Escolar Documentos
Profissional Documentos
Cultura Documentos
2, JUNE 2005
Abstract—High Temperature Superconductor (HTS) cable regulators. Thus, VLI circuits can function like fully control-
is regarded as one of the most promising new technologies to lable DC circuits, but without the expense and complexity asso-
address grid bottlenecks. Among HTS cable designs, one in ciated with AC-DC terminal stations.
particular—shielded cold dielectric cable—offers performance
advantages particularly well suited to today’s siting, reliability and The introduction of VLI cable enables new approaches
performance challenges. Shielded cold dielectric HTS transmis- to important challenges in grid management. The strategic
sion cables feature lower electrical losses; the virtual elimination insertion of relatively short segments of VLI cable to bridge
of stray EMF; and significantly lower impedance than conven- bottlenecks can offload flows from overburdened conventional
tional cables and lines. Of particular importance, the very low circuits, thereby expanding grid capacity, extending the useful
impedance (VLI) inherent in cables of coaxial design makes it
possible to control power flows over VLI circuits. In addition, life of conventional network elements, and raising overall asset
variable impedance may be cost-effectively added to VLI circuits utilization.
with relatively small angle, conventional phase angle regulators. VLI cable users will pay less to solve power flow problems
Thus, VLI circuits can function like fully controllable DC circuits. with shorter lengths of cable, at lower voltage ratings, and with
The introduction of VLI cable enables new approaches to impor- greater controllability. Siting options for new generators will be
tant challenges in grid management. The strategic insertion of
relatively short segments of VLI cable to bridge bottlenecks can expanded, and grid bottlenecks will be eased, improving overall
offload flows from overburdened conventional circuits, thereby power system efficiency and lowering total system costs.
expanding grid capacity, extending the useful life of conventional Adoption of VLI cable will lead to enhanced system fuel
network elements, and raising overall asset utilization. With power efficiency and reduced air emissions, the elimination of stray
markets in turmoil and transmission increasingly the center of EMF, and a much smaller physical footprint for grid expansion
attention, VLI cable is a breakthrough technology that has great
potential as a cost-effective solution for many of the industry’s projects, because VLI cable can be routed underground within
most pressing problems. a variety of existing rights-of-way.
Unobtrusive VLI cable offers a new way to achieve several
Index Terms—Impedance, superconducting cables.
important objectives. It can help to break the logjam over trans-
mission siting; improve overall power system reliability, en-
I. INTRODUCTION hance power market competitiveness, attract merchant transmis-
sion investment, and advance environmental objectives.
T HE power density and siting advantages generic to all HTS
cables have been well understood for several years. The
implications of low impedance in cold dielectric HTS cables,
Initial VLI superconductor cable projects now underway pro-
vide an opportunity to develop a reliability record and resolve
however, are less broadly known. system integration and other implementation issues. However,
Coaxial construction and the close spacing of the conductor to speed the commercialization cycle for VLI cable, it is ur-
to the shield of cold dielectric HTS transmission cables results gent to expand the range of demonstration projects to implement
in several advantages: lower electrical losses; the virtual elim- comprehensive system level demonstrations and identify early
ination of stray EMF; and significantly lower impedance than commercial opportunities. With power markets in turmoil and
conventional cables and lines. Of particular importance, the very transmission increasingly the center of attention, VLI cable is a
low impedance (VLI) inherent in cables of coaxial design makes breakthrough technology with great potential to solve many of
it possible to control power flows over VLI circuits. These cir- the industry’s most pressing problems.
cuits inherently attract power flows, offloading adjacent, higher-
II. VLI CABLE ARCHITECTURE
impedance conventional circuits. Thus, for example, VLI su-
perconductor cable (“VLI cable”) offers a means of “pulling” Interest in the field of superconducting power cable dates
power away from heavily-loaded lines onto high-capacity path- to the 1960s, but because conventional metallic superconduc-
ways that flow directly into congested urban centers. This ap- tors required cooling with liquid helium, these cable system de-
proach offers compelling advantages compared to the traditional signs were unduly complex and cost-prohibitive. Interest in the
strategy of “pushing” power into load centers using multiple, field was renewed following the discovery of ceramics-based
large overhead circuits with higher impedance ratings. In addi- high-temperature superconductors in the late 1980s, which en-
tion, variable impedance may be cost-effectively added to VLI abled the use of liquid nitrogen as a cooling medium. Liquid ni-
circuits with relatively small angle, conventional phase angle trogen is widely used in a variety of industrial applications and
is recognized as a cheap, abundant and environmentally benign
coolant.
Manuscript received October 6, 2004. Over the last several decades, a variety of cable designs were
The author is with American Superconductor Corporation, Westborough, MA
01581 USA (e-mail: michaelmccarthy@amsuper.com). prototyped and developed to take advantage of the efficiency
Digital Object Identifier 10.1109/TASC.2005.849477 and operational benefits of superconductivity, while minimizing
1051-8223/$20.00 © 2005 IEEE
Authorized licensed use limited to: UNIVERSIDADE DE SAO PAULO. Downloaded on March 19,2010 at 12:23:57 EDT from IEEE Xplore. Restrictions apply.
MCCARTHY: VERY LOW IMPEDANCE (VLI) SUPERCONDUCTOR CABLES 2139
Authorized licensed use limited to: UNIVERSIDADE DE SAO PAULO. Downloaded on March 19,2010 at 12:23:57 EDT from IEEE Xplore. Restrictions apply.
2140 IEEE TRANSACTIONS ON APPLIED SUPERCONDUCTIVITY, VOL. 15, NO. 2, JUNE 2005
than in conventional cables (and may be lower to the extent that applications, the VLI attribute will provide a major benefit in
fewer circuits would be required for a given load). facilitating flows and relieving congestion. At the same time,
In fact, if not modified, insertion of these cables into networks in other applications, the very low impedance of the cable may
that already have existing parallel paths with higher impedance lead to undesirable changes in power flow, and/or require ad-
ratings will sharply reduce the amount of flow that would oth- ditional investments in compensation equipment that may mit-
erwise be borne by these other conventional network elements. igate or neutralize the VLI benefit. Thus, VLI cable should not
Viewed from a different perspective, however, low impedance be regarded as a universal solution, but rather as a targeted so-
can offer important advantages. Under some circumstances, it lution that is most effectively applied after careful evaluation of
can be much easier and less expensive to “pull” power onto conditions in the surrounding grid.
high-capacity pathways that flow directly into a congested load It is also important to note that the capacity of a single VLI
pocket, through a low-impedance cable, than to site, construct cable circuit inserted into a grid may not be fully usable because
and “push” comparable quantities of power to the same spot on of contingency considerations. In fact, the addition of a new
the grid using conventional approaches. high-capacity VLI cable may initially create the largest single
In addition, impedance may be added to a VLI circuit, simply contingency on a system. In this respect, the incorporation of
and inexpensively, by installing conventional substation equip- a single, high-capacity VLI cable into an existing network is
ment, e.g., inductors or phase angle regulators (PARs), yielding conceptually similar to adding the first line of a new and higher
effective and economical control of flows over “current hog- voltage level into a conventional system (e.g., adding a 765 kV
ging” VLI cables. Thus, VLI superconductor cables can be con- line into a 345 kV system). However, as additional VLI cables
figured to function like fully controllable DC circuits, while op- are added, the usable capacity of other VLI elements in the same
erating in the synchronous AC environment—thereby avoiding network may be increased. Each successive VLI cable inser-
the cost of AC/DC converter stations ( $300/kW). In addition, tion, in other words, will tend to increase the usable capacity
small angle and less expensive PARs ( $5/kW) can achieve and contribution to reliability of previously-installed VLI cable
the same degree of control over a VLI circuit as the larger, elements.
costlier phase shifting equipment needed for a conventional cir-
cuit. Moreover, it would be feasible to develop compact, inte-
IV. CASE STUDY—URBANIZED LOAD POCKET
grated PARs that could fit into the congested areas of a power
grid. In short, VLI cable introduces the prospect of an unobtru- The benefits of this concept for using VLI cable can be il-
sive, low-impact and fully controllable transmission solution, lustrated by considering a case study. A utility provides service
operating at HV transmission voltages or distribution voltages to an area that includes a congested, urbanized “load pocket.”
within the existing AC environment. It has encountered thermal limits on total power deliveries into
The introduction of VLI cable into the transmission planner’s the area due to a combination of load growth and local generator
arsenal also suggests a potent new strategy for expanding grid retirements. To increase service to the affected area, the utility
capacity. As thermal transfer limits are reached on power plans an 80-kilometer, EHV overhead transmission line looped
grids, congestion bottlenecks appear. Historically, utilities in available rights-of-way from the existing regional backbone
have preferred to relieve these bottlenecks, when possible, by EHV network. The expected cost of this solution, driven pre-
constructing overhead lines which are typically the least-cost dominately by high local real estate values, is approximately
solution. However, this approach is becoming increasingly $250 M, or $3.1 M per kilometer.
difficult, particularly in urban areas, because of siting restric- Overhead transmission construction costs have become
tions. Moreover, recent experience has shown that bottlenecks highly variable across the nation, differing by a factor of five
often arise in and around urban areas where the combination or more based on such factors as real estate values, availability
of short distances and high real estate costs make HTS cable a of right of way, terrain, electrical configuration, mitigation
viable alternative solution. In such situations, power flow prob- requirements and the level of community opposition. A stan-
lems could be solved by overlaying the existing, conventional dard 345-kV circuit in a rural area, where there is no siting
network of lines and cables with relatively short, strategic opposition, may cost as little as $0.7 M–$0.9 M per kilometer.
insertions of VLI cable across these congested interfaces. This Physically identical facilities in an urbanized area, however,
approach would draw currents away from other conventional are commonly quoted at $1.8–$2.4 M per kilometer and have
grid elements operating at or near their limits. By reducing high been projected to cost as much as $8.4 M per kilometer (ISO
current flows and associated overheating on existing lines, VLI New England SWCT). “Soft” costs (real estate, mitigation,
cables can slow or prevent the dielectric breakdown, annealing permitting and litigation) often represent 70%–80% of the cost
and other processes that often cause conventional cable or lines of a conventional cable installation. The total installed cost for
to age and fail. Employing such a strategy judiciously will an HTS cable system, by contrast, is likely to be dominated by
increase grid capacity, extend the useful life of conventional the cost of the cable itself. Because of the compact size of HTS
network elements, and improve overall asset utilization—all cable installations and the ability in some instances to reuse
at lower cost and with much less environmental impact than existing underground infrastructure, “soft” costs are expected
would result from a conventional strategy of wide-area network to be significantly lower.
upgrades. Given local community opposition and the presence of phys-
As with any type of grid enhancement, the usefulness of VLI ical siting obstacles, routing is necessarily circuitous and there
cable will depend upon a situation-specific analysis. In some is a high degree of project completion risk.
Authorized licensed use limited to: UNIVERSIDADE DE SAO PAULO. Downloaded on March 19,2010 at 12:23:57 EDT from IEEE Xplore. Restrictions apply.
MCCARTHY: VERY LOW IMPEDANCE (VLI) SUPERCONDUCTOR CABLES 2141
The utility investigates VLI cable as an alternative solution congested grids in urban areas. As volumes increase and costs
to deliver a comparable level of power into the heart of the con- decline, its advantages can be expected to expand to a broader
gested area. It develops an alternative solution that flows power range of applications.
directly, in a highly targeted fashion, into the heart of the con- The impact of VLI cable technology on critical problems in
gested area over the VLI circuit. Because of the higher ampacity dense urban areas of the electric power grid will be profound.
of the cable, the utility finds that it can deliver comparable MVA New capabilities provided by VLI cables for improving AC
levels at lower HV (115/138/161 kV) voltages. This enables power transfers in the grid under the control of the system op-
re-use of an existing right-of-way without the special permit- erator will lead new and less expensive ways to tackle grid con-
ting requirements often associated with EHV projects. In addi- gestion problems.
tion, because the utility’s HV (115/138/161 kV) network is more
pervasive than the EHV network, it can find a point of intercon-
nection that is much closer to the heart of the load pocket. ACKNOWLEDGMENT
The alternative VLI solution requires a directly routed seven-
teen kilometer segment of unobtrusive, underground VLI cable This paper is based on an unpublished white paper enti-
plus associated power flow control equipment. If a conserva- tled “Very Low Impedance (VLI) Superconductor Cables:
tive cost of $6 M per kilometer on an installed basis (including Concepts, Operational Implications and Financial Bene-
ancillary equipment) is assumed for VLI cable, the overall so- fits” which was issued in November 2003. Coauthors of
lution is $102 M or 60% lower than the conventional solution. that paper include: J. Howe—American Superconductor
In other words, even though VLI cable can be more expensive Corporation, B. Kehrli—American Superconductor Corpo-
than conventional solutions on a kilometer-for-kilometer basis, ration, F. Schmidt—Nexans Deutschland Industries GmbH
the ability of VLI superconductor cables to solve power flow & Co. KG, Dr. M. Gouge—Oak Ridge National Labora-
problems with shorter lengths of cable, at lower voltages and in tory, S. Isojima—Sumitomo Electric Industries, Ltd., and
a shorter timeframe due to simplified siting and permitting re- D. Lindsay—Ultera.
quirements can provide offsetting advantages that lead to lower
installed-cost system solutions.
REFERENCES
V. CONCLUSION [1] Jipping, J. Mansoldo, and J. Wakefield, “The impact of HTS cables on
power flow distribution and short circuit currents within a meshed net-
While VLI cable remains an early-stage, low-volume work,” presented at the IEEE/PES Transmission Distrib. Conf. Exposi-
product, initial projects are likely to be focused on highly tion, Atlanta, GA, Oct. 28–Nov. 2 2001.
Authorized licensed use limited to: UNIVERSIDADE DE SAO PAULO. Downloaded on March 19,2010 at 12:23:57 EDT from IEEE Xplore. Restrictions apply.