Escolar Documentos
Profissional Documentos
Cultura Documentos
Comment note.
Contractor's Transmittal No. KSL1-HEC-TPI-T2006 Rev. No. A Issue date 14-Apr-17
Employer's comment
No. Reference Owner's Comment Contractor's reply applied to next
Revision (Y/N)
Minimum overlap shall be following the manufacture recommendation Adjust ITP 3.2
1 ITP 3.2 Y
of each brands that used. : Minimum overlap : 50mm → Each Manufacturer's instruction
2 ITP change all HGU inspection level : Witness → Hold Adjust all HGU inspection level to 'H'. Y
We always think about that and work carefully. Also our RFI form
For all work that interface with other discipline, shall be add with
3 General already have each discipline blank for interface work. So we think N
"interface work" column.
adding new column for interface work is no need.
OWNER
PROJECT :
KALSEL-1 COAL FIRED POWER PLANT PROJECT
CONTRACTOR :
D.H.Nam 31.05.17
CHECKED BY DATE
INSPECTION AND TEST PLAN
J.H.Seo 31.05.17
FOR BUILDING
APPROVED BY DATE
Y.H.Chung 31.05.17
JOB NO. DOCUMENT NUMBER REV.
KSL1L-YYB-G-05-089 B
KALSEL-1 2x100MW Coal Fired Power Plant
CONTENT
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev.B
2
KALSEL-1 2x100MW Coal Fired Power Plant
1.0 Purpose
This document establishes the instruction for the preparation and control of inspection and
test plan about building work and notification to the TPI for their selected inspection point in
a timely manner.
2.0 Scope
This document is applicable to the all works relevant to inspection and testing for building
work in KALSEL-1 2 x 100MW Coal Fired Power Plant such as :
3.0 Definition
Inspection and Test Plan (ITP) : A document which identifies the main activities and test
to be performed during construction or installation.
Spot Witness Points (SW) : Contractor / Subcontractor shall submit request for inspection
(Sampling, 10%) to the Employer decide whether they will attend such inspection or not.
Witness Points (W) : Contractor / Subcontractor shall submit request for inspection to the
Employer decide whether they will attend such inspection or not.
Hold Points (H) : Downstream construction and other activities shall not proceed without
attendance or any written approval of the Employer.
4.0 Responsibility
Approval of ITP
Overall supervision the inspection and test activities for Work.
Maintain and update the approved ITP and its master files
Preparation of ITP
Selection of witness and/or hold points of site work to verify conformance to the
requirements of specified document (i.e. procedure, specification, drawings, code a
nd standard etc.)
Performing the inspection and test pertaining to witness and/or hold points at the
appointed time
Submitting the notification to the OWNER for their selected witness and/or hold po
int inspections of site work according to Inspection and Test Procedure.
5.0 Attachment
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev.B
4
KALSEL-1 2x100MW Coal Fired Power Plant
Inspection by
Acceptance Criteria/ Verifying
No Description Remarks
Reference Document Document Sub-
con HGU TPI
Masonry
- Concrete Block shall be laid in plumb & horizontal Joint,
2.1
For length 6m (-10mm to +10mm)
For vertical height 3m (-10mm to +10mm) Tech. Spec
ITR 5.01
Drawing H H SW
ITR 5.02
Plastering Procedure
- Cement plaster : Minimum thickness
2.2
20mm for exterior plaster
15mm for interior plaster
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
5
KALSEL-1 2x100MW Coal Fired Power Plant
Inspection by
Acceptance Criteria/ Verifying
No Description Remarks
Reference Document Document Sub-
con HGU TPI
Tech. Spec
- Horizontal alignment
4.1 Drawing - H H SW
- Elevation level.
Procedure
Surface Preparation
5.1 - Clean, free from dust, superficial moisture etc.
- Cracks, wavy, air voids shall be repair
Tech. Spec
Painting Application SSPC-SP10
ITR 5.05 H H SW
5.2 - Each coat of paint shall be dry & harden as per Drawing
manufacturer instruction. Procedure
Coating Inspection
5.3
- DFT Test
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
6
KALSEL-1 2x100MW Coal Fired Power Plant
Inspection by
Acceptance Criteria/ Verifying
No Description Remarks
Reference Document Document Sub-
con HGU TPI
Tech. Spec
Tile Installation (PVC, Ceramic tile) Drawing
7.2 - Gap, alignment and expansion joint Procedure
- Approved material
ITR 5.07 H H SW
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
7
KALSEL-1 2x100MW Coal Fired Power Plant
Inspection by
Acceptance Criteria/ Verifying
No Description Remarks
Reference Document Document Sub-
con HGU TPI
8.0 STRUCTURE
Cladding Works
8.1 ITR 5.04
- Check approved material Tech. Spec
Drawing H H SW
Gypsum Works Procedure
8.2 ITR 5.10
- Check approved material
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
8
KALSEL-1 2x100MW Coal Fired Power Plant
Inspection by
Acceptance Criteria/ Verifying
No Description Remarks
Reference Document Document Sub-
con HGU TPI
Tech. Spec
Final Building Inspection
11.1 Drawing ITR 5.11 H H W
- Punch check for each Building structure
Procedure
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
9
KALSEL-1 2x100MW Coal Fired Power Plant
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
10
KALSEL-1 2x100MW Coal Fired Power Plant
5 Lath
Inspect application of plaster
5 Proportioning of plaster mixtures Minimum
6 Application Technique thickness :
20mm for
7 Subsuface preparation exterior plaster,
8 Thickness of application 15mm for
interior plaster
9 Installation of accessories (corner beads, etc.)
Ascertain Workmanship
10 Plater face plumb and in one plane
No defects,
11 Plater flush with inserts No crack
12 Troweled surface uniform
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
11
KALSEL-1 2x100MW Coal Fired Power Plant
Slope:
2 Surface preparaton Min. 1:150
Bituminous felt:
3 Bitumen primer
4mm
4 Proofing membrane
As per
5 Coats, laps and thickness
draw ing
As per
7 Protection board for wall
draw ing
thickness
9 Polyethlene sheet for roof 0.1,
PE film 2PLY
as per
10 Water proofing test manufacture
specification
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
12
KALSEL-1 2x100MW Coal Fired Power Plant
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
13
KALSEL-1 2x100MW Coal Fired Power Plant
4 Correct colors
Inspect painting application
5 Surface preparation
6 Number of coats SSPC-SP10
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
14
KALSEL-1 2x100MW Coal Fired Power Plant
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
15
KALSEL-1 2x100MW Coal Fired Power Plant
2 Insepction of substrate
As per
5 Application procedures acceptable draw ing
As per
6 Subsurface preparation
specification
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
16
KALSEL-1 2x100MW Coal Fired Power Plant
600x600mm
square panel
alignment ±
4 Verify system level and square 2.5mm
whole area
& ±1.5mm /
3m distance
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
17
KALSEL-1 2x100MW Coal Fired Power Plant
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
18
KALSEL-1 2x100MW Coal Fired Power Plant
As per
3 Stud track is fixed frimly and the space is identified draw ing
Manufacturer's
6 Joints of each gypsum board are applied by proper sealant
recommendation
* Note
Signature
Date
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
19
KALSEL-1 2x100MW Coal Fired Power Plant
PUNCH LIST
Project KALSEL-1 2x100 MW Coal Fired Power Plant
Subcontractor Report No.
Location / Item Related Report No.
Level
No Discipline Description Remark
(A/B/C)
SIGNATURE
DATE
KSL1L-YYB-G-05-089
INSPECTION AND TEST PLAN FOR BUILDING
Rev. B
20