Escolar Documentos
Profissional Documentos
Cultura Documentos
Answer: B
2) Decision trees are best used for :
A. Determining the interaction of the
amount at stake and the expected value
B. Association of the probabilities with the
risk events
C. An illustration of how to see the
interactions between decisions and the
associated events
D. A flow chart which determines the
standard deviation of the risk event
Answer: C
3) The total Value of risk that is calculated for a
project is found by
A.Multiplying the sum of each the risk times
the amount at stake
B.Calculating the cumulative sum of the
probability for each risk and multiplying
this value times the consequence of
occurrence of the risk events
C.Cannot be calculated since all risks are not
know
D.The amount of project reserves available
Answer: B
4) A situation in which one of two or more risk events
will follow an act, but the precise nature of these
events may not be known and the probabilities of
their occurring cannot be objectively assigned, is the
definition of
A. certainty
B. uncertainty
C. risk
D. risk adversity
Answer: B
5) Andrew has joined as the Project Manager of
a project. One of the project documents
available to Andrew lists down all the risks in a
hierarchical fashion. What is this document
called?
Answer: D
6) Beta is the Project Manager of a Road
construction project. During a project review,
Beta realizes that one particular risk has
occurred. To take appropriate action against
risk that has happened, Beta needs to refer to
which document?
Answer: C
8) John Strauss is a Project Manager for a
reforestation project. To identify the risks
involved, John sends a questionnaire to gather
inputs from experts. Which technique is John
using?
A. Delphi technique
B. Interviews
C. Brain storming
D. Documentation review
Answer: A
9) Which of these is not a valid response to positive
risks?
A. Exploit
B. Mitigate
C. Enhance
D. Share
Answer: B
10) During which stage of Risk planning are risks
prioritized based on probability and impact?
A. Identify Risks
B. Plan Risk responses
C. Perform Qualitative risk analysis
D. Perform Quantitative risk analysis
Answer: C
• Probabilistic Analysis of a project, probability
of achieving cost and time objectives and
trends in Quantitative Risk Analysis results
are done during _______.
1.Perform Qualitative Risk Analysis
2.Perform Quantitative Risk Analysis
3.Plan Risk Management
4.Identify Risks
• Documentation reviews
• Data precision rankings
• Diagramming techniques
• Risk planning meetings
• You are a project manager of a project.
Customer has requested a change which will
increase the project risk. What is your NEXT
step?
1.Analyze the impact of the change.
2.Report to Senior Management.
3.Report to Sponsor.
4.Change the Risk Management Plan.
1) Expert power is the power that comes from the amount of
knowledge a person has obtained in a specific area. This type of
power is:
Answer: D
2) To successfully manage a project, the PM
must play both a manager and leadership role.
In the manager role the PM will do all but
which of the following:
A. Develop procedures
B. Align people
C. Produce results for stakeholder
D. Focus on the organization and its structure
Answer: B
3) Which form of power is the LEAST effective
from the project manager's viewpoint in
terms of influencing functional managers?
A. Formal power
B. Expert power
C. Penalty power
D. Referent power
Answer: C
4) All of the following can be used to document
team member roles and responsibilities
EXCEPT:
Answer: D
5) Resource Breakdown Structure is an example
of:
Answer: A
6) Which of the following is not true for a
Responsibility Assignment Matrix (RAM):
Answer: C
7) Building a virtual team for a project will limit
the usability of which of the following tools
and techniques for Team Development:
A. Team Building
B. Establishing Ground Rules
C. Co-Location
D. Reward and Recognitions
Answer: C
8) The belief that management's high levels of
trust, confidence and commitment to workers
leads to high levels of motivation and
productivity on the part of workers is a part of
which motivation theory?
A. Theory Y
B. Theory Z
C. Theory X
D. Contingency Theory
Answer: B
9) A document or tool which describes when and
how human resources will be brought onto
and taken off the project team is called a:
Answer: A
10) You have just been assigned as the project
manager of a 15 year, 200 trillion dollar project
to marry the first couple on Mars. In addition to
buying a wedding present, you will probably
want to describe which type of project
organization in your management plan?
A. Functional
B. Expeditor
C. Matrix
D. Projectized
Answer: D
1. Most of the project manager's external
communication links consist of:
A. Written documents
B. Oral communication
C. Horizontal contact
D. Informal contact
Answer: A
2) The process of communication contains four
major parts. Which part is the vehicle or
method used to convey the message?
A. Sender
B. Message
C. Medium
D. Receiver
Answer: C
3) The contemporary view of conflict is that:
A. Conflict is bad
B. Conflict is caused by trouble makers
C. Conflict should be avoided
D. Conflict is often beneficial
Answer: D
4) Approximately what percentage of the project
manager's time is spent in some form of
communication, such as: conferences, meetings,
writing memos, reading and preparing reports,
and talking with project team members, upper
management, and all other stalk holders?
A. 20%
B. 70%
C. 90%
D. 45%
Answer: C
5) Which of the following process is not included
in project communication knowledge area?
Answer: A
6) Which of the following is not an example of
formal communication?
A. Contract
B. email
C. Project status report
D. Status meeting
Answer: B
7) You are a project manager of a project and want to
report the actual project result and the planned
status. You should use?
A. Forecasting report
B. Trend reports
C. Status report
D. Variance report
Answer: D
8) In the communication process, "noise" is the
word used to describe factors and forces
inhibiting the exchange of information
between two or more parties. Noise includes
all of the following but __________
A. Culture
B. Language
C. Traditional way of doing things
D. Loud talking
Answer: D
9) Project managers must write correspondence to
many individual parties who are project
stakeholders. The most important aspect of the
project manager's correspondence is to ensure
__________:
A. The grammar is correct
B. The format is correct for the message
C. The message is clearly conveyed
D. The delivery of the message is made within 24
hours
Answer: C
10) Emails and voice mails are example of
______.
A. Interactive Communications
B. Pull Communication
C. Push Communication
D. Noise
Answer: C
• You are the project manager of the PLN Project. The team
members are somewhat “afraid” of you as project manager
because they see you as management. They know that a
negative review from you about their project work will impact
their yearly bonus. This is an example of which of the
following?
A. Formal power
B. Coercive power
C. Expert power
D. Referent power
• B. When the project team is afraid of the power the project
manager yields, this is called coercive power. A, C, and D are
incorrect because they describe assigned, referential, and
technical power over the project, respectively. For more
information, see the PMBOK, Section 9.4.2.
You are the project manager of the MMB Project. The president of the company
has spoken to the project team and told them of the confidence and respect
he has in you to lead the project to a successful completion. The project
manager has what type of power on this project?
A. Formal power
B. Coercive power
C. Expert power
D. Halo power
• A. The company president has assigned you to the position of the project
• manager, so you have formal power. B is incorrect because coercive power
• is the fear associated with the project manager. C is incorrect because expert
• power is derived from the project manager’s experience with the technology
• being implemented. D is also incorrect; halo power is not a viable answer to
• the question. For more information, see the PMBOK, Section 9.4.2.
Management has approached Tyler, one of your project team members.
Tyler is a database administrator and developer whose work is always on
time, accurate, and of quality. He also has a reputation of being a “good
guy” and is well liked. Because of this, management has decided to move
Tyler into the role of a project manager for a new database administration
project. This is an example of which of the following?
A. Management by exception
B. The halo effect
C. Management by objectives
D. McGregor’s theory of X and Y
• B. The halo effect is the assumption that because the person is good at a
• technology, he would also be good at managing a project dealing with
that said technology. A, C, and D are all incorrect because these do not
describe the halo effect. For more information, see the PMBOK, Section
9.4.2.
Which problem-solving technique is the best for most project
management situations?
A. Confronting
B. Compromising
C. Forcing
D. Avoiding
• A. Confronting is the best problem-solving technique because it
meets the problem directly. B is incorrect; compromising requires
both sides on an argument to give up something. C is incorrect;
forcing requires the project manager to force a decision based on
external inputs, such as seniority, experience, and so on. D is also
incorrect; avoiding ignores the problem and does not solve it. For
more information, see the PMBOK, Section 9.4.2.3.
• Harold is an outspoken project team member. All of the project team members
respect Harold for his experience with the technology, but often, things have to go
in Harold’s favor or things do not go well. During a discussion on a solution, a
project team member waves her arms and says, “Fine, Harold, do it your way.” This
is an example of which of the following?
• A. A win-win solution
• B. A leave-lose solution
• C. A lose-lose solution
• D. A yield-lose solution
D. When Harold always has to win an argument and team members begin to
give in to Harold’s demands simply to avoid the argument rather than finding
an accurate solution, this is a yield-lose situation. A is incorrect because both
parties do not win. B is incorrect because the project team member did not
leave the conversation, but instead ended it. C is incorrect; a lose-lose is a
compromise where both parties give up something. For more information,
see the PMBOK, Section 9.4.2.3.
You are the project manager for the GBK Project. This project affects a line
of business, and the customer is anxious about the success of the project.
Which of the following is likely not a top concern for the customer?
A. Project priorities
B. Schedule
C. Cost
D. Personality conflicts
• D. Personality conflicts are likely a concern for the customer, but are not as
important as project priorities, schedule, and cost. The customer hired
your company to solve the technical issues. A, B, and C are all incorrect
because these are most likely the top issues for a company in a project of
this magnitude. For more information, see the PMBOK, Section 9.4.2.3.
Which theory believes that workers need to be involved with the
management process?
• A. McGregor’s theory of X and Y
• B. Ouchi’s theory Z
• C. Herzberg’s theory of motivation
• D. Expectancy theory
• B. Ouchi’s theory Z states that workers need to be involved with
the management process. A is incorrect; McGregor’s theory of X
and Y believes that X workers don’t want to work and need
constant supervision; Z workers will work if the work is
challenging, satisfying, and rewarding. C is incorrect; Herzberg’s
theory of motivation describes the type of people and what
excites them to work. D, the expectancy theory, describes how
people will work based on what they expect in return. For more
information, see the PMBOK, Section 9.4.2.
• ___________________ states that as long as workers are
rewarded they will remain productive.
• A. McGregor’s theory of X and Y
• B. Ouchi’s theory Z
• C. Herzberg’s theory of motivation
• D. Expectancy theory D. The expectancy theory describes
how people will work based on what they
• expect in return. If people are rewarded because of the
work they complete, and they like the reward (payment),
they will continue to work. A, B, and C are all incorrect
because these theories do not accurately describe the
scenario presented. For more information, see the
PMBOK, Section 9.4.2.3.
• You are the project manager for Industrial Lights Project. You have been hired by
your organization specifically because of your vast experience with the
• technology and with projects of this nature. The project team is aware of your
experience. You likely have what type of power on this project?
A. Formal power
B. Coercive power
C. Expert power
D. Referent power
C. You, the project manager, have expert power on this project because of your
experience with the technology and with projects that are similar in nature. A,
B, and D are all incorrect. These project management powers do not accurately
describe the scenario. Formal power is appointed power. Coercive power describes
fear of the project manager. Referent power describes power by association and
personal knowledge. For more information, see the PMBOK, Section 9.4.2.
• There have been too many disagreements within two
team-members in your project over the design of a
particular product. You would like to incorporate the
best features of the two designs. You also want to
create an environment that avoids conflicts and
emphasizes similarities. The conflict handling mode
you would like to implement is:
• Choice 1 Smoothing
• Choice 2 Compromising
• Choice 3 Confrontation
• Choice 4 Withdrawal
• Correct Choice : 1
You are in the build phase of a Build-Operate-Transfer (BOT) project, which
has run into several unanticipated problems. Several risks have surfaced
which you had not anticipated earlier. The project is over-budget and
significantly behind
schedule. What should you do?
Choice 1 Create updates to risk response plan
Choice 2 Create a revised project plan
Choice 3 Perform risk audits
Choice 4 Perform updated risk identification and analysis
Correct Choice : 4
Justification :
Results from earned value analysis may indicate potential deviation of the
project at completion from cost and schedule targets. When a project
deviates significantly from the baseline, updated risk identification and
analysis should be performed.
Which of the following statements about quality control is not accurate?
Choice 1 Prevention refers to keeping errors out of the process, whereas
inspection refers to keeping errors out of the hands of the customer.
Choice 2 Attribute sampling determines whether the result conforms or not,
and variables sampling determines the degree of conformity.
Choice 3 Tolerances refer to specified range of accepted results and control
limits refer to thresholds, which can indicate whether the process is out of
control.
Choice 4 Quality control is only performed in Monitoring and Controlling
process.
Correct Choice : 4
Justification :
Quality control is performed throughout the project.
• You are annoyed with your team members because of
their constant disagreements. You ask them to stop
arguing and do
• the work the way in which you want it to be done. The
conflict handling approach you are following is:
• Choice 1 Smoothing
• Choice 2 Forcing
• Choice 3 Confrontation
• Choice 4 Withdrawal
• Correct Choice : 2
In your project, you want to determine which risks have the most potential impact on
the project. So, you examine the extent to which the uncertainty of each project
element affects the objective being examined when all other uncertain elements
are held at their baseline values. This is an example of:
Choice 1 Risk response planning
Choice 2 Expected monetary value analysis
Choice 3 Sensitivity analysis
Choice 4 Simulation
Correct Choice : 3
Justification :
Sensitivity analysis helps to determine which risks have the most potential impact on
the project. It examines the extent to
which the uncertainty of each project element affects the objective being examined
when all other uncertain elements are
held at their baseline values.
In managing risks for your project, you examine the extent to which the uncertainty of
each project element affects the objective being examined when all other
uncertain elements are held at baseline values. This helps to:
Choice 1 Get a qualitative analysis of the risk.
Choice 2 Determine which risks may have impact on the project.
Choice 3 Translate the uncertainties at a detailed level into potential impact on
objectives expressed at the level of the total
project.
Choice 4 Determine the implication of choosing one alternative over the other.
Correct Choice : 2
Justification :
Sensitivity analysis helps to determine which risks have the most potential impact on
the project. It examines the extent to
which the uncertainty of each project element affects the objective being examined
when all other uncertain elements are
held at their baseline values.
Your company is a pioneer in the construction industry. The government recently
floated a tender for setting up a new airport. Since you do not have all the
requisite skills within the company, you enter into a joint venture with a leading
airport construction company to bid jointly for the government contract. This is an
example of:
Choice 1 Risk exploitation
Choice 2 Risk sharing
Choice 3 Risk enhancing
Choice 4 Risk mitigating
Correct Choice : 2
Justification :
Strategies for positive risks or opportunities (share): Sharing a positive risk involves
allocating some or all of the ownership to a third party who is best able to capture
the opportunity for the benefit of the project. Examples of sharing actions include
forming risk-sharing partnerships, teams, special-purpose companies, or joint
ventures, which can be established with the express purpose of taking advantage
of the opportunity so that all parties gain from their actions.
As part of Perform Quantitative Risk Analysis process, you, as a project manager, have already
done a sensitivity analysis, created decision trees and done a project simulation using Monte
Carlo technique. However, when you show your results to your manager, she is not happy.
She thinks that your analysis is not acceptable because:
Choice 1 Monte Carlo simulations are not a standard methodology used in the company for risk
quantification.
Choice 2 The quantitative value of identified risks is too high.
Choice 3 You have not performed risk audits as part of your project.
Choice 4 You have not conducted an interview with the project stakeholders and subject matter
experts.
Correct Choice : 4
Justification :
Interviewing techniques draw on experience and historical data to quantify the probability and
impact of risks on project objectives. The information needed depends upon the type of
probability distributions that will be used... Documenting the rationale of the risk ranges and
the assumptions behind them are important components of the risk interview because they
can provide insight on the reliability and credibility of the analysis.
Reference: PMBOK® Guide Fourth Edition, Page Number:296
:
Option 1: This may or may not be true. There is nothing in the question which suggests that
Monte Carlo Analysis should
not be used and this is a standard tool for Perform Quantitative Risk Analysis process.
Option 2: A high quantitative value of risks does not render the Quantitative Risk Analysis process
unacceptable.
Option 3: This refers to a tool and technique in Monitor and Control Risk (not Quantitative) Risk
Analysis process.
Option 4: This is the correct answer. Since a risk interview was not conducted, the results of
Perform Quantitative Risk Analysis process will not be dependable.
In the Executing phase of a project, a project manager should ideally
be:
Choice 1 Coaching
Choice 2 Directing
Choice 3 Authoritarian
Choice 4 Supportive
Correct Choice : 1
• Justification :
• Given below are the different leadership styles adopted by the
project manager during various phases of the project: During
Initiating phase of the project, the leadership style will be Directing.
During Planning, Executing, Monitoring and Controlling phases of
the project, the leadership style will be Facilitating and Coaching.
• During Closing phase, the leadership style will be Supportive.
You are the project manager for GHB Project. You have served as a project
manager for your organization for the past 10 years. Practically all of your projects
come in on time and on budget. The project team has worked with you in the past,
and they consider you to be an expert project manager. They also like working with
you. Given all of this, you likely have what type
of power on this project?
A. Formal power
B. Coercive power
C. Expert power
D. Referent power
D. This is referent power because the project team knows the project manager
personally. A and B are incorrect choices; these do not describe the scenario. C
is incorrect; expert power does not deal with the ability to lead and complete
a project, but it focuses on being an expert with the technology that the
project deals with. For more information, see the PMBOK, Section 9.4.2.3.
Which of the following is an example of coercive power?
A. A project manager who has lunch with the project team every Thursday
B. A project manager who will openly punish any team member who is late
with an activity
C. A project manager who has worked with the technology on the project for
several years
D. A project manager who is friends with all of the project team members
• B. Coercive power is the formal authority a project manager yields over
• the project team. A is incorrect; only referent power may come through
• lunch meetings. C is incorrect; experience is expert power. D is incorrect;
• interpersonal relationships are examples of referent power. For more
• information, see the PMBOK, Section 9.4.2.3.
Mike is the project manager for a project with a very tight schedule. The project is
running late, and Mike feels that he does not have time to consider all the possible
solutions that two team members are in disagreement over. He quickly decides to
go with the team member with the largest amount of seniority. This is an example
of which of the following?
A. Problem solving
B. Compromising
C. Forcing
D. Withdrawal
C. Forcing happens when the project manager makes a decision based on factors
that are not relevant to the problem. Just because a team member has more
seniority does not mean this individual is correct. A, B, and D are incorrect choices.
A, problem solving, is not described in the scenario. B, compromising, happens
when both parties agree to give up something. D, withdrawal, happens when a
party leaves the argument. For more information, see the PMBOK, Section 9.4.2.3.
Of the following, which one is an example of noise?
A. Fax machine
B. Ad-hoc conversations
C. Contractual agreements
D. Distance
• D. Noise is anything that interferes with the transmission
and understanding of the message. Distance is an example
of noise. A, a fax machine, is an example of a decoder. B is
incorrect; ad-hoc conversations are informal
conversations. C, contractual agreements, are a type of
formal communication. For more information, see the
introduction to Chapter 10 in the PMBOK.
• You are the project manager for the JHG Project. Management has requested that
you create a document detailing what information will be expected
from stakeholders and to whom that information will be disseminated.
Management is asking for which one of the following?
A. The roles and responsibilities matrix
B. The scope management plan
C. The communications management plan
D. The communications worksheet
C. Management is requesting a communications management plan,
which details the requirements and expectations for communicating
information among the project stakeholders. A is incorrect, since a rolesand-
responsibilities matrix depicts who does what and who makes which
decisions. B, the scope management plan, is also incorrect because this
plan explains how changes to the scope may be allowed, depending on the
circumstances. D is not a valid choice for the question. For more information,
see the PMBOK, Section 10.1.
Which of the following will help you, the project manager, complete
the needed communications management plan by identifying the
stakeholders’ communication needs?
A. Identification of all communication channels
B. Formal documentation of all communication channels
C. Formal documentation of all stakeholders
D. Lessons learned from previous similar projects
• D. Lessons learned and historical information from a previous
project are ideal inputs to communications planning. A, B, and C
are incorrect because these choices do not fully answer the
question. Lessons learned from previous, similar projects are the
best tool to identify stakeholders’ requirements for
communication. For more information, see the PMBOK, Section
10.1.1.2.
You are the project manager for the KLN Project. You had 19
stakeholders on this project and have added three team members
to the project. How many more communication channels do you
have now compared to before?
A. 171
B. 231
C. 60
D. 1
C. The question asks how many more communication channels exist.
You’ll have to calculate the new value, which is 231, and then
subtract the original value, which is 171, for a total of 60 new
channels. A is incorrect. 171 is the original number of
communication channels. B is incorrect because this value reflects
the new number of communication channels. D is not a valid
choice. For more information, see the PMBOK, Section 10.1.2.1.
A memo has been sent to you, the project manager, the
project team members, and the project customers from the
project sponsor. In this instance, who is the encoder?
A. Project sponsor
B. Project manager
C. Project team members
D. Project customers
• 6. A. The project sponsor is the source of the memo, since
this is the sender of the message. B, C, and D are all
recipients of the memo, not the sender,so they cannot be
the source of the message. For more information, see the
• introduction to Chapter 10 in the PMBOK.
• Of the following, which term describes the pitch and tone of an
individual’s voice?
A. Paralingual
B. Feedback
C. Effective listening
D. Active listening
• A. Paralingual is a term used to describe the pitch and tone of one’s
voice. B, feedback, is a request to confirm the information sent in
the conversation. C, effective listening, is the ability to understand
the message through what is said, facial expressions, gestures,
tone, pitch, and so on. D, active listening, is the process of
confirming what is understood and asking for clarification when
needed. For more information, see the PMBOK, Section 10.2.2.1.
What percentage of a message is sent through nonverbal
communications, such as facial expressions, hand gestures,
and body language?
A. Greater than 50 percent
B. 30 to 40 percent
C. 20 to 30 percent
D. 10 to 20 percent
• A. Greater than 50 percent of a message is sent through
nonverbal communications. B, C, and D are incorrect. For
more information, see the introduction to Chapter 10 in
the PMBOK and the section titled “Examining
Communication Factors and Technologies” in this chapter.
• Why should a project team complete lessons-learned
documentation?
A. To ensure project closure
B. To show management what they’ve accomplished on the
project
C. To show the project stakeholders what they’ve
accomplished on the project
D. To help future project teams complete their projects more
accurately
• C. Lessons learned takes place throughout the project life
cycle, not just at the end of the project or its phases. A, B,
and D are incorrect choices. For more information, see the
PMBOK, Section 10.2.2.4.
• You are the project manager for the PMU Project. Your project has
13 members. You have been informed that next week your project
will receive
• the seven additional members you requested. How many channels
of communication will you have next week?
A. 1
B. 78
C. 190
D. 201
• C. The project currently has 13 team members, and next week,
seven additional team members will come aboard, thus making a
total of 20 team members. Using the formula N (N – 1) / 2, where N
is the number of identified stakeholders, the communication
channels equal 190
Frances is the project manager of the LKJ Project. Which of the
following techniques will she use to create the risk management
plan?
A. Risk tolerance
B. Status meetings
C. Planning meetings
D. Variance meetings
• C. Planning meetings are used to create the risk management
plan. The project manager, project team leaders, key stakeholders,
and other individuals with the power to make decisions regarding
risk management attend the meetings. Choices A, B, and D are
incorrect, since these choices do not fully answer the
• question.
• You are the project manager of the GHK Project. You and the manufacturer have
agreed to substitute the type of plastic used in the product to a slightly thicker
grade should there be more than 7 percent error in production. The thicker plastic
will cost more and require the production to slow down, but the errors should
diminish. This is an example of which of the following?
A. Threshold
B. Tracking
C. Budgeting
D. JIT manufacturing
A. An error value of 7 percent represents the threshold the project is allowed to
operate under. Should the number of errors increase beyond 7 percent, the
current plastic will be substituted. B is incorrect, since tracking is the
documentation of a process through a system or workflow or the documentation
of events through the process. C, budgeting, is also incorrect. D, JIT manufacturing,
is a scheduling approach to ordering the materials only when they are needed in
order to keep inventory costs down. For more information, see the PMBOK,
Section 11.5.2.1.
An organization’s risk tolerance is also known as what?
A. The utility function
B. Herzberg’s theory of motivation
C. Risk acceptance
D. The risk-reward ratio
• A. The utility function describes a person’s willingness to
tolerate risk. B is incorrect. Herzberg’s theory of motivation
is a human resources theory that describes motivating
agents for workers. C is also incorrect. Risk acceptance
describes the action of allowing a risk to exist because it is
deemed low in impact, low in probability, or both. D, the
risk-reward ratio, is incorrect. This describes the potential
reward for taking on a risk in the project.
The customers of the project have requested additions to the project scope. The
project manager notifies you that additional risk planning will need to be added to
the project schedule. Why?
A. The risk planning should always be the same amount of time as the activities
required by the scope change.
B. Risk planning should always occur whenever the scope is adjusted.
C. Risk planning should only occur at the project manager’s discretion.
D. The project manager is incorrect. Risk planning does not need to happen at every
change in the project.
B. When the scope has been changed, the project manager should require risk
planning to analyze the additions for risks to the project’s success. A is incorrect.
The scope changes may not require the same amount of time as the activities
needed to complete the project changes. C is incorrect because risk planning
should not occur at the project manager’s discretion. Instead, it should be based
on evidence within the project and the policies adopted in the risk management
plan. D is also incorrect. When changes are added to the project scope, risk
planning should occur. For more information, see the PMBOK, Section 11.6.1.3.
Which one of the following best describes the risk register?
A. It documents all of the outcomes of the other risk
management processes.
B. It’s a document that contains the initial risk identification
entries.
C. It’s a system that tracks all negative risks within a project.
D. It’s part of the project’s project management information
system (PMIS) for integrated change control.
• A. The risk register documents all of the outcomes of the
other risk management processes. B, C, and D are all
incorrect definitions of the risk register. For more
• information, see the PMBOK, Section 11.2.3.1.
You are the project manager for a project that will create a new and improved
Web site for your company. Currently, your company has over eight million users
around the globe. You would like to poll experts within your organization with a
simple, anonymous form asking about any foreseeable risks in the design,
structure, and intent of the Web site. With the collected information, subsequent
anonymous polls are submitted to the group of experts. This is an
example of _________________________________.
A. Risk identification
B. A trigger
C. An anonymous trigger
D. The Delphi Technique
D. An anonymous poll that allows experts to freely submit their opinion
without fear of backlash is an example of the Delphi Technique. A, B, and C
are incorrect. These choices do not accurately answer the question. For more
information, see the PMBOK, Section 11.2.2.2.
A table of risks, their probability, impact, and a number
representing the overall risk score is called a
____________________________.
A. Risk table
B. Probability and impact matrix
C. Quantitative matrix
D. Qualitative matrix
• B. A table of risks, their probability, and impact equate to a risk
score in a risk matrix. A is incorrect, since it does not fully answer
the question. C and D are incorrect because a risk matrix can be
used in both quantitative and qualitative
• risk analyses. For more information, see the PMBOK, Section
11.3.2.2.
In your project, you want to determine which risks have the most potential impact on
the project. So, you examine the
extent to which the uncertainty of each project element affects the objective being
examined when all other uncertain
elements are held at their baseline values. This is an example of:
Choice 1 Risk response planning
Choice 2 Expected monetary value analysis
Choice 3 Sensitivity analysis
Choice 4 Simulation
Correct Choice : 3
Justification :
Sensitivity analysis helps to determine which risks have the most potential impact on
the project. It examines the extent to which the uncertainty of each project
element affects the objective being examined when all other uncertain elements
are held at their baseline values. Reference: PMBOK® Guide Fourth Edition, Page
298
You are in the build phase of a Build-Operate-Transfer (BOT) project, which
has run into several unanticipated problems. Several risks have surfaced
which you had not anticipated earlier. The project is over-budget and
significantly behind schedule. What should you do?
Choice 1 Create updates to risk response plan
Choice 2 Create a revised project plan
Choice 3 Perform risk audits
Choice 4 Perform updated risk identification and analysis
Correct Choice : 4
Justification :
Results from earned value analysis may indicate potential deviation of the
project at completion from cost and schedule targets. When a project
deviates significantly from the baseline, updated risk identification and
analysis should be performed.
• As part of Perform Quantitative Risk Analysis process, you, as a project manager,
have already done a sensitivity analysis, created decision trees and done a project
simulation using Monte Carlo technique. However, when you show your results to
your manager, she is not happy. She thinks that your analysis is not acceptable
because:
Choice 1 Monte Carlo simulations are not a standard methodology used in the
company for risk quantification.
Choice 2 The quantitative value of identified risks is too high.
Choice 3 You have not performed risk audits as part of your project.
Choice 4 You have not conducted an interview with the project stakeholders and
subject matter experts.
Correct Choice : 4
Justification :
Interviewing techniques draw on experience and historical data to quantify the
probability and impact of risks on project objectives. The information needed
depends upon the type of probability distributions that will be used...
Documenting the rationale of the risk ranges and the assumptions behind them
are important components of the risk interview because they can provide insight
on the reliability and credibility of the analysis. Reference: PMBOK® Guide Fourth
Edition, Page Number:296
As part of Perform Quantitative Risk Analysis process, you, as a project manager, have
already done a sensitivity analysis, created decision trees and done a project
simulation using Monte Carlo technique. However, when you show your results
to your manager, she is not happy. She thinks that your analysis is not acceptable
because:
Choice 1 Monte Carlo simulations are not a standard methodology used in the
company for risk quantification.
Choice 2 The quantitative value of identified risks is too high.
Choice 3 You have not performed risk audits as part of your project.
Choice 4 You have not conducted an interview with the project stakeholders and
subject matter experts.
Correct Choice : 4
Justification :
Interviewing techniques draw on experience and historical data to quantify the
probability and impact of risks on project objectives. The information needed
depends upon the type of probability distributions that will be used...
Documenting the rationale of the risk ranges and the assumptions behind them
are important components of the risk interview because they
can provide insight on the reliability and credibility of the analysis.
Reference: PMBOK® Guide Fourth Edition, Page Number:296
In managing risks for your project, you examine the extent to which the uncertainty of
each project element affects the objective being examined when all other
uncertain elements are held at baseline values. This helps to:
Choice 1 Get a qualitative analysis of the risk.
Choice 2 Determine which risks may have impact on the project.
Choice 3 Translate the uncertainties at a detailed level into potential impact on
objectives expressed at the level of the total
project.
Choice 4 Determine the implication of choosing one alternative over the other.
Correct Choice : 2
• Justification :
• Sensitivity analysis helps to determine which risks have the most potential
impact on the project. It examines the extent to which the uncertainty of each
project element affects the objective being examined when all other uncertain
elements are held at their baseline values.
• Reference: PMBOK® Guide Fourth Edition, Page Number:298
Your company is a pioneer in the construction industry. The government recently
floated a tender for setting up a new airport. Since you do not have all the
requisite skills within the company, you enter into a joint venture with a leading
airport construction company to bid jointly for the government contract. This is an
example of:
Choice 1 Risk exploitation
Choice 2 Risk sharing
Choice 3 Risk enhancing
Choice 4 Risk mitigating
Correct Choice : 2
Justification :
Strategies for positive risks or opportunities (share): Sharing a positive risk involves
allocating some or all of the ownership to a third party who is best able to capture
the opportunity for the benefit of the project. Examples of sharing actions include
forming risk-sharing partnerships, teams, special-purpose companies, or joint
ventures, which can be established with the express purpose of taking advantage
of the opportunity so that all parties gain from their actions.
Reference: PMBOK® Guide Fourth Edition, Page Number:304
In your project, you identified disaster situations (e.g. floods, earthquakes, etc.) as
potential risks. The project sponsor suggested that, at the project level, no steps
could be taken to deal with such risks and recommended creation of a contingency
reserve (with 5% of the project budget) which could be used in case of disaster
situations. This is an example of:
Choice 1 Risk mitigation
Choice 2 Risk acceptance
Choice 3 Risk avoidance
Choice 4 Bad policy decision
Correct Choice : 2
Justification :
Accept: This strategy is adopted because it is often not possible to eliminate all threats
from a project. This strategy indicates that the project team has decided not to
change the project management plan to deal with a risk, or is unable to identify
any other suitable response strategy... The most common active acceptance
strategy is to establish a contingency reserve, including amounts of time, money,
or resources to handle the risks. Reference: PMBOK® Guide Fourth Edition, Page
Number:304
In Plan Risk Management, you define how to conduct risk management activities for a project
because careful and explicit planning enhances the probability of success for the subsequent
risk management processes. In this context, what will you NOT do when you Plan Risk
Management?
Choice 1 Identify Risks
Choice 2 Establish an agreed-upon basis for evaluating risk
Choice 3 Ensure that the degree, type, and visibility of risk management are commensurate with
both the risks and the importance of the project
Choice 4 Provide sufficient resources and time for risk management activities
Correct Choice : 1
Justification :
Planning risk management processes is important to ensure that the degree, type, and visibility
of risk management are commensurate with both the risks and the importance of the
project to the organization. Planning is also important to provide sufficient resources and
time for risk management activities, and to establish an agreed-upon basis for evaluating
risks.
Reference: PMBOK® Guide Fourth Edition, Page 276 PMstudy.com comments: Risk
identification (Identify Risk process) is not done during Plan Risk Management process.
In Plan Risk Management, you define how to conduct risk management activities for a project because
careful and explicit planning enhances the probability of success for the subsequent risk
management processes. In this context, what will you NOT do when you Plan Risk Management?
Choice 1 Identify Risks
Choice 2 Establish an agreed-upon basis for evaluating risk
Choice 3 Ensure that the degree, type, and visibility of risk management are commensurate with both
the risks and the
importance of the project
Choice 4 Provide sufficient resources and time for risk management activities
Correct Choice : 1
Justification :
Planning risk management processes is important to ensure that the degree, type, and visibility of risk
management are commensurate with both the risks and the importance of the project to the
organization. Planning is also important to provide sufficient resources and time for risk
management activities, and to establish an agreed-upon basis for evaluating risks.
Reference: PMBOK® Guide Fourth Edition, Page 276
You are a retail company which routinely buys goods from foreign countries. Since
currency fluctuation is an important risk, you keep all other factors constant and
try to find out how much your project will be impacted if the currency rate
fluctuates by 5%, 10%, 20% or 25%. This helps you determine appropriate risk
response. This can also be effectively shown using:
Choice 1 Beta probability distributions
Choice 2 Expected monetary value analysis
Choice 3 Tornado diagram
Choice 4 Simulation
Correct Choice : 3
Justification :
Sensitivity analysis helps to determine which risks have the most potential impact on
the project. It examines the extent to which the uncertainty of each project
element affects the objective being examined when all other uncertain elements
are held at their baseline values. One typical display of sensitivity analysis is the
tornado diagram, which is useful for comparing relative importance and impact of
variables that have a high degree of uncertainty to those that are more stable.
Reference: PMBOK® Guide Fourth Edition, Page 298
A documented direction to perform an activity that can reduce the
probability of negative consequences associated with
project risks is called:
Choice 1 Corrective action
Choice 2 Preventive action
Choice 3 Defect repair
Choice 4 Risk mitigation
Correct Choice : 2
Justification :
Preventive action: A documented direction to perform an activity
that can reduce the probability of negative consequences
associated with project risks. Reference: PMBOK® Guide Fourth
Edition, page 92
When your company buys computers from Dell, you also pay extra for a three
year warranty which ensures that any manufacturing defects will be taken
care of by Dell. The risk response strategy used is:
Choice 1 Exploit
Choice 2 Avoid
Choice 3 Mitigate
Choice 4 Transfer
Correct Choice : 4
Justification :
Transfer. Risk transfer requires shifting some or all of the negative impact of a
threat, along with ownership of the response, to a third party…
Transference tools can be quite diverse and include, but are not limited to,
the use of insurance, performance bonds, warranties, guarantees, etc.
Reference: PMBOK® Guide Fourth Edition, Page 303
Kelly, a new project manager in your organization, is ready to enter into a
contract with a buyer for supply of ball bearings, but is unsure of the type
of contract she should select. Which type of contract represents the
highest risk to the seller?
Choice 1 Cost reimbursable plus incentive
Choice 2 Fixed- price
Choice 3 Fixed price plus incentive
Choice 4 Cost- reimbursable
Correct Choice : 2
Justification :
Fixed price contracts involve setting a fixed total price for a defined product
or service to be provided. Sellers are under highest risk as fixed-price
contracts are legally obligated to complete such contracts, with possible
financial damages, if they do not. Reference: PMBOK® Guide Fourth
Edition, page 322
In your project, you could use all the following strategies for
opportunities EXCEPT:
Choice 1 Exploit
Choice 2 Contingent
Choice 3 Share
Choice 4 Accept
Correct Choice : 2
Justification :
Strategies for positive risks or opportunities: Three of the four
responses are suggested to deal with risks with potentially positive
impacts on project objectives. The fourth strategy, accept, can be
used for negative risks or threats as well as positive risks or
opportunities. These...are exploit, share, enhance, or accept.
Reference: PMBOK® Guide Fourth Edition, Page 304
You are a project manager and have just discovered a risk in your
project that requires an immediate corrective action.
During which Project Risk Management Process is this action
performed?
Choice 1 Plan Risk Management
Choice 2 Identify Risks
Choice 3 Perform Qualitative Risk Analysis
Choice 4 Monitor and Control Risks
Correct Choice : 4
Justification :
Monitor and Control Risks is the process of implementing risk respose
plans, tracking identified risks, monitoring residual risks, identifying
new risks, and evalulating risk process effectiveness throughout the
project. Reference: PMBOK® Guide Fourth Edition, Page 308
The Project manger is concerned about potential
risks occurring as a result of performance
deviations from the baseline. What should the
project manager do?
A. Perform risk audits.
B. Conduct technical performance
measurement.
C. Perform variance and trend analysis.
D. Reassess all risks
Which of the following is an output of
performing risk monitoring and control
activities?
A. The development of contingency Plans
B. Recommended preventive actions
C. Risk related contractual agreements
D. Changes to the project management
Plan
• How is earned value analysis used in Project
risk management?
A. Delphi Technique
B. Brainstorming - Biasing of results
C. Interviewing. – Duplicate risks
D. Expert judgment – Biasing of results
• All of the following are included within the risk
management plan except:
A. Approach to performing risk management
activities.
B. Risk categories
C. Contingency plans
D. Estimate costs for risk activities for the Project.
• What are the some of the responsibilities of a risk audit
team.
A. Beta
B. Uniform
C. Continuous
D. Lognormal
• Graphical representations of situations
showing causal influences, time ordering of
events, and other relationships among
variables and outcomes is also referred to as
• a. Cause-and-effect diagrams
• b. System flow charts
c. Influence diagrams
d. Tornado diagram
• A risk manager will most likely display the
results of sensitivity analysis using:
1. Identify Risks
2. Plan Risk responses
3. Perform Qualitative risk analysis
4. Perform Quantitative risk analysis
During which stage of Risk planning are
modeling techniques used to determine
overall effects of risks on project objectives for
high probability, high impact risks?
• Identify Risks
• Plan Risk responses
• Perform Qualitative risk analysis
• Perform Quantitative risk analysis
Andrew is a Project Manager for Green Valley
project. A risk management plan has been
prepared for the project. Which of the
following should Andrew do next?
A. Perform Qualitative risk analysis
B. Perform Quantitative risk analysis
C. Identify Risks
D. Plan Risk responses
John Strauss is a Project Manager for a
reforestation project. To identify the risks
involved, John sends a questionnaire to gather
inputs from experts. Which technique is John
using?
A. Delphi technique
B. Interviews
C. Brain storming
D. Documentation review
Mathew is a Project Manager for software
migration at a bank. A major risk that has been
identified is attrition of resources. As a strategy to
respond to this risk, Mathew, with support from
Senior Management, provides good increments
to his team members. What type of risk response
is Mathew following?
A. Accept
B. Avoid
C. Transfer
D. Mitigate
Mathew is a Project Manager for software
migration at a bank. A major risk that has been
identified is attrition of resources. As a strategy to
respond to this risk, Mathew, with support from
Senior Management, provides good increments
to his team members. What type of risk response
is Mathew following?
A. Accept
B. Avoid
C. Transfer
D. Mitigate
Overtime associated with the execution effort of
a project is estimated at 120 hours with
probability 0.5, 250 hours with probability 0.6,
and 300 hours with probability 0.3. What is
the monetary value of the amount of
overtime?
1.300 hours
2.670 hours
3.250 hours
4.100 hours
Overtime associated with the execution effort of a project is
estimated at 120 hours with probability 0.5, 250 hours with
probability 0.6, and 300 hours with probability 0.3. What is
the monetary value of the amount of overtime?
1.300 hours
2.670 hours
3.250 hours
4.100 hours
A: Exploit.
B: Transference.
C: Acceptance.
D: Contingency planning
Transference places the ownership and responsibility of the risk
onto a third party. It usually involves payment of some type of
insurance premium to the party assuming the risk.
• What is not a true statement about the Perform
Qualitative Risk Analysis process?
• A: Addresses individual risks descriptively.
• B: Prioritizes individual risks for subsequent
analysis.
• C: Assesses the discrete probability of occurrence
and impact on objectives if it does occur.
• D: Identifies risks with greatest effect on overall
project risk.
Your call center project is almost completed. As the project
manager in a Projectized organization, what is your biggest concern
as you enter the project closeout?
250
Your call center project is almost completed. As the project
manager in a Projectized organization, what is your biggest concern
as you enter the project closeout?
A, B and C are all true statements of the qualitative risk process. D is a true statement
for the quantitative risk process.
You have just been appointed project manager of a project that is approved to start the
planning phase and the team has already been chosen by upper management. The
best way to begin communications with the team and set appropriate expectations is
to:
B: Schedule a kick-off meeting to present project objectives and solicit input from the
team on how to achieve them.
C: Schedule a briefing session to present objectives and direct how they will be met.
D: Meet individually with each team member to determine how they intend to
contribute to the project objectives.
B is the most effective way of getting the team to buy in to project objectives and
commit to their achievement.
You have been hired for a short term contract to assist with setting up a PMO. You
meet with one of the department managers Judi, who is working on grouping her
department's projects which all have unique objectives into subcategories such as
Inventory Control, Purchasing and Vendors. Judi believes this will assist her in project
prioritization and more effective project reporting to upper management. What is
Judi attempting to create?
A: PMIS.
B: Portfolio.
C: Sub-projects.
D: Program.
Your team has created several documents that serve as historical records for future
projects. These historical documents are archived:
D: During closure.
D: Your management is looking for rapid and visible action on this project to rectify
the problems.
You know you are brought into a project that is out of control. You immediately start
to assess what "out of control" means by asking management to identify the
problems. The fact that they can not pinpoint or isolate any problem and simply
state over budget and behind schedule, immediately flags to me there is little if any
documentation. Without documentation, a.k.a. project plan there is no control, no
way to satisfy the client, no way to action. What can we action if there is no plan?
Bottom line, documentation is a key process in project management and when it is
not done sufficiently we are very concerned and need to take action immediately.
You have been asked by your local PMI chapter to be a guest speaker at the next
chapter meeting. Since your passion is "risk" you have decided to speak on the topic
of project risk related to your most recent completed project. In reference to risk
management, when the outcome of the decision is not known in advance, it is the
definition of:
A: Certainty.
B: A risk.
C: Uncertainty.
D: A known-unknown.
What is the most important reason to analyze the network diagram from a risk
management perspective?
A contingency reserve is a means of reducing the risk of time or money overruns for
a project. Contingency reserve is not related to communications.
Barriers to communication may include all of the following except:
A contingency reserve is a means of reducing the risk of time or money overruns for
a project. Contingency reserve is not related to communications.
Your risk assessment has a high probability that you will have a schedule overrun
due to insufficient resources available to you on the critical path. You start to look at
the costs and the effect on the schedule of contracting externally with a company
that are experts in testing which is where the resource limitation will occur the
most. What tool and technique best describes what you are doing?
A: Benefit/cost analysis.
B: Design of experiment.
C: Benchmarking.
D: Product analysis.
Design of experiment: An analytical technique which identifies factors which
influence specific variables in a project. Very useful to identify which variables
(such as cost and schedule trade-offs) have the most influence on overall project
outcomes to help determine an optimal solution. In this case, what effect will the
hiring of external resources vs. internal resources have on the budget and reduce
the risk of a schedule overrun since external resources should be more readily
available than the limited internal resources. Benefit/cost analysis: This technique
is more applicable to the overall financial measures or return on investment the
project will produce.
Nominal group technique, Root cause analysis and Assumption Analysis are all tools
of:
A: Identifying risks.
B: Qualifying risks.
C: Responding to Risks.
D: Quantifying Risks.
Group decision making may be prone to failure if symptoms of what phenomenon
are present?
A: Group talk.
B: Groupthink.
C: Loose matrix
D: Strong matrix
Nominal group technique, Root cause analysis and Assumption Analysis are all tools
of:
A: Identifying risks.
B: Qualifying risks.
C: Responding to Risks.
D: Quantifying Risks.
Para linguistics and metacommunication usually refer to what type of
communication?
A: Nonverbal.
B: Multilingual.
C: Bilingual.
D: Interpretive.
A: Team.
B: Stakeholders.
C: Project Manager.
D: Sponsor.
Organizational learning is complex in that we learn at many levels simultaneously.
Some leading experts in organizational learning, believe that managers of
competitive organizations often find themselves in situations where relative
position with regard to a competitor matters. This possible competitive advantage
through enhanced learning is the essence of the study of experience and learning
curves. The experience curve theory states that as:
A: Cumulative production decreases, time and costs associated with that production
lower at a constant and predictable rate.
B: Cumulative production doubles, time and costs associated with that production
increase at a constant and predictable rate.
C: Cumulative production doubles, time and costs associated with that production
increase randomly.
D: Cumulative production doubles, time and costs associated with that production
lower at a constant and predictable rate.
Also referred to as the "learning curve theory" with the underlying concept that
costs and labour effort will decrease the more we repeat the same work tasks.
Specifically, each time a company doubles their output, cost and time savings are in
the neighbourhood of 10 to 30%.
Matrix charts are used to illustrate the roles and responsibilities of individuals on a
project when performing Human Resource planning. One common matrix
illustration is the Responsibility Assignment Matrix, also known as the RAM. A
popular type of RAM is the RACI chart. Another type of RAM that is used in practice
is the:
A: RONALD chart
B: ADIL chart
C: PARIS chart
D: ROCCI chart
The PARIS chart is another popular means to illustrate roles and responsibilities.
Much like the RACI chart, we list the work packages on each row and the roles on
each column. We then assign the value P (Participate), A (Accountable), R (Review),
I (Input), S (Signoff) in each cell of the chart.
You have just completed a response to the prioritized risks in the risk register. Prior
to proceeding to risk monitoring and control what should you do?
B: Develop workarounds.
A: Identify Risk.
A: Identify Risk.
B: A random event that needs no investigation until more points are outside limits.
If any of the data points are outside the limits, the process is considered out of
control and should be investigated.
You have just returned from an eventful holiday vacation and a note has been left
on your desk to contact your client. The company you work for provides project
management services on contract for software development initiatives and your
client has asked to cancel the project. Unfortunately, your client's business
outlook is bleak and there are no funds available to continue any project
activities. As project manager, what should you do:
A: Contact senior management and determine how the legal department should
treat the request.
B: Inform your project team that they may pack up and move onto other
initiatives.
D: Ask the client how you can trim the scope in hopes to realign the budget with
whatever funds the client has remaining.
You have just returned from an eventful holiday vacation and a note has been left
on your desk to contact your client. The company you work for provides project
management services on contract for software development initiatives and your
client has asked to cancel the project. Unfortunately, your client's business
outlook is bleak and there are no funds available to continue any project
activities. As project manager, what should you do:
A: Contact senior management and determine how the legal department should
treat the request.
B: Inform your project team that they may pack up and move onto other
initiatives.
D: Ask the client how you can trim the scope in hopes to realign the budget with
whatever funds the client has remaining.
The closing processes include:
C: Completing and settling contracts and excluding resolution of any open items.
D: Ensuring the project will satisfy the needs for which it was undertaken.
The project closing processes include all the activities required to formally
establish the project or project phase is completed. It includes the updates to
the organizational process assets.
Generally speaking the detail and frequency of performance reporting increases:
C: With contractors.
In general the detail and frequency of reporting decreases the higher up you are
reporting. In the case of risk reporting - the riskier the project is, the more detail
and frequency you will need to report at all levels.
Generally speaking the detail and frequency of performance reporting increases:
C: With contractors.
In general the detail and frequency of reporting decreases the higher up you are
reporting. In the case of risk reporting - the riskier the project is, the more detail
and frequency you will need to report at all levels.
Project termination responsibilities include all of the following except:
B, C and D are all activities that would be conducted during project termination.
A: Modifying quality standards, if applicable would have been conducted during
the quality assurance process.
Which approach or process will assist the most at increasing project opportunities
and reducing threats to a project?
B is correct: Plan Risk Response is the process that ensures we enhance the
opportunities and reduce the threats to the risks identified and analyzed in the
previous processes.
Which approach or process will assist the most at increasing project opportunities
and reducing threats to a project?
B is correct: Plan Risk Response is the process that ensures we enhance the
opportunities and reduce the threats to the risks identified and analyzed in the
previous processes.
You are a Program Manager responsible for the health of 5 projects currently
underway. You have asked each Project Manager to report on the current status
of their projects, using the Earned Value Technique. At the last quarterly project
audit, you discover that one PM is reporting overly optimistic status on one
project, and it is in worse shape than is reported. The project is a mission-critical
one to the organization and if it continues at the current pace, the final delivery
date will be missed, leading to serious consequences for the company. What is
your immediate response?
A: Have a one-on-one meeting with the PM to understand why his Earned Value
reports are off, determine the actual status, and monitor the PM moving forward
to ensure it doesn't happen again.
C: Meet with the PM, work with the PM to devise and execute a plan to get the
project back on track, and inform the sponsor.
A: Have a one-on-one meeting with the PM to understand why his Earned Value
reports are off, determine the actual status, and monitor the PM moving forward
to ensure it doesn't happen again.
C: Meet with the PM, work with the PM to devise and execute a plan to get the
project back on track, and inform the sponsor.
A: Have a one-on-one meeting with the PM to understand why his Earned Value
reports are off, determine the actual status, and monitor the PM moving forward
to ensure it doesn't happen again.
C: Meet with the PM, work with the PM to devise and execute a plan to get the
project back on track, and inform the sponsor.
Constructive and destructive team roles indicate how your attitude effects
overall team development. A constructive team role is one that helps team
development and a destructive one is that which hampers team development.
Constructive team roles are:
1. Initiator - let's do this
2. Information seeker - don't we have better information?
3. Information giver - My experience has been that...
4. Encourager - Mary, that was very helpful
5. Clarifiers - I believe we are saying that....
6. Gate Keeper - We have not heard Elizabeth's opinion on this issue yet. What
do you think, Elizabeth?
7. Harmonizer - I believe that we are all saying the same thing
8. Summarizer - I feel that we can now reach an agreement
When is the earliest time we can start to close the project?
Close Project activities should be conducted at the end of each project phase
and not delayed until the very end of the project.
You are a Program Manager responsible for the health of 5 projects currently
underway. You have asked each Project Manager to report on the current status
of their projects, using the Earned Value Technique. At the last quarterly project
audit, you discover that one PM is reporting overly optimistic status on one
project, and it is in worse shape than is reported. The project is a mission-critical
one to the organization and if it continues at the current pace, the final delivery
date will be missed, leading to serious consequences for the company. What is
your immediate response?
A: Have a one-on-one meeting with the PM to understand why his Earned Value
reports are off, determine the actual status, and monitor the PM moving forward
to ensure it doesn't happen again.
C: Meet with the PM, work with the PM to devise and execute a plan to get the
project back on track, and inform the sponsor.
A: The process average is moving to the lower values and needs to be corrected.
C: No action is required because the points are still within the control limits.
An abnormal trend is formed when seven or more consecutive data points reflect
a steadily increasing or decreasing pattern over time.
You are reviewing several project contracts for overall performance reporting to
determine the earned value techniques to be used for performance reporting.
One of the contracts scope of work contains a repetitive process. Since this
contract entails 70% of the total project work, which earned value reporting
technique would be the best to use?
A: Apportioned.
C: 50/50.
D: Milestone.
Line Of Balance (LOB) is an earned value technique for collecting, measuring and
presenting facts relating to time, cost and accomplishment - all measured against
a specific plan. It shows the process, status, background, timing and phasing of
the project activities. The manufacturing of parts and the assembly of units in a
factory are two candidates for the use of LOB. The LOB itself is a graphic device
that enables a manager to see, at a single glance, which of the many activities
that make up a complex operation are "in balance". He /she can determine
whether those which should have been completed at the time of the review
actually are completed and whether any activities scheduled for future
completion are lagging behind schedule.
There are 2 core close-out processes - close project and close procurement. What
is the key difference between these 2 processes?
A: Close procurement uses the term procurement audit and close project uses
the term admin closure.
D: Close project is completed only once at the end of the project while contract
close is completed at the end of every phase.
It's important you understand the differences between the 2 close out
processes. Contract closeout performs an audit of procurement, is completed at
the end of the contract when both parties have met their contractual
agreement and prior to the final project close of the entire project. Close project
performs a detailed lessons learned document, a complete set of indexed
records and may be completed at the end each phase and at the end of the
project.
You are a Program Manager responsible for the health of 5 projects currently
underway. You have asked each Project Manager to report on the current status
of their projects, using the Earned Value Technique. At the last quarterly project
audit, you discover that one PM is reporting overly optimistic status on one
project, and it is in worse shape than is reported. The project is a mission-critical
one to the organization and if it continues at the current pace, the final delivery
date will be missed, leading to serious consequences for the company. What is
your immediate response?
A: Have a one-on-one meeting with the PM to understand why his Earned Value
reports are off, determine the actual status, and monitor the PM moving forward
to ensure it doesn't happen again.
C: Meet with the PM, work with the PM to devise and execute a plan to get the
project back on track, and inform the sponsor.
A: Design of experiment.
B: Benchmarking.
C: Attribute sampling.
D: Variable sampling.
Since the question focuses on the response time, the answer is D, variable
sampling. The response time from the support team may vary from 1 hour to 3
days depending on the time zone and could be plotted as a range (or
distribution) on a histogram. If the control measurement was simply to ask -
"do the testers like or dislike the user manual" it would be possible to use
attribute sampling.
The 2 closing processes - close procurement and close project both involve:
A: Product verification.
B: Kick-off meetings.
C: Audits.
D: Performance reporting.
A: Visual.
B: Auditory.
C: Kinesthetic.
D: Electronic.
The 3 types are: Visual¾-¾ intake by seeing, Auditory¾- intake by hearing,
Kinesthetic -¾ intake by doing and touching. Each learner may have any
combination of these three. Some might fall strongly into one category, some
have no preference difference between two, and some are equally able to intake
with all three.
In the field of Neuro-Linguistic Programming (NLP), studies on how individuals
prefer to accept and retain new information into their heads have been
conducted for years. Although these categories could be broken down further,
they tend to fall into three. Which of the following is not one of the three?
A: Visual.
B: Auditory.
C: Kinesthetic.
D: Electronic.
The 3 types are: Visual¾-¾ intake by seeing, Auditory¾- intake by hearing,
Kinesthetic -¾ intake by doing and touching. Each learner may have any
combination of these three. Some might fall strongly into one category, some
have no preference difference between two, and some are equally able to intake
with all three.
During a procurement audit of a software development project, you discover that
the value of the contract to the vendor has increased substantially. There were no
incentives, fees or milestones in place to limit the risk to you (the customer). This
is an example of what type of contract?
A: CPPC.
B: FFP.
C: CPIF.
D: CPFF.
A correct: CPPC - cost plus percentage of the cost contract is a type of Time and
Materials contract that puts no limitations on the seller. In addition, all the risk is
assumed by the purchaser. For this reason, these types of contracts are not valid
for Federal contracts. C and D incorrect: CPIF - cost plus incentive fee and CPFF -
cost plus fixed fee contracts place some limit on the contract cost and share the
risk between buyer and seller.
A seller agrees to perform a service to furnish supplies for a lump sum amount.
The advantage of this type of contract to you as the project manager is:
B: uncertain events
C: stakeholder tolerances
A: Delphi.
B: Parametric.
C: Analytical Design.
D: Design of Experiments
Design of experiments uses statistical methods to balance certain factors
resulting in the most favourable outcome. It is a systematic approach to
investigation of a system or process. A series of structured tests are designed in
which planned changes are made to the input variables of a process or system.
The effects of these changes on a pre-defined output are then assessed.
If a project manager has developed a contingency plan, which risk response
strategy is being applied?
A: Avoidance
B: Mitigate
C: Acceptance
D: Transference
You are analyzing the schedule risk for your project using the Monte Carlo
Simulation. What is not true about the Monte Carlo simulation?
A: It will tell you the probability of completing the project on any specific day.
C: It will tell you the probability of completing the project for any specific amount
of cost.
D: It will tell you the probability of any task actually being on the critical path.
The Monte Carlo simulation uses the multipoint estimates optimistic, most
likely and pessimistic - but does not use the Pert weighted values which is the
optimistic, plus 4 times the most likely plus the pessimistic over 6.
Project management continues to be a hot topic and is becoming more influential
on a daily basis. Many organizations have already realized the benefits of project
management and simply require process implementation support and mentoring.
Project management provides organizations with a methodology to:
A: Charter
A is output from the initiating process group.B and D are outputs from the
executing process group.
"Schedule compression" means:
B: Analyzing the project plan to identify work tasks that could be done in parallel
without adding resources.
C: Moving resources from the non critical path to the critical path.
D: Removing items from the scope document to complete the project sooner.
B: Contingency and management reserves are basically the same and treated the
same for approval to spend.
B: Present value.
D: Contingency budget.
Expected monetary value (EMV) is a mathematical formula that can help make
comparisons between a range of uncertain outcomes. It is the probability x the
outcome. In this example there is an 80% chance the outcome will be $10,000. 80
x 10,000 equals an EMV of $8,000.
Which of the following choices indicates that a project has a burn rate of .833?
This is definitely a tough formula question that you may not have been exposed to
even if you are familiar with earned value formulas! The term "burn rate" from a
project management perspective determines the rate at which hours allocated to
a project are being used. It helps to identify when work is going out of scope, or
when efficiencies are being lost. Specific to earned value management, the burn
rate is calculated via the formula, 1/CPI, where CPI stands for Cost Performance
Index, which is equal to Earned Value(BCWP) / Actual Cost(ACWP).
Which of the following best describes a functional organization:
A: On target. This is small slippage and there is still plenty of time to recover.
B: On schedule. Most project plans are not accurate to less than one or two weeks.
C: Report the project one week behind schedule and include the action plans to
bring the project back on schedule.
D: Report the project one week behind schedule and then issue a new report next
week showing the problem fixed.
As the project manager working on a new software release project, a team member
has just brought to your attention a risk that has occurred that was not reflected in
the risk register. What should be your first course of action?
This is an unplanned risk since it was not reflected on the risk register which you
should first evaluate and determine the appropriate work around.
As the project manager working on a new software release project, a team member
has just brought to your attention a risk that has occurred that was not reflected in
the risk register. What should be your first course of action?
This is an unplanned risk since it was not reflected on the risk register which you
should first evaluate and determine the appropriate work around.
As the project manager working on a new software release project, a team member
has just brought to your attention a risk that has occurred that was not reflected in
the risk register. What should be your first course of action?
This is an unplanned risk since it was not reflected on the risk register which you
should first evaluate and determine the appropriate work around.
An approved change request impacting scope is:
A: Delphi technique.
C: Interviewing.
D: Documentation reviews.
A: Delphi technique.
C: Interviewing.
D: Documentation reviews.
A: Random causes.
B: Common causes.
D: Special causes.
Special causes are unusual events such as a snow storm not inherent in the
process itself. Random causes, maintenance problems are normal process
variations.
You are attending a kick-off meeting with approximately 13 participants. The project
manager starts the meeting with defining the roles and responsibilities for each of
the participants. You observe one of the members is giving body signals which is
generally associated with a feeling of uncertainty. What body signal would you most
likely be observing?
C: Bending forward.
D: Rubbing hands.
Body language of scratching the head or face is generally associated with
uncertainty or risk. A: Clenched fists or crossed arms is associated with a defensive
attitude.C: Bending forward is associated with interest. D: Rubbing is associated
with expectation
You are the PM in charge of running a Mix Martial Art (MMA) pay-per-view in
London, Ontario. This is the first MMA pay-per-view of its kind in this city. Tickets
will be sold at a first come first serve basis, with a flat fee of $25 a piece. One of
your responsibilities is to determine the location in which the event will be held.
There is a 45% chance that you can procure an outdoor venue for the event. If the
outdoor event is chosen, there is a 15% chance the event will be cancelled due to
rain. The outdoor venue has a capacity of 60,000 seats. If the indoor event is
chosen, there is 95% chance that the event would be a success, but this would
result in a 20% reduction in sales. What is the approximate probability that the
event will be held outdoors and in good weather?
A: 85%.
B: 0.38
C: 0.25
D: 0.52
45% x 85% = 38.25%
You are the PM in charge of running a Mix Martial Art (MMA) pay-per-view in
London, Ontario. This is the first MMA pay-per-view of its kind in this city. Tickets
will be sold at a first come first serve basis, with a flat fee of $25 a piece. One of
your responsibilities is to determine the location in which the event will be held.
There is a 45% chance that you can procure an outdoor venue for the event. If the
outdoor event is chosen, there is a 15% chance the event will be cancelled due to
rain. The outdoor venue has a capacity of 60,000 seats. If the indoor event is
chosen, there is 95% chance that the event would be a success, but this would
result in a 20% reduction in sales. What is the approximate probability that the
event will be held outdoors and in good weather?
A: 85%.
B: 0.38
C: 0.25
D: 0.52
45% x 85% = 38.25%
Sensitivity Analysis can be used in risk analysis to:
A: Estimate the effect of change of one project variable on the overall project
objectives.
B: Reporting formats.
The risk management plan describes how risk management will be structured and
performed on the project. It does not address the cost of individual risk
occurrences.
A project life cycle:
A: No action is required because the points are still within the control limits.
C: The process average has moved to the lower values and needs to be corrected.
A correction is required because even a slight change would move the data points
outside of the lower limit.
Which of the 7 main statistical processing charts determines possible causes of
potential problems and actual problems?
A: Flow charts.
B: A fishbone diagram.
C: A control chart.
D: Scatter diagram
The cause and effect diagram or "fishbone" is the brainchild of Kaoru Ishikawa, who
pioneered quality management processes in the Kawasaki shipyards, and in the
process became one of the founding fathers of modern quality management.¾ The
cause and effect diagram is used to explore all the potential or real causes (or
inputs) that result in a single effect (or output). Causes are arranged according to
their level of importance or detail, resulting in a depiction of relationships and
hierarchy of events. This can help you search for root causes, identify areas where
there may be problems, and compare the relative importance of different causes.
Causes in a cause and effect diagram are frequently arranged into four major
categories. While these categories can be anything, you will often see: manpower,
methods, materials, and machinery (recommended for manufacturing)
equipment, policies, procedures, and people (recommended for administration and
service).
You are leading a project team of 11 very senior chemical analysts. The client has
agreed to accept a cost variance in order to add one additional senior analyst to the
team so the project date can be advanced by one month. How many more
communication channels does this add to your current team?
A: 12
B: 11
C: 78
D: 66
The CPI (cost performance index) will identify how much is being produced for
every dollar spent on the project. I.e. we are only getting 90 cents for every dollar
we are spending on the project. To calculate the CPI: Earned value divided by the
actual costs to date. Remember an indicator of 1 or more is good. Less than 1 you
are in trouble.
You have just been contracted to be the project manager for a large telephone
switching centre upgrade involving approximately 58,000 existing telephone lines.
You have been a PM on many similar projects of this size and know there will be
significant data record validation prior to conversion to the new technology. Your
new boss informs you the project is approximately 25% into the planning phase.
What is the first thing you should do?
B: Schedule a status meeting with the team leaders and ask for their individual
project status reports. It's best to get the information face to face with the team.
C: Stop all tasks until you have had the chance to review the project charter to
ensure the scope is sufficiently defined.
D: Read the project charter, plans and current team status reports
This is a good situational question that emphasizes the value of a project charter
and regular performance reporting. Before you meet with the team you should be
knowledgeable on all the project documentation.
You are reviewing the 3 month cumulative earned value progress report for a
software development project. The indicators reflect an SPI of .87 and a CPI of .94.
What is the more likely explanation for why this occurred?
C: Less experienced resources are being assigned to complete the project work to
date.
D: The leasing of the server hardware was more expensive than expected.
Both the budget and the schedule are running behind since the indices are less than
"1". The best answer that would negatively affect both the time and cost would be
"C" since typically less experienced resources would take longer to complete
activities resulting in an increase to the budget. B: A task could take longer than
originally planned without necessarily increasing the costs since the task may not
start when planned.
Your project scope entails the production of 100 hand held math games to be
produced in 5 weeks to meet the prototype milestone marketing has mandated.
Your BAC is $10,000. It is now the beginning of week 3 and your status report
reflects actual costs to date of $2,000 with 40 handhelds successfully built. What
statement below should be included in your status report?
D: The project is producing $2 of work for every dollar spent. In order to calculate
the schedule and cost project status, you need to analyze the information provided
and determine the budgeted dollar values for the planned (PV) and the earned (EV).
And of course we need to know what the actual cost (AC) is which the questions
provides as $2,000.
You are working in the PMO when your immediate boss has asked you for your best
recommendation on how we can reduce the risk to the seller, from proposals
received from within the organization. You respond:
B: Have the purchasing department review all the proposals to ensure they are
compliant with outside industry practices.
C: Ensure a project manager assists in the creation of the estimates provided in the
proposal.
D: Add contingency to both the cost and schedule to accommodate for delays and
budget overruns.
C is correct: Assigning a project manager to assist in the proposal estimates will
help to make the estimates much more reliable as effective project management
tools such as a WBS, conduct risk analysis and various estimating techniques based
on the complexity of the activities would be utilized.
The statistical limits for process or product variation are called:
A: Specification limits.
B: Tolerances.
D: Quality standards.
The statistical limits for process or product variation are called:
A: Specification limits.
B: Tolerances.
D: Quality standards.
You have received anonymous complaints that the status meetings are dragging on
past the one hour mark. Your project team is comprised of a dozen project leads
and one such lead seems to be disrupting the flow of communication on a frequent
basis. Given the size of the project, access to information is critical and you rely on
all project leads to provide the necessary updates in a timely manner. The project
lead in question is not complying with your expectations. What destructive team
role is this individual exhibiting:
A: Topic Jumper
B: Devil's Advocate
C: Blocker
D: Withdrawer
What is the name or title of the individual on the project team responsible to
monitor the risk triggers and manage the risk response in the event the risk does
occur?
A: Project Manager.
C: Sponsor.
D: Risk owner.
D is correct: The risk owner which is identified in the risk register for each risk is
the person ultimately responsible to watch for risk triggers and to manage the risk
response. This person can be the project manager, team leader, risk action owner
or any other appr0priate stakeholder.
As the Director of the PMO for a large call centre, you meet monthly with your
project managers to review upcoming risks for all new technology projects
underway. One project being reviewed is at the half way completion mark and the
project manager has identified 9 risks that are "yellow" ranking. What does this
mean?
A: Quality audits.
B: 175000
C: 180000
D: 172000
B Correct: The target price for a FPI contract is the total of the target cost and
target fee. In this case: $150k plus $25k is $175k.
D Incorrect: $172k is the total contract price payout. AC 145 + TF 25 = 170 + 40% of
underage 5 is 2k for a total of $172k.
You are the project manager for a software company developing wireless mobile
application. You are currently in the Risk Identification process where you are trying
to identify and document all the risks that might impact your project. You have
assemble your experts in one room for face-to-face discussion. You intend to use a
face-to-face group judgment technique in which participants generate silently, in
writing, responses to a given question/problem; responses are collected and posted,
but not identified by author, for all to see; responses are openly clarified, often in a
round-robin format, further iterations may follow; and a final set
of responses is established by voting/ranking. Which technique are you using?
A. Brainstorming
B. Assumption analysis
C. Norming group technique
D. Delphi technique
Answer: C
Which of the following statements are false regarding sensitivity analysis?
A. Sensitivity analysis is a tool used in quantitative risk analysis
B. Sensitivity analysis is useful for determining the relative importance of
variables that have a high degree of uncertainty to those that have low
uncertainty
C. Sensitivity analysis helps determine which risks have the most potential impact
on the project
D. Sensitivity analysis examines how variations and uncertainty of individual
project element impacts the project objective, assuming all other project element
are varied concurrently
Answer: A
You are a project manager at an utility company. Due to the recent rise in the
cost of petroleum, the market demand for cheaper, alternate forms of energy
have grown exponentially. Your company has identified, a multibillion dollar
market opportunity for alternate forms of energy.
However your organization does not have enough resources and expertise to
exploit this market opportunity. Hence your organization has decided to form
joint ventures and risk sharing relationship with various other utility companies
to coordinate research and development activities. Which of he following best
describes the best strategy you are using with this market opportunity?
A. Enhance
B. Share
C. Avoidance
D. Exploit
Answer: B
The risk register describes all identified risks.
Which of the following is? not including as a part
of risk register?
A. Probability of occurrence, impact on objectives
B. Reporting formats, tracking
C. Proposed responses, owners, current status
D. Risk description, category, causes
Answer: B
Which of the following describes how the various risk
management processes will be implemented,
monitored, and controlled throughout the project and
describes the criteria that are used to establish the
risk threshold?
A. Workaround plans
B. Residual risks
C. Risk management plans
D. Checklists
Answer: C
You are a project manager at a project company developing wireless mobile
applications. You are currently in the risk identification process, where you are trying
to identify and document all risk that might impact the project.
You have assembled your experts both from inside and outside the company. You have
asked them to make a anonymous questionnaire to identify the potential risks of the
project. The experts will then mail back the questionnaire directly to you. Once you
have received the Feedback, you intend to organize the responses in order to compile
a final list of potential project risks. Which of the following best describes the
techniques are you using?
A. Normal group technique
B. Assumption analysis
C. Delphi technique
D. Brainstorming
Answer: C
Mary is the project manager of the HGH Project for her company. She and her
project team have agreed that if the vendor is late by more than ten days they will
cancel the order and hire the NBG Company to fulfill the order. The NBG Company
can guarantee orders within three days, but the costs of their products are
significantly more expensive than the current vendor. What type of a response
strategy is this?
A: Expert judgment
B: Contingent response strategy
C: External risk response
D: Internal risk management strategy
What are the tools and techniques of the Quantitative Risk Analysis
process?
A. Checklists, flowcharting, interviewing
B. Interviewing, sensitivity analysis, decision tree analysis,
simulation
C. Checklists, sensitivity analysis, decision tree analysis, information
gathering techniques
D. Interviewing, checklists, assumptions analysis, risk probability
impact
Answer: c Risk mitigation is the process of reducing a risk to acceptable levels. In risk
mitigation the risk has either a reduced impact or probability or both. This reduces the
risk severity to levels below the risk tolerance.
The project has done its risk analysis. In the process of risk identification the
project team has determined that there are risks that will probably happen that
have not been identified or evaluated except by noting that other projects of this
type have historically had a certain amount of risk discussed in the lessons learned
of the project. This project team should set aside money to handle these risks in
which financial category?
a. Risk management fund
b. Contingency budget
c. Management reserve
d. Emergency fund
Answer: c Management reserve is funds set aside to manage unidentified risks.
PMI refers to these as the ‘‘unknown unknowns.’’ When the management
reserve is used,it is moved from the management reserve to the cost or schedule
baseline.
A project manager observes that in one part of the project several activities are
being completed late. All of these activities have several days of free float
associated with them. These are early warnings of the risk that the project will be
late in completion. They are called:
a. Risk triggers.
b. Warning messages.
c. Risk forecasts.
d. Schedule risks.
Answer: a Risk triggers, sometimes called risk symptoms, are indications that a
risk is about to occur. In this example there is a risk that the project will be
delayed. There is a warning that this will occur because several activities are
now overdue for completion. They do not affect the project schedule yet, but if
this trend continues the project will be late.
A project manager and her project team are analyzing risk in their project. One of
the things that they might do to help identify potential risks or opportunities
would be to review:
a. The project budget.
b. The goals and objectives of the project.
c. Lessons learned from other similar projects.
d. The monetary value of changes for similar projects.
Answer: c The lessons learned document from other similar projects can be a
great help in determining the new risks associated with this project. Many
times risks repeat themselves from one project to another. This makes the
lessons learned document very important for all projects.
You are the project manager of the NHQ Project for your company. You have
completed qualitative and quantitative analysis of your identified project risks and
you would now like to find an approach to increase project opportunities and to
reduce threats within the project. What project management process would best
help you?
A. Monitor and control project risks
B. Create a risk governance approach
C. Create the project risk register
D. Plan risk responses
Answer: D
Frank is the project manager of the NHQ project for his company.
Frank is working with the project team, key stakeholders, and several
subject matter experts on risks dealing with the new materials in the
project. Frank wants to utilize a risk analysis method that will help
the team to make decisions in the presence of the current
uncertainty surrounding the new materials. Which risk analysis
approach can Frank use to create an approach to make decisions in
the presence of uncertainty?
A. Monte Carlo Technique
B. Qualitative risk analysis process
C. Quantitative risk analysis process
D. Delphi Technique
Answer: C
You’re managing a project to fulfill a military contract. Your project team is
assembled, and work has begun. Your government project officer informs you
that a supplier that you depend on has lost the contract to supply a critical part.
You consult your risk register and discover that you did not plan for this. What’s
the BEST way to handle this situation?
a) Consult the probability and impact matrix
b) Perform quantitative and qualitative risk analysis
c) Recommend preventive actions
d) Look for a new supplier for the part
19. Answer: D You’ve got an unplanned event that’s happened on your project.
Is that a risk? No. It’s a project problem, and you need to solve that problem.
Your probability and impact matrix won’t help, because the probability of this
happening is 100%—it’s already happened. No amount of risk planning will
prevent or mitigate the risk. And there’s no sense in trying to take preventive
actions, because there’s no way you can prevent it. So the best you can do is
start looking for a new part supplier.
At his Indonesia-based software manufacturing company, Daniel realizes
that risk management has become more important as the company
continues to evolve. He needs to begin the process of incorporating risk
management into all of his new projects. What is the first step in using a
WBS as an effective tool for risk management?
❑ A. Determine the probability of occurrence of risks.
❑ B. Review WBS elements and segment into risk events.
❑ C. Further define high-risk areas in the WBS.
❑ D. Include contingency activities in the WBS.
Answer B is correct. Answers A, C, and D are incorrect because they are
done after risk events are identified.
You are a project manager working on a software development project. You’ve
developed the risk management plan, identified risks, ad determined risk
responses for the risks. One of the risks you identified occurs, and you
implement the response for the risk. Then another risk occurs as a result of the
response you implemented. What type of risk is this called?
Trigger Risk
Residual Risk
Secondary risk.
Mitigated risk.
Answer C: Secondary risks occur as a result of the implementation of a
response to another risk.
The project manager of a large project meets several times with the client for
the project. During the meeting the project manager judges that the client
has a very low risk tolerance. This means that the client will probably:
a. Be willing to take large risks to make large profits.
b. Be unwilling to take large risks to make large profits.
c. Will understand when risks happen on the project.
d. Will not understand when risks happen on the project.
Answer: b Risk tolerance is the measure of the client to take risks. A client
with a low risk tolerance will not be willing to take very many or large risks
even though they may produce considerable opportunities to make large
profits.
A project manager is dealing with risk analysis on a software development
project. There is a risk that the module that creates the most important report
that the system will create will not work properly and will require 200 person-
hours to correct. The project manager decides to do nothing about this risk.
Which of the following risk strategies is the project manager employing?
a. Acceptance
b. Avoidance
c. Mitigation
d. Deflection
Answer: a Risk acceptance is doing nothing about the risk until it happens. This
is done with risks that are below the risk tolerance level.
The project manager has critical parts that are needed for the project. If the first
order of parts is delivered late, the project will be late delivering a critical deliverable
to the customer. The seller that has been selected to make these parts for the
project has been used in the past and historically has failed to deliver on time 10% of
the time. Another vendor can be found that has the same delivery record. The
project manager decides to divide the order between the two vendors in hopes that
at least one of them will deliver on time. What is the probability that at least one of
the vendors will deliver on time?
a. .81
b. 1.8
c. .99
d. 1.0
Answer: c The probability is that at least one of the sellers will deliver the parts on
time. This is the same as saying either vendor A or B must deliver. This is the
addition rule in probability. The probability that the first seller will deliver is .9. The
probability that the second seller will deliver is also .9, but the second seller
delivering on time is only of consequence if the first seller fails to deliver on time,
or .1. The calculation is then .9 + (.1x .9) =.99.
You are managing the construction of a data center, but the location is in an area
highly prone to earthquakes. In order to deal with this risk, you have chosen a type of
building and foundation that is particularly earthquake resistant. 'This is an example
of:
A. Risk transfer.
B. Risk avoidance.
C. Risk mitigation.
D. Risk acceptance.
C. The best answer here is risk mitigation since you are taking steps to lessen the risk.
'A' is incorrect because you are not transferring the risk to anyone else. 'B' is incorrect
because you would need to relocate in order to completely avoid the risk of
earthquake. 'D' is incorrect because you are not merely accepting the risk - you are
taking steps to make it less severe.
You are currently on a 3-week vocation in Australia. You’ve decided to rent a
car as your means of transport around the country. Driving in a foreign country
can be potentially a risky activity as you are unfamiliar with the terrain. Hence,
the probability of being involved in an accident is higher. You are very
concerned with regards to the financial liability incurred if you were involved in
an accident. As a project manager, you are aware of various techniques used to
respond to understand risks. You would like to apply your risk management
knowledge to reduce the risks associated with your driving. Which of the
following is the BEST example of risk
transference?
A. Be extra careful while driving defensively
B. Avoid driving, use public transportation instead
C. Accept the risk associated with driving
D. Buying auto insurance
Answer: D
You are currently on a 3-week vocation in Australia. You’ve decided to rent a car
as your means of transport around the country. Driving in a foreign country can
be potentially a risky activity as you are unfamiliar with the terrain. Hence, the
probability of being involved in an accident
is higher. As a project manager, you are aware of various techniques used to
respond to understand risks. You would like to apply your risk management
knowledge to reduce the risks associated with your driving. Which of the
following is the BEST example of risk avoidance?
A. Accept the risk associated with driving
B. Be extra careful while driving defensively
C. Buying auto insurance
D. Avoid driving, use public transportation instead
Which of the following processes involves ensuring that risk plans are
properly executed?
A. Risk monitoring and control
B. Risk response planning
C. Risk identification
D. Risk management planning
Answer: A
Which of the following best describes secondary
risks?
A. Risks that still remain after implementing a risk
response
B. Risk that arise due to quality issue
C. Risk that come about as a direct result of
implementing a risk response
D. None of the choices are correct
During project executing, a previously unidentified risk has just occurred. This risk
will negatively effect the outcome of the project.Which of the following is best to
perform next?
A. Alert the management team
B. Develop the contingency plan
C. Perform the risk audit
D. Create a work around
Answer: D
Which of the following best describes project funds that are held in reserve to
account for and offset known risks, such as project scope risks, schedule risks,
cost or quality risks?
A. Contingency reserve
B. Secondary risk
C. Residual risk
D. Contingency plan
Answer: A
Analysis of the errors occurring during a phase of your project indicates that 75%
are caused by operator error, 15% by substandard material and 10% by unknown
factors. You decide to focus on improving operator training. In doing so, you are
applying:
C: Quality management.
A: 7%.
B: 55%.
C: 38%.
D: 10%.
Surprisingly, words account for only 7%. 55% of the meaning of a message is
through facial expressions and body language; while 38% is through vocal tones.
What % of a message is conveyed through words?
A: 7%.
B: 55%.
C: 38%.
D: 10%.
Surprisingly, words account for only 7%. 55% of the meaning of a message is
through facial expressions and body language; while 38% is through vocal tones.
You have decided to respond to one of your project risks by buying insurance. What
will this risk response not protect against?
A: Secondary risks.
B: Theft.
C: Loss.
D: Flooding.
What % of a message is conveyed through words?
A: 7%.
B: 55%.
C: 38%.
D: 10%.
Surprisingly, words account for only 7%. 55% of the meaning of a message is
through facial expressions and body language; while 38% is through vocal tones.
There is a well known heuristic that 80% of the problems usually stem from 20% of
the causes. This is a concept of:
A: Crosby.
B: Deming.
C: Tachugi.
D: Pareto.
Remember the concept "worry about the major few, not the trivial many".
Vilfredo Pareto, an economist, determined 80% of the wealth was controlled by
20% of the population. Pareto charts are used to display the Pareto principal in
action by arranging data so that the few vital factors that are causing most of the
problems reveal themselves. Concentrating improvement efforts on these few
will have a greater impact and be more cost-effective than undirected efforts.
What is the key to understanding Herzberg's theory of motivation?
D: Hygiene factors relate to the work environment while motivators relate to the
work itself
.
General management skills provide much of the foundation for building project
management. What are not considered general management skills?
A: Fishbone diagrams.
B: Control charts.
C: Pareto charts.
D: Histograms.
D: Your management is looking for rapid and visible action on this project to rectify
the problems.
Statistical quality control is the method used to measure variability in a product or
process under evaluation. The two major systems used in statistical quality control
are:
B is correct: Plan Risk Response is the process that ensures we enhance the
opportunities and reduce the threats to the risks identified and analyzed in the
previous processes.
You are a Program Manager responsible for the health of 5 projects currently
underway. You have asked each Project Manager to report on the current status of
their projects, using the Earned Value Technique. At the last quarterly project audit,
you discover that one PM is reporting overly optimistic status on one project, and it
is in worse shape than is reported. The project is a mission-critical one to the
organization and if it continues at the current pace, the final delivery date will be
missed, leading to serious consequences for the company. What is your immediate
response?
A: Have a one-on-one meeting with the PM to understand why his Earned Value
reports are off, determine the actual status, and monitor the PM moving forward to
ensure it doesn't happen again.
C: Meet with the PM, work with the PM to devise and execute a plan to get the
project back on track, and inform the sponsor.
B is correct: Plan Risk Response is the process that ensures we enhance the
opportunities and reduce the threats to the risks identified and analyzed in the
previous processes.
All of the following are outputs from performance reporting except:
C: Performance reports.
D: Resolved issues.
A: No action is required because the points are still within the control limits.
C: The process average has moved to the lower values and needs to be corrected.
A correction is required because even a slight change would move the data points
outside of the lower limit.
You have just been contracted to be the project manager for a large telephone
switching centre upgrade involving approximately 58,000 existing telephone lines.
You have been a PM on many similar projects of this size and know there will be
significant data record validation prior to conversion to the new technology. Your
new boss informs you the project is approximately 25% into the planning phase.
What is the first thing you should do?
B: Schedule a status meeting with the team leaders and ask for their individual
project status reports. It's best to get the information face to face with the team.
C: Stop all tasks until you have had the chance to review the project charter to
ensure the scope is sufficiently defined.
D: Read the project charter, plans and current team status reports.
According to standard statistical control rules, if the data results reflect 7
consecutive data points on either side of the mean, this tells you:
C is correct: Contingency reserves are included in the original project baseline for
potential risks that do occur as identified in the risk register. A incorrect:
Management approval is required to spend management reserve which is for
unplanned risks that may occur.
You are getting ready to present your project status to your sponsor next week. You
are reviewing the contingency reserve variance which is tracking well within the
thresholds you set. This contingency reserve is:
C is correct: Contingency reserves are included in the original project baseline for
potential risks that do occur as identified in the risk register. A incorrect:
Management approval is required to spend management reserve which is for
unplanned risks that may occur.
Your sponsor has made it very clear she will pay for the project but wants it as soon
as possible. Your sponsor is considered to be:
A: Risk adverse.
B: Authoritarian.
C: Risk accepting.
D: Unreasonable
Finally after one month of working at your new company you are assigned your first
project and have started applying the many project management practises you have
learned from past projects. You are reading the scope statement in detail to
evaluate the complexity of the project from a risk perspective to determine if this is
a typical project or atypical project this company has experience with. What risk
management process are you most likely in?
D: Identify Risks.
A is correct: The scope statement is an input to the Perform Qualitative Risk
Analysis process. Review of the scope statement will determine the complexity of
the project work to assess the uncertainty in more detail.
Your risk analysis involving your project scope reflects your project has a 70%
chance of completing the scope by a specified date with an 80% chance of receiving
approval for the scope by a certain date. Based on this data, what is the probability
of both events occurring?
A: 75%.
B: 80%.
C: 50%.
D: 56%.
One event will not happen unless the other event occurs. We calculate by
multiplying the probability of event 1 by the probability of result 2. In this case
.80 x .70 for 56% probability of occurrence.
You are the PM on a major pipeline project which has been chartered to carry crude
oil from the city port to various processing plant across the province. Portions of the
pipeline are shared with each processing plant, and custom software will be built to
manipulate the numerous dampers within the pipes to direct oil to the proper
location. A special quality focus is placed on this project as any malfunction in the
dampers could potentially cause a pipeline backup. This could result in crude oil
escaping the pipes and leaking into the environment. You call a meeting with your
developers and civil engineers and begin to graphically represent the interaction of
failures and other events within the pipeline system. This technique is known as :
C: Biohazard Analysis
A: Project files.
A: Contact your company legal team to research the options to handle this
situation.
B: Stop all the payment to the contracting firm until this threat is fully assessed.
C: Call for an urgent meeting with your senior management to inform them about
the threat.
D: Quickly perform additional risk response planning to control the threat on this
situation.
D is correct: As a project manager, you should first plan for the new threats this
situation poses. A might be another correct answer, but this is not the first thing
you should do as a project manager. B incorrect: You cannot simply withhold
payment if you are in contract with another company. C incorrect: A project
manager should deal with the problem first and not escalate to senior
management.
The five basic quality concepts deal with:
A: Zero defects, doing the right thing right the 1st time, the next recipient in the
process is treated as customer, continuous improvement process and process
capability.
B: Inspecting for errors, zero defects, acceptance sampling, control charts, and
cause and effect diagrams.
C: Doing the right thing right the first time, waste elimination, audits, walkthroughs,
and continuous improvement.
A: Project files.
When summing the probability distributions if the distributions are skewed to the
__________, the project mean will always be significantly higher than the sum of
the most likely estimates.
Right
Left
Middle
Not skewed
Risks classified as unknown (i.e., those which cannot be identified or evaluated):
Should be deflected to the contracting officer
Should be handled via contingency allowances
Should be ignored since they cannot be identified
Should be ignored, since they are not covered in the Project Risk Assessment
Risks can be divided into two basic types: business risk and pure (or insurable risk).
Of the following, which one(s) fall(s) under business risk?
Liability Loss
Direct property loss
Profit loss
Personnel-related loss
The type of contract (payment mechanism) chosen for a project is of the degree of
risk associated with completing that project. For a firm fixed price contract,
payment for risks:
Is accomplished by paying the actual costs to the contractor
Is accomplished by paying the contractor for his cost plus a fixed fee (profit)
Is an undisclosed contingency in the contractor's bid
Is accomplished by paying for the budgeted costs of dealing with as predicted in the
Project Risk Assessment
Total Project Risk
1. should not be calculated for small project
2. is the probability of each project event times the sum of the consequences of
individual project risk events
3. is the cumulative sum of the probability of each individual project risk event
times the consequences of occurrence of that risk event
Risk event probability is determined as:
The total number of possible events divided into the expectation or frequency of
the risk event
The number of times the risk event may occur
The fraction of the total project tasks which may be affected by the risk event
The total number of possible events divided into the consequences of the risk event
Final risk quantification and modeling normally considers the impacts of all risks
combined and:
Translated the impacts into economic terms for analysis
Concentrated on schedule impacts
May not consider safety and environmental impacts
A and B
A and C
40. Sensitivity Analysis can be used in risk analysis to:
1. Substitute for uncertainty analysis in risk quantification
2. Estimate the level of risk aversion adopted by management
3. Estimate the effect of change of one project variable on the overall project
4. A and B
Many companies self-insure against some risks. Problems which can arise from self-
insurance include
1. failure to reserve funds to handle worst-case scenarios (low probability events)
resulting in sever financial damage to the company
2. stiff competition from insurance companies
3. confusion of business risks with insurable risks
4. A and C
Final risk quantification and modeling normally considers the impacts of all risks
except possibly those due to producibility
reliability
affordability
acceptability
Risk event is the precise description of what might happen to the _________ of the
project. manager
detriment
schedule
Budget
In the risk management context, mitigation and deflection are moth means of
_________ the risk to the _________ objectives.
1. improving; client's
2. increasing; project's
3. decreasing; sponsor's
4. decreasing; project's
Suppose the project is set at $2,300,000 for the total project. Some work that must
be accomplished has not been identified in the initial planning. The most
appropriate source of funds to cover this work is the __________.
management reserve
contingency reserve
slush fund reserve
sinking fund
corporate profit
Suppose the project manager is planning courses of action to develop the strategy
for the project. Courses "A" and "B" are both feasible options and can be
implemented. Senior management has directed that risk be considered, but there is
a need to maximize the profit on this project. A decision tree is used as a valid
means for selecting the most profitable option. Course "A" has a potential profit of
$27,500 with a probability of 0.75 success. Course "B" has a potential profit of
$20,800 with a probability of 0.90 success. The course of action that should be
selected is __________.
1. Course "A" because it has a higher profit potential
2. Course "B" because it has a higher probability of success
3. Course "A" because it has an expected value of $36,667 when the probability is
factored into the decision
4. Course "A" because it has an expected value of $1,905 more than Course "B"
5. Either course because there is no difference in expected value
Suppose the project has many hazards that could easily injure one or more persons
and there is no method of avoiding the potential for damages. The project manager
should consider __________ as a means of deflecting the risk. abandoning the
project
buying insurance for personal bodily injury
establishing a contingency fund
establishing a management reserve
not acknowledging the potential for injury
The primary characteristic that distinguishes external and internal risk areas is the
__________.
1. magnitude of the impact on the project
2. project manager's perception of risk
3. technical nature of the project
4. use of more or fewer subcontractors
5. project manager's ability to influence the risk
There are two general categories of risk areas, internal and external. Examples of
external risk areas are __________.
1. schedule delays, cost overruns, and changes in technology
2. regulatory, project completion, and taxation
3. natural disasters, regulatory, and design
4. currency rates, design, and social impact
5. inflation rates, performance, and schedule delays
In the area of legal risks, there are two reasons for licensing of projects. One reason
is for revenue generation by the community, while the other is for __________.
1. harassment of the project manager
2. bureaucratic interest in the project
3. public safety of the product
4. monitoring of the project schedule
5. identification of the project manage
During the conduct of impact analysis for any risk, the individual performs
screening. Screening is for the purpose of determining whether the risk is
__________ the project.
1. within or outside the scope of
2. a contingency item for
3. significant enough to adversely affect
4. realistic and treatable during implementation of
5. all of the above
74. Suppose a project of $1.5 million has an adverse event that has a probability of
0.07 of occurrence and a potential loss of $15,000. This represents an expected
negative value of __________.
1. $10,500
2. $1,050
3. $105
4. $15,000
5. cannot be determined from the available data
The assigned values of risk for a project is best accomplished through a structured
methodology that ensures all project elements are evaluated. The project tool
that is best suited for the structured analysis of the project risk is the
__________. contract
1. specification
2. statement of work
3.work breakdown structure
4. linear programming diagram
During the assessment of the risk to attempt to quantify the probability of failure
and the amount of potential loss, the project manager uses the __________
personnel to make the estimates. engineering
A. marketing
B. experienced
C. planning
D. project
You work with several full-time project managers in a software company who share
1 administrative person. Typically the company undertakes 8-10 projects per year,
utilizing approximately 25% of the company's employees, however these employees
do not report to you. This organization structure can best be described as a:
A: Functional.
B: Strong matrix.
C: Projectized.
D: Balanced matrix.
We can rule out functional and weak matrix organization types since there is a
group of full time project managers. Since the project staff work 25% on the
project, the only one that accomplishes this restriction is a balanced matrix.
Tim is the project manager for a project that involves the production of a new line
of computer software that is used to track and manage designated substance (Dub)
information found with in buildings. Tim is having regular bi-weekly meetings with
his team. He had his team do a first cut on its view of what risks affect the project.
What should Tim do next?
D: Involve stakeholders in a 2nd review and then people not directly involved in
the project for a final, unbiased review.
A: =(1+4*2+5)/6
B: =(1+5)/2
C: =(1+2+5)/3
D: 5
Since the task has a high level of uncertainty, it is best to use the PERT non-
weighted to take the emphasis off of the most likely. (P + ML + O)/6
Updates to the risk register after the Perform Qualitative Risk Analysis process
include:
D: Contingency reserves are for unplanned but potentially required changes that
can result from risks identified in the risk register.
A: Risk categories.
B: Risk Policies.
D: Risk constraints.
These could be examples of high level risk categories that could be found on risk
checklist or risk breakdown structure.
Which of the following is considered an information gathering technique to use
during the Identify Risks process?
A: Documentation reviews.
B: SWOT Analysis.
B: Ordinal.
D: Continuous
C is correct: Cardinal/quantitative scales assign numeric values and can be either
linear such as this example .1 .3 .5 .7 .9 or non linear such as: .05 .1 .2 .4 .8.
A is not correct: Cardinal non linear would be .05 .1 .2 .4 .8.
B is not correct: Ordinal/qualitative scales are rank-ordered values, such as, very
low, low, moderate, high, and very high.
You have just attended a meeting with the Netcon Incorporated executives and learned they
are considering the introduction of two new software products to the market. The result of
this meeting is the company has four options regarding these two new software products:
Introduce neither product, introduce product 1 only, introduce product 2 only, or introduce
both products. Research and development costs for product 1 is $180k and for product 2 is
$150,000. There is no associated costs with the status quo. The marketing department has
provided a forecast of expected sales revenue for both products in the Canadian market based
on the probabilities of realizing a strong, fair and weak trend in the economy for the upcoming
year at 0.30, 0.50, and 0.20, respectively. From the view exhibit button (top right hand corner)
what option from a risk perspective would you recommend the executives approve?
A: Product 1 only.
B: Both Products.
C: Product 2 only.
D: Insufficient data to decide best option to recommend to the executives.
B is correct: Both products have the biggest gain at $151k. Product 1 gain is $124k and
Product 2 gain is $113k. There are 2 parts to this equation: multiply each dollar value
by the probability of it occurring, sum up for EMV and then for each option deduct the
Research and Development costs to determine the option with the biggest gain.
Product 1: $304k EMV minus R & D costs of $180k total gain $124k.
Product 2: $263k EMV minus R & D costs of $150k total gain $113k.
Both Products: $481k EMV minus R & D cost for both products $330k total gain $151k.
A major process in project integration management is:
B: Initiation.
C: Sequence Activity.
D: Define Scope.
B: Having a point outside the control limits is the most easily detectable out-of-control
condition.
C: The likelihood of having a single data point out of control by chance is only about 1 in 1,000.
Common cause variations would reflect all points within the upper control limits
(UCL) and the lower control limits (LCL). The fact that the control chart has one
data point outside the control limits leads to a special cause variation is present.
Your team is planning responses to the risks that were identified and analyzed already. What
would not be required to do now during this process?
D is correct: It would be too late in the process to be verifying project information. This
should be done during the Identify Risk process.
Specific results from lessons learned include all of the following except:
A, B and C will not ensure that the message is understood as intended. Only by employing
active listening and focusing on the team member's response and asking him/her to
feedback to you what they understand as the requirements, will you be sure that they
understand what they are expected to accomplish.
As the risk prime for all the technical risks, you have called a
meeting with a few experts with both software and hardware
expertise to assess the impact of the technical risks reflected in
the risk register. What risk management process are you most
likely in?
A: A cause-and-effect diagram.
B: Pareto diagram.
C: Design of experiments.
The cause and effect diagram is used to explore all the potential or real
causes (or inputs) that result in a single effect (or output). Causes are
arranged according to their level of importance or detail, resulting in a
depiction of relationships and hierarchy of events. This can help you search
for root causes, identify areas where there may be problems, and compare
the relative importance of different causes.
Which of the 6 Risk Processes assigns the risk owner?
A: The risk owners are assigned after the analysis
processes during the Plan Risk Response process.
A: Mean = 5.1.
B: Mode = 4.
C: Median = 6.
D: Range = 8.
C is correct: The median for this set of data is 5 not 6. The median is the middle value of the
data ordered when they are ranked top to bottom or bottom to top. In the event your set of
data is an even number, take the average of the middle 2 numbers for the median.
A wrong: The mean is the average of the set of data. In this case 5.1 Add all the numbers and
divide by the number of total data points.
B wrong: The mode is the most frequent number. In this case 4.
D wrong: The statistical range is the difference between the lowest and highest valued
numbers in a set of numbers. To find the range of a group of numbers: Arrange the numbers
in order by size then subtract the smallest number from the largest number. In this case 9
from 1 = 8.
Your team lead has just advised you that a task estimate is
significantly flawed. The revised estimate submitted naturally
adds time to the original estimate. What is the first thing as the
project manager you should do?
C: Notify management.
A: Duplication of effort on some tasks, project manager has to negotiate with other PMs for resource
availability, and project communication is more complex.
B: Project communication is more complex, team members work themselves out of a job, and resources
report to functional managers.
C: Lack of deep expertise of each functional department, professional growth is difficult in a specialized
area, and a high probability for contention.
D: Projects are prioritized lower, resources may likely be less loyal to PM, and the project manager has to
negotiate with other PMs.
A: This is a tricky question as each possible answer contains at least one drawback from a matrix
organization combined with drawbacks from both functional and projectized organizations. The drawbacks
for a matrix organization are:
- Duplication of effort on some tasks which results in higher overhead.
- Project managers not only must negotiate with functional managers for resources, but must negotiate with
other PMs as well.
- Communication is more complex.
- Resources report to a functional manager.
- A high probability for contention between PM and functional manager.
- Because resources don't report directly to the PM, they may be les loyal to the PM's cause.
War rooms have many functions, one of which is to give the project a
physical identity, another of which is to hold the coffee pot; but they are
not a requirement on every project. They will give the project an
advantage since it provides a single place where all project information can
be located.
Your project will involve some communications between the customer and
several contractors during the execution phase. What is the best method
for communication between the customer executive and the contractor
executives?
A: Formal.
B: Informal.
D: Not required.
A: PERT does not show the critical path, but CPM does.
C: Project charter.
D: Project budge
Answers B or A may factor into the decision, but alone would not make the
Sponsors move a launch date. One of the key responsibilities of a PMO is to
optimize the use of shared organizational resources across all projects.
Your solution-delivery organization is going through a transformation
exercise, which will adapt the structure to focus on changes in the
marketplace. You would like to recommend that the transformation include
setting up a PMO to assist in managing projects. What should you make
sure is in place from the outset to ensure the success of the PMO?
A: Provide the most recent status update, even though it is not entirely
current.
C: Respond as requested.
D: Call a meeting of the core team members and ask them directly why
they are not reading the reports.
An informal feedback survey reflects that more than 60% of your core team
members are not reviewing the bi-weekly project updates distributed to them
via the internal company project web site. As the project manager what course
of action should you take?
A: Revise the communications plan appropriately to meet the informational
needs of the stakeholders.
Though there is dispute over what the exact percentages are, face to face
communication can be broken down into Verbal (words - 7%), Para lingual
(tone and inflection - 38%) and Visual (non-verbal - 55%) Components.
You have 3 independent activities, A, B, and C that are scheduled to start on
the same day. Each activity has a duration estimate of 3 days to complete.
What are the chances of starting the converging activity D on day 4 if the
probability to complete each activity is 50%, 50% and 50% respectively?
A: 13%.
B: 40%.
C: 50%.
D: 10%.
This is a tough questions to answer. Probability of starting the converging
activity D on day 4, is 13%. (0.5 * 0 .5 * 0.5) = 0.125 or 13%.
There are 8 logical outcomes from this scenario, with only one of them
being all of them on time. 1/8 = 12.5%.
Manual filing systems, electronic text databases, project management
software, are examples of:
B: Communication technology.
D: Project records.
Project information can be completed through various media - such as
manual, electronic, software and processes that permit access to technical
documentation, such as engineering drawings and specifications.
In communications, the receiver filters messages based on all but which of
the following?
A: Culture.
B: Semantics.
C: Language.
D: Distance.
The assumption here is that the media used for distance communication
is acceptable. i.e. the fax or phone is operational.
Internal rate of return is:
C: The interest rate that equates the present value of expected future net
cash inflows to the initial cost outlay.
D: The interest rate that equates all future cash inflows to zero
Internal Rate of Return is the discount rate where the present value of the
cash inflows exactly equals the initial investment. In other words, IRR is the
discount rate when NPV is zero. Present Value can be expressed as a
number. Therefore answer A and B are incorrect. Answer D indicates cash
inflows, not inflows and outflows. Note that IRR relates to both inflows and
outflows and the calculations are extremely complex and not frequently
used.
Internal rate of return is:
C: The interest rate that equates the present value of expected future net
cash inflows to the initial cost outlay.
D: The interest rate that equates all future cash inflows to zero
Internal Rate of Return is the discount rate where the present value of the
cash inflows exactly equals the initial investment. In other words, IRR is the
discount rate when NPV is zero. Present Value can be expressed as a
number. Therefore answer A and B are incorrect. Answer D indicates cash
inflows, not inflows and outflows. Note that IRR relates to both inflows and
outflows and the calculations are extremely complex and not frequently
used.
Your team or technical risk experts are meeting to conduct a risk probability
and impact assessment on the risks for the next two phases of your project.
What will the team of experts require to review first to conduct the P/I
assessment?
C: P/I matrix.
D: P/I definitions.
D is correct: The P/I definitions are defined in the Risk Management Plan
to ensure the ranking of project risks are consistently measured and
ranked. These definitions are then referenced by the team during the P/I
assessment meeting.
The PMO has contacted you as the project manager and advised a "Quality
Audit" on your 2 year project has been scheduled for the beginning of the
next quarter. At the next team meeting, you inform the project team of the
scheduled quality audit. The team is highly stressed to begin with due to
the recent company budget cuts and strongly object to this upcoming audit.
You start to explain to the team that the purpose of a quality audit is:
D: Delphi.
A is correct: Affinity diagramming will sort risks identified in a way that
promotes new risks to be identified thus making it the best choice.
B is incorrect: This is a relatively slow technique and probably does not
have a reasonably good chance of uncovering something new after risk
identification has been completed.
C is incorrect : At first glance brainstorming may appear to be a good idea,
however this has already been completed.
Its 10:30 in the morning, and as creatures of habit you enjoy making a
"coffee-run" for you and your fellow associates in the office. Massimo, a
PM who you've worked with in the past, decided to join you on your way to
the coffee shop. Massimo begins to discuss an interesting technique for
stakeholder analysis that he is currently using on his latest project.
Massimo mentions this technique involves the act of taking a job
traditionally performed by designated agents and outsourcing it to an
undefined, generally large group of people in the form of an open call.
What technique is Massimo referring too:
A: Phishing
B: Off shoring
C: Crowd sourcing
D: Distributive Prototyping
Crowd sourcing is a bottom up approach to stakeholder analysis. It taps
into the feedback and design of a collective group of individuals who share
an interest in a given subject matter. These individual replace the
traditional designated agents, the Business Analysis, and provide a different
spin on the subject matter by utilizing lateral thinking.
A project manager is in the process of evaluating and prioritizing risks in the
project by calculating Risk Priority number (RPN) for the risks. What are the
3 attributes required to calculate the RPN to further prioritize the identified
risks?
B: An audit.
C: A recall.
A: 627,000
B: 114,0000
C: 573,750
D: 127,000
55% x 95% x $1,200,000 = $627,000.
Ticket sales for the outdoor event: $25 x 60,000 seats = $1,500,000
Ticket sales for the indoor event: We know that there is a 20% reduction in sales as compared to the
outdoor event. $1,500,000 x 20% = $300,000.
Therefore, $1,500,000 - $300,000 = 1,200,000 expected sales/revenues.
Now we determine the risk factor of having the event indoors (55%) and a successful event (95%) and we
have a probability of success of (55% x 95% ) is 52.25%.
Risk factor 52.25 X expected gain of 1,200,000 to reach an EMV of 627,000 .
The ultimate goal of applying the risk management process to a project is
to:
A: Portfolio Management.
B: Project Management.
C: Program Management.
B: Correctness of understanding.
The sender is responsible for the completeness of the message along with
the clarity and unambiguousness
You are looking at the risk register after the risk analysis processes have
been done. What should be your next action?
C is correct. The risk management plan is the only output of the Plan Risk
Management process. B: The risk register is created during the Identify
Risk process.D: The revised stakeholder tolerances if applicable are
included in the risk management plan.
You are estimating the risk of outsourcing vs. staffing internally to complete
the periodic drafting tasks in your project. The service provider for
outsourcing explains that they can not guarantee that your company will be
assigned the same individuals to complete your work each time you require
drafting services as it is just based on availability. If you consider each time
you receive staff from this company to be an event, these events would be
considered to be:
A: Mutually exclusive.
B: Statistically independent.
C: Statistically dependent.
D: Mutually inclusive.
D: Flowcharting.
Benchmarking is a tool used for process improvement. Areas where the
team is having trouble are identified and then an organization which has
successfully mastered that problem is located. That organization's
processes are studied and adapted where practical.
As the project manager for the new medical wing expansion, a team leader has
brought to your attention a new process to complete several work packages
that would normally take 6 weeks can now be finished in just 3 weeks. You
decide to take advantage of this opportunity and rework the schedule with the
new advanced project delivery date. Your actions would be good example of:
B: Checklist analysis.
D: Assumptions analysis.
A: Functional.
B: Strong matrix.
C: Projectized.
D: Balanced matrix.
We can rule out functional and weak matrix organization types since
there is a group of full time project managers. Since the project staff
work 25% on the project, the only one that accomplishes this restriction is
a balanced matrix.
You are a team member working on a project which will deliver a new extra
spicy sauce. During the development phase, you are tasked to determine the
optimum torque requirement for the new jar the sauce will be packaged in. Any
torque greater than 8 pounds will mar the finish on the glass. You start to look
at all the factors such as line speed, lid placement and conveyor speed that can
contribute to the torque. This is called _________ which is conducted during
the _________ process.
D: A and B.
It would be next to impossible to eliminate all risks from a project,
therefore in some cases we must accept the risk. Risk acceptance
indicates the project team has decided not to change the project plan. It
can be both passive - do nothing at all, or we can actively accept the risk
by establishing a contingency reserve, including amounts of time, money
or resources to handle the identified risk.
Tim is the project manager for a project that involves the production of a
new line of computer software that is used to track and manage designated
substance (Dub) information found with in buildings. Tim is having regular
bi-weekly meetings with his team. He had his team do a first cut on its view
of what risks affect the project. What should Tim do next?
A: Formal / Legitimate.
B: Expert / Referent.
C: Penalty / Coercive.
D: Charismatic / Technical.
Expert and referent are "earned" types of power based on the knowledge,
skills and experience an individual has obtained. Formal, reward and
penalty are "legitimate" powers based on one's position in the company.
You are trying to obtain estimates for the duration of building a shed and
you ask the contractor to provide you with an estimate for the duration. He
explains that best case, it will take 1 day; however, based on past
experience it usually takes 2 days. Knowing that the weather is quite
uncertain at this time of year, there is often a delay, resulting in the task
taking 5 days. Based on the high level of uncertainty in this effort, what
would be the expected duration of this task?
A: =(1+4*2+5)/6
B: =(1+5)/2
C: =(1+2+5)/3
D: 5
Since the task has a high level of uncertainty, it is best to use the PERT non-
weighted to take the emphasis off of the most likely. (P + ML + O)/6
What would be the most effective method to quantify a risk that was ranked with a
high impact and medium probability to review and discuss with your sponsor?
A: Expected monetary value.
B: Utility theory.
C: Sensitivity analysis.
D: Probability analysis
C is correct: Sensitivity analysis helps to determine which risks have the most
potential impact on the project. T typically you would perform for variables which
are likely to have a major impact on project performance in terms of cost, time, or
economic return. It is a simple method of analyzing the impact of potential risk and
its results are easy for project stakeholders to understand. Tornado charts are often
used to visually depict the sensitivities.
Note the disadvantage: it does not lend itself well to assessing combination of risk
and how they might affect a project. Furthermore the sensitivity diagram does not
provide an indication of anticipated probability of occurrence of the risk event.
A is incorrect: EMV is a method to determine which decision to take by factoring in
the risks associated with each possible decision.
B is incorrect: Utility theory is stakeholder risk tolerance level. i.e. risk adverse, risk
taker or risk neutral.
D is incorrect: Probability analysis is a qualitative method not quantitative method.
A histogram ordered by frequency of occurrence that reflects the vital few and
trivial many is called a:
A: Statistical histogram.
B: Control chart.
C: Quality chart.
D: Pareto diagram.
The chart derives its name from the Pareto Law - 80% of all errors are
attributable to 20% of all causes.
It is a rank ordering, arranging data in descending order according to magnitude or
influence thus identifying that the fewest causes produce the most defects, so by
eliminating the few causes (vital few), the greatest number of defects can be
eliminated.
Control charts are used to routinely monitor quality. When using control charts,
control limits are chosen so that almost all of the data points will fall within these
limits as long as the process remains in-control. What is the horizontal line in the
middle of the chart referred to?
A: Mean.
B: Specification limit.
C: Data point.
All control charts have three basic components: a centerline, usually the
mathematical average of all the samples plotted, upper and lower statistical control
limits that define the constraints of common cause variations and performance data
plotted over time.
The purpose of making control charts is to look at variation, seeking special causes
and tracking common causes. Special causes can be spotted using several tests:
1 data point falling outside the control limits
An example of verify scope is:
A: Identify Risks.
Answer A is the exact PMBOK Guide definition of what a program is which makes it
the best answer from all the possible choices.
You are reviewing several control charts with the quality control team. One of the
charts reflects seven data points in a row on one side of the mean. What action
should be taken based on these results?
This is the rule of 7 - which refers to non-random data points grouped together in a
series that total seven on one side of the mean. The rule of seven tells you, that
although none of these points are outside of the control limits, they are not random
and the process is indeed out of control. Chances of this happening are 1.56%. This
type of situation should be investigated to determine the cause of the variation.
Your team uses statistical sampling to estimate the mean value of the quality
characteristic of your product. A quantitative measure of precision of this
estimation is standard error. Which one of the following statements is true?
A: Functional manager.
B: Project sponsor.
C: Project manager.
D: Business manager.
Due to a recent downsizing in the company, it is inevitable that you will be
reassigned within the next 3 months. After meeting with your current boss, you
mutually agree it would be in your best interest to transfer to the department that
controls project managers, documentation, methodologies and policies and gathers
and distributes lessons learned from the company projects. What does this
department best describe?
B: Value Engineering.
C: Process Analysis.
D: Benchmarking.
D is correct: Benchmarking is a Plan quality management tool. It is the process of
comparing the business processes and performance metrics including cost, cycle
time, productivity, and/or quality to another that is widely considered to be an
industry standard benchmark or best practice. The objective of Benchmarking is:
1: To determine what and where improvements are called for
2: Assess how other firms achieve their high performance levels
3: Use this information to improve the firm's performance.
Unfortunately, the project produced less than desirable results. Should you, as the
project manager proceed with a lessons learned session?
A: Performance measurement.
B: Alternatives identification.
C: Product analysis.
D: Inspection.
Inspection is the only tool and technique for verify scope. Measuring, examining,
testing undertaken to determine whether results conform to requirements.
Sometimes referred to as: reviews, product reviews, audits, and walk-throughs.
A: Performance measurement is an earned value technique of cost and schedule
control.B and C are tools and technique for scope definition.
The type of information that we distribute is a reflection of stakeholder
requirements. Typically senior management would require what type of
communication?
Typically senior management requires less detail with more graphical information.
They are looking for status and warnings along with problem isolation and proposed
recommendations.
Communicating involves understanding the other person and agreeing on what was
said. The use of _____________ is a means of giving feedback to the speaker by
paraphrasing the speaker's words to ensure there is a common level of
understanding.
A: Double talk.
B: Double speak.
C: Give-back.
D: Active listening.
According to the PMBOK Guide definition of contingency reserve, which of the
following is a false statement about contingency reserves?
C: Contingency reserve is added to the budget to allow for the risk of overruns on
the project objectives to a level acceptable to the organization.
D: Contingency reserves are normally included in the project's cost and schedule
baselines.
Contingency reserves are included in the baseline and do not require management
approval to spend. Management reserves, which are not included in the baseline
require management approval. This is for unplanned changes to project scope and
cost.
Your team lead Susan has agreed to take on the responsibility to identify and assess
the technical risks for the large enterprise resource platform project you are the
project manager for. Susan is reviewing the results she recently ran using the Monte
Carlo technique. The results she is reviewing are most likely displayed as a:
A: Trend Chart.
B: Control Chart.
D: Probability Distribution.
The missing piece of information here to assess correctly is "the value of the work
that has been accomplished to date". Or in earned value terms: EV or BCWP.
As a project manager your project is placing approximately 50 miles of sewer pipe
for a new residential development site. Some of your responsibilities involve
analyzing if there are changes to the scope of the project, the schedule, the budget
and the technical requirements. These responsibilities are part of which process?
A: Executing.
B: Controlling.
C: Planning.
D: Closing.
Controlling: Ensuring that the project objectives are met by monitoring and
measuring progress and taking corrective action when necessary.
A newly-minted Project Manager working under you in your portfolio is frustrating
his team by demanding that all documents in the PMI process be created as
separate stand-alone documents that must be reviewed and signed off by the team.
This is causing the progress of the team to slow which is a concern since the
delivery date is fast approaching and no clear plan is in place yet. Everyone is
anxious to get started, but no one knows how to speak to the PM. You have been
asked to assist. What is your best approach?
B: Take on the project yourself and get it to a point where you can pass it back to
the PM for day-to-day management.
C: Leave the PM in place, but ask the senior developer to pull together a plan that
can be executed.
D: Have a one-on-one with the PM to explain that the PMI Methodology consists
of best practices that should be scaled appropriately to the complexity of the
project.
PMI states that the process should not be applied rigidly but with flexibility based
on the complexity of the project. Any other option would be an overreaction at
this point.
During the risk response planning meeting with your technical experts, discussion
about various plans took place. What is not a true statement about risk responses?
B: Contingency plan takes place before the risk event occurs, while a workaround
takes place after the risk event occurs.
D: Both contingency plans and workaround plans are strategies for risk acceptance.
C is correct: You require a contingency plan to be created and take place before a
fallback plan.
The tools and techniques in the administer procurements process are:
A: Formal written.
B: Formal verbal.
C: Para lingual.
D: Informal verbal.
There are a variety of communication methods: Written and oral, listening and
speaking both informal and formal. Internal (within the project ) and external
(customer, the media, the public)Formal (reports, briefings) and informal (memos,
ad hoc conversations)n Vertical (up and down the organization) and horizontal (with
peers) Answer C: Para lingual (pitch and tone of voice) would be a type of
communication not a method of communication.
Your integrated project plan and project schedule have been
approved by the steering committee and accepted by key the
stakeholders. The project plan and schedule should be
distributed to:
B: Can be used for analyzing sensitivity in other project constraints such as cost,
time, quality and risk objectives.
C: It is a variance of the sensitivity charts where the variable with highest impact is
displayed at the top of the chart followed by other variables in descending impact
order which represents a Tornado.
D: It is a statistical technique that calculates the average outcome when the future
includes scenarios that may or may not happen.
D is a definition of expected monetary value technique.
A, B and C are all true statements about a tornado diagram.
In order to maintain a consistent level of quality, your company's maintenance
department makes process adjustments at the end of every 8 hour shift. Your company
has a formal quality management system. Being a QA manager, you know that these
process adjustments have a cost attached, including production interruptions. As a result
of recent changes in the specifications of the input material, your QA tests show that the
quality of the product will not be affected and the process will remain in control if
process adjustments are done after every two production shifts. Which of the following
statements will be an appropriate approach?
A: In order to save costs and production interruptions, ask your maintenance
department to immediately change the process adjustment frequency.
B: The process adjustment frequency change should be handled according to
procedures for integrated change control.
C: In order to save costs and production interruptions, ask the Operations department to
immediately change the process adjustment frequency.
D: In order to save costs and production interruptions, ask the concerned technician to
immediately change the process adjustment frequency
Answer B is the best choice as it is in-line with the integrated change control concept.
The question states the company has a "formal" quality management system which
means all changes would be handled according to an established procedure. The change
may potentially impact several stakeholders (functions within the organization - e.g.
operations, maintenance, warehousing, sales & marketing because of increased
production level, perhaps finance to measure the new performance levels, Human
Resources, and so on) and need to be properly coordinated as per existing procedures
and involving all stakeholders.
Approval has been obtained by the sponsor to crash your
project in order to avoid penalty payments stated in the
contract. As the project manager you should analyze:
A: All activities.
B: Activities with the longest time durations.
D: An external deliverable.
A: Personnel files.
C: Design of experiments.
A: Conciliatory
B: Promotional
C: Passive
D: Facilitating
As part of the communication process, which best describes the
responsibility of the sender?
A: Clarity.
B: Unambiguousness.
C: Completeness of message.
D: Correctness of understanding.
A: Using control charts to identify random variations and unusual variations and adjusting
the process when out of control.
B: Using control charts to identify process variations and adjusting when variations are
present.
C: Cost sharing.
A: Delphi technique.
B: Decision-tree analysis.
D: Identify Risks.
A: Uncertainty and the impact of risks are lowest at the beginning of the
project.
C: Cost levels start low then increase over time before trailing off as the
project ends.
D: Level of effort, staffing and cost vary from phase to phase. Typically they
start low and increase to a maximum point, then taper off.
B: No action is required because the points are still within the control
limits.
A: Communications planning.
B: Information distribution.
A: Secondary risks.
C: Direct cost.
D: Sunk cost.
Sunk costs are all the costs spent to date and cannot be
recovered.
In some highly technical projects there is a severe limitation on the
qualified resources that can perform the work. In addition to pre-assigning
of resources, negotiating, resource levelling etc., a project manager may
arrange for a skilled contractor to perform the work in the event that a
technical resource is not available. This would be known as:
A: Resource mitigation.
B: Risk mitigation.
C: Risk avoidance.
D: Wishful thinking.
A: At the extreme end of the uncertainty spectrum. They will definitely affect you, although
you have no control over them.
C: Items that will affect you, although you are not able to predict how or how much they will
affect you.
D: Rework.
Risk is the notion of dealing with uncertainty. Knowns at the extreme end of the uncertainty
spectrum will definitely affect you, although you have no control over them. Objective
probabilities from experienced or available data. i.e. insurance, no estimate required, costs
are known. Items or situations containing no uncertainty (taxes).
Known- Unknowns: These items will affect you although you are not able to predict how or
how much they will affect you. Items we know exist but we do not know how they will affect
us (rework). If you are subject to supplier price increase based on next year's consumer price
index, you are facing a known-unknown risk. Rely on subjective probabilities qualified
judgment based on experience or expert opinion. No estimate possible costs are unknown.
Unknown-Unknowns. Items or situations whose existence we cannot imagine ("Who knew ?")
No reasonable person would have expected this to happen. If you were a slide rule
manufacturer in the middle of the 20th century the advent of the electronic calculator was an
unknown-unknown.
Which of the following is the best definition of acceptance of a risk during
the Plan Risk Response process?
A: You are lucky as you have the solution to prevent the risk.
D: Whatever - do nothing.
C: Prioritize the high impact risks for close monitoring and controlling.
A: EMV.
B: Sensitivity Analysis.
D: Monte Carlo.
C correct: The risk action owner is assigned by the risk owner to ensure the risk
responses are executed.A incorrect: Risks rated low to moderate ratings are usually
placed on a "watchlist".
B incorrect: Workarounds are responses to unidentified risks.
D incorrect: The risk owner is the individual responsible to determine the
effectiveness of the response plan. Note the risk owner and risk action owner can
be the same person.
One of the engineers working on your project identifies that the key design
software has a problem and will not be operational for 2 days. As the risk
manager you had already considered that there was a chance something
may happen with the software since it was new. Now you must first:
If this is a risk you considered, it would be in the risk register and there may
be a response plan if it was found to be warranted.
'A' is not correct as once something occurs, it is no longer a risk. In this
case it would be an issue on entered in the issue log.
Updates to the risk register after the Identify Risks process
include:
The question is asking for the highest risk related to the schedule category.
Answer A would affect the budget not the schedule.
B is the most correct answer as delays in approvals can stop the project
work completely. Many times if approval is delayed by one or two weeks
this could delay the project even more i.e. one month. In other words the
approval delay and schedule delay are not like for like.
In a company best described as a weak matrix organization,
where will the project manager encounter the most conflict
with respect to staffing or resource issues?
A: Functional Manager.
D: Outside Contractor.
A: Decision Theory.
B: Utility theory.
C: Theory Y.
C: Identify Risks.
A: SWOT.
B: Delphi.
C: Root cause identification.
D: Simulation.
Simulation is a technique used during the
Quantitative risk analysis process.
Updates to the risk register after the Monitor and Control Risks
process include:
C: Negotiated contracts.
C: Negotiated contracts.
A correct: Outcomes of risk assessments; risk audits; risk reviews are all results of the
Monitor and Control Risks process.
Project risk is concerned with the expected value of one or more results of one or more future
events in a project. It is an uncertain condition that, if it occurs, has an effect on at least one
project objective. Objectives can be scope, schedule, cost, and quality. Project risk is always in
the future.
Identify Risks is the process of determining which risks may affect the project. It also
documents risks' characteristics. The Identify Risks process is part of the Project Risk
Management knowledge area. As new risks may evolve or become known as the project
progresses through its life cycle, Identify Risks is an iterative process. The process should
involve the project team so that they can develop and maintain a sense of ownership and
responsibility for the risks and associated risk response actions. Risk Register is the only output
of this process.
What is meant by cause in project risks?
A cause in project risks is a necessity, limitation, assumption or situation that creates the
chance of negative and positive outcomes. A cause can be the condition of permit to do work,
or having restricted personnel assigned to design the project. If either of these conditions
occurs, there may be an impact on the project cost, schedule, or performance.
Preparing for risk communication.
What is Planning Meeting and Analysis in the Plan Risk Management process?
Planning Meeting and Analysis is a tool and technique in the Plan Risk Management
process. Planning meetings are organized by the project teams to develop the risk
management plan. Attendees at these meetings include the following:
Project manager Selected project team members Stakeholders Anybody in the
organization with the task to manage risk planning Sophisticated plans for conducting
the risk management activities are defined in these meetings, responsibilities related
to risk management are assigned, and risk contingency reserve application
approaches are established and reviewed.
What is the risk utility function?
The risk utility function describes a person's or organization's willingness to accept risk.
It is synonymous with stakeholder tolerance to risk. Risk utility function facilitates the
selection and acceptance of risk and provides opportunity to merge the approach with
setting thresholds of risk acceptability and using utility-risk ratios if necessary.
What is an issue log?
An issue log is used to record all the issues within a project. It helps to monitor the
types of issues and follow the procedures taken to determine them. The issue log
reduces the impact that issues have on the project and hence increases the chances of
success. The issue log provides different ways to help the project manager. The purpose
of the issue log is as follows:
• It gives priority to each issue raised.
• It analyzes the impact that the issue is having on the project.
• It tracks the actions taken to resolve the issue.
• It tracks the outcome of the actions taken.
•The issues must be clearly declared and classified based on necessity and the probable
impact.
•Unresolved issues are an important basis for conflict and project delays.
What is change log?
A change log is used to record the changes that take place during the project. The
changes and their impacts in the project can be expressed in terms of cost, time, and
risk, and must be communicated to the right stakeholders. It provides a place to store
all the information related to the changes in a project. Approximately, every project
practices the changes at some point. When change occurs, one must record the
information related to alteration, so that it should help an individual to monitor and
control the effect of that change on the project. Managing Risks and Project Changes.
The uncertainty in the parameter associated with the largest bar, the one at the top of
the chart, has the maximum impact on the result, with each successive lower bar
having a lesser impact. Tornado diagrams are useful for sensitivity analysis - comparing
the relative importance of variables.
What is SWOT analysis?
SWOT stands for Strengths, Weaknesses, Opportunities, and Threats. It is a part of
business policy that helps an individual or a company to make decisions. It includes the
strategies to build the strength of a company and use the opportunities to make the
company successful. It also includes the strategies to overcome the weaknesses of and
threats to the company.
What is Monte Carlo simulation?
Monte Carlo simulation is a process for iteratively evaluating a deterministic form using
sets of random numbers as inputs. This method is repeatedly used when the model is
complex, nonlinear, or involves more than just a couple of vague parameters. Monte
Carlo simulation is named after the city in Monaco, where the major attractions are
casinos that have games of chance. Gambling games, such as roulette, dice, and slot
machines, exhibit random behavior. This technique works particularly well when the
process is one where the underlying probabilities are known but the results are more
difficult to determine. It is a process that generates hundreds or thousands of probable
performance outcomes based on probability distribution for cost and schedule on
individual tasks. The outcomes are then used to generate a probability distribution for
the project as a whole.
What are the tools and techniques for Qualitative Risk Analysis process?
The tools and techniques for Qualitative Risk Analysis process are as follows :
Risk Probability and Impact Assessment: Risk probability assessment investigates the
chances of a particular risk to occur. Risk Impact Assessment investigates the possible
effects on the project objectives such as cost, quality, schedule, or performance,
including positive opportunities and negative threats. Probability and Impact Matrix:
Estimation of risk's consequence and priority for awareness is conducted by using a
look-up table or the probability and impact matrix. This matrix specifies the mixture of
probability and impact that directs to rating the risks as low, moderate, or high priority.
Risk Data Quality Assessment: Investigation of quality of risk data is a technique to
calculate the degree to which the data about risks are useful for risk management.
Risk Categorization: Risks to the projects can be categorized by sources of risk, the area
of project affected and other valuable types to decide the areas of the project most
exposed to the effects of uncertainty.
Risk Urgency Assessment: Risks that requires near-term responses are considered
more urgent to address. Expert Judgment: It is required to categorize the probability
and impact of each risk to
determine its location in the matrix.
What is the watchlist of low-priority risks?
The watchlist of low priority risks is prepared for monitoring the risks that are not
assessed as important in the Perform Qualitative Risk Analysis process. The output of
Perform Qualitative Risk Analysis process is an updated Risk Register, which contains
the relative ranking of risks and watchlists of low priority risks.
What is the output of perform qualitative risk analysis process?
The output of perform qualitative risk analysis process is Risk Register Updates. Risk
register is updated with the information from perform qualitative risk analysis and the
updated risk register is included in the project documents. Updates include the
following important elements: Relative ranking or priority list of project risks
Risks grouped by categories Causes of risk or project areas requiring particular
attention List of risks requiring response in the near-term List of risks for additional
analysis and response Watch list of low priority risks Trends in qualitative risk analysis
results
What is brainstorming?
Brainstorming is a technique to gather general data. It can be used to identify risks,
ideas, or solutions to issues by using a group of team members or subject-matter
expert. Brainstorming is a group creativity technique that also provides other benefits,
such as boosting morale, enhancing work enjoyment, and improving team work.
a. Quantitative
b. Qualitative
c. General
d. Characteristic
Answer: b
Qualitative assessment of risks is often appropriate.
When there is little impact from a risk or when little
is known about the risk parameters it may only be
practical to evaluate risks in a qualitative way.
A project manager working on a large project finds that there are
several risks that have a severity that is higher than the
acceptable risk tolerance. They cannot be avoided or deflected.
The project manager will need to use which of the following
approaches?
a. Change the risk tolerance of the client
b. Buy insurance for the risk
c. Ignore the risk
d. Mitigate the risk
a. Risk model.
b. Simulation.
c. Computer risk program.
d. Decision tree.
Answer: b
The Monte Carlo technique is a simulation technique that
assigns a value to the duration for each activity in the schedule.
This assignment can be by user-selected probability
distributions. Depending on the values of the duration for each
activity the critical path may change from simulation run to
simulation run.
The Monte Carlo technique can be used to:
a. Determine the amount of contingency budget needed for
the project.
b. Determine the amount of the management reserve.
c. Determine the criticality index for an activity in the
schedule.
d. Determine the risk index for a risk in the project.
Answer: c
The Monte Carlo technique is a refinement of PERT. In the
PERT process the range of values and the probability that
they can occur are calculated for the project completion date
or parts of the project. The Monte Carlo technique allows for
shifts that may occur in the critical path during possible
values of the durations of the activities of the project. It is a
simulation technique that produces a value called the
criticality index, which is the percent of simulations that a
particular activity is on the critical path.
22. A project team evaluates risk in the project. As an
outcome there are some positive and negative risks that are
identified and evaluated. To evaluate the worst case for
the project the project team should evaluate and summarize:
a. All of the risks affecting the project.
b. Only the negative risks.
c. The negative risks minus the positive risks.
d. The positive risks minus the negative risks.
Answer: b
In determining the worst-case situation, all of the negative
risks are included and none of the positive risks are included
in the total. This makes the assumption of the worst case as
being that all of the bad things happen and none of the good
things happen.
21) The project team has put together a project plan for a
project, and the plan has been approved by the stakeholders.
The customer asks the project manager if the project
can be delivered seven weeks sooner. The customer offers
sufficient monetary incentive for the project manager. The
project manager decides to fast track the project. This decision
will:
a. Increase risk.
b. Decrease risk.
c. Not affect risk.
d. Risk change cannot be determined.
Answer: a
Fast tracking is changing the project plan to schedule activities
that were planned to be done
in sequence so that they can be done completely or partially in
parallel. This will increase
risk, because more work will be done if a problem is discovered.
20. A risk event in a project is something that can have an effect
on the project:
a. For the better only, a positive effect.
b. For the worse, a negative effect.
c. Both better or worse, a positive or negative effect.
d. Neither better nor worse, neither a positive nor a negative
effect.
Answer: c
Risks are events that affect a project for better or worse. Positive
risks increase the positive
cash flow or benefits to the project, and negative risks increase
the negative cash flow or
effects of the project.
19. In managing the risk of the project schedule we are managing
the risk that the project will not be delivered or completed on time.
If we assume that the project’s possible completion dates are
normally distributed and we promise the client the most likely of
the project’s possible completion dates, what is the probability that
the project will be delivered late?
a. 5%
b. 10%
c. 50%
d. 77%
Answer: c
In the normal probability distribution or any symmetric probability
distribution, the most likely value of the distribution is the peak of
the distribution curve. This is the value that has the highest
probability of occurring. In a symmetric probability distribution this
will be the center of the curve as well. There is a 50% probability
that the project will finish past the most likely date and a 50%
chance that the project will finish earlier than that date.
17. A project manager uses the breakeven point to justify his project.
He presents this as a justification for buying a new machine. What
risk does the project manager run by using this technique to justify
buying a new machine for his company?
Answer: c
The management reserve is time and money used to
offset the effect of unknown risks affecting cost and
schedule. These risks can only be approximated since
none of them are specifically identified. PMI refers to
these risks as the known-unknown risks and the
identified risks as the known-known risks.
15. In the Monte Carlo technique, what is the criticality index?
a. The number of days the project will be late divided by the
project duration
b. The percent of time a given activity will be on the
critical path
c. The percent of time an activity will be late.
d. The sum of the duration of the critical path activities divided by
the project expected value for duration
Answer: b
The Monte Carlo technique is a refinement of PERT. In the PERT
process the range of values and the probability that they can occur
is calculated for the project completion date or parts of the project.
The Monte Carlo technique allows for shifts that may occur in the
critical path during possible values of the durations of the
activities of the project. It is a simulation technique that produces
a value called the criticality index, which is the percent of
simulations that a particular activity is on the critical path. That
is, criticality index is the percent of the number of simulations
that an activity is on the critical path.
14. A project manager holds the first risk meeting of the project
team. The client is present at the meeting. At the meeting several
risks are identified and assigned to members of the project team
for evaluation and quantification. The result of the meeting is:
a. Expected value of the risk events.
b. Strategies for the risk events.
c. A list of potential risk events.
d. General statements about risks for the project.