Você está na página 1de 13

9.

3
VOLUME

DELAY AND DISSATISFACTION


IN THE
AQUINO ADMINISTRATION’S
PPP PROGRAM:
RECOMMENDATIONS
FOR FUTURE
PARTNERSHIPS IN
INFRASTRUCTURE

OCCASIONAL
PAPER MARCH 2016
OCCASIONAL PAPER MARCH 2016

02
DELAY AND DISSATISFACTION
IN THE
AQUINO ADMINISTRATION’S
PPP PROGRAM:
RECOMMENDATIONS
FOR FUTURE PARTNERSHIPS
PPP PROGRAM
IN INFRASTRUCTURE
could have been a good avenue to improve our country's infrastructure industry but
has thus far failed to fully deliver. The Aquino administration can use the
remaining time in office to fast track the PPP scheme without
sacrificing transparency and legitimacy in the process.
Image Credit: apec2015.ph

The Public Private Partnership (PPP) program, claimed as a dissatisfying. Moreover, the President must realize that the comparing Philippine performance vis-à-vis neighboring
pillar of this administration’s economic and infrastructure number of awarded PPP projects should not be the sole Southeast Asian countries. It then turns to the chokepoints in the
development plan, is under greater pressure this 2016 basis of measuring success; the completion and successful PPP scheme: the insufficient technical capacity within some
as President Aquino has only three months left in office. The operation of the infrastructure should also be made the basis. government agencies, the under-empowered PPP center,
emphasis President Aquino placed on the importance of Nonetheless, the Aquino administration can use the remaining an improperly implemented bidding process,
infrastructure development back in 2010 should have been time in office to fast track the PPP scheme without and barriers to foreign capital investment.
a good measure of the administration’s consistent sacrificing transparency and legitimacy in the process.
support for the PPP program. In concluding, the paper provides recommendations to be
This paper aims to identify the reasons why the PPP program considered for the next administration. In the time remaining, the
However, delay in the progress of the PPP scheme has been could have been a good avenue to improve our country’s Aquino administration should focus on maintaining the
evident since its launch in 2010. The minimal number of PPP infrastructure industry but has thus far failed to fully deliver. transparency and legitimacy of the PPP process as it seeks to
projects that have been awarded since Aquino assumed of- The first part tackles the Philippines’ overall competitiveness fast-track the awarding of projects. Doing so in this manner will
fice—12 out of the 53 projects in the pipeline— is and the importance of infrastructure in this regard, help it leave a legacy of enduring public-private partnerships.

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. * The views and opinions expressed in this Paper are those of the author and do not necessarily reflect those of the Institute.
OCCASIONAL PAPER MARCH 2016

03 The Public-Private Partnership Program

PPP was first introduced in the Philippines in 1990, ture spending, increased private investment and Big ticket projects that investors have been
through the passage of Republic Act (RA) No. 6957, eventually higher tourism receipts, which will only watching out to fund under the PPP program have
known as the Build, Operate and Transfer Law (BOT be possible by increasing investor confidence in the been slow to materialize. To date, out of the fifty
Law), signed by then President Corazon Aquino. The country’s ability to finance and complete these PPP three projects in the PPP pipeline, only twelve
BOT Law authorizes private entities to construct, finance, projects. The resurgence of the PPP program in projects have been awarded:
operate and maintain a public infrastructure facility. this Aquino administration shows its commitment to
Four years later, RA 6957 was amended by RA 7718 to accelerating public infrastructure development that (1) Daang Hari-South Luzon Expressway Link
provide financial incentives and to minimize government would likely attract more foreign investment Road;
regulations so that the private sector will be more and boost tourism, thereby increasing (2) First phase of the PPP for School Infrastruc-
encouraged to participate in the PPP program. RA 7718 job opportunities for Filipinos. ture Project;
governs the procurement of infrastructure or development (3) Ninoy Aquino International Airport Express-
projects by the private sector. Under this law, In 2011, Stratbase Research Institute published way;
infrastructure or development projects may be its analysis on PPP through its Occasional Paper (4) Second phase of the PPP for School Infra-
undertaken through any of the contractual arrangements entitled “The PPP Challenge”. The paper sought to structure Project;
provided* therein for which pertinent incentives will be establish the importance of PPP to the country’s (5) Modernization of the Philippine Orthopedic
given to stimulate private resources for the purpose of economic growth for the succeeding years and, Center;
financing the construction, operation and maintenance of further, provided recommendations on how PPP (6) Automatic Fare Collection System;
infrastructure and development projects normally can be properly implemented by the Aquino (7) Mactan-Cebu International Airport Project;
undertaken by the government. administration so as to make it an effective (8) LRT Line 1 South Extension;
tool in national development. (9) Integrated Transport System-Southwest
Recognizing the importance of infrastructure in building Terminal Project;
the foundations of a strong economy, past administra- Yet, the promise of growth via PPP has been (10) Cavite-Laguna Expressway (CALAX);
tions consistently focused on improving infrastructure, weakened by the vulnerability of the scheme to (11) Integrated Transport System (ITS) – South
certain that investments in this area would bring benefits politics. Had the Aquino administration maximized Terminal Project; and
across sectors and create more opportunities for the the full potential of the PPP scheme, the Philippines (12) Bulacan Bulk Water Supply Project.
fast-growing population. Conversely, poor infrastructure would have reaped the benefits of a growing
is widely accepted to be a significant barrier to economy and a high rate of inclusive growth. Out of these twelve projects, only the Daang
trade and discourages investment. The underlying question arises as to how the Hari-South Luzon Expressway Link Road, now
slow progress of the PPP program of the called the Muntinlupa Cavite Expressway
Projects through PPP are expected to boost the country’s Philippines has affected its competitiveness. (MCX), is operational.2
growth rate to 7-8%.1 This means intensified infrastruc-
* Section 1 of R.A. 7718 enumerated/defined the following contractual arrangements: 1. Build-operate-and-transfer; 2. Build-and-transfer; 3. Build-own-
and-operate; 4. Build-lease-and-transfer; 5. Build-transfer-and-operate; 6. Contract-add-and-operate; 7. Develop-operate-and-transfer; 8. Rehabilitate-
operate-and-transfer; 9. Rehabilitate-own-and-operate; and 10. Such other variations as may be approved by the President of the Philippines.

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

04
As of February 2016, 10 PPP projects are up for In other words, a more competitive economy is
bidding: one that is likely to grow faster over time.”4
Table 1. Global Competitiveness report
(2015-2016)
(1) Operation and Maintenance of LRT Line 2; Infrastructure is one of four pillars in the Global
(2) Regional Prison Facilities; Competitiveness Report’s index (GCI), alongside
(3) Laguna Lakeshore Expressway Dike Project; institutions, macroeconomic environment, and
(4) Davao Sasa Port Modernization Project; health and primary education. In elevating
(5) PPP Airport Operations and Maintenance of infrastructure as a pillar, the Global Competitiveness
the Bacolod (Silay) Airport & Iloilo Airport (bundle Report finds that “[a] well-developed infrastructure
1); system reduces the effect of distance between
(6) PPP Airport Operations and Maintenance of regions, integrating the national market and
the New Bohol (Panglao) Airport, Laguindingan connecting it at low cost to markets in other
Airport and Davao Airport (bundle 2); countries and regions. In addition, the quality and
(7) Road Transport IT Infrastructure Project extensiveness of infrastructure networks
(Phase II); significantly impact economic growth and reduce
(8) North-South Railway Project (South Line); income inequalities and poverty in a variety of ways.
(9) Civil Registry System-Information Technology A well-developed transport and communications
Project (Phase II); and infrastructure network is a prerequisite for the
(10) LRT Line 6 Project3 access of less-developed communities to core
economic activities and services.”5

Infrastructure Limits Philippine Overall, the Philippines has improved its


Competitiveness competitiveness: rising five notches on the Report’s
2015-2016 index to 47th of 140 countries. The
The World Economic Forum (WEF)’s Global country’s latest performance followed a 7-notch
Competitiveness Report defines competitiveness jump to 52nd in the 2014-2015 report and a
as “the set of institutions, policies, and factors that 6-notch jump to the 59th spot in 2013-2014. The
determine the level of productivity of a country. The Philippines has jumped 33 places in total under the
level of productivity, in turn, sets the level of Aquino administration, showing the ‘largest gain’
prosperity that can be reached by an economy. The among all other countries in the study since 2010.
productivity level also determines the rates of return The Philippines got the highest ranking in terms of
obtained by investments in an economy, which in macroeconomic environment followed by market
turn are the fundamental drivers of its growth rates. size and business sophistication (see Table 1). Source: the Global Competitiveness report 2015-2016

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

05
The same report shows, however, that the
country lags behind in terms of infrastructure,
labor market efficiency and goods market
efficiency. The report lists the Philippines’
infrastructure score as the second most Table 2: Philippines Infrastructure Pillar Sub-index Ranking
problematic factor for doing business in the 2015-2016
Philippines, with the country ranking 91st of
the 140 countries in the study. As the report
illustrates, the country’s poor infrastructure
holds back its total productivity, even given a
permissive macroeconomic environment and
other positive indicators. With infrastructure as
the second pillar of competitiveness, serious
actions must be taken in improving the quality
of the country’s infrastructure. The specific
difficulties in the country’s infrastructure
can be seen in Table 2.

Compared to other Southeast Asian countries,


Philippines is still lagging behind, stuck behind
Singapore, Malaysia, Thailand and Indonesia
at the bottom of the so-called “ASEAN 5”.
Disappointingly, the country did not even show
a close margin among the higher four; Indo-
nesia, the next ranking neighbor placed ten Source: The Global Competitiveness Report 2015-2016
notches away at 37 (see Table 3). With this in
mind, the Philippines must identify
best practices in these four countries to be
able to know what it must follow for the
betterment of the country.

Singapore ranks to be one of the top


competitive countries, not just in Asia, but in

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER FEBRUARY 2016

06
the world ranking. It has an outstanding and stable
performance across all pillars. It takes pride in its Table 3: Global Competitiveness Index Ranking 2015-2016 of Southeast Asian Economies
world-class infrastructure such as its roads, ports
and air transport facilities. Malaysia remains to be
highest among the developing Asian economies,
and has been achieving high tourist arrivals.
Thailand, which has been experiencing political
crisis, performs well on macroeconomics pillars. Like
the Philippines, there are barriers challenging market
competition, most especially those that restrict
foreign investment. Aside from these, Thailand faces
challenges such as political instability, excessive red
tape, pervasive corruption, security concerns and
high uncertainty on property rights. Indonesia has Source: The Global Competitiveness Report 2015-2016

prioritized infrastructure: Presidential Special Staffer


for Economic Affairs and Development Prof.
Firmanzah, Ph.D. mentioned that “infrastructure de- Table 4: Global Competitiveness Index Ranking 2015-2016 of Southeast Asian Economies for the Infrastructure Pillar
velopment in the last five years is the Government’s
main priority to strengthen the country’s national
competitiveness”.6 The accelerating infrastructure
development is supported by the Master Plan for
Acceleration and Expansion of Indonesia’s Econo-
mic Development (MP3EI), according to Firmanzah.

With these assessments, the Philippines can learn a


lesson or two from each of the countries mentioned.
First, the country must focus its efforts on invest-
ing on world-class infrastructures, in order to be at
Source: The Global Competitiveness Report 2015-2016
par with or at the least approach Singapore’s rank.
Second, it should find out how Thailand manages to
obtain a high rank despite facing the same challeng- It has been said that the Philippines lacks competitiveness in the level playing field, and consistent government policies are crucial
es similar to the Philippines, especially in the aspect global arena and has an unattractive investment climate. Investors factors that foreign investors are right to expect from the PPP
of market competition. By doing so, the Philippines have been repeatedly affected by the unpredictable policy environ- scheme. Returns on investment should be attractive and, more
may be able to combat these barriers and excel ment; government inefficiency, and a poor regulatory quality and importantly, the investment should be secured from political
in other pillars wherein Thailand stands out. ineffective control of corruption in the Philippines. Transparency, a reprisals. Investors to PPP expect a well-managed process.

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

07
Critics of the Aquino government’s PPP Policy are tor Cosette Canilao of the PPP Center, the process and Aboitiz Equity Ventues, Inc. and Optimal Infra-
quick to point out that “no capitalist will invest in of conceptualizing the PPP projects and reviewing structure Development Corp., a subsidiary of diversi-
big-ticket projects in a relatively small market like the qualified companies who can participate in the fied conglomerate San Miguel Corp (SMC).
the Philippines without certain guarantees that will bidding takes time. The concerned government
ensure the protection and profitability of his agencies play the bigger role of conceptualizing and The financial proposal of Team Orion consisted of a
investment.” It is unlikely that investors will come in evaluating the projects. Although these government premium/concession payment of P11.659 billion. On
with fewer incentives. More investors will come only agencies are guided by a timeline, these are merely the other hand, the concession payment of Optimal
if given guarantees and protection such as guar- notional and can be adjusted. Thus, no direct was P20.105 billion. Optimal was disqualified to pro-
anteed investment return, access to loans backed accountability can be attributed to the PPP Center. ceed with the bid due to a defect in its bid security.
by government guarantees, and in recent years, In its defense, Optimal submitted that its bid security
protection from risks arising from unfavorable For the implementing agencies, a major cause of is valid until 29 November 2014 and thus was fully
court decisions that affect profitability”7 delay is the prolonged period of consultation bet- compliant with the bid requirements. In consonance
ween the private sector and the concerned with the provisions of the BOT law, Team Orion won
government agency. There is uneven technical cap- the project as the highest bidder.
PPP Program’s Choke Points pacity within the implementing agencies, with many
government officials not equipped with technical Rebidding of CALAX was then approved by the
The majority of the delays occur during the feasibil- training nor exposure to the nitty-gritty of infrastruc- NEDA Board chaired by President Aquino. The Pres-
ity study and prequalification stages. The tendering ture projects. As such, consultants are often hired to ident explained that foregoing the P9-bilion differ-
stage would range anywhere between nine to twelve provide an in-depth understanding of the complexi- ence in premium bid of Optimal could bankroll other
months: “Invitation to Bid (21 days); Response (45 ties involved and a full assessment of the projects. government projects. With the Department of Public
days), Prequalification (60 days), Preparation of Bids Works and Highways as its implementing agency,
(120-150 days), Evaluation & Award (30-60 days). The Premium Bid (aka Concession Payment) it underwent a revamped procurement process in
Next comes contract negotiation and government controversy in the case of CALAX June 2015 after the government learned its lessons
approvals and this takes three months. Then there is from a previous bidding mired in controversies. The
financial closing which takes anywhere from three to The controversial Cavite-Laguna expressway Board also approved a minimum bid price of P20.1
12 months.”8 The target deadlines keep on moving (CALAX), which aims to connect Bacoor and Kawit billion, the same amount submitted by Optimal. The
and moving for months, as seen in all projects. in Cavite and South Luzon Expressway areas, is a supposed winner of the CALAX project, Team Orion
P35.4 billion project under the Build-Operate-and- no longer participated in the rebidding.
The PPP Center coordinates this process, working Transfer structure. CALAX faced an issue on its bid-
to ensure that timelines for proposals and ding done in 2014. Among the bidders were Team Aside from Team Orion’s expression of disappoint-
studies are met. According to then Executive Direc- Orion, the 50-50 joint venture of Ayala Corporation ment towards the government’s decision, other

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

08
investors have likewise expressed their sentiments light on the nature of premium payments. “The Reference must be made to Section 4.2. (h) of the
towards the government’s blunders. Speaking on PPP Center would like to point out that premium Revised BOT Law Implementing Rules and Regula-
behalf of local and foreign investors, Peter Angelo B. payments for the CALAX Project, just like in any tions, which sets out the parameters and criteria for
Perfecto, Executive Director of the Makati other PPP contracts previously awarded, will not evaluation of financial component of the bids, viz:
Business Club (MBC) previously pointed out that be passed on to the public through increased user
the group’s level of confidence will erode if the charges as these charges are pre-determined prior i. Lowest proposed toll, fee, rental or charge at
government approves a rebidding of the CALAX to the bidding process and will be subject to the the start of project operation, if a pre-agreed
project. Notwithstanding Aquino’s approval of the review and approval by the concerned regulatory parametric tariff adjustment formula is
rebidding, Perfecto remains firm in his statement but agency (e.g., Toll Regulatory Board). These premium prescribed in the bid document;
pointed out that “there remains still a level of payments will go straight to the National Treasury
confidence that the government will roll out which can then be used to fund other equally ii. Lowest present value of government subsidy
more PPPs without such similar issues”9 important projects of the national government.”10 to be provided for the period covered
Further, it was noted that R.A. 7718 allows as by the contract;
In the end, rebidding happened between San bid parameter the highest present value of iii. Highest present value of proposed payments
Miguel Corporation’s Optimal Infrastructure proposed payments to the government. to Government, such as: concession fees,
Development, Inc. and Metro Pacific Investments lease/rental payments, fixed/guaranteed
Corporation’s MPCALA Holdings (MPIC). MPIC R.A. 7718 does not unequivocally provide as a bid payments, and/or variable payments/
won with the highest bid of P27.3 billion. parameter the highest present value of proposed percentage shares of revenue for the
payments to the government. Verily, Section 5 of period covered by the contract; or
The President’s decision to order the re-bidding R.A. 7718 only provides that in case of build-
of said CALAX project instigated the public to review operate-and-transfer arrangement, the contract iv. Any other appropriate financial bid parameter
previous bids for certain PPP awarded projects like shall be awarded to the bidder who, having satisfied as may be approved by the approving Body.
the Mactan-Cebu International Airport the minimum financial, technical, organizational and
Passenger Terminal Building and Automatic Fare legal standards has submitted the lowest bid and Except for item iii, the foregoing criteria find sup-
Collection System. Contracts were awarded to most favorable terms for the project, based on the port from R.A. 7718, which for emphasis, provides
bidders who submitted the highest present value of present value of its proposed tolls, fees, rentals and that the contract should be awarded to the lowest
proposed payments to government pursuant charges over a fixed term. On the other hand, in the complying bidder. On the other hand, the criterion
to Section 4.2 (H) of the Revised Implementing case of build-and-transfer or build-lease-and-trans- of highest present value of proposed payments to
Rules and Regulations of BOT law, in lieu of the fer arrangement, the contract shall be awarded to government was not contemplated in R.A. 7718.
lowest bid and most favorable terms for the the lowest complying bidder based on the present
project, as set out in R.A. 7718. value of its proposed schedule of amortization If at all, the premium/s (to be) paid by winning bid-
payments for the facility to be constructed accord- ders, which represents the highest present value of
In a statement issued by the PPP Center, Deputy ing to the prescribed minimum design and proposed payments to government, are mere ad-
Executive Director, Ms. Sherry Ann N. Austria, shed performance standards, plans and specifications. vance payments or prepaid tax to government and/

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

09
Only Filipinos or corporations
or its share of revenue, to the detriment of the
future users of said infrastructure.

As Henry Schumacher, Executive Vice President of the


European Chamber of Commerce of the Philippines that are AT least
60% owned by Filipinos
(ECCP), stated, “It is also important to understand that
the higher the bidding goes, it only favors government
coffers; Juan de la Cruz will later on have to pay more
for the utilization of CALAX.”11 Business logic dictates
that proponents will seek to recover their investment for
are allowed to own land in the
Philippines, but foreigners are
the said project/s, which necessarily translates
to higher costs to the public. This arrangement
defeats the purpose of a PPP.

This view was supported by Senator Ralph Recto in


allowed to lease land
for 50 to 75 years
his statement on August 10, 2014,12 thus: “If a public
infrastructure or basic service is the one being
auctioned off, logic dictates that the best lowest bid
should win it as it would translate to lower fees to be
paid by the public who will use it. The higher the bid, the appropriate Senate Committee to conduct an inquiry, in foreigners may hold interests in corporations, partnerships
the higher the fees that the public will eventually aid of legislation, on the bidding process of PPP projects with and other entities in the Philippines, provided that these are not
shoulder. It has a domino effect and the last tile will fall the end in view of ensuring that the Filipino will benefit quality engaged in an activity that is reserved by law only to Philippine
on the people.” Further, he stated that the govern- public services at the least possible costs. citizens or entities that are wholly owned by Philippine
ment’s main consideration in awarding contracts should citizens. The maximum amount of foreign equity that is
be what the public will pay at the minimum, which will allowed in a company depends on the type of activity that the
not be achieved if the government will get an advance The 60/40 Rule Applied to Infrastructure Investments company is engaged in, which is undesirable for the foreign
payment or a prepaid tax, by way of premium, investors. Only Filipinos or corporations that are at least 60%
for a structure that has yet to be built. Easing restrictions on foreign investments will give the owned by Filipinos are allowed to own land in the Philippines,
country’s PPP program a shot in the arm. Republic Act No. but foreigners are allowed to lease land for 50 to 75 years
In view of the foregoing, the Senate passed 7042 or Foreign Investments Act of 1991, the law that governs depending on the land’s classification. Private corporations,
Resolution No. 810 on August 6, 2014, which the participation of foreign entities in economic and whether local or foreign, can only lease up to 1,000 hectares of
resolution was introduced by Senator Recto, directing commercial activities in the Philippines, states that alienable public lands. There is no limitation regarding private

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

10

lands. The difficulty lies when foreign investors try to tap the domestic market and work their way through
complicated bureaucratic procedures, local government corruption, only to find out that they are not
qualified to do business in the Philippines due to the foreign equity restriction. However, foreign
investors could still participate in the public bidding by partnering with a
Philippine national or domestic corporation, provided that.13

“at least sixty percent (60%) of the capital stock outstanding and entitled to vote is owned and held by
citizens of the Philippines; or a trustee of funds for pension or other employee retirement or separation
benefits, where the trustee is a Philippine national and at least sixty (60%) of the fund will accrue to the
benefit of the Philippine nationals: Provided, That where a corporation and its non-Filipino stockholders
own stocks in a Securities and Exchange Commission (SEC) registered enterprise, at least sixty percent
(60%) of the capital stocks outstanding and entitled to vote of both corporations must be owned and
held by citizens of the Philippines and at least sixty percent (60%) of the members of the Board of
Directors of both corporations must be citizens of the Philippines, in order that the
corporations shall be considered a Philippine national”

Notwithstanding the foregoing options, Philippines is still not an attractive place for foreign investments,
whose capital is especially important for infrastructure investment. Big investments in infrastructure
developments are brought in by foreign investors, yet their ownership cannot go beyond 40% of the
equity and their participation in the management therefor is likewise subject to the same limitation. A
minority shareholder is often at risk of losing. Thus, without removal of the foreign equity limitations,
at least in the area of infrastrusture development, the confidence level of foreign investors
in the country will not improve, which is to the Philippines’ detriment.

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. Image Credit: corporatelivewire.com www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

11
Recommendations and Conclusion

1. President Aquino can hasten the awarding of PPP projects in the pipeline will be awarded before the term of President Aquino ends in three months.
more PPP projects, focus on monitoring already
existing PPP projects, or do both. Improved 4. The proposed amendments to the BOT Law, which is one of the priority bills of President Aquino
transportation and infrastructure are needed to fully would have institutionalized the supposed reforms initiated by his administration and thus would
harness the country’s economic potential. These ensure that said reforms would be continued by the next administration.
projects are also beneficial in terms of
generating additional employment, investments and In particular, House Bill No. 6331, the House of Representatives version of the proposed amendments
more foreign arrivals. The failure of the to the BOT Law, features provisions attuned to international standards, where private sector participation is
government’s flagship program thrust to take truly encouraged and the partnership valued. Among the notable clauses of HB 6331 are on the following:
off has been a source of frustration since
its launch in November 2010. a) Issuance of Administrative Franchise, License or Permit. HB 6331 provides for the automatic
grant of administrative franchise, local or national permits, or any other requirement for the
2. For the progress of the program to accelerate, the implementation of the PPP project once the contract is duly executed;
government should be firm on the observance of its
processes and timelines. Stakeholders such b) Projects of National Significance. Upon classification by the President of energy, toll road, mass
as the bidders, among others, should also do its transit, water, sewerage, and such other projects, HB 6331 proposes that said projects deemed
part in strictly observing the process. There should imbued with national significance shall be exempt from the real property taxes levied under the Local
be a strong mechanism for collaboration and Government Code, and from all local taxes and fees. The project shall also be automatically
consultation between the public and private issued the necessary business permits, including renewals of such permits; and
sectors in order to facilitate project development
with minimum legal impediments. c) Recovery of Investment. HB 6331 likewise mandates that PPP contracts include an agreement on
the recovery of the proponent’s investment by collecting of tolls, fees, rentals or charges, engaging in
3. The success of a country’s PPP program commercial development, or receiving viability gap funding (VGF), that is financial support from
depends on the continuity of a government policy, government to make user fees affordable, or direct payment from government, among others.
a perception of minimal political and economic risk
that is instilled in the minds of the investors and The above cited provisions reflect modern governance where there is acknowledgement that
stable macroeconomic management. As reality through a robust partnership with the private sector, the government can
checks were made since its ambitious launch, the better deliver the services our country and our people need.*
PPP Center is still optimistic that at least 80% of the
* House Bill No. 6331, An Act Institutionalizing and Strengthening Public-Private Partnerships, and Appropriating Funds Therefor,
as part of Committee Report No. 947, submitted by the Committee on Public Works and Highways, the Committee on Appropria-
tions, and the Committee on Ways and Means on December 14, 2015, Sections 13, 20, 28 (c).

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
OCCASIONAL PAPER MARCH 2016

12
5. The best lowest bid should always win as it would leeway to act independently on proposals, whether
translate to lower fees to be paid by the public for solicited or unsolicited projects. The PPP Center
who will use it. The higher the bid, the higher the should be able to independently address the whole
fees that the public will eventually shoulder. process of the PPP scheme. For that purpose,
Inevitably, it will be the public who will suffer from the PPP Center becomes a one-stop shop for
such arrangement. The government’s main infrastructure developments which would include
consideration in awarding contracts should be what the conceptualization, evaluation and approval of
the public will pay at the minimum, which will not be projects. This concept would eliminate or at the very
achieved if the government will get an advance least, minimize the bureaucracy problem.
payment, by way of premium, for a structure that
has yet to be built. Not only is the public required PPP projects should be a reflection of the
to pay a fee for a basic service that a government Philippines on how modernized and integrated our
should have rendered for free, but the public will be facilities will be, a link for an innovative and
required to pay a higher fee in order to recompense competitive environment for the future. Certainly, the
the bidder for its premium payment to the govern- PPP scheme has yet to reach its fullest potential.
ment. Government should see that PPP is not
crafted for the purpose of raising revenues
but rather to be able to provide public services that
the government cannot afford.

6. Finally, more than being just a mere coordina-


ting agency, the PPP Center should be given more

Endnotes: 6
Sekretariat Kabinet Republika Indonesia. (September 21,
2014). Increase in Indonesia’s Global Competitiveness Index Reflects
10
PPP Center. (September 1, 2014). “PPP Centers reaction
to Calax commentary. Retrieved from http://ppp.gov.ph/?in_the_
1
Global Source Partners. (2011). A Bet on PPP. Retrieved from Improvements in Its Economic Performance. Retrieved from http:// news=ppp-centers-reaction-to-calax-commentary
http://www.globalsourcepartners.com setkab.go.id/en/increase-in-indonesias-global-competitiveness-in-
dex-reflects-improvements-in-its-economic-performance/ 11
Amojelar, Darwin. (November 24, 2014). European Chamber of
2
PPP Center. (2016). Pipeline of Projects. Retrieved from http:// Commerce of the Philippines. President Aquino orders rebidding of
ppp.gov.ph/?page_id=26075
7
IBON. (November 11, 2010). PPP: More public debt, less gov’t Cavite-Laguna Expressway project. Retrieved from http://www.eccp.
responsibility. Retrieved from http://ibon.org/2010/11/ppp-more-pub- com/articles-page.php?category=2&article_id=1064#details
3
PPP Center. (2016). Pipeline of Projects. Retrieved from http:// lic-debt-less-govt-responsibility/
ppp.gov.ph/?page_id=26075 12
Senate of the Philippines. (August 10, 2014). Recto: High PPP
8
Chanco, B. (Feb. 28, 2011). Philippine Star. Stale bureaucratic bids could lead to higher user charges. Retrieved from https://www.
4
World Economic Forum. (September 2014). The Global Com- thinking delays PPP Retrieved from http://www.philstar.com/busi- senate.gov.ph/press_release/2014/0810_recto1.asp
petitiveness Report 2014-2015 ness/661176/stale-bureaucratic-thinking-delays-ppp
13
Republic Act No. 7042 Foreign Investments Act of 1991
5
World Economic Forum. (September 2014). The Global Com-
9
Business Mirror. (February 17, 2015). ‘Calax should be sole
petitiveness Report 2014-2015 exception’. Retrieved from http://www.businessmirror.com.ph/calax-
should-be-sole-exception/

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. www.stratbase.com.ph
9.3
VOLUME

ABOUT
Victor Andres “Dindo” C. Manhit
is the CEO and Managing Director of the Stratbase Group and
President of the ADR Institute. He specializes in Strategic Public
Management, Legislative Research and Governance Reforms. His
research interest and field of specialization had led him to pursue
active involvement in legislation, bureaucratic work
and civil society advocacy.

Maria Claudette L. Guevara is the Chief of Staff of the


Stratbase Group and is a Research Analyst at the ADR Institute.

Stratbase’s Albert Del Rosario Institute


is an independent international and strategic research
organization with the principal goal of addressing the
issues affecting the Philippines and East Asia
9F 6780 Ayala Avenue, Makati City
Philippines 1200
V 8921751
F 8921754
www.stratbase.com.ph

C 2016 ADRiNSTITUTE for Strategic and International Studies. All rights reserved. Image Credit: joc.com

Você também pode gostar