BAR CHART SCHEDULE 252 Working Days

ITEM NO. ITEM OF WORK DAYS 1 2 3 4 5 6 7 8 9


1000 Gen. Conditions 7
2000 Siteworks 19
3000 Reinforced Concrete
Foundation 6
Columns 1st 9
Beam, Slab, Stairs 2F 33
Columns 2nd 9
Beam, Slab, Stairs 3F 33
Columns 3rd 9
Beam, Slab, Stairs 3F 33
Ground Slab 6
4000 Masonry 12
7000 Waterproofing 18
8000 Doors and Windows 40
Wall Finish
9220 Plastering 9
9310 Ceramic Tiles 51
9100 Suspended Ceiling 25
9900 Painting 20
6000 Electricals 120
5400 Plumbing 112
Demobilization 7
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
25 26 27 28 29 30 31 32 33 34 35 36