apply the 4. At the same points in time as the ¯ oat is assessed
delay to each in turn and note the largest change the level of resourcing also must be noted. The
in project budget. number of labour days being worked on the site,
4. Whenever possible apply the change to a including machine drivers, is calculated.
Indirect costs of contract variations 267

in order to judge the full scale of the task.


The rigidity (for total ¯ oat) and resource curves were
combined (summed) to give an alternative in¯ uence
curve. This curve was almost identical in shape to the
curve derived using approach A.
Although the scope of the research was limited in
terms of the number of projects that could be evalu-
ated, it was encouraging to ® nd that both approaches
resulted in a curve of the shape that the steering group
had anticipated.
Regarding the actual in¯ uence factors the steering
group agreed that if either the client or the contractor
felt that the scale was inappropriate to them then
Figure 1 In¯ uence curve for a project new factors could be negotiated or bid. However, once
the in¯ uence factors have been agreed for a project
5. The rigidity and labour days are summed to give then they should be ® xed. This does not dilute the
an in¯ uence curve. effectiveness of the approach as the outcome would
still be the same, that is, there would be a systematic
Study of cumulative cost curves showed an envelope
approach to the evaluation of variations.
if the tasks are scheduled to take place as soon as
possible and as late as possible. This envelope is at its
broadest when the project is two-thirds complete and
Case study
illustrates a number of points: (i) the wider the band,
the more ¯ oat is available for rescheduling the tasks
The project used to illustrate brie¯ y the use of the
at any given point in time; and (ii) the narrower the
in¯ uence curve consisted of the construction of
envelope from project to project, the less scope there
two kilometres of a single carriageway rural road in
is for rescheduling tasks as the project progresses,
North Yorkshire. The indirect costs associated with
consistent with the ® ndings of Hajarat and Smith
the change may be evaluated using the in¯ uence curve
(1992). The implications for in¯ uence factors are that
shown in Figure 1.
as the project progresses there is greater scope for the
The ® rst variation was a disruption to the disposal
manoeuvre of individual tasks until a point approxi-
of unsuitable excavated material. The contract price
mately two-thirds of the way through the project, but
was £2 093 124. The scheduled accumulated price by
since many tasks are going on at any one time the
the time of the change was £370 067, or 17% of the
effect of any change is large.
total. Using this ® gure, an in¯ uence factor of 3% is
The analysis of the cumulative cost envelope led to
given and so should be applied to the direct costs to
an investigation of the availability of ¯ oat as a project
give the total compensation due to the contractor. This
progresses, both total and free ¯ oat. It was found that
® gure may seem low as compensation for the disrup-
the number of days available reduces to approximately
tive effects, but the project is still at a relatively early
5% of the original amount with 25% of the project
stage of its development and so there is time for
duration remaining. This reinforces the theory that
economic replanning. At this time the number of other
although there are fewer tasks that may be disrupted,
live activities is relatively low, so the ripple effect will
the scope for reducing the effect of change through the
be minimal. The direct charges associated with this
use of ¯ oat decreases.
variation are: 1 no. wagon for 55 days = £14 850 and
The other half of the theory behind the shape of the
two days extra work from excavation plant = £5011,
in¯ uence curve when using this approach is that the
giving a total direct cost of £19 861. The total amount
amount of control required increases steadily until
of compensation due to the contractor is therefore
the project is about 60% complete and then, as the
£19 861 3 1.03 = £20 457. The direct costs could be
number of tasks decreases, the amount of control
determined from a number of sources depending on
required falls off. In approach A the number of live
the conditions of contract.
tasks at any one point in time was measured to give
The second variation relates to the reworking of the
an indication of this effect. The alternative approach
surface levels of a stretch of the road. The kerbing
taken here was to measure the number of men working
subcontractor was already on the site when the change
at any one time. This required summation of the
was introduced, and therefore a charge for standing
number of man-hours being worked at any given time
time was incurred. As the kerbing was delayed, the
through the project; machine operators were included
surfacing was disrupted. The surfacing subcontractor
268 Bower

was already on site, so again standing time has to be ® nancial risks to both parties should lead to lower bid
paid. In this example there were four classes of prices. The rapid evaluation of the payment due to the
work which needed price adjustment. These are contractor would decrease the management effort
outlined below, with an opinion as to whether or not required in the measurement and valuation process,
they constitute direct charges or are included in the reducing project overheads. This systematic technique
in¯ uence factor. should help the industry achieve the team working advo-
cated in major reports and supported by many in the con-
Subbase Ð direct charge Ð involves actual work
struction industry in the UK, USA and other countries
being done due to variation: of £1132.
(Latham, 1994; Construction Industry Board, 1997).
Kerbs Ð direct charge Ð direct delay due to vari-
ation: of £4823.
Surfacing Ð direct charge Ð systematic evaluation
is possible: £14 207. Acknowledgements
Overheads Ð indirect charge Ð in¯ uence factor
accounts for change to indirect charges. The research team are very grateful to Fluor Daniel
Ltd and all the members of the Steering Group for
The appropriate in¯ uence factor should therefore be
their advice and ideas on this research.
applied to £1 132 + £4 823 + £14 207= £20 162.
When the variation was noti® ed the project was 72%
complete in terms of price, giving an in¯ uence factor
of 70%, and hence the total compensation due to the References
contractor is 1.7 3 £20 162 = £34 275.
Akinsola, A.O., et al. (1997) Identi® cation and evaluation
of factors in¯ uencing variations on building projects,
International Journal of Project Management, 15(4), 263± 67.
Conclusions Bower, D.A. (1996) Evaluating the Indirect Cost of Change,
International Project Management Association Congress,
Existing methods of evaluating payment due for vari- Paris.
ations cause disputes and con¯ ict on site and between Construction Industry Board (1997) Partnering in the Team,
all parties’ representatives. This con¯ ict needs to be Report WG12, Thomas Telford, London.
removed. If the reputation of the construction industry Hajarat, D.A. and Smith, N.J. (1992) Exposure Envelopes: An
is to be enhanced, encouraging investment, then the Assessment of the Exposure to Time and Cost Overruns during
parties to the contract must have aligned goals. A goal Construction Projects, University of Shef® eld.
that the parties share is to optimize their pro® ts or Institution of Civil Engineers (1973) Civil Engineering
improve their business performance. For the client Standard Method of Measurement (CESMM), Thomas
Telford, London.
this may mean working to a tight budget or schedule
Institution of Civil Engineers (1996) Civil Engineering
to meet constraints external to the project. To a Procedure, 5th Edn, Thomas Telford, London.
contractor it may mean achieving an acceptable pro® t Langford, D.A. and Rowland, V.R. (1995) Managing Overseas
margin, enhanced by reduced ® nancing costs and a Construction Contracting, Thomas Telford, London.
secure ¯ ow of cash into his organization. Latham, M. (1994) Constructing the Team, HMSO, London.
The optimum level of the in¯ uence curve can be McGowan, H., Horner, R.M.W., Jones, D. and Thompson,
fully veri® ed only through data collection of the indi- P.A. (1992) The Allocation and Evaluation of Risks in
rect costs associated with contractual change: this Construction Contracts, Occasional Paper No. 52, Chartered
requires dedicated research over a long period of time. Institute of Building, Ascot.
The results from the different approaches taken in the Merna, A., Bower, D.A. and Abbasi, A. (1996) Dispute
curve derivation inspire con® dence that the in¯ uence Resolution in Construction and Infrastructure Projects, Asia Law
& Practice, Hong Kong.
factors are robust. The simplicity of the derivation and
Smith, N.J., and Wearne, S.H. (1993) Construction Contract
the scope for negotiation before the work on site
Arrangements in EU Countries, European Construction
commences further support the use of the curves. Institute, Loughborough.
The in¯ uence curve method can prevent many of Thomas H.R. and Napolitan C. (1993) Anatomy of a
today’ s problems. It increases clients’ certainty as to the Construction Change in Proceedings of CIB-W65 Conference,
® nal cost of a project. It increases the contractor’s cer- Trinidad, pp. 1195± 203.
tainty as to the compensation he will be paid in the event World Bank (1995) Procurement of Works, The World Bank,
of a change to the work. This general reduction in the Washington.

Você também pode gostar