CITY OF SHREVEPORT

Administrative Action Plan


2015-2018:
Roadway
Improvements

Ollie S. Tyler, Mayor


1
Administrative Action Plan 2015-2018

Roadway Improvements

City of Shreveport Street Projects

Table of Contents

Executive Summary ………………………………………………………..……………..…………………………….. 3

Appendix A (2018 Roadway Improvements) …………………………………………………………..…… 4

Appendix B (2017 Roadway Improvements) …………………………………………….………..……….. 7

Appendix C (2016 Roadway Improvements) ………………………………………………….….....…… 10

Appendix D (2015 Roadway Improvements) …………………………………………………………...... 14

2
ADMINISTRATIVE ACTION PLAN 2015-2018
Roadway Improvements

City of Shreveport Street Projects

The information below and in this report represents a year-by-year description of the total street
improvements undertaken by the City in 2015-2017 and those chosen by the Administration for 2018. It
should be noted that the last three years represent one of the most aggressive citywide street
improvement efforts.

As in previous years, streets chosen for improvement or overlay in 2018 were done so in accordance
with those demonstrating the greatest need as provided by the Pavement Condition Index (PCI)
conducted through the City Engineers’ Office. The PCI rates the condition of the road surface and
provides a numerical ranking based on the type, extent, and severity of the pavement surface (typically
cracks and rutting) as well as the smoothness and ride comfort of the road. The ratings are from 0,
being the worst, to 100 being the best.

Total Street Improvement Schedule 2015-2017

From January 2015 through December 2017 there were 216 street improvements undertaken by the
City at a cost of $58.6 million:

 175 street projects, totaling $39.1 million were completed from January 2015 to December 2017

 41 street project, totaling $19.5 million will carry over to 2018

Proposed Street Improvement Schedule 2018

In 2018, there will be 82 new street projects totaling $6.6 million: 77 of those will be primarily asphalt
neighborhood street projects and 5 of those will be concrete reconstruction projects (Appendix A). At
this point, the City will begin addressing local roadway networks and continue work on Linwood Avenue.
Along with these 82 designated streets, $500,000 will be added to the Concrete Street Improvements
project to address concrete street panel repairs that fall beyond the capacity of the Public Works
Department. The total expenditure for all of 2018’s street improvements and the other street programs
listed is an estimated at $7.1 million.

3
APPENDIX A

2018 STREET FUNDING and REPAIRS


Administrative Proposal

The following is a summary of available funding sources and Administration’s proposal for street repairs for fiscal
year ending of 2018. The proposed lists were developed using information from the City Engineering’s Pavement
Management System and other appropriate factors.

Local Asphalt Repair and Overlay Program ($3.8 million)


The following 77 street repair list has been developed as a continuation of 2017’s Asphalt Repair Program and will
begin addressing local asphalt streets. For the most part, these will be residential neighborhood streets. The funds
proposed for this program is $3.8 million and provided through the Streets Special Revenue Fund.

Street Name From To Length (ft.) Avg. PCI Est. Cost


DISTRICT A
Abel St. Jamison St. Aline Ave. 309 10.00 $11,619
Aline Ave. Abel St. Russell Rd. 1931 15.00 $103,728
Christopher Glen St. Russell Rd. Dead End 554 22.00 $18,907
Chester St. Christopher St. Dead End 1090 41.00 $26,786
Christopher St. Bowman St. Dead End 726 17.50 $15,084
Stafford St. David Raines Rd. Rentie Ln 1121 16.00 $31,130
Anderson St. Rentie Ln. David Raines Rd. 1171 16.00 $27,178
Fisher St. Rentie Ln. David Raines Rd. 1129 17.00 $25,371
Rentie Ln. Stafford Dr. Anderson St. 246 24.00 $15,064
Ragsdale Ave. Oak Forest Ln. Yorktown Dr. 1370 23.33 $27,583
Hill St. MLK Dr. Kelsey St. 1384 23.80 $44,287
March St. Patzman St. Dead End 1515 28.67 $36,786
Willis St. Audrey Ln. Linear St. 1334 33.00 $23,133
Yorktown Dr. Shreveport Blanchard Ragsdale Ave. 1504 41.67 $48,787
Terry St. Ethyl Cir. David Raines Rd. 1176 20.00 $43,132
Ethyl St. Pouncey Ln. Terry St. 293 41.00 $13,376
Pouncey Ln. David Raines Rd. Dead End 1339 31.00 $48,348
Skelly St. David Raines Rd. Miller Ave. 1369 27.00 $45,278
DISTRICT B
Gladstone Blvd. Line Ave. Fairfield Ave. 1321 22.00 $62,205
Pinehurst Blvd. Dalzell St. Robinson Pl. 922 34.00 $42,590
Woodrow St. Linwood Ave. Dowdell St. 1274 39.00 $29,920
Dowdell St. Woodrow St. Dickinson St. 659 53.00 $29,306
McNeil St. Cotton St. Fannin St. 2682 59.00 $210,233
Jordan St. Line Ave. Cornwell Ave. 5287 50.83 $286,794
Coty St. Stoner Ave. Olive St. 2664 47.75 $153,337
Joplin St. Midway Ave. Desoto St. 664 9.50 $27,496
DICTRICT C
Dillingham Ave. Pierremont Rd. Oak Hill Dr. 2781 46.43 $95,474
Stratford Ave. Beverley Pl. Youree Dr. 1837 48.75 $76,080
Centenary Blvd. Gladstone Blvd. Concrete 795 47.50 $36,172
Creswell Ave. Oak Hill Dr. Gilbert Dr. 972 46.50 $29,562
Gladstone Blvd. Gilbert Dr. Centenary Blvd. 1070 45.00 $47,954
th
Querbes Dr. Gilbert Dr. E 70 St 1901 43.00 $87,665

4
Oak Hill Dr. Line Ave. Creswell Ave. 1584 42.50 $62,385
Huron St Line Ave. Concrete 1305 49.00 $56,788
DISTRICT D
Peach Dr. Ellerbe Rd. Dead End 1305 46.00 $56,040
Ellerbe Ridge Dr. Ellerbe Rd. Peach Dr. 1856 47.00 $61,860
Emberwood Dr. Ellerbe Rd. Cobblestone Dr. 752 44.00 $41,054
Emberwood Cir. Cobblestone Dr. Cul-De-Sac 408 54.00 $19,515
Bentway Cir. Ellerbe Rd. Cul-De-Sac 636 41.00 $22,801
Capilano Dr. Alvamar Dr. Long Lake Dr. 1279 46.50 $47,521
Alavamar Dr. Capilano Dr. Dead End. 1411 55.00 $47,652
Woodmere Dr. Woodvale Dr. Dead End 1748 37.67 $57,654
DISTRICT E
Helmsdale Ct. Stonehaven Dr. Cul-De-Sac 319 18.00 $19,364
Danfield Ct. Stonehaven Dr. Cul-De-Sac 245 22.00 $10,340
Anne Ave. Southside Dr. Crestwood Dr. 1097 26.00 $33,584
Crestwood Dr. Jewella Ave. Dead End 297 34.00 $31,790
Hoyte Dr. Walker Rd. Southwood Dr. 1922 37.00 $96,061
Dawn Ridge Dr. Bert Kouns Ind. Lp. Dashwood Dr. 1206 36.00 $41,124
Lola Ln. Mansfield Rd. Brookwood Dr. 1738 47.50 $72,428
Prestwick Dr. Stonehaven Dr. Windbrook Dr. 482 46.00 $19,239
Dashwood Dr. Dawn Ridge Dr. Highcrest Dr. 352 45.00 $15,264
Highcrest Dr. Dashwood Dr. Dawn Ridge Dr. 1366 40.00 $49,212
Windbrook Dr. Prestwick Dr. Cherryfield Ct. 594 35.00 $23,387
Coronado Dr. Mansfield Rd. Birch Dr. 752 29.00 $39,270
Birch Dr. Coronado Dr. Normandie Dr. 300 52.00 $17,259
Sandman Dr. Dawnridge Dr. Cul-De-Sac 310 26.00 $19,678
Lucille St. Betty St. Amelia Ave. 2084 32.33 $70,876
DISTRICT F
Valley Ridge Rd. Prentiss Ave. Hearne Ave. 1975 43.00 $44,955
Baxter St. Kennedy Dr. Roberts St. 606 44.00 $19,462
Roberts St. Baxter St. Dead End 485 52.67 $12,536
Westover Rd. Fairy Ave. Velva Ave. 659 46.00 $29,752
Velva Ave. Bibb St. Vivian St. 1320 52.25 $40,444
Murray St. Hearne Ave. Werner Ave. 1074 43.50 $25,246
Mayfield St. Broadway Ave. Coleman College St. 2501 46.25 $55,020
Wagner St. E. Jewella Ave. W. Canal Blvd. 1728 49.00 $42,016
Carver Ln Broadway Ave. Long St. 959 45.00 $36,188
Vivian St. Virginia Ave. Mansfield Rd. 766 40.00 $24,599
Millard St. Jewella Ave. Lotus Ln. 2587 34.50 $91,025
DISTRICT G
Faust Dr. Hobbs Dr. Buncombe Rd. 1640 37.00 $54,052
Hermosa Dr. Briar Ridge Dr. Concrete 856 30.50 $42,003
Shadow Creek Dr. Santa Monica Dr. Dead End 985 31.00 $30,868
S. Inwood Rd. Trailwood Ter. Santa Monica Dr. 3108 53.40 $115,602
Grove St. Lakeshore Dr. Elon St. 1240 37.00 $71,303
Lakeland St. Jewella Ave. San Jacinto Ave. 1310 46.00 $43,228
W. College St. Lakeshore Dr. Jewella Ave. 1702 46.00 $61,772
Inwood Rd. Border Ln. Santa Monica Dr. 1698 40.00 $64,835
Lillian St. Arkansas Ave. Exposition Ave. 1522 39.33 $57,754
77 Projects Totaling $3,818,171

5
Concrete Panel Replacements – Collector & Arterial Streets and General ($2.0 million)

Street From To District Est. Cost


th
Line Ave. Pierremont Rd. 70 Street C $529,173.33
Audrey Ln. MLK Kelsey St. A $269,500.00
th
Pines Rd. Westport Ave. 70 Street G $133,466.67
Jewella Ave Greenwood Rd. Milam St. G $550,550.00
General Concrete Panel Replacement $500,000.00
Total $1,982,690.00

Linwood Avenue Reconstruction Phase II ($1.3 million)


Phase I of Linwood Avenue Reconstruction is currently ongoing from Bert Kouns Industrial Loop to Gravois Dr. With
the need to continue critical repairs, Phase II of this project will continue from Gravois Dr. to Mount Zion Rd. The
estimate cost for this phase is $1.3 million.

6
APPENDIX B
2017 ROADWAY IMPROVEMENTS

Street Name From To Length Cost


District A
Completed Overlay
Kelsey Northside Legardy 4031 $68,946
Hawkins Legardy Falcon 5570 $121,948
Legardy MLK Hawkins 4764 $145,123
Missouri Greenwood Stonewall 610 $21,880
Norma Milam Weinstock 990 $36,694
Pine Hill Rd N. Market City Limits 2684 $77,693.00
Dowling Patzman Dead End 1515 $57,877.00
Fullerton N. Hearne Aero 2453 $118,589.00
Ongoing
1
Ravendale N. Market Old Mooringsport 2325 $83,938
1
S. Lakeshore Concrete City Limits 16588 $719,338
District B
Completed Overlay
Kentucky Milton Fredrick 609 $9,522
St. Vincent Samford Clanton 7500 $182,616
Missouri Greenwood Stonewall 1950 $82,316
Wilkinson Highland Creswell 665 $21,565
Marks Claiborne Dead End 760 $9,889
Cedar Park Texas 411 $18,198
Park Cedar Caperton 362 $16,028
Bell Texas Dead End 927 $27,495
Murphy Texas Snow 1015 $51,634
Milam Commerce Common 2754 $99,713
Ongoing
1
Gladstone Line Creswell 1320 $58,891
1
Cedar Texas Park 411 $24,475
1
Crockett Common Commerce 2750 $208,831
1
Southern Fairfield Kings Hwy 5590 $358,430
1
Marshall Fairfield Stoner 4550 $575,131
1
Fairfield Christian Marshall 2350 $260,485

District C
Completed Overlay
th
60 Fairfield Southern 1305 $26,251
Holly Street Washington Dalzell 1619 $36,817
Thornhill Drexel Pierremont 1646 $38,238
Ongoing
th th 1
Southern 60 78 7250 $546,577
Other Capital Improvement Project – Construction estimated in 2018
2
Knight Street LA 3032 E. Preston 6790 $3,029,095

7
District D
Completed Overlay
th
Thornhill 79 Marx 1241 $19,090
Karla Cir Walker Cul-de-sac 748 $30,071
Ongoing
1
Roselawn Harris Gideon 572 $18,040
1
Kidd Broad Range 357 $7,497
1
Broad Kidd Dead End 644 $13,531
1
Flournoy Lucas Ellerbe Kingston 17423 $631,148
District E
Completed Overlay
Cedar Ridge Dr. Cedar Creek Dead End 1164 $36,370
Cedar Creek Cir Cedar Creek Cul-De-Sac 293 $13,145
Turner Dr Brookwood Marlow Dr 1154 $27,994
Southland Park Baird Mansfield 5080 $124,713
South Brookwood Bert Kouns City Limits 2162 $378,541
Ongoing
1
Southland Park Mansfield Rd Bert Kouns 2426 $99,854
Flournoy Lucas Ellerbe Kingston See Dist. D
District F
Completed Overlay
Portland Midway Woodford 990 $15,695
Union 73rd 70th 1120 $22,727
Ongoing
1
Suntan Dollarway Concrete 876 $21,045
1
Gloria Street Hollywood Kennedy 1670 $73,370
1
Doris Broadway Jewella 2630 $102,830
th 1
Suntan 70 Concrete 1610 $57,950
City Wide Street Improvements
Ongoing Asphalt Overlay
Oak Leaf Evers Dead End 250 $8,850
th
Wallace Browning 76 1650 $60,000
Argyle Linwood Woodfield 2630 $74,800
th th
Union 70 75 1850 $53,200
Portland Midway Malcolm 1650 $46,400
Morrow McAlpine Jewella 1480 $48,000
82nd Linwood Dead End 1300 $32,800
th
Lardner 87th 84 990 $25,700
Ongoing Concrete Panel Replacement
2
Valleyview Jewella Mansfield $420,000
District G
Completed Overlay
Murray Lakeshore Suntan 2439 $68,844
Glen Michigan Sunset 1364 $39,072
Regent Hudson Orla 1980 $69,925
Darrien Stonewall Exposition 640 $37,070
Mertis Penick Milton 900 $28,765
Grove Hardy Jackson 670 $21,490

8
Ongoing
1
Spruce San Jacinto Exposition 800 $25,600
1
Masters Pines Sea Pines 1651 $66,044
1
Aragon Newcastle W. Aragon 1046 $37,690
1
W. Aragon Aragon Bert Kouns 623 $29,926
1
Castlebrook Aragon Newcastle 1006 $36,232
All Districts
2
2017 School Sidewalk Repair Program 41 Schools $2,089,640
69 projects totaling $12,111,650
1
This footnote indicates that this is the estimated cost of the overlay improvements and is has not been completed at the time of
publication.
2
This footnote indicates that this is the estimated cost of the project and is has not been completed at the time of publication.

9
APPENDIX C
2016 ROADWAY IMPROVEMENTS

DISTRICT A
Completed Overlay:
Street From To Length Cost
Gilliam Thomas E. Howard Legardy 2280 $64,058.10
Jamison Russell Legardy 2790 $92,897.80
Hanna Legardy Montana 3070 $113,383.60
Audrey Ln MLK Hawkins 4750 $272,043.87
Cadillac Fontenot Dead End 660 $18,140.90
Old Blanchard Rd Russell Holcomb 750 $20,395.00
Norma Av Laurel White 1209 $33,077.00
Pierre Av Ford I-20 5010 $141,651.00
Portland Av Kings Highway Portland 650 $64,546.00
Pines Rd St. Lakeshore Jefferson Paige 7250 $115,053.00
City Wide Street Improvements:
Completed
Hersey D. Wilson (II) Hill Legardy 4250 $206,769
DISTRICT B
Completed Overlay:
Street From To Length Cost
Franklin Market Marshall 590 $25,481
Desoto Linwood RR Tracks 2700 $83,901
Cornwell East Merrick East Wilkerson 2120 $66,318
Desoto Virginia Portland 795 Combined
Levy St Texas Linwood 2180 $52,122
Louisiana Av Fannin Jordan 6750 $237,957
Market St Youree Drive Stoner 1940 $52,216
Marshall St Caddo Fairfield 2940 $71,512
Midway Av St. Vincent Florence 730 $11,965
Portland Av Kings Highway Portland 2454 See A
Travis Commerce Common 2750 $100,983
Creswell Av Marshall Ockley 13490 $450,271
Ockley Line Ockley 1890 $121,145
East Washington Anderson Oak 2000 $58,460
Fairfield Southern Pierremont 10857 $333,949
Gilbert Stoner Gregg 8703 $386,463
Centenary Stoner Kings Highway 6672 $281,170
Highland Jordan Ockley 10252 $553,314
City Wide Improvements:
Completed
C.E. Galloway Dalzell Olive 1360 $529,951
Common Street Bridge Cotton 518 $149,763
Ongoing
Oakdale Wallace St Cul-De-Sac 1590 $924,610
Line at Hulcee I-20 Hulcee 1025 $594,414

10
DISTRICT C
Completed Overlay
Street From To Length Cost
Mitchell Lane Line Dillingham 685 $8,901
th
Waterview 70 Dead End 630 $34,032
Atlantic Finley Youree 895 $43,469
th
East Ridge 70 Pierremont 4472 $122,896
Fern Av Ockley Atlantic 350 $31,135
Fairfield Av Southern Pierremont 3953 $121,590.00
Gilbert Stoner Gregg 1902 $84,460.00
City Wide Street Improvements:
Completed
Captain Shreve Dixie Gardens Preston 3418 $496,135
th th
Fairfield 84 70 5277 $920,277
Ongoing
Akard St. Southfield Ockley 3115 $1,539,940
DISTRICT D
Completed Overlay
Street From To Length Cost
Lloyd Lane Creswell Gilbert 822 $23,162
Hood Street Ellerbe Road Dead End 1422 $37,648
st th
Henderson 81 77 1462 $41,147
Turner Lane Harris Street Creswell 1520 $34,973
Norris Ferry Rd Ellerbe City Limits 17135 $151,262
City Wide Street Improvements
Completed
Village Green S. Dresden Town South 2126 $281,505
Ashbourne Albemarle Spring Lake 1405 $210,137
DISTRICT E
Completed Overlays:
Street From To Length Cost
Wardlow Flournoy Lucas Dead End 16222 $77,059
Hollyhock Drive Rosewood Dead End 1740 $42,662
Candlestick Lane Cedar Ridge Cedar Ridge 1832 $60,518
Belleview Drive Kingston Brookwood 286 $11,620
Dundee Circle Savannah Dead End 316 $13,238
Baird Rd Mansfield Bert Kouns 9600 $248,398
Live Oak Dr Kingston Old Mansfield 2900 $57,100
th
Meriwether Rd West 70 Mansfield 12076 $256,895
Mount Zion Rd Linwood St. Vincent 3199 $65,528
Ardis Taylor Dr Colquitt Mansfield 4101 $87,840
Capital Projects
Ongoing
Jewella Avenue Mansfield Hollywood 16766 $1,449,508
Linwood Avenue Bert Kouns Mt. Zion 5280 $3,385,070

11
DISTRICT F
Completed Overlays:
Street From To Length Cost
Clift Avenue Browning Argyle Combined
th th
Clift Avenue 75 70 2804 $73,934
David Street Wallace Concrete 785 $26,954
Standard Oil Lotus Concrete 2430 $68,365
Lotus Lane Standard Oil Dead End 745 $23,673
th
Meriwether Rd West 70 Mansfield 3206 $68,202
Broadway Av Forest Oak Kennedy 2380 $70,101
th
Suntan 70 Dead end 1610 $42,959.00
Ongoing
1
Long Street Cleveland Dead End 2170 $52,514.00
City Wide Street Improvements:
Completed
Lynnbrook Linwood Ave St. Vincent 1188 $83,231
Capital Projects:
Ongoing
Jewella Avenue Mansfield Hollywood See E
DISTRICT G
Completed Overlays:
Street From To Length Cost
Maywood Drive East and West I-49 1020 $55,185
Rose Faith Jefferson Paige 555 $18,244
Barbara Avenue Lyba Greenwood 1975 $45,129
Kentucky Av Fredrick Lakeshore 1671 $49,606
Woodrow St San Jacinto Dead End 590 $15,445
Roundtree Jefferson Paige Faith Combined
Faith Lane Roundtree Dead End 1158 $27,714
McCutchen Milton Darien 1520 $36,659
Laurel Exposition Dead End 732 $27,789
Milton Jewella Thayer 2100 $28,804
th
Klug Pines 70 Westport 4150 $99,893
Trailwood Ter. Santa Monica Pines Road 1464 $53,727
Stonewall Arkansas Exposition 1500 $47,768
Oaktree Parkwood Dead End 220 $9,491
Shirley Francis Woolworth City Limits 4615 $91,266
Westport Pines Road Klug Pines 1650 $124,509
Jefferson Paige Pinecrest City Limits 1600 $67,807
Flournoy Lucas Buncombe Road City Limits 1000 $20,449
th
Meriwether Rd West 70 Mansfield 805 $17,124
Old Blanchard Rd Russell Holcomb 2447 $66,544
Pines Rd St. Lakeshore Jefferson Paige 3625 $57,526
City Wide Street Improvements:
Completed
Lytham Street Newcastle Dead End 1430 $109,777
Newcastle Blvd Bert Kouns Dead End 2385 $183,090
Chadwick Chadwick Trevor 810 $62,182

12
Stoneridge Chadwick Newcastle 650 $49,899
Ongoing
Greenway Street Greenwood Rd Scott 1450 $694,571
OTHER CAPITAL IMPROVEMENT PROJECTS (on-going)
I-49 Landscaping Along I-49 Along 3132 $999,330
97 projects totaling: $19,735,546.27

13
APPENDIX D
2015 ROADWAY IMPROVEMENTS

District A
Asphalt Overlay Programs: Cost
Completed
Milam Street – Douglass to Exposition $241,263
Jefferson Paige Road – Pines Road to I-220 $405,432
Freddie Street – David Raines to Gilliam $74,419
th
5 Street – David Raines to Audrey $210,003
Russell Road – Shreveport Blanchard to Gain Street $247,299
Legardy Street – MLK to Jamison $239,275
Missouri Street – Lakeshore to Stonewall $123,500
City Wide Street Improvements:
Completed
Hersey D. Wilson – Hill Street to Legardy $2,419,848
District B
Asphalt Overlay Programs:
Completed
Kings Highway – Hearne to Linwood Avenue $242,168
Southern Avenue – Mall St. Vincent Southfield $119,048
Mansfield Road – Greenwood to Hearne $193,198
Milam Streets – Douglass to Exposition $241,263
Stoner Avenue – Louisiana Creswell $45,419
Cotton – Marshall to Edwards $25,139
Edwards – Cotton to Travis $58,656
Capital Projects:
Carried over into 2016
*Murphy Street Bridge Replacement (completed) $4,875,000
*Youree Drive at Kings Highway – North (completed) $3,458,520
District C
Asphalt Overlay Programs:
Completed
Southern Avenue – Mall St. Vincent to
$124,323
Pierremont/Southfield
Dixie Gardens – E. Kings Highway to City Limits $120,968
th
Gilbert – 70 to Southfield $236,654
City Wide Street Improvements:
Completed
Carroll Street Annette to Anniston $808,491
Carried over into 2016
st th
Fairfield – 71 to 84 (complete) $220,353

14
Capital Projects:
Carried over into 2016
*Youree Drive at Kings Highway – South (completed) $4,227,080
District D
Asphalt Overlay Programs:
Completed
Ellerbe Road – Overton Brooks to City Limits $203,037
Southern Loop – Wallace Lake Road to Norris Ferry Road $372,974
Overton Brooks – Railroad to Ellerbe Road $175,721
City Wide Street Improvements:
Completed
Grover Street – India to Pomeroy $259,654
Carried over into 2016
th
University at 70 – Intersection (completed) $98,490
st th
Fairfield – 71 to 84 (completed) $730,963
Capital Projects:
Carried over into 2016
th
70 Street Turn Lanes – Intersection (completed) $1,050,352
District E
Asphalt Overlay Programs:
Completed
Linwood Avenue – Bert Kouns to City Limits 185,627
Williamson Way – Hwy 171 to Kingston 378,595
Lotus Lane – Standard Oil Road to Dead End 10,336
Wallace Lake Road – Bert Kouns to Flournoy Lucas 129,576
Crabapple Drive – Baird Road to Kingston 217,807
City Wide Street Improvements
Carried over into 2016
South Kirkwood – Blom to North Kirkwood (completed) $67,147
Kingston Road – Melba to Inner Loop (completed) $283,012
District F
Asphalt Overlay Programs:
Completed
Mansfield Road – Hearne Avenue to Greenwood Road $342,253
th
Buncombe Road – 70 to Cross Timber $30,500
Lotus Lane – Standard Oil Road to Dead End $10,336
Carried over into 2016
th
St. Vincent – 70 to Naomi (completed) $264,600
City Wide Street Improvements:
Carried over into 2016
Huntington Lane (completed) $889,600.00

15
District G
Asphalt Overlay Programs:
Completed
Buncombe Road – Cross Timbers to Bert Kouns $679,760
Woolworth Road – Tanner Drive to city Limits $434,766
Milam Street – Douglass to Exposition $98,577
Flournoy Lucas – Bert Kouns to Pines Road $224,647
Santa Monica – Scenic Drive to City Limits $99,688
Jefferson Paige Road – Pinecrest Mobile home to city
$125,450
Limits
City Wide Street Improvements:
Carried over into 2016
Braelock Drive – Pines Road to Dead End (completed) $185,350
Woolworth Bridge (completed) $248,500
50 projects totaling: $26.8 million
*Constitutes a State DOTD Project