Escolar Documentos
Profissional Documentos
Cultura Documentos
MECHANISM
By S.KEJRIWAL
Executive Engineer(Commercial)
ERPC, KOLKATA
Sequence of Events
• Two part Tariff since 1992 (K.P.Rao Committee
Report)
• Till late 90’s Govt of India determined tariff as
per Section 43A(2) of the Electricity Supply
Act, 1948
• Deficiences of tariff regime
• Govt appoints M/s ECC,USA in 1994 to
prepare and submit a report
Sequence of Events.....contd
• The study funded by ADB
• M/s ECC,USA submits report in Nov,1994
• Suggests implementation of ABT
• Govt constitutes NTF/RTFs in 1995 to study
the report
• CERC established under Electricity Regulatory
Commissions Act,1998 to regulate tariff
owned by Gencos owned and controlled by
central govt w.e.f 15.05.1999
Sequence of Events.....contd
• Govt pursued its efforts, held due consultations
and finally forwarded the ECC report alongwith
NTF minutes and a note on ABT to CERC in May
1999
• The matter was heard in CERC from 26-28th of
July,1999
• CERC issued ABT order dated 04.01.2000
• Order stayed various High courts of the country
due to objections/apprehensions expressed by
various SEBs/GENCOs
• Hon’ble Supreme court finally vacated the stay
Implementation of ABT:
ABT was finally implemented in India in the
following manner:
• From 01.07.2002 in WR
• From 01.10.2002 in NR
• From 01.01.2003 in SR
• From 01.04.2003 in ER
• From 01.11.2003 in NER
Basic Problems in Pre-ABT regime
• Low freq during peak time
• High freq during off-peak time
• Rapid and wide changes in freq ( apprx 1 Hz in
5-10 minutes)
• Frequent grid disturbance resulting in tripping
of generating stations, interruption of supply
to large blocks of consumers and
disintegration of regional grid
Basic Problems in Pre-ABT regime
• Damages caused at both load and generation
ends remained unquantified and unevaluated
• Operational/Commercial disputes/disagreements
amongst various utilities due to conflict of
interest
• Absence of suitable incentives and disincentives
for those responsible for the problem
• Lack of adequate generation, transmission and
distribution capacity
Possible Solution
• Maximization of generation along with load
curtailment during peak hours
• Backing down of generation to match low
demand during off-peak hours
• Imposing suitable incentives/disincentives to
ensure efficient grid operation
• Enhancing generation and transmission
capacity
• Demand side management
PRE-ABT TARIFF STRUCTURE:
TWO PART TARIFF:
FIXED CHARGE:
• Return on equity
• O & M expenses
• Interest on loan
• Interest on Working capital
• Depreciation
• Income Tax
PRE-ABT TARIFF STRUCTURE:
2. VARIABLE CHARGE:
• Primary fuel – Coal/gas
• Secondary fuel – Oil
1. FIXED CHARGE:
• Generators assigned target availability
• Total fixed cost payable to a generator over the year is
linked to the average annual availability. Hence the name
Availability Based Tariff
• Charged to beneficiaries in the proportion of their share in
the generating station
2. VARIABLE CHARGE:
• Charged to beneficiaries to the extent of their drawal
schedule
ABT TARIFF STRUCTURE:
THREE PART TARIFF:
3. UNSCHEDULED INTERCHANGE(UI) CHARGE:
• Actual Generation – Scheduled Generation (For
Generators)
• Total Actual Drawal – Total Scheduled Drawal
(For Beneficiaries)
• Worked out for each 15 min time block
• Based on average frequency of the relevant time
block
ABT TARIFF STRUCTURE:
THREE PART TARIFF:
3. UNSCHEDULED INTERCHANGE(UI) CHARGE:
• Overdrawal/Underinjection under low freq
(Penalty)
• Overinjection/Underdrawal under high freq (Nil
or low reward)
• Overdrawal/Underinjection under high freq (Nil
or low Penalty)
• Overinjection/Underdrawal under low freq
(Reward)
ADVANTAGES OF ABT:
• Incentivises generators to maximise generation
during peak hours
• No financial loss due to backing down of
generation during off peak hours
• Facilitates merit order despatch
• Better system operation
• Ensures grid discipline
ADVANTAGES OF ABT:
• Introduces transparency and works as
vigilance
• Opens avenue for interstate, inter-regional
bilateral trading of power
• Harness surplus captive generation
• Embedded generators can sell surplus
power to other SEBs
UI ACCOUNTING – PRELIMINARY PROCESS AND
ROLE OF RLDCs:
SCHEDULING:
• Each day of 24 hours starting from 00.00 hours be
divided into 96 time blocks of 15 minutes each
• Each generating station is to make advance
declaration of its capacity for generation in terms
of MWh delivery ex-bus for each time block of
the next day
• Based on the above declaration, concerned RLDC
shall communicate to the various beneficiaries
their respective shares of the available capability
UI ACCOUNTING – PRELIMINARY PROCESS AND
ROLE OF RLDCs:
SCHEDULING:
• After the beneficiaries give their requisition for
power based on the generation schedules, the
RLDC shall prepare the generation schedules and
drawal schedules for each time block after taking
into account technical limitations and
transmission constraints
• The schedule of actual generation shall be
quantified on ex-bus basis for generators
• scheduled drawals shall be quantified at their
respective receiving points for beneficiaries
UI ACCOUNTING – PRELIMINARY PROCESS AND
ROLE OF RLDCs:
SCHEDULING:
• In case of any forced outage of a unit, or in case of any
transmission bottleneck, RLDC will revise the
schedules.Revision will be effective from 4th time block
• Any beneficiary/generator may also request RLDC for
revision of Schedule. Revision will be effective from 6th time
block
• RLDC is also entitled to revise (if need be), the schedules
during the day in the interest of better system
operation.Revision will be effective from 4th time block
• In the event of any grid disturbance, the schedules of both
generation and drawal shall be deemed to have been
revised to be equal to their actual generation/drawal
UI ACCOUNTING – PRELIMINARY PROCESS AND
ROLE OF RLDCs:
METERING AND METERDATA PROCESSING:
ABT complaint Special Energy Meters (SEM of appropriate
accuracy class) to be installed by CTU at :
• HV side of GT (For Generators)
• All outgoing feeders (For Generators)
• Auxiliary and Station Transformers (For Generators)
• CTU-State interface including state end (For
States/beneficiaries)
• Both ends of inter-state tie lines (For States/beneficiaries)
• Inter-regional interfaces
UI ACCOUNTING – PRELIMINARY PROCESS AND
ROLE OF RLDCs:
METERING AND METERDATA PROCESSING: