Escolar Documentos
Profissional Documentos
Cultura Documentos
Edward Nowatzki, P.E., Fellow, ASCE1 and Naresh Samtani, P.E., Member, ASCE.2
INTRODUCTION
The city of Tucson is located in the Sonoran Desert in a broad basin surrounded by
four mountain ranges. The general geologic setting of the Tucson Basin is typical of
the Basin and Range Province that constitutes the southwestern half of the state of
Arizona. The basin is filled with thick sequences of relatively young sediments, with
depth to bedrock increasing laterally from the hard rock ranges toward the center of
the basin where sediments are up to 500 m thick. The site is located on the edge of an
alluvial fan at the base of the foothills of the Santa Catalina Mountains just north of
the city of Tucson. Fig. 1 shows an overview of the site prior to construction
including two of the impacted structures at the Altamira Apartment complex.
1
Principal Engineer, NCS Consultants, 640 W. Paseo Rio Grande, Tucson, AZ
85737 USA; eanowatzki@msn.com;
2
President, NCS Consultants, 640 W. Paseo Rio Grande, Tucson, AZ 85737 USA
-1- Nowatzki & Samtani
As part of its scope of work under an “on-call” contract with PCDOT, Envirotech
Southwest, LLC, (ESW) of Tucson, AZ researched the local literature to obtain
information on the geotechnical properties of subsurface soils on or near the site. The
quality of much of the existing data was not adequate for the proposed project.
Therefore, ESW contracted with AGRA Earth and Environmental, Inc. (AGRA) to
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
Fig.1 Overview of site prior to construction with apartment complex on bluff and
River Road in the foreground.
DESIGN CONSIDERATIONS
Public Participation
The soil nail wall system was designed to blend in with the natural surroundings of
the site in accordance with guidelines established by the Tucson Citizens Advisory
Committee (TCAC). In the final design the architectural facing incorporated artificial
naturalistic rockwork and sculpted shotcrete that mimicked eroded banks along
nearby portions of the River Road corridor. The look of the natural slopes is shown
in Fig. 2.
Fig. 3 shows a plan view of the site with the final configuration of the soil nail wall
superimposed upon it. As indicated in the figure, only a small portion of the deck
area around the swimming pool was lost because of the soil nail wall system. With
the conventional reinforced concrete (RC) retaining wall system originally proposed,
the swimming pool, recreation center, and the apartment building east of them would
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
have had to been totally replaced. Except for Boring B-1 advanced by AGRA, the
other borings listed in Table 1 are not shown in Fig. 3 because they are not within the
work site. They are included only to show the range of values that can be expected
for the variably-cemented soils typically encountered in the Tucson Basin.
Fig. 4 Access road to top level of West wall – Campaña Drive in foreground.
DESIGN
Project Scope
The design and construction of the soil nail wall systems on the two bluffs near 1st
Avenue were part of a widening and realignment project along River Road, a major
arterial roadway in Tucson, Arizona. In addition to numerous conventional RC
cantilever retaining walls, the project included two near-vertical soil nail walls
ranging in height from 2 to 3-m. meters at their ends to more than 17-m. at their
highest point. The west wall is approximately 130-m. long and the east wall is about
156-m. in length. The finished area of the walls is approximately 3,530 m2.
Design Approach
Earth retention systems considered by PCDOT in the early planning stages for this
project included crib walls, mechanically stabilized earth (MSE) walls, and a tiered
system of standard RC cantilever walls. The costs of replacing impacted structures at the
Altamira Apartments, including land acquisition costs, were prohibitive for all of these
systems. A soil nail wall system was found to be most cost-effective. In addition, its
architectural facing appealed to a citizen’s advisory group. The soil nail system was
designed in accordance with procedures described in the Manual for Design &
Construction Monitoring of Soil Nail Walls (FHWA, 1998). The guidelines
contained in FHWA’s design manual are considered the standard of practice for soil
Soil Properties
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
The following soil parameters were used in the design of the soil nail wall system.
These values were assigned based on the field and laboratory test results presented in
Table 1.
Effective cohesion, c´ = 24 kPa
Effective friction angle, φ´ = 33º
Total unit weight, γ´ = 18 kN/m3
The lead author, while a principal at ESW, performed the initial design based on an
estimated pullout resistance of 14.6 kN/m. ESW’s design called for nine (9) rows of
18.3-m. long cased nails (# 8 bars centered in 101.6-mm. diameter grout holes)
installed at an inclination of 15º on a 1.524-m. x 1.524-m. grid. For the purpose of
design, surcharges based on loads outlined in the Uniform Building Code (ICBO,
1994) were added to the crest of the wall at the locations of the swimming pool deck
and apartment building. The top row of nails in the vicinity of the swimming pool
was inclined at 30º in order to avoid hitting the pool substructure.
The ESW design was put out to bid by PCDOT. Only pre-qualified drilling
contractors were invited to respond to the bid. Malcolm Drilling Co., Inc. (MCI) of
Vista, CA, one of the specialty contractors to submit a bid, proposed a value
engineered (VE) design developed by their sub-consultant Ground Support, PLLC
(GS) of Redmond, WA. GS’s design was based on an estimated pullout resistance of
29.2 kN/m that was subsequently confirmed by verification pullout tests conducted to
twice the design load. The value-engineered design modified the original design by
calling for nine (9) rows of variable diameter, self-drilling/grouting nails (IBO/Titan
40/20, 30/11) of variable length (4.877-m. to 15.24-m.) installed at an inclination of
15º on a 1.829-m. x 1.829-m. grid. The dual numbering of the hollow IBO/Titan
nails refers to the outside/inside diameters in mm. The 40/20 rod is equivalent to a #
9 bar in terms of nominal cross sectional area. The 30/11 rod has a cross sectional
area that is approximately the average of a # 7 and # 8 bar. The rods are threaded and
have “purple marine” epoxy coating for corrosion protection. In both designs the top
row of nails was assumed to be within 1-m. of the top of the slope, and in the area of
the pool they were horizontally offset from the basic nail pattern and inclined at 30-
degrees to avoid hitting the pool substructure. In both designs the toe of each soil
nail wall extends a minimum of 0.61-m. below final grade. The elevation view of the
mid section of the west wall in the area of the swimming pool is shown on Fig. 5.
IBO/Titan nails have a hollow core so as to allow injection of grout through the
center during installation. A sacrificial drill bit larger in diameter than the nail
advances the hole. Grout is pumped under low pressure through the hollow core of
-6- Nowatzki & Samtani
grout” nails. This was reflected in greater pullout resistance during the verification
tests and resulted in overall cost-savings. An attractive feature of the IBO/Titan
system is that the installation is in essence a cased method. It was preferable to a wet
rotary method on this project because wet drilling may have caused destabilization of
the nail hole and necessitated the use of casing. The value-engineered design was
accepted by PCDOT and resulted in savings of over $190,000.
Corrosion Protection
The soils in the vicinity of the proposed soil nail slopes were found to have low to
no corrosion potential. In accordance with FHWA guidelines, in the original design
the soil nail tendons were specified as epoxy-coated with a minimum of 25.4-mm
grout cover all around, but not double encapsulated. The “purple marine” epoxy-
coated IBO/Titan nails used in the VE design satisfied this requirement. Additional
corrosion protection was obtained from the minimum 102-mm diameter grout column
specified by PCDOT to assure adequate pullout resistance.
connected to footing drains and weep holes that drain to the wall face. A concrete-
lined gutter or V-ditch was installed along the base of the wall to collect drainage
from weep holes and runoff from the face of the wall and direct them away from the
site. Additional subsurface drainage was provided under the swimming pool by
standard horizontal drains that are typically placed above impermeable clay layers to
relieve hydrostatic pressure that may result from perched water. A 152-mm high
PVC water-stop was installed continuously on the top of the shotcrete construction
facing to prevent water from seeping between it and the architectural facing.
Shotcrete Facing
The design of the shotcrete construction facing was checked for punching shear and
flexure in accordance with FHWA (1998) requirements. The facing design utilized
27.58-MPa (minimum 28-day strength) shotcrete with a minimum shotcrete thickness
of 102-mm. The shotcrete was reinforced with two continuous # 4 bars in both the
horizontal and vertical direction at each nail head and 6 x 6 - W1.4 x W1.4 welded
wire mesh. Bearing plates connecting the nails to the facing were specified at 22.86-
cm. x 22.86-cm. x 1.9-cm. at a minimum. All steel was Grade 60.
CONSTRUCTION
Fig.7 Raveling sand and gravel on 4th Fig. 8 Void behind soil nail wall face
bench of West wall from raveling of sand and gravel
the unbonded length as an acceptance criterion. Each test also included a 10-minute
creep test under maximum load with a failure criterion based on maximum movement
of 1-mm. The results of the tests equaled or exceeded FHWA (1998) acceptability
criteria.
Wall Movement
Because of the proximity of major structures to the edge of the bluff, potential
movements during and after construction were major concerns. A comprehensive
finite element analysis was performed as part of the original design to assess the
stability of various slope configurations and to estimate the magnitude of potential
horizontal and vertical ground movements at the crest of the wall and at strategic
locations within the existing apartment complex (DeNatale, 1998a, 1998b). The
analyses were performed by utilizing a two-dimensional finite element computer code
and a basic isotropic, linear-elastic constitutive model for the soil. A minimum value
of elastic modulus = 21 Mpa was used based on interpretation of data presented in
Table 1. The results of the finite element analyses indicated that vertical ground
movements in the vicinity of the swimming pool and apartment buildings because of
construction of the soil nail wall should be less than 25-mm. Horizontal and vertical
movements at the crest of the walls were calculated to be approximately 25-mm and
38-mm, respectively. These values are within the range of values expected at the
crest of an 18-m high wall in dense granular soils (FHWA, 1998). The results of the
analyses were used to develop an instrumentation program to monitor actual
movements before, during, and after construction.
Monitoring Plan
ARCHITECTURAL FACING
Fig. 9 shows the wall as it appears today. The artificial rockwork and sculpted
shotcrete facing shown in Fig. 9 compare favorably with the natural slopes shown in
Fig. 2. Construction of both walls started in June 2001. The shotcrete construction
facing for both walls was done concurrently and the walls were completed in October
2001. The architectural facing was done by the Larson Company (LC) of Tucson,
AZ one wall at a time and was not completed until June 2002.
CONCLUSIONS
The design guidelines and procedures contained in the Manual for Design &
Construction Monitoring of Soil Nail Walls (FHWA, 1998) provide the geotechnical
engineer with the tools needed to design soil nail walls. Commercially available
computer codes enhance the engineer’s ability to perform such designs. However,
-11- Nowatzki & Samtani
sands, gravels and cobbles that displayed standard penetration blow counts (N) in
excess of 30 blows/foot. Such high values of N have meaning for foundation analysis
and design where that type of soil remains confined under load just as it was during
the SPT. However, such high values are meaningless when cuts are made into the
same type of soil as is done during the installation of a soil nail wall system.
Confinement is destroyed under such conditions and dry, lightly- to non-cemented
granular soils will run with even the slightest disturbance as they did in this case. In
hindsight, the use of water-soaked berms throughout construction would have been
one way to circumvent potential raveling problems on this project.
ACKNOWLEDGMENTS
The authors wish to acknowledge the contributions of Mr. Robert Johnson, P.E., of
PCDOT and Dr. Jay S. DeNatale, P.E., of the California Polytechnic State University
in San Luis Obispo.
REFERENCES