a) Labour
0.02 Mate 361 day 7.22
0.5 Mazdoor (Unskilled) 314 day 157
b) Machinery 164.22
4 Tractor with Grader @ 25 cum per hour 380 hour 1520
2 Water tanker 6 kl capacity 310 hour 620
1.25 Three wheel 80-100 kN Static Roller 460 hour 575
2715
c) Material Km : 0/000 - 1/000 Km : 1/000 - 2/000
116 Gravel (assuming 16 per cent 283.92 Cu.m 32934.72 291.51 33815.16
12 Water 130 kl 1560 130 1560
1 Labour 164.22 164.22 164.22 164.22
1 Machinery 2715 2715 2715 2715
d) Overheads @ 12.5 % on (a+b+c) 4671.74 4781.8
Cost for 100 cum = a+b+c+d 42045.68 43036.18
Rate for 1 m3 420.46 430.36
from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 3
Km :2/000 - 3/000
299.1 34695.6
130 1560
164.22 164.22
2715 2715
4891.85
44026.67
440.27
to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)