Escolar Documentos
Profissional Documentos
Cultura Documentos
LIST OF APPENDICES
Appendix A Forms and Checklists ............................................................................................................... 6-17
Appendix B Drawings .................................................................................................................................. 6-18
LIST OF TABLES
Table 6-1:Standard Pipe Details ..................................................................................................................... 6-2
Table 6-2: Standard Pipe Configuration ......................................................................................................... 6-2
Table 6-3: Rider Mains ................................................................................................................................... 6-2
Table 6-4: Minimum Cover Requirements ...................................................................................................... 6-3
Table 6-5: Valve description ........................................................................................................................... 6-7
Table 6-6: Valve and Hydrant Tolerances .................................................................................................... 6-12
Table 6-7: Disinfection Dosing Requirements .............................................................................................. 6-15
Table 6-8: Forms and Checklists .................................................................................................................. 6-17
Table 6-9: Drawing Register ......................................................................................................................... 6-18
Section 6 Water
6.1 Introduction
This section sets out requirements for the design and construction of drinking water supply
systems for land development and subdivision. It covers the design of water pipes up to and
including 225 mm diameter. All bulk mains and reservoirs will require specific design and are
excluded from this specification.
6.1.1 Objectives
The design of any water network shall ensure an acceptable water supply for each property,
including fire flows, by providing either a:
a) water main allowing an appropriate point of supply to each property
b) service connection from the main to each property
The Designer shall consider:
a) The hydraulic adequacy of the system
b) The ability of the water system to maintain acceptable water quality
c) The structural strength of water system components to resist applied loads
d) The requirements of SNZ PAS 4509
e) Environmental requirements
f) The environmental and community impact of the works
g) The ‘fit for purpose’ service life for the system
h) Optimising the ‘whole of life’ cost;
i) Each components resistance to internal and external corrosion or degradation
j) Integrated three waters management
6.2 Design
6.2.1 Design Life
All water supply systems shall be designed and constructed for an asset life of at least 100
years. Some components such as pumps, metering, control valves, and control equipment may
require earlier renovation or replacement.
Area Configuration
Residential Principal main on one side of the road and a
rider main on the other - refer Table 6-1.
Industrial, Commercial and Arterial or Dual Principal main on both sides of the road
Carriageway Streets
All Other Areas Principal main on one side of the road
Where the number of dwelling units exceeds the maximum number for a rider main, a
principal main shall be installed on both sides of the road.
6.2.4 Clearances
Clearance from underground services shall be as per NZS 4404:2010 Section 5.3.7.9.
6.2.7 Hydrants
Hydrants are installed in reticulation systems for fire fighting and/or operational purposes.
Operational purposes may include mains flushing, chlorination, and to allow the escape of air
during charging and the release of water during the dewatering of the main.
6.2.7.1 Hydrant Design
a) The preferred location for hydrants is in the road berm rather than the carriageway.
However, NZS 4509 requires hydrants not to be located within 6.0m of any exiting or
proposed building. Where this contradiction exists in a design, advice should be sort
from Council
b) Hydrants shall not be fitted to any main less than DN 150
c) Hydrant risers shall be used, or the water main laid deeper, where necessary to ensure
the top of the spindle is between 50mm and 200mm below the fire hydrant lid
d) Hydrants shall be spaced at intervals not exceeding the following
i. Residential areas 135m
ii. Commercial and Industrial areas 90m (on each side of the road)
e) In a cul-de-sac or in other terminal roads, the last hydrant shall be not more than 65m
from the end of the road measured at the property boundary
f) Where houses or residential units are situated on private ways, there shall be a hydrant
within 135m of any house or unit
g) Hydrants should be located clear of vehicle crossings (in the grassed roadway berm). In
new developments, where formation of vehicle crossings are deferred until construction
of the buildings, hydrants should be located in the centre of the street frontage to avoid
the most likely location of the vehicle crossings alongside boundaries
h) In addition to hydrant spacing for fire fighting, hydrants shall be positioned at high
points to facilitate flushing air from the mains and at low points to facilitate flushing
sediment from the mains
i) Hydrants shall be placed within hydrant boxes designed in accordance with the Drawing
D6.3. The location of the hydrants shall be marked in accordance with the requirements
set out in SNZ PAS 4509:2008
j) Flushing points (valve or hydrant) shall be installed at the end of DN50 / 63 OD rider
mains refer Drawing D6.1)
6.2.8 Valves
Valves shall be installed to permit isolation of sections of the pipe network for maintenance
and operational purposes. The spacing and location of valves shall be such as to limit the
number of dwellings affected by a shutdown to no more than 30.
Valves shall be provided as follows.
a) Each side of arterial roads and railway crossings
b) Adjacent to street intersections, having regard to the safety requirements for
operational access
c) On at least two legs leading from each tee intersection
d) A maximum spacing of 250m
Valve Type
Sluice Valves Sluice valves shall be used on principal mains. The valves shall
be resilient seated, anticlockwise closing with a non-rising
spindle to NZS/AS 2638.2:2011 (pressure rated PN16). All
valves shall be thermal-bonded polymeric coated to NZS/AS
4158:2003
Gate Valves (also known as Gate valves DN 50 or less shall be clockwise closing with cast
Peet valves) iron T bar handles. Valves to be manufactured to BS 5154 or
AS 1628
Air/Vacuum Valves and Scour Shall only be used when required by Council. Air valves and
Valves Scour valves shall be specifically designed to suit the installed
location
Butterfly Valves Butterfly valves shall only be used with the approval of Council
6.2.9 Connections
6.2.9.1 General
Before connection to the water network, the Council connection process and forms shall be
completed by the applicant and acceptance provided. This applies to:
• All new connections and disconnections from private property.
• All new connections of new water mains to be tied into the existing public sewer.
For all connections where volumes greater than 15m3 are required, compliance HCC’s
Resource Consent 113941 (Condition No’s. 8-11) is required.
The connection should be designed to suit the existing situation and any future development
and be supported with an approved ICMP or WIA.
6.2.9.2 Requirement of Design
The point of supply to the consumer is shown on Drawing D6.7.
The following design requirements shall be met.
a) All residential connections shall be DN20mm unless supplying a site above 45.0m RL
(Moturiki Datum) or served by an accessway longer than 45.0m. In these cases a DN25
connection is required
Point of Supply
at Boundary
Supply Pipe
Point of Supply Additional Backflow Alternative
at Boundary F
Prevention, Metering, Locations of Fire
etc. Supply Isolation.
Main Main
Service Pipe
Manifold
Note: Private piplines are indicative only, refer to Building Act / Code
v. The supply pipe shall have a flushing valve of minimum 50mm internal diameter
at the furthest point from the reticulation
vi. Metallic detector tape, laid directly above the supply pipe at a maximum depth of
200mm is required where; the alignment of the pipe is not clearly defined as a
straight line between valve box lids and, in other circumstances as required by
Council
vii. An "Easement in Gross" shall be granted in favour of the Council to allow access
for maintenance of the pipe
viii. Ownership of the supply pipe shall transfer to Council. The Council's responsibility
for maintenance of the supply pipes shall cease at the boundary to each individual
lot
Service Line
Main
Service Pipe Main
Manifolds, may share
a single meter box.
Note: Private piplines are indicative only, refer to Building Act / Code
Flushing Valve
at end of line
Point of Supply
at Boundary
Main
Note: Private piplines are indicative only, refer to Building Act / Code
6.3 Construction
6.3.1 Pipe Laying
All water main pipe laying and associated fitting installation shall only be carried out by a
qualified water Service Person holding the qualification of National Certificate in Water
Reticulation.
Pipes shall be handled, stored and laid in accordance with the approved pipe manufacturers
specifications and relevant standards.
Pipes and fittings shall be free of defects (internally and externally) and cleaned of dirt on the
inside prior to lowering them into the excavation. Pipes shall be set true to line and level and
care taken to ensure that joints are kept free from dirt.
Pipes shall be laid with product labelling uppermost in the trench.
At any time when the pipeline is not being worked upon, open pipe ends shall be blanked off
in a manner which prevents the ingress of animals and deleterious material.
6.3.3 Jointing
Electrofusion welded jointing shall only be carried out by experienced certified PE welders.
The certifying organisation shall be acceptable to Council. In addition, welders may be required
to carry out satisfactory test welds for each joint type and to stamp the welder's number on
each joint. Butt welds shall be, at least, 90% of the tensile strength of the parent pipe material,
when tested in accordance with ISO 13953:2001. All internal weld beads shall be removed in
an approved manner, to be smooth and flush with the pipe inner surface, without
compromising the strength of the pipe joint.
6.3.4 Valves
Where the valve is fitted to the branch of a tee it shall be flanged unless this results in the
valve being in the carriageway. In these cases spigot ended valves connected to adjoining pipes
with gibaults are the acceptable alternative. Spigot ended valves shall be secured to anchor
blocks designed to NZS 4404:2010.
The tolerances shall be measured from a 1.0m diameter of the surrounding surface across the
box and work may be rejected if the tolerances are not met.
6.3.5.4 Valve and Hydrant Markers
Marker posts shall be installed near all valves in accordance with Drawing D6.5.
All fire hydrants and valves shall be marked according to SNZ PAS 4509:2008 which includes
the following requirements.
• The lid of the fire hydrant box painted yellow with NZTA M/7-Y
• A yellow painted triangle on or near the centre line of the road
• A yellow painted circle encircling the hydrant if its location can be obscured by parked
vehicles
Fire hydrants installed in commercial and industrial areas shall be indicated with blue raised
reflective pavement markers in addition to the markings indicated above. (Refer to SNZ PAS
4509:2008).
6.3.6 Connections
Refer drawings D6.7, D6.8, D6.9 and D6.10.
All connections shall be sealed by removable caps until such time as they are required.
All connections and disconnections to or from Council pipes and all works outside the property
boundary shall be undertaken by Council.
The physical connection to the existing water reticulation can only be carried out once the
pressure and bacteriological test results have been submitted to, and approved by Council.
Connections shall be made under pressure wherever possible.
Domestic supplies will not be metered, however a manifold box. Backflow protection is
required as per NZ Building Code – Clause G12 “Water Supplies”.
Care shall be taken during installation of the connection to ensure that no foreign matter
enters the pipes or meter. All meters shall be checked after installation to ensure that the
meter is recording the flow passing through it.
6.3.6.1 Tapping Bands, Ferrules and Service Pipes
Service connections to principal mains shall be by means of a tapping band and a ferrule.
Service connections to rider mains shall be by means of a tee-joint or Tapping Saddle. Ferrules
are to be left fully opened and gate valves fully closed.
All service pipes shall be laid at right angles to the street (refer to Drawing D6.7).
Tapping bands and ferrules on the water main shall be fitted when the mains are first laid.
The tracer wire shall be tested for continuity between surface boxes using an electronically
generated tone and detector probe or alternative approved method.
This procedure also applies when a pipe is installed by a directional drilling technique.
Appendix A
Forms and Checklists
Table 6-8: Forms and Checklists
Number Title
F6.1 Quality Assurance Design Certificate
F6.2 Pipe Laying Checklist
F6.3 Final Inspection Checklist
I hereby confirm that the design of the water reticulation / wastewater provision / Stormwater provision for the
above site has been designed in accordance with the following standard _________________________________
Signed: Date:
Location:
To
To
To
To
To
Name of qualified water service person:
From
From
From
From
From
Pipe Laying Checks
• Pipe size, quality, approved materials
checked.
• Set out checked (control points)
• Foundation support
• penetrometer results available
• if under cutting required, note
chainage and CBR results.
• Alignment and cover.
• Bedding type and backfill material (CBR
results available for road crossings and
driveways).
• All service connections in place.
• Connections and Toby Box correctly
located horizontally and vertically.
• Hydrants and valves positioned correctly.
• Thrust blocks installed.
• No debris in pipelines.
Council representative.
• Bacto sample taken and passed by Council
representative PRIOR to connection to the
________________________________________ ________________________________________
Developer Date
Location:
Plan No:
Pre-Meeting Tasks
Site Meeting
________________________________________ ________________________________________
Developer Council
Appendix B
Drawings
Table 6-9: Drawing Register
Ridermain
Lot 8 Lot 12
See D5.6
Lot 7
Lot 13
For location
see Standard
Requirements
Lot 6
Lot 14 Lot 15
Service Connection D6.6
Lot 18
Lot 2 Main
Ridermain
Alternative
Valve Indicator D6.4 Layout
Lot 1
Lot 19
This valve may be relocated
in a different position as Valve Indicator D6.4
required by the relevant Location of valves
District Council
City Council
100
150
160
145
100
Direction of Main
300 255
D
ir
of ect
M i o
ai n
RECTANGULAR VALVE BOX AND COVER n
(with concrete surroundings for grass berms)
Backfill as per
D3.2.3
NOTES:
1. In Berm Areas
a) the TNZ backfill can be replaced with pitsand
b) the finished surface shall match the surrounding
City Council
110
150
280
145
110
Direction of Main
D
ir
of ect
M i o
HYDRANT BOX AND COVER ai n
n
(with concrete surroundings for grass berms)
50 -200
Sawcut existing seal Tolerance +10mm - 0mm
Standard C.I.
hydrant box
An alternative
Cast iron valve is a 375mm dia.
packers (- min 1, Concrete or
max. 3) PVC surround
pipe
Pre-cast concrete
surrounds
(100mm thick)
Backfill as
per D3.3.1
Heavy duty concrete
base (100mm)
75
Hydrant tee
Sand backfill
NOTES:
1. In Berm Areas
a) the TNZ backfill can be replaced with pitsand
b) the finished surface shall match the surrounding
City Council
50
65
36
3
4 1
90
9
1 5
50
65
80
NOTES:
105
50
25
19mm sq x 8mm
deep recess
80
10mm x 6mm
SV
50
38 12 38
City Council
n.cover
For details of hydrant
installation see D6.3 Riser fabricated
from one piece
500m m M i
150mm pipe
Concrete Surround
300 M ax.
Concrete thrust block
450 Min.
1000 Max.
Ridermain
NOTE:
City Council
y
Boundar
PLAN
Moulded manifold box with base and
mounting lugs with blue moulded lid (with
’WATER’ moulded into top) and lid secured
to surround via stainless steel flexible Boundary
coupling. Male Adaptor, sealed
250mm LG x to prevent ingress of
contaminants
200mm Wide 300mm 300mm Tail
N
50m m M I
Isolating valve
gh
Hi
HCC Supply
25mm MDPE Pipe
NOTE:
1.When a connection is made to an existing watermain, a gunmetal self-tapping ferrule shall be installed directly on the
tapping saddle prior to the installation of other fittings.
City Council
63mm MDPE
230
NOTES:
2.
Connections from ridermains to be made using 63 x 63 MDPE tee in place of a tapping band
or tapped gibault. Tee to be placed horizontally to maintain standard cover.
3.
RMC manifolds with pressure caps to be installed on all 20mm diameter domestic
connections. Meters installed on all connections serving commercial / industrial zoned lots.
City Council
Lid
To customer
Valve Valve
Watermain
NOTES:
Tapping Band
1. Upstream and downstream spacing in accordance with
(or cut-in tee on
80mm dia or larger) manufacturer’s specification or otherwise minimum 5
times pipe diameter.
230
DETAIL A
City Council
NOTES:
BOUNDARY
1. Upstream and downstream spacing
in accordance with manufacturer’s
GIBAULT JOINT PVC PIPE specification or otherwise minimum
of 5 times pipe diameter.
SECTIONAL ELEVATION
(100mm CONNECTION SHOWN)
City Council