Você está na página 1de 39

Presupuesto

Presupuesto CONSTRUCCION DE TROCHA CARROZABLE LLACLLIN - QUISUAR KM : 3+240 - 5+540.


Subpresupuesto CONSTRUCCION DE TROCHA CARROZABLE LLACLLIN - QUISUAR KM : 3+240 - 5+540.
Cliente MUNICIPALIDAD DISTRITAL DE HUANCHAY
Lugar ANCASH - HUARAZ - HUANCHAY Costo al 01/10/2008

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PRELIMINARES 1,088.67


01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m glb 1.00 586.00 586.00
01.02 ALMACEN OFICINA Y SS.HH glb 1.00 502.67 502.67

02 TRABAJOS PRELIMARES 17,876.30


02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO PESADO glb 1.00 12,000.00 12,000.00
02.02 ROCE Y DESBROCE m2 10,000.00 0.42 4,200.00
02.03 TRAZO Y REPLANTEO km 2.00 838.15 1,676.30

03 EXPLANACIONES 222,309.51
03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=400 m3/día m3 6,847.35 7.60 52,039.86
03.02 CORTE ROCA SUELTA (PERFORACION Y DISPARO) m3 1,310.00 46.17 60,482.70
03.03 CORTE ROCA FIJA (PERFORACION Y DISPARO) m3 1,115.24 65.17 72,680.19
03.04 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES m3 430.06 4.88 2,098.68
03.05 RELLENO CON MATERIAL DE PRESTAMO MANUAL m3 2,500.00 3.14 7,850.00
03.06 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE m3 6,772.59 4.01 27,158.09

04 OBRAS DE ARTE Y DRENAJE 28,295.53


04.01 CUNETAS 16,400.00
04.01.01 CONSTRUCCION DE CUNETAS LATERALES EN MATERIAL SUELTO m 1,200.00 7.00 8,400.00
04.01.02 CONSTRUCCION DE CUNETAS LATERALES EN ROCA SUELTA m 800.00 10.00 8,000.00

04.02 BADENES 8,158.26


04.02.01 EXCAVACION MANUAL m3 24.08 24.65 593.57
04.02.02 ELIMINACION DE MATERIAL CARGUIO MANUAL m3 36.55 1.96 71.64
04.02.03 ENCOFRADO Y DESENCOFRADO PARA BADENES m2 20.78 73.38 1,524.84
04.02.04 CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO m3 5.19 476.21 2,471.53
04.02.05 CONCRETO f'c=140 kg/cm2 m3 3.38 423.14 1,430.21
04.02.06 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS DE FONDO PISO kg 251.73 8.08 2,033.98
04.02.07 JUNTAS ASFALTICAS m 5.19 6.26 32.49

04.03 ALCANTARILLADO 3,737.27


04.03.01 EXCAVACION MANUAL m3 4.82 24.65 118.81
04.03.02 RELLENO ESTRUCTURAL m3 2.36 65.91 155.55
04.03.03 ENCOFRADO Y DESENCOFRADO m2 14.25 48.03 684.43
04.03.04 CONCRETO f'c=140 kg/cm2 m3 2.38 423.14 1,007.07
04.03.05 CONCRETO f'c=210 kg/cm2 m3 1.62 496.47 804.28
04.03.06 ACERO fy=4200 kg/cm2 GRADO 60 kg 50.35 8.13 409.35
04.03.07 ALCANTARILLA TMC 0=36" m 2.00 278.89 557.78

05 FLETE 8,900.00
05.01 TRANSPORTE DE PETROLEO Y OTROS glb 1.00 8,900.00 8,900.00

COSTO DIRECTO 278,470.01


GASTOS GENERALES (8.00%) 22,277.60
UTLIDADES (8.00%) 22,277.60
------------------
SUBTOTAL 323,025.21
IGV (19%) 61,374.79
------------------
PRESUPUESTO TOTAL 384,400.00
SON : Cuatrocientos Mil Y 01/100 NUEVOS SOLES
------------------
S10

Análisis de precios unitarios

Presupuesto 0402006 CONSTRUCCION DE TROCHA CARROZABLE LLACLLIN - QUISUAR KM : 3+240 - 5+840.


Subpresupuesto 001 CONSTRUCCION DE TROCHA CARROZABLE LLACLLIN - QUISUAR KM : 3+240 - 5+840
Partida 01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m

Rendimiento glb/DIA EQ. Costo unitario directo por : glb

Código Descripción Recurso Unidad Cuadrilla Cantidad


Materiales
0239130017 CARTELES DE OBRA glb 1.0000

Partida 01.02 ALMACEN OFICINA Y SS.HH

Rendimiento glb/DIA EQ. Costo unitario directo por : glb

Código Descripción Recurso Unidad Cuadrilla Cantidad


Materiales
0239130018 ALMACEN DE OBRA glb 1.0000

Partida 02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO PESADO

Rendimiento glb/DIA 1.0000 EQ. 1.0000 Costo unitario directo por : glb

Código Descripción Recurso Unidad Cuadrilla Cantidad


Materiales
0232970001 MOVILIZACION Y DESMOVILIZACION DE EQUIPO est 1.0000

Partida 02.02 ROCE Y DESBROCE

Rendimiento m2/DIA 400.0000 EQ. 400.0000 Costo unitario directo por : m2

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0020
0147010004 PEON hh 3.0000 0.0600

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 5.0000

Partida 02.03 TRAZO Y REPLANTEO

Rendimiento km/DIA 0.4000 EQ. 0.4000 Costo unitario directo por : km

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147000032 TOPOGRAFO hh 1.0000 20.0000
0147010004 PEON hh 2.0000 40.0000

Materiales
0230550058 NIVEL hm 22.8571
0244010001 ESTACA DE MADERA p2 50.0000
0254060037 PINTURA ESMAL. METAL - MAT. ESMALTEX C/COLOR gal 0.2000

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000
0349880003 TEODOLITO hm 1.0000 20.0000

Partida 03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=400 m3/día

Rendimiento m3/DIA 600.0000 EQ. 600.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147000023 OPERADOR DE EQUIPO PESADO hh 1.0000 0.0133
0147010001 CAPATAZ hh 0.2000 0.0027
0147010003 OFICIAL hh 1.0000 0.0133
0147010004 PEON hh 3.0000 0.0400
0147010023 CONTROLADOR OFICIAL hh 1.0000 0.0133

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000
0349080095 TRACTOR D7 hm 1.0000 0.0133

Partida 03.02 CORTE ROCA SUELTA (PERFORACION Y DISPARO)

Rendimiento m3/DIA 250.0000 EQ. 250.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147000023 OPERADOR DE EQUIPO PESADO hh 1.0000 0.0320
0147010001 CAPATAZ hh 0.2000 0.0064
0147010003 OFICIAL hh 1.0000 0.0320
0147010004 PEON hh 3.0000 0.0960
0147010023 CONTROLADOR OFICIAL hh 1.0000 0.0320
0147010025 PERFORISTA OFICIAL hh 0.5000 0.0160

Materiales
0227000001 MECHA NARANJA m 1.0000
0227020011 FULMINANTE u 1.0000
0228000022 DINAMITA kg 0.2500
0230020096 BARRENO 5' X 1/8" u 0.0170

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000
0349020003 COMPRESORA NEUMATICA 196 HP 600-690 PCM d 1.0000 0.0040
0349060001 MARTILLO NEUMATICO DE 21 kg hm 1.0000 0.0320
0349080095 TRACTOR D7 hm 1.0000 0.0320

Partida 03.03 CORTE ROCA FIJA (PERFORACION Y DISPARO)

Rendimiento m3/DIA 220.0000 EQ. 220.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147000023 OPERADOR DE EQUIPO PESADO hh 1.0000 0.0364
0147010001 CAPATAZ hh 0.2000 0.0073
0147010003 OFICIAL hh 1.0000 0.0364
0147010004 PEON hh 4.0000 0.1455
0147010023 CONTROLADOR OFICIAL hh 1.0000 0.0364
0147010025 PERFORISTA OFICIAL hh 2.0000 0.0727

Materiales
0227000001 MECHA NARANJA m 1.0000
0227020011 FULMINANTE u 1.0000
0228000022 DINAMITA kg 0.2500
0230020096 BARRENO 5' X 1/8" u 0.0170

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000
0349020002 COMPRESORA NEUMATICA 196 HP 600-690 PCM hm 1.0000 0.0364
0349060001 MARTILLO NEUMATICO DE 21 kg hm 4.0000 0.1455
0349080095 TRACTOR D7 hm 1.0000 0.0364

Partida 03.04 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES

Rendimiento m3/DIA 75.0000 EQ. 75.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0213
0147010003 OFICIAL hh 1.0000 0.1067
0147010004 PEON hh 5.0000 0.5333

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 5.0000

Partida 03.05 RELLENO CON MATERIAL DE PRESTAMO MANUAL

Rendimiento m3/DIA 1,000.0000 EQ. 1,000.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0016
0147010003 OFICIAL hh 1.0000 0.0080
0147010004 PEON hh 4.0000 0.0320

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 2.0000
0349080095 TRACTOR D7 hm 1.0000 0.0080

Partida 03.06 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE

Rendimiento m3/DIA 720.0000 EQ. 720.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0022
0147010003 OFICIAL hh 1.0000 0.0111
0147010004 PEON hh 3.0000 0.0333
0147010023 CONTROLADOR OFICIAL hh 0.5000 0.0056
Equipos
0349080095 TRACTOR D7 hm 1.0000 0.0111

Partida 04.01.01 CONSTRUCCION DE CUNETAS LATERALES EN MATERIAL SUELTO

Rendimiento m/DIA 26.0000 EQ. 26.0000 Costo unitario directo por : m

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0615
0147010003 OFICIAL hh 1.0000 0.3077
0147010004 PEON hh 4.0000 1.2308

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 5.0000

Partida 04.01.02 CONSTRUCCION DE CUNETAS LATERALES EN ROCA SUELTA

Rendimiento m/DIA 20.0000 EQ. 20.0000 Costo unitario directo por : m

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0800
0147010003 OFICIAL hh 1.0000 0.4000
0147010004 PEON hh 4.0000 1.6000

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 5.0000

Partida 04.02.01 EXCAVACION MANUAL

Rendimiento m3/DIA 2.8000 EQ. 2.8000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.5714
0147010004 PEON hh 1.0000 2.8571

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000

Partida 04.02.02 ELIMINACION DE MATERIAL CARGUIO MANUAL

Rendimiento m3/DIA 175.0000 EQ. 175.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0091
0147010003 OFICIAL hh 2.0000 0.0914
0147010004 PEON hh 3.0000 0.1371

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000
Partida 04.02.03 ENCOFRADO Y DESENCOFRADO PARA BADENES

Rendimiento m2/DIA 8.0000 EQ. 8.0000 Costo unitario directo por : m2

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010002 OPERARIO hh 1.0000 1.0000
0147010003 OFICIAL hh 1.0000 1.0000
0147010004 PEON hh 3.0000 3.0000

Materiales
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 0.3000
0202010022 CLAVOS Fo No C/C 3/4 " kg 0.1700
0243600002 MADERA NACIONAL P/ENCOFRADO - CARP p2 5.3200

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 2.0000

Partida 04.02.04 CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO

Rendimiento m3/DIA 22.0000 EQ. 22.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0727
0147010002 OPERARIO hh 1.0000 0.3636
0147010003 OFICIAL hh 2.0000 0.7273
0147010004 PEON hh 4.0000 1.4545

Materiales
0221000001 CEMENTO PORTLAND TIPO I (42.5 kg) bls 9.7300
0238000000 HORMIGON (PUESTO EN OBRA) m3 1.3400
0239050000 AGUA m3 0.2100

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 1.0000
0349070006 VIBRADOR DE CONCRETO 3/4" - 2" hm 1.0000 0.3636
0349100007 MEZCLADORA DE CONCRETO TAMBOR 18 HP 11 p3 hm 1.0000 0.3636

Partida 04.02.05 CONCRETO f'c=140 kg/cm2

Rendimiento m3/DIA 15.0000 EQ. 15.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.1067
0147010002 OPERARIO hh 1.0000 0.5333
0147010003 OFICIAL hh 2.0000 1.0667
0147010004 PEON hh 8.0000 4.2667

Materiales
0221000001 CEMENTO PORTLAND TIPO I (42.5 kg) bls 6.4000
0238000000 HORMIGON (PUESTO EN OBRA) m3 1.4700
0239050000 AGUA m3 0.1470

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 1.0000
0349100007 MEZCLADORA DE CONCRETO TAMBOR 18 HP 11 p3 hm 1.0000 0.5333

Partida 04.02.06 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS DE FONDO PISO

Rendimiento kg/DIA 210.0000 EQ. 210.0000 Costo unitario directo por : kg

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0076
0147010002 OPERARIO hh 1.0000 0.0381
0147010003 OFICIAL hh 1.0000 0.0381

Materiales
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 0.0500
0203020003 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1.0500

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 2.0000

Partida 04.02.07 JUNTAS ASFALTICAS

Rendimiento m/DIA 100.0000 EQ. 100.0000 Costo unitario directo por : m

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0160
0147010003 OFICIAL hh 1.0000 0.0800
0147010004 PEON hh 3.0000 0.2400

Materiales
0204000000 ARENA FINA m3 0.0020
0213000006 ASFALTO RC-250 gal 0.1330

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000

Partida 04.03.01 EXCAVACION MANUAL

Rendimiento m3/DIA 2.8000 EQ. 2.8000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.5714
0147010004 PEON hh 1.0000 2.8571

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000

Partida 04.03.02 RELLENO ESTRUCTURAL

Rendimiento m3/DIA 86.0000 EQ. 86.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147000023 OPERADOR DE EQUIPO PESADO hh 1.0000 0.0930
0147010004 PEON hh 31.4200 2.9228

Materiales
0205010004 ARENA GRUESA m3 0.5450
0239050000 AGUA m3 0.0650

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 2.0000
0349030001 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 1.0000 0.0930

Partida 04.03.03 ENCOFRADO Y DESENCOFRADO

Rendimiento m2/DIA 8.0000 EQ. 8.0000 Costo unitario directo por : m2

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010002 OPERARIO hh 1.0000 1.0000
0147010003 OFICIAL hh 1.0000 1.0000
0147010004 PEON hh 0.2000 0.2000

Materiales
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 0.1200
0202010022 CLAVOS Fo No C/C 3/4 " kg 0.2200
0243600002 MADERA NACIONAL P/ENCOFRADO - CARP p2 4.0700

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000

Partida 04.03.04 CONCRETO f'c=140 kg/cm2

Rendimiento m3/DIA 15.0000 EQ. 15.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.1067
0147010002 OPERARIO hh 1.0000 0.5333
0147010003 OFICIAL hh 2.0000 1.0667
0147010004 PEON hh 8.0000 4.2667

Materiales
0221000001 CEMENTO PORTLAND TIPO I (42.5 kg) bls 6.4000
0238000000 HORMIGON (PUESTO EN OBRA) m3 1.4700
0239050000 AGUA m3 0.1470

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 1.0000
0349100007 MEZCLADORA DE CONCRETO TAMBOR 18 HP 11 p3 hm 1.0000 0.5333

Partida 04.03.05 CONCRETO f'c=210 kg/cm2

Rendimiento m3/DIA 12.0000 EQ. 12.0000 Costo unitario directo por : m3

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.1333
0147010002 OPERARIO hh 1.0000 0.6667
0147010003 OFICIAL hh 1.0000 0.6667
0147010004 PEON hh 6.0000 4.0000

Materiales
0221000001 CEMENTO PORTLAND TIPO I (42.5 kg) bls 9.7300
0238000000 HORMIGON (PUESTO EN OBRA) m3 1.3400
0239050000 AGUA m3 0.1850

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000
0349100011 MEZCLADORA DE CONCRETO TROMPO 8 HP 9 p3 hm 1.0000 0.6667

Partida 04.03.06 ACERO fy=4200 kg/cm2 GRADO 60

Rendimiento kg/DIA 250.0000 EQ. 250.0000 Costo unitario directo por : kg

Código Descripción Recurso Unidad Cuadrilla Cantidad


Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0064
0147010002 OPERARIO hh 1.0000 0.0320
0147010003 OFICIAL hh 1.0000 0.0320

Materiales
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 0.0600
0203020003 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1.0700

Equipos
0337010001 HERRAMIENTAS MANUALES %MO 3.0000

Partida 04.03.07 ALCANTARILLA TMC 0=36"

Rendimiento m/DIA 10.0000 EQ. 10.0000 Costo unitario directo por : m

Código Descripción Recurso Unidad Cuadrilla Cantidad


Subpartidas
909701043205 RELLENO DE FUNDACIONES RENDIMIENTO=12 m3/día m3 1.5520
909701043410 ALCANTARILLA TMC 0=36" C=14 R=10 m/día m 1.0000

Partida 05.01 TRANSPORTE DE PETROLEO Y OTROS

Rendimiento glb/DIA EQ. Costo unitario directo por : glb

Código Descripción Recurso Unidad Cuadrilla Cantidad


Materiales
0232010007 TRANSPORTE DE PETROLEO Y OTROS glb 1.0000

Fecha :
Página : 1

Fecha presupuesto 01/10/2008

580.00

Precio S/. Parcial S/.

580.00 580.00
580.00

600.00

Precio S/. Parcial S/.

600.00 600.00
600.00

16,000.00

Precio S/. Parcial S/.

16,000.00 16,000.00
16,000.00

0.42

Precio S/. Parcial S/.

10.63 0.02
6.25 0.38
0.40

0.40 0.02
0.02

838.15

Precio S/. Parcial S/.

3.75 75.00
6.25 250.00
325.00
4.20 96.00
5.50 275.00
32.00 6.40
377.40

325.00 9.75
6.30 126.00
135.75

5.05

Precio S/. Parcial S/.

11.25 0.15
10.63 0.03
10.25 0.14
6.25 0.25
10.25 0.14
0.71

0.71 0.02
325.00 4.32
4.34

33.07

Precio S/. Parcial S/.

11.25 0.36
10.63 0.07
10.25 0.33
6.25 0.60
10.25 0.33
10.25 0.16
1.85

4.62 4.62
6.30 6.30
12.61 3.15
195.00 3.32
17.39

1.85 0.06
270.00 1.08
71.43 2.29
325.00 10.40
13.83

45.65

Precio S/. Parcial S/.

11.25 0.41
10.63 0.08
10.25 0.37
6.25 0.91
10.25 0.37
10.25 0.75
2.89

4.62 4.62
6.30 6.30
12.61 3.15
195.00 3.32
17.39

2.89 0.09
84.03 3.06
71.43 10.39
325.00 11.83
25.37

4.88

Precio S/. Parcial S/.

10.63 0.23
10.25 1.09
6.25 3.33
4.65

4.65 0.23
0.23

2.91

Precio S/. Parcial S/.

10.63 0.02
10.25 0.08
6.25 0.20
0.30

0.30 0.01
325.00 2.60
2.61

4.01

Precio S/. Parcial S/.

10.63 0.02
10.25 0.11
6.25 0.21
10.25 0.06
0.40
325.00 3.61
3.61

12.06

Precio S/. Parcial S/.

10.63 0.65
10.25 3.15
6.25 7.69
11.49

11.49 0.57
0.57

15.70

Precio S/. Parcial S/.

10.63 0.85
10.25 4.10
6.25 10.00
14.95

14.95 0.75
0.75

24.65

Precio S/. Parcial S/.

10.63 6.07
6.25 17.86
23.93

23.93 0.72
0.72

1.96

Precio S/. Parcial S/.

10.63 0.10
10.25 0.94
6.25 0.86
1.90

1.90 0.06
0.06
73.28

Precio S/. Parcial S/.

11.25 11.25
10.25 10.25
6.25 18.75
40.25

6.30 1.89
6.30 1.07
5.50 29.26
32.22

40.25 0.81
0.81

476.21

Precio S/. Parcial S/.

10.63 0.77
11.25 4.09
10.25 7.45
6.25 9.09
21.40

27.00 262.71
130.00 174.20
4.20 0.88
437.79

21.40 0.21
21.01 7.64
25.21 9.17
17.02

423.14

Precio S/. Parcial S/.

10.63 1.13
11.25 6.00
10.25 10.93
6.25 26.67
44.73

27.00 172.80
130.00 191.10
4.20 0.62
364.52

44.73 0.45
25.21 13.44
13.89

7.86

Precio S/. Parcial S/.

10.63 0.08
11.25 0.43
10.25 0.39
0.90

6.30 0.32
6.30 6.62
6.94

0.90 0.02
0.02

6.26

Precio S/. Parcial S/.

10.63 0.17
10.25 0.82
6.25 1.50
2.49

120.00 0.24
26.00 3.46
3.70

2.49 0.07
0.07

24.65

Precio S/. Parcial S/.

10.63 6.07
6.25 17.86
23.93

23.93 0.72
0.72

65.91

Precio S/. Parcial S/.

11.25 1.05
6.25 18.27
19.32

80.00 43.60
4.20 0.27
43.87

19.32 0.39
25.00 2.33
2.72

47.97

Precio S/. Parcial S/.

11.25 11.25
10.25 10.25
6.25 1.25
22.75

6.30 0.76
6.30 1.39
5.50 22.39
24.54

22.75 0.68
0.68

423.14

Precio S/. Parcial S/.

10.63 1.13
11.25 6.00
10.25 10.93
6.25 26.67
44.73

27.00 172.80
130.00 191.10
4.20 0.62
364.52

44.73 0.45
25.21 13.44
13.89

496.47

Precio S/. Parcial S/.

10.63 1.42
11.25 7.50
10.25 6.83
6.25 25.00
40.75

27.00 262.71
130.00 174.20
4.20 0.78
437.69

40.75 1.22
25.21 16.81
18.03

7.90

Precio S/. Parcial S/.

10.63 0.07
11.25 0.36
10.25 0.33
0.76

6.30 0.38
6.30 6.74
7.12

0.76 0.02
0.02

403.98

Precio S/. Parcial S/.

136.50 211.85
192.13 192.13
403.98

6,000.00

Precio S/. Parcial S/.

6,000.00 6,000.00
6,000.00

###
CONSTRUCCION Y APERTURA DE UNA TROCHA CARROZABLE
Item Partida Und Metrado
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m glb 1.00
01.02 ALMACEN OFICINA Y SS.HH glb 1.00
02 TRABAJOS PRELIMARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO PESADO glb 1.00
02.02 ROCE Y DESBROCE m2 10,000.00
02.03 TRAZO Y REPLANTEO km 2.00
03 EXPLANACIONES
03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=400 m3/día m3 6,847.35
03.02 CORTE ROCA SUELTA (PERFORACION Y DISPARO) m3 1,310.00
03.03 CORTE ROCA FIJA (PERFORACION Y DISPARO) m3 1,115.24
03.04 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES m3 430.06
03.05 RELLENO CON MATERIAL DE PRESTAMO MANUAL m3 2,500.00
03.06 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE m3 6,772.59
04 OBRAS DE ARTE Y DRENAJE
04.01 CUNETAS
04.01.01 CONSTRUCCION DE CUNETAS LATERALES EN MATERIAL SUELTO m 1,200.00
04.01.02 CONSTRUCCION DE CUNETAS LATERALES EN ROCA SUELTA m 800.00
04.02 BADENES
04.02.01 EXCAVACION MANUAL m3 24.08
04.02.02 ELIMINACION DE MATERIAL CARGUIO MANUAL m3 36.55
04.02.03 ENCOFRADO Y DESENCOFRADO PARA BADENES m2 20.78
04.02.04 CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO m3 5.19
04.02.05 CONCRETO f'c=140 kg/cm2 m3 3.38
04.02.06 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS DE FONDO PISO kg 251.73
04.02.07 JUNTAS ASFALTICAS m 5.19
04.03 ALCANTARILLADO
04.03.01 EXCAVACION MANUAL m3 4.82
04.03.02 RELLENO ESTRUCTURAL m3 2.36
04.03.03 ENCOFRADO Y DESENCOFRADO m2 14.25
04.03.04 CONCRETO f'c=140 kg/cm2 m3 2.38
04.03.05 CONCRETO f'c=210 kg/cm2 m3 1.62
04.03.06 ACERO fy=4200 kg/cm2 GRADO 60 kg 50.35
04.03.07 ALCANTARILLA TMC 0=36" m 2.00
05 FLETE
05.01 TRANSPORTE DE PETROLEO Y OTROS glb 1.00
ERTURA DE UNA TROCHA CARROZABLE
Op Of Peon Prod Un. (REND.)

1.00
1 3 400.00
1 2 0.40

1 1 3 600.00
1 1 3 250.00
1 1 4 220.00
1 1 5 75.00
1 1 4 1000.00
1 1 3 720.00

1 1 4 26.00
1 1 4 20.00

1 1 2.80
1 2 3 175.00
1 1 3 8.00
1 2 4 22.00
1 2 8 15.00
1 1 1 210.00
1 1 3 100.00

1 1 2.80
1 31 86.00
1 1 1 8.00
1 2 8 15.00
1 1 6 12.00
1 1 1 250.00
10.00
ANALISIS DE PLANIFICACIÓN - PROGRAMACION DE OBRA CON LOK HEAND

CONSTRUCCION Y APERTURA DE UNA TROCHA CARROZAB


ETAPA 1 - PRELIMINARES Y EXPLANACIONES
Item Partida Und Metrado Op Of Peon
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO PESADO glb 1.00
02.02 ROCE Y DESBROCE m2 10,000.00 1 3
02.03 TRAZO Y REPLANTEO km 2.00 1 2
03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=400 m3/día m3 6,847.35 1 1 3
03.02 CORTE ROCA SUELTA (PERFORACION Y DISPARO) m3 1,310.00 1 1 3
03.03 CORTE ROCA FIJA (PERFORACION Y DISPARO) m3 1,115.24 1 1 4
03.04 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES m3 430.06 1 1 5
03.05 RELLENO CON MATERIAL DE PRESTAMO MANUAL m3 2,500.00 1 1 4
03.06 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE m3 6,772.59 1 1 3

ANALISIS POR PARETO


Cantidad de partidas 9
Numero de actividades restrictivas 2

PROGRAMACIÓN MENSUAL
EN
Item Partida F asumido DIAS APROX. ENTEROS
TABLA
SOBRA

02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO PESADO 1 1.00 1 1 0.00


02.02 ROCE Y DESBROCE 4 6.25 6 1600 400.00
02.03 TRAZO Y REPLANTEO 1 5.00 5 0.4 0.00
03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=400 m3/día 2 5.71 5 1200 847.35
03.02 CORTE ROCA SUELTA (PERFORACION Y DISPARO) 1 5.24 5 250 60.00
03.03 CORTE ROCA FIJA (PERFORACION Y DISPARO) 1 5.07 5 220 15.24
03.04 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES 1 5.73 5 75 55.06
03.05 RELLENO CON MATERIAL DE PRESTAMO MANUAL 1 2.50 2 1000 500.00
03.06 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE 2 4.70 4 1440 1012.59

CONSTRUCCION Y APERTURA DE UNA TROCHA CARROZAB


CONSTRUCCION Y APERTURA DE UNA TROCHA CARROZAB
ETAPA 2 - OBRAS DE ARTE Y DRENAJE
Item Partida Und Metrado Op Of Peon
04.01.01 CONSTRUCCION DE CUNETAS LATERALES EN MATERIAL SUELTO m 1,200.00 1 1 4
04.01.02 CONSTRUCCION DE CUNETAS LATERALES EN ROCA SUELTA m 800.00 1 1 4
04.02.01 EXCAVACION MANUAL (BADENES) m3 24.08 1 1
04.02.02 ELIMINACION DE MATERIAL CARGUIO MANUAL (BADENES) m3 36.55 1 2 3
04.02.03 ENCOFRADO Y DESENCOFRADO PARA BADENES m2 20.78 1 1 3
04.02.06 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS DE FONDO PISO kg 251.73 1 1 1
04.02.04 CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO (BADENES) m3 5.19 1 2 4
04.02.05 CONCRETO f'c=140 kg/cm2 (BADENES) m3 3.38 1 2 8
04.02.07 JUNTAS ASFALTICAS (BADENES) m 5.19 1 1 3
04.03.01 EXCAVACION MANUAL (ALCANTARILLADO) m3 4.82 1 1
04.03.02 RELLENO ESTRUCTURAL (ALCANTARILLADO m3 2.36 1 31
04.03.03 ENCOFRADO Y DESENCOFRADO (ALCANTARILLADO) m2 14.25 1 1 1
04.03.06 ACERO fy=4200 kg/cm2 GRADO 60 kg 50.35 1 1 1
04.03.04 CONCRETO f'c=140 kg/cm2 m3 2.38 1 2 8
04.03.05 CONCRETO f'c=210 kg/cm2 m3 1.62 1 1 6
04.03.07 ALCANTARILLA TMC 0=36" m 2.00

ANALISIS POR PARETO


Cantidad de partidas 16
Numero de actividades restrictivas 3

PROGRAMACIÓN MENSUAL
EN
Item Partida F asumido DIAS APROX. ENTEROS
TABLA
SOBRA

04.01.01 CONSTRUCCION DE CUNETAS LATERALES EN MATERIAL SUELTO 7 6.59 6 182 108.00


04.01.02 CONSTRUCCION DE CUNETAS LATERALES EN ROCA SUELTA 6 6.67 6 120 80.00
04.02.01 EXCAVACION MANUAL (BADENES) 2 4.30 4 5.6 1.68
04.02.02 ELIMINACION DE MATERIAL CARGUIO MANUAL (BADENES) 1 0.21 0 36.55
04.02.03 ENCOFRADO Y DESENCOFRADO PARA BADENES 1 2.60 2 8 4.78
04.02.06 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS DE FONDO PISO 1 1.20 1 210 41.73
04.02.04 CONCRETO f'c=210 kg/cm2 PARA LOSAS DE FONDO (BADENES) 1 0.24 0 5.19
04.02.05 CONCRETO f'c=140 kg/cm2 (BADENES) 1 0.23 0 3.38
04.02.07 JUNTAS ASFALTICAS (BADENES) 1 0.05 0 5.19
04.03.01 EXCAVACION MANUAL (ALCANTARILLADO) 1 1.72 1 2.8 2.02
04.03.02 RELLENO ESTRUCTURAL (ALCANTARILLADO 1 0.03 0 2.36
04.03.03 ENCOFRADO Y DESENCOFRADO (ALCANTARILLADO) 1 1.78 1 8 6.25
04.03.06 ACERO fy=4200 kg/cm2 GRADO 60 1 0.20 0 50.35
04.03.04 CONCRETO f'c=140 kg/cm2 1 0.16 0 2.38
04.03.05 CONCRETO f'c=210 kg/cm2 1 0.14 0 1.62
04.03.07 ALCANTARILLA TMC 0=36" 1 0.20 0 2.00
K HEAND - LEAN CONSTRUCTION

CARROZABLE
NUEVO
REND. (Ru) R Tu (dias) HH Tp F F entero Op Of Peon
1.00 0.00 1.00 0.00 1.00 1.00 1.00 0
400.00 0.08 25.00 800.00 11.00 2.27 3.00 3 0
0.40 60.00 5.00 120.00 5.00 1.00 1.00 1 0
600.00 0.07 11.41 456.49 11.00 1.04 2.00 2 2
250.00 0.16 5.24 209.60 5.24 1.00 1.00 1 1 3
220.00 0.22 5.07 243.33 5.07 1.00 1.00 1 1 4
75.00 0.75 5.73 321.11 5.73 1.00 1.00 1 1
1000.00 0.05 2.50 120.00 2.50 1.00 1.00 1 1
720.00 0.06 9.41 376.26 9.41 1.00 1.00 1 1
11.00

SEMANA 1 SEMANA 2
L M M J V S D L M M J V S D L

CARROZABLE
CARROZABLE
NUEVO
REND. (Ru) R Tu (dias) HH Tp F F entero Op Of Peon
26.00 1.85 46.15 2215.38 11.00 4.20 5.00 20
20.00 2.40 40.00 1920.00 11.00 3.64 4.00 4 4
2.80 5.71 8.60 137.60 8.60 1.00 1.00 1
175.00 0.27 0.21 10.03 0.21 1.00 1.00 1 2
8.00 5.00 2.60 103.90 2.60 1.00 1.00 1 1 3
210.00 0.11 1.20 28.77 1.20 1.00 1.00 1 1 1
22.00 2.55 0.24 13.21 0.24 1.00 1.00 1 2 4
15.00 5.87 0.23 19.83 0.23 1.00 1.00 1 2 8
100.00 0.40 0.05 2.08 0.05 1.00 1.00 1 1 3
2.80 5.71 1.72 27.54 1.72 1.00 1.00 1 1
86.00 2.98 0.03 7.03 0.03 1.00 1.00 1 31
8.00 3.00 1.78 42.75 1.78 1.00 1.00 1 1 1
250.00 0.10 0.20 4.83 0.20 1.00 1.00 1 1 1
15.00 5.87 0.16 13.96 0.16 1.00 1.00 1 2 8
12.00 5.33 0.14 8.64 0.14 1.00 1.00 1 1 6
10.00 0.00 0.20 0.00 0.20 1.00 1.00
8.00

SEMANA 1 SEMANA 2
L M M J V S D L M M J V S D L
SEMANA 3 SEMANA 4
M M J V S D L M M J V S
SEMANA 3 SEMANA 4
M M J V S D L M M J V S
SEMANA 4
D
SEMANA 4
D
ESTRUCTURAS PABELLON N°4
ETAPA 1 - CIMENTACIONES
Item Partida Und Metrado Op Of Peon
11 CONSTRUCCION DE PABELLON Nº04-1ER PISO:05 AULAS DE 56.0M2 C/U Y 02
ESCALERAS DE MATERIAL NOBLE
11.01.01 EXCAVACIONES SIMPLES PARA CIMENTACION m3 497.85 1
11.03.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (zapata) kg 1453.3 1 1
11.03.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (columna) kg 4303.67 1 1
11.03.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (viga de cimentacion) kg 4937.74 1 1
11.02.01 SOLADO PARA ZAPATAS E=0.10 m, f'c=100 kg/cm2 m2 219.12 1 1 5
11.03.01.01 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 113.54 1 1 7
11.03.02.02 ENCOFRADO Y DESENCOFRADO EN VIGA DE CIMENTACION m2 224.17 1 1
11.03.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (sobrecimiento) kg 2220.29 1 1
11.03.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (columnetas) kg 479.12 1 1
11.03.02.01 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 38.67 1 1 8
11.03.02.04 CURADO DE CONCRETO TIPO MEMBRANA EN VIGAS DE CIMENTACION m2 224.17 1
11.03.04.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 58.8 1 1
11.03.04.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 23.2 1 1 8
11.03.04.04 CURADO DE CONCRETO TIPO MEMBRANA EN COLUMNAS m2 58.8 1
11.03.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m2 352.18 1 1
11.03.03.01 CONCRETO EN SOBRECIMIENTOS f'c=175 kg/cm2 m3 34.09 2 1 8
11.03.03.04 CURADO DE CONCRETO TIPO MEMBRANA EN SOBRECIMIENTOS m2 352.18 1
11.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 272.57 1 1
11.01.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO(H:T.R. 70%:30%) m3 55.97 1 1
11.02.02 CIMIENTOS CORRIDOS f`c=140 Kg/cm2 m3 15.78 2 1 7
11.01.04 ACARREO INTERNO DE MATERIAL PROCEDENTE DE EXCAVACIONES m3 225.27 1
11.01.05 ELIMINACION DE MATERIAL EXCEDENTE(CARG. 135HP/VOLQ. 15m3, D=10Km) m3 281.59 2
11.02.03 FALSO PISO MEZCLA C:H 1:8, E=4" m2 318.84 1 1 7
11.04.01 MURO DE LADRILLO KK TIPO IV CABEZA, M:1:1:4 E=1.5cm m2 209.08 1 0.5
11.04.02 MURO DE LADRILLO KK TIPO IV SOGA, M:1:1:4 E=1.5cm m2 70.15 1 0.5

PROGRAMACIÓN MENSUAL
DIAS
Item Partida F asumido
APROX.
ENTEROS EN TABLA SOBRA
DIAS
Item Partida F asumido
APROX.
ENTEROS EN TABLA SOBRA

11 CONSTRUCCION DE PABELLON Nº04-1ER PISO:05 AULAS DE 56.0M2 C/U Y 02


ESCALERAS DE MATERIAL NOBLE
11.01.01 EXCAVACIONES SIMPLES PARA CIMENTACION 25 6.64 6 75 47.85
11.03.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (zapata) 1 5.81 5 250 203.30
11.03.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (columna) 3 5.74 5 750 553.67
11.03.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (viga de cimentacion) 3 6.33 6 780 257.74
11.02.01 SOLADO PARA ZAPATAS E=0.10 m, f'c=100 kg/cm2 1 2.19 2 100 19.12
11.03.01.01 CONCRETO ZAPATAS f'c=210 kg/cm2 1 5.68 5 20 13.54
11.03.02.02 ENCOFRADO Y DESENCOFRADO EN VIGA DE CIMENTACION 3 6.23 6 36 8.17
11.03.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (sobrecimiento) 2 4.44 4 500 220.29
11.03.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 (columnetas) 1 1.92 1 250 229.12
11.03.02.01 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 1 2.76 2 14 10.67
11.03.02.04 CURADO DE CONCRETO TIPO MEMBRANA EN VIGAS DE CIMENTACION 1 0.70 0 320 224.17
11.03.04.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS 1 4.90 4 12 10.80
11.03.04.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 1 1.66 1 14 9.20
11.03.04.04 CURADO DE CONCRETO TIPO MEMBRANA EN COLUMNAS 1 0.18 0 320 58.80
11.03.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS 4 6.29 6 56 16.18
11.03.03.01 CONCRETO EN SOBRECIMIENTOS f'c=175 kg/cm2 1 2.84 2 12 10.09
11.03.03.04 CURADO DE CONCRETO TIPO MEMBRANA EN SOBRECIMIENTOS 1 1.10 1 320 32.18
11.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO 5 6.81 6 40 32.57
11.01.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO(H:T.R. 70%:30%) 2 3.50 3 16 7.97
11.02.02 CIMIENTOS CORRIDOS f`c=140 Kg/cm2 1 0.99 0 16 15.78
11.01.04 ACARREO INTERNO DE MATERIAL PROCEDENTE DE EXCAVACIONES 4 5.63 5 40 25.27
11.01.05 ELIMINACION DE MATERIAL EXCEDENTE(CARG. 135HP/VOLQ. 15m3, D=10Km) 1 0.88 0 320 281.59
11.02.03 FALSO PISO MEZCLA C:H 1:8, E=4" 1 3.19 3 100 18.84
11.04.01 MURO DE LADRILLO KK TIPO IV CABEZA, M:1:1:4 E=1.5cm 5 5.97 5 35 34.08
11.04.02 MURO DE LADRILLO KK TIPO IV SOGA, M:1:1:4 E=1.5cm 2 3.90 3 18 16.15
NUEVO
REND. (Ru) R Tu (dias) HH Tp F F enteroOp Of Peon

3 2.67 ### ### ### 6.64 7 7


250 0.06 5.81 93.01 5.81 1.00 1 1 1
250 0.06 17.21 ### ### 1.00 1 1 1
260 0.06 18.99 ### ### 1.00 1 1 1
100 0.56 2.19 ### 2.19 1.00 1 1 1 5
20 3.60 5.68 ### 5.68 1.00 1 1 1 7
12 1.33 18.68 ### ### 1.00 1 1 1
250 0.06 8.88 ### 8.88 1.00 1 1 1
250 0.06 1.92 30.66 1.92 1.00 1 1 1
14 5.71 2.76 ### 2.76 1.00 1 1 1 8
A4
320 0.03 0.70 5.60 0.70 1.00 1 1
12 1.33 4.90 78.40 4.90 1.00 1 1 1
14 5.71 1.66 ### 1.66 1.00 1 1 1 8
320 0.03 0.18 1.47 0.18 1.00 1 1
14 1.14 25.16 ### ### 1.01 2 2 2
12 7.33 2.84 ### 2.84 1.00 1 2 1 8
320 0.03 1.10 8.80 1.10 1.00 1 1
8 2.00 34.07 ### ### 1.36 2 2 2
8 2.00 7.00 ### 7.00 1.00 1 1 1
16 5.00 0.99 78.90 0.99 1.00 1 2 1 7
10 0.80 22.53 ### ### 1.00 1 1
320 0.05 0.88 14.08 0.88 1.00 1 2
100 0.72 3.19 ### 3.19 1.00 1 1 1 7
7 1.71 29.87 ### ### 1.19 2 2 1
9 1.33 7.79 93.53 7.79 1.00 1 1 0.5

SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4


L M M J V S D L M M J V S D L M M J V S D L M M

75 75 75 75 75 75 47.9
250 250 250 250 250 203
750 750 750 750 750 554
780 780 780 780 780 780 258
100 100 19.12
20 20 20 20 20 13.14
36 36 36 36 36 36 8.17
500 500 500 500 220
250 229
14 14 10.67
224
12 12 12 12 10.8
14 9.2
58.8
56 56 56 56 56 56 16.18
12 12 10.09
320 32.18
40 40 40 40 40 40 32.57
16 16 16 7.97
15.78

282
100 100 100
35 35 35
18
SEMANA 4
J V S D

A3

18.84
35 35 34.08
18 18 16.15

Você também pode gostar