STEP 1 All Employees will be notified in advance by the person performing Lockout-Tagout of the
specific date, time, location & machine affected by the Lockout-Tagout.
STEP 2 EQUIPMENT ISOLATION: Locate all devices that control the flow of energy to the Wysong 4’
Shear (hereafter “Shear”).
a. Turn off at Control Panel: Deactivate the Shear by pushing the “STOP” button.
b. Turn off Power Control Breaker on the front of the Shear by turning the on/off switch to the
“OFF” position.
c. Switch circuit breaker marked “Panel # HV-1, Breaker # 17” located in the Breaker Panel on the
center West wall to the “OFF” position.