ANALISA PERHITUNGAN GORONG – GORONG BUIS BETON

Ket : Beda Tinggi = 10 %

Analisa Kebutuhan Tenaga dan Bahan


Gorong-gorong Buis Beton
Diameter Panjang Pekerja Tukang Batu Pasir PC Buis Beton
( M3 ( M3 ( ZAK
( CM ) (M) ( HOK ) ( HOK ) ) ) ) ( Buah )
5 21 7 4.9 2.0 13 5
6 21 7 5.0 2.0 13 6
40 7 22 7 5.1 2.1 13 7
8 23 7 5.2 2.1 13 8
9 23 7 5.2 2.1 13 9
10 24 8 5.3 2.2 14 10
5 22 8 5.3 2.2 14 5
6 23 8 5.4 2.2 14 6
50 7 24 8 5.5 2.2 15 7
8 25 8 5.6 2.3 15 8
9 26 8 5.7 2.3 16 9
10 27 8 5.8 2.4 16 10
5 24 8 5.6 2.3 14 10
6 25 8 5.8 2.4 15 12
60 7 26 8 5.9 2.4 15 14
8 27 8 6.0 2.4 15 16
9 28 8 6.1 2.5 16 18
10 30 8 6.2 2.6 16 20
5 28 9 6.3 2.6 16 10
6 29 9 6.5 2.6 16 12
80 7 31 9 6.6 2.7 17 14
8 32 9 6.7 2.8 17 16
9 34 9 6.9 2.8 17 18
10 35 9 7.0 2.9 18 20
5 32 9 7.1 2.9 18 10
6 34 10 7.2 2.9 18 12
100 7 36 10 7.4 3.0 18 14
8 38 10 7.6 3.1 19 16
9 40 10 7.8 3.2 20 18
10 42 10 8.0 3.3 21 20
Keterangan :
= jumlah kebutuhan tenaga kerja dalam satuan Hari Orang
HOK Kerja
= kebutuhan batu belah dalam meter
Batu kubik
= kebutuhan pasir beton dalam meter
Pasir kubik
= kebutuhan semen PC dalam zak ( 50 kg
PC )
= kebutuhan buis beton dalam
Buis Beton buah
Referensi : SNI 2008