Você está na página 1de 6

USED TECHNOLOGIES ARE :-

 PQC
 DLC
 PCC

 PAVEMENT QUALITY CONCRETE (PQC)

PURPOSE:-

 The purpose of this Quality Plan for Construction ofPavement


Quality Concrete (PQC) is to provide detailed Construction
Methodology, Materials used, Resources deployed.

SCOPE:-

 The Scope of this Segmental Quality Plan/ Methodology shall covers


the construction of pavement quality concrete insertion of dowel bars,
tie bars in accordance with the requirement of Technical
Specifications and in conformity with the line, grades and cross
sections shown in drawings.

It covers the following activities:

Selection, Testing and Acceptance of all incorporated Materials for


PQC.
Design of Mixes for PQC and Trials, Acceptance etc.
Details of Plant, Equipment / Machinery as required in execution of
PQC.
Batching, Mixing, Transporting, Placing, Finishing and Curing of
Concrete for PQC.
Mechanized Texturing and Curing operation for PQC.
Joint Cutting and application of Joint Sealing compound as approved.
Quality Assurance and Control Checks during operation and post
concreting
DEFINITIONS:-

The words like contract, Contractors, Engineer (Synonymous to


Engineer's representative), Drawing, Employer, Government, Works,
Worksite used in this Quality Plan shall be considered to have the
meaning as understood from the definitions pertaining Quality
Management System Developed for the Particular Project.

The following abbreviation shall have the meaning as set forth below:

MORT & H: Ministry of Roads Transport & Highways


NHAI: National Highways Authority of India
BIS: Bureau of Indian standards
QA: Quality Assurance
PQC: Pavement Quality Concrete
MTC: Manufacture's Test Certificate
ITP: Inspection Test Plan

CROSS REFERENCE:-

This Segment Quality Plan should be read in conjunction with the


following documents:
ISO 9001 2000 Quality management system
Contractor Document / Technical Specifications
MoRTH/IS/ASTM /ACI Codes, where applicable
IRC: SP: 57-2000, Guideline on Quality system for roads.

Survey and Setting out for PQC:

Material Required:

Cement:

Any of the following types of cement may be used with prior approval
of the Engineer:
(i) Ordinary Portland Cement IS: 269
(ii) Portland Slag Cement IS: 455
(iii) Portland Pozzolana Cement IS:1489

Cement to be used may preferably be obtained in bulk form. It shall be


stored in accordance with stipulations contained in Clause 1014 and shall
be subjected to acceptance test prior to its immediate use.
.

Coarse Aggregate:

Aggregates to be used in the construction of PQC will be Crushed


aggregates .

The aggregate complying IS: 383 will be used.

Max Size of coarse aggregate 25mm as per MoRTH 601.2.3.2


(Fourth Revision : August 2001).

Fine Aggregate:

Clean, natural sand from River Banas form location Triveni 20km form
Ladpura will be used. The material conforming IS: 383 is ensured.

The fine aggregate shall consist of clean, natural sand or crushed


stone sand or a combination of the two and shall conform to IS: 383.
Fine aggregate shall be free from soft particles, clay, shale, loam,
cemented particles, mica, organic and other foreign matter. The fine
aggregate shall comply with MoRTH 602.2.4.3.(Fourth Revision :
August 2001).
Water:

Water used for mixing and curing concrete conforming to IS:


456: 2000.
In case of PQC During hot weather, water for preparation of
concrete will be taken form water chilling plant.

Admixtures:

Admixture conforming to IS: 6925 and IS: 9103 to improve


workability of concrete or extension of setting time to be done.

Storage of materials :

Aggregates:

Aggregate will be stock piled separately and sufficient distance will


be maintained from each fraction to avoid intermingling.
Storage space must be easy to inspection, removal and restorage
of materials.
Regular testing of aggregate stock pile will be exercised to ensure
required gradation control.

Cement
Bulk cement will be stored in bulk storage containers having
200MT capacity and the number of such bulkers will be sufficient
to cater to the requirement at site.

Water

Water will be tanks covered at top and cleaned at regular intervals.


The intake of pipe will be enclosed to exclude silt and other solid
materials and there shall be a minimum depth of 0.60 m of water
below the intake at all times.

Proportioning of concrete

Concrete Strength

The pavement concrete should be a class M-40 concrete with a


minimum 28 days compressive characteristic strength of 40 MPa
1. Characteristic flexural strength at 28 days = 4.5 MPa
2. Target mean strength at 28 days = 5.80MPa
3. Water cement ratio =0.45 Maximum
4. Slump as per IS: 1199 =31+/-15 mm
Minimum flexural characteristic strength of 4.5 MPa.
The ration between the 7 & 28 days strengths of 4.5 Mpa.
For each batch
7days (avg.)
The average flexural strengths ( R7) =
28 days (avg.)

R7 to be determined for three decimal levels.

(Flexural strength of any Six consecutive 7day test result) >4.50+1.65*s


S: Standard deviation of the group.

Workability:

The control of workability will be done by the slump test


Slump will be controlled so that mix is compacted and finished
without undue flow.
The exact slump required at plant and site will be exercised during
trail patch.
Separation Membrane :

Two applications of approved wax-based white �pigmented curing


compound will be applied on DLC.
First coat will be applied immediately after DLC laying and
compaction and the other before start of PQC.
The process of application will be done using mechanical sprayer.
The other parameters will be meeting the additional specification
Clause- A-12.
Preparation of base :

Any visible defects / cracks more than 10mm size to be required by


fine cement concrete mix.
Surface will be made clean of dirt or extraneous material and free
from damage before application compound.

Joints:

The exact location and type of joint to be transferred at site as


mentioned in drawing.
Concrete Penetrometer and testing as per ASTM C 403 will be
used in monitoring setting of concrete / Maturity of concrete and
saw cutting period.
Initial saw cut of 3mm wide , 100mm depth in transverse and
longitudinal direction will be provided after initial set(approximately
6~8hrs).
Final saw cutting 10~12mm wide ,20~25mm depth will de provided
after 14days of curing at accommodate joint sealant.
The staggering of transverse joints with reference to the base will
be minimum 0.3m.

Você também pode gostar