Retention : 5%
Area of Project : 8 ha
SITE PLAN
FUNCTION
Mechanism / method
Neccesary of project Total area that need Mechanism of Can predict the cost
of the project Position of materials Place of temporary
transportation to placement the transfering materials of Project operational
transportation building is setting well
materials to the site plan
and can give the
optimum function
START
Enviroment observation
Accessibility
Determine the temporary project facilities
Exixtence Building
Construction project appropriate with PT.PP plan and standart
Work Method
FINISH
Sumber: http://www.selectplanthire.com
GROUP 1 - OPB PT. PP XXXVII
SITE PLAN FLOW CHART
4 5 6 7 8
3 2 1
1 : Site Office
2 : Barracks
6 3 : Temporary Service 1
9 4 : Security
5 : Gate for Labor
6 : Gate for Equipment
7 : Tower Crane
5
8 : Access for Worker
10
8 3
4
11 1
2
7
Reason :
“The condition of soil is very easy to be change. The soil will be cracked if
exposed by heat and it will be sliding if poured by rain. So it will be hard to find
the hard soil. That’s why bore pile and raft foundation was decided for this
project“
• Advantage
1. Less vibrations, so recommended to preserve the safety of the
adjoining structure.
2. Could be use for poor soil condition
• Disadvantage
1. Installation of cast-in-situ piles requires careful supervision
2. The method is quite cumbersome if compared with concrete spun
pile.
• Advantage
1. Increase the efficiency of progress
2. It can cope with mixed or poor ground condition.
3. It reduces differential settlement.
• Disadvantage
1. Mat foundation requires specific treatment for point loads.
2. Crack occurs if not treated properly.
Determination of
Next Point Point by Surveyor
Concrete Set Up
Casting Equipment
Bore Pile
Installation of Pre Boring
Reinforcement Process
Installation of
Boring Process
Chasing
Intallation the
reinforcement
Control the
Start The Mass
temperature of
Concrete Process
concrete every 1 layer
Waterproofing
Ok?
Reinforcement bar
START
Determination of Coloumn As
Formwork installation
Adjustment
Inspection
NOT OK
OK
Concrete casting
Formwork Dismantling
CURING
• Determination of Coloum
As
Coloumn As is determinated using total
station according to shopdrawing and
measured from nearest benchmark
(BM)
• Coloumn reinforcement
Installation
After coloumn reinforcement steel arranged
in the workshop, it will be installed to the
detereminated place with TC help. Then it will
be tied with
plywood
GROUP 1 - OPB PT. PP XXXVII
Inspection
Make sure the formwok is well oiled to make sure its not stuck to the concrete
Apply super
Check concrete Concrete lifting
bonding
quality with TC
agent
cast in situ
Vibration
Loosen up T-rod
Remove push
pull
Put the
formwork to the
workshop
• Smooth edge
Quality control
• Uniform color
• No segregation
Beam formwork
installation
SHE
Organizing, and Action to reach
the goals in Safety, Health and
Environment of a Project
Environmental Control
GROUP 1 - OPB PT. PP XXXVII
SHE POLICY
3 SHE MEETING
MEVA FORMWORK
REUSABLE MATERIALS
• USING WASTED
CONSTRUCTION MATERIALS
FOR STOCK CAR STOPPER
• USING WASTED STEEL REBAR
FOR SIMPLE COLUMN
• USING WASTED STEEL REBAR
TO BUILD TEMPORALLY OFFICE
WASTED MATERIALS AND SUPPORTING TOOLS