PROGREES STATUS REPORT AS OF 28th  January 2018

Project No  :‐ GTC 644E/ 2014 Project Start Date  11‐Aug‐15


Project Name  :‐ Extension Distribution of Network Phase 06, Package E  Project Completion  Date (REV) 2‐Dec‐18
Clinent  :‐ Kahramaa  Project Duration  1209
Consultant  :‐ KEO Internatinal Consultant  M‐01  Completion Date  21‐Jun‐18
Contractor  :‐ AALCO Group M‐02  Completion Date  2‐Dec‐18

PROJECT  TIME STATUS 
Contract Amout  174,200,000.00
Varaiation Order  Nil OVERALL  MILESTONE 01 MILESTONE 02
13.78%
Value of Varaiation order  Nil 25.48%
25.48%
74.5% 74.5%
Valuation No   18
86.2%
Work Done  51,272,194.29
Amount of invoiced  47,224,662.23
Elapsed Time  % Remaining Time % Elapsed Time  % Remaining Time % Elapsed Time  % Remaining Time %
Approved Amount  47,224,662.23

Construction Phase Progress 
120.00%
This Weeks Progress Cummaltive Progress
Cumm Plan % , 100.00%
100.00% Planned Actual Planned Actual

1.01% 0.47% 100.00% 46.27%


80.00%

Cumm Actual %
Variance -0.54% Variance -53.73%
Percentage  %

Cumm Plan %
60.00%

Cumm Actual % 46.27
Actual
40.00% Cummaltive Progress

This Weeks Progress

20.00%
Planned

0.00%
0.00% 50.00% 100.00%

Construction S‐Curve (WHERE FULL CLEARANCE AVAILABLE)
Physcial Progress Each Site 
Length  This Period  Cummulative  Actual  120.00%
Project Area  BL Start  BL Finish Actual Start  Status
(m) Plan  Actual  Variance   Plan  Actual  Variance   Finish
Milestone 01
Garafat Rayyan  1206 100.00% 100.00% 14‐Jan‐15 16‐Apr‐16 22‐Feb‐16 Completed  100.00% 98.75%
Wadi Aba Seela  3422 100.00% 100.00% 29‐Nov‐15 17‐Apr‐16 8‐Dec‐16 Completed  Cum Plan % 94.73%
90.72%
Umm Slal Ali ‐01 242 100.00% 100.00% 25‐Jan‐16 4‐Apr‐16 30‐Mar‐16 14‐Jun‐16 Completed  Cum Actual % 86.52% 81.93%
82.58%
Umm Slal Ali ‐02 1399 8.00% 2.50% ‐0.50% 93.00% 95.00% 27‐Jan‐16 3‐May‐16 ongoing  80.00% 78.84%
77.01%
Umm Slal Ali‐03 529 100.00% 100.00% 18‐Feb‐16 21‐Apr‐16 25‐02‐16 Completed  Percentage%  70.87% 75.52%
Al Refaig  7441.5 7.00% 5.00% ‐2.00% 44.00% 57.00% 15‐Nov‐16 30‐Jul‐16 on going  65.08% 72.49%
69.33%
Milestone 02 60.00% 59.31% 65.80%
54.52% 60.56%
58.69%
Lebsayyer part 01 12757 100.00% 100.00% 13‐Feb‐16 4‐Dec‐16 14‐Feb‐16 Completed  51.52%
49.08%
46.70% 53.89%
AL Galeetha  2401 100.00% 100.00% 14‐Jan‐16 30‐Nov‐16 27‐Mar‐16 Completed 43.72% 49.54%
Umm Birka  5224 9.00% 4.00% ‐5.00% 85.00% 74.00% ‐11.00% 19‐Apr‐16 27‐Oct‐16 On going  40.00% 38.73% 46.34%
36.18% 42.91%
40.72%
32.49%
Al Gharafa Nort A 1286 15.00% 1.00% ‐14.00% 95.00% 74.00% ‐21.00% on going  29.76% 36.52%
34.72%
25.68% 31.58%
Al Gharafa Nort B 331 Pending  22.85% 29.62%
20.00% 20.35% 25.54%
Zekreet & Broog  6319 100% 100.0% 20‐Mar‐16 22‐Oct‐16 1‐May‐16 completed  14.73%
22.74%
18.89%
Al Ebb  305 on going  7.22% 11.57%
2.70%
Lebsayyer Part 02 6750 3.00% 0.50% ‐2.50% 98.00% 81.00% ‐17.00% 2‐Feb‐17 on going  0.00% 0.56%
0.01% 4.59%
2.20%
30‐Nov‐15

30‐May‐16

30‐Sep‐16
30‐Nov‐16

30‐May‐17

30‐Sep‐17
30‐Nov‐17
30‐Jan‐16
30‐Mar‐16

30‐Jul‐16

30‐Jan‐17
30‐Mar‐17

30‐Jul‐17
0.83%
0.44%
0.11%
Umm Slal Ali  202 100.00% 100.00% 27‐Dec‐16 10‐Mar‐17 Completed 
Al Khesaha  5617 100.00% 100.00% 20‐02‐2017 Completed 

Lebsayyer Lewaijiya  8749 100.00% 100.00% 0.00% 15‐Nov‐16 Completed  Month


Physcial 
Length 
Excavation  Pipe Laying  1st Layer Backfilling  9 Bar Test 
Pipe  Length (m) (m)
Available 
Diameter  This  This  Cummulati This  Cummulativ This  Cummul
BOQ Scope of  Previous  Cummulative  % Previous % Previous % Previous %
(mm)  Period Period ve  Period e  Period ative 
work 
100 10078 7122 6375 0 6375 63.26% 6251 0 6251 62.0% 6182 66 6248 62.0% 5966 0 5966 59.20%

150 20694 19238 19328 0 19328 93.4% 18973 0 18973 91.7% 17857 0 17857 86.3% 16233 0 16233 78.44%

200 13179 14658 13859 0 13859 105.2% 13262 386 13648 103.6% 9805 880 10685 81.1% 6404 0 6404 48.59%

300 32589 19739 19799 275 20074 61.6% 16246 423 16669 51.1% 14708 0 14708 45.1% 11470 0 11470 35.20%

400 36051 8646 7143 55 7198 20.0% 6685 0 6685 18.54% 5990 0 5990 16.6% 689 0 689 1.91%

600 2401 3874 3277 175 3452 143.8% 2515 45 2560 107% 2402 0 2402 100% 2402 0 2402 100%

1200 8 8 8 0 8 100.0% 8 0 8 100% 8 0 8 100% 8 0 8 100%

Total  115000 73285            505              70,294           854      64,794           946         57,898        ‐   43,172

@ Ras Al Noof, Surrounding @ Waterlogged Area  @ Al Refaig  , Pipe laying  @ Ras Al Noof  , Final  Layer Backfilling  @ Lebsayyer , W.P for Chamber Wall @ Rawdath Razeed , Pipe Laying 


The status of project Area which was received from Kahramaa up to 27th January 2018

Project Name :‐Extension Distribution of Network, Phase 06 – GTC 644 ‐Package E                          

Original Scope of Work                                                                                                                                                                                          115 km
Length of RO and Other Permits Cleared Area (M1 & M 2)                                                                         86.396 Km
Length of MME Rejected                                                                                                                                  1.779 Km
Length of issues and under discussion with Kaharamaa Planning Department                                   10.652 Km
Dele on of Area from Scope of work                                                                                                          34.571  Km
5

RO and Other Permits Cleared Area

1200 Dia
100 Dia

150 Dia

200 Dia

300 Dia

400 Dia

600 Dia

Length
Total 
Milest
Site/Area Drawing No  Status
one

1 Garrafat Al Rayyan NDS‐12BP‐011 415 316 475 1,206 Commissioned 


2 M‐01 Umm Slal Ali ‐Area ‐1 NDS‐12BP‐013 242 242 Commissioned 
3 Wadi Aba seleel NDS‐11F‐108 RevB 6 39 1135 1630 612 3,422 Commissioned 
4 Lebsayyer ‐ Part 01 NDS‐12BP‐003  8268 2205 2295 12,768 Commissioned 
5 AL Ghaleeda NDS‐12F‐047 Rev 2 2401 8 2,409 Commissioned 
6 Zekreet & Broog 72‐ 05‐00d 385 2757 6 3232 5 13 6,398 Commissioned 
7 Lebsayyer & Lewaijiya 80‐15‐00b 55.92 2070 2370 4,496 Commissioned 
M‐02
8 Naga Al Mamlaha (HDPE) NDS‐16F‐012a 890 890 Commissioned 
9 Rawdath Egdaim NDS‐17F‐BP03 770 770 Commissioned 
10 Umm Slal Ali ‐Area ‐4  NDS‐16F‐BP001   202 202 Commissioned 
11 Umm Slal Ali‐ Area 3 NDS_13F_BP16a 95 434 529 Commissioned 
Al Keesha (70/20/00) 70‐20‐00
13 3565 776 842 568 5,751 Completed ‐ Not Commissioned 
14 M‐01 Umm Slal Ali ‐ Area 2 NDS_13F_BP15b 744 28 627 1,399 95 % Completed 
15 Al Refaig 72/04/00  7445 7,445 57 % Completed 

Lebsayyer‐ Part 02 NDS‐12BP‐003 
17 1094 5668 12 6,774 81% Completed 
18 Ras Al Noof (New Proposal ) 74/28/00  27 3965 3  3,995 78% Completed 
19 Gharafa North A NDS‐DMA‐512A 10 64 1,213 1,287 68% Completed 
20 Umm Birka NDS‐12F‐046d 1,976 3,222   5,198 74 % Completed 
Lebsayyer & lewaijiya 80‐15‐00b
22 4296 4,296 Completed ‐ Not Commissioned 
23 M‐02 Al Wukair  91/23/00 Rev B 1390 1,390 20% Completed 
24 Mekaines & Rawdath Rasid  82/12/00 Rev A 2361 58 2,419 23% Completed 
WadiAba Seleel 91/21/00 Rev E
26 2 4 627 3902 4,535 New Site Received On 21‐01‐2018
Al Refaig  72/04/00 Rev E 
27 3213 3627 6,840 New Site Received On 21‐01‐2018
Feereej Absel Aziz  14/03/00
28 882 491 362 1,735 New Site Received On 21‐01‐2018

Total Length  (Meter) HDPE Pipe  890

Total Length  (Meter) DI Pipe  10329 23360.92 15020 20366 12548 3874 8 86,396

MME Rejected ‐ Hold 

Si. Mile  Site/ Area Drawing No   Total 


No stone 100 Dia 150 Dia 200 Dia 300 Dia 400 Dia 600 Dia 1200 Dia. Length Status
Simsima NDS‐12BP‐014 RevA
1 M‐02 209 491 741 338   1,779 MMUP Rejected due to no ROW

Total Length  (Meter) 1,779

Corridor issues Discussion with Kahramaa Planning Department ‐ Hold

Mile   Total 
Site Area  Drawing No 
Si. stone 100 Dia 150 Dia 200 Dia 300 Dia 400 Dia 600 Dia 1200 Dia. Length Status

  MME Approved 600mm Line only 
2 Ras Al Noof  NDS‐13F‐017B 4942 2344 7286 and Corridor not yet confirm, DR 
under process ‐ Oh Hold 

Al Ebb  ‐ Zone 70  NDS‐15F‐BP46     
M‐02 305 305 On Holddue to Site Obstruction  
Under discussion with M/s. 
Furssiya  54‐10‐00 C Ashghal & Water Planning 
7 13 21 1622 177 1,840 Department. 

Rawdat Al Jahaniya  51/18/00 Rev A Ro Under Process ‐ WP Hold due 


18 14 525 664 1,221 to 350 m out off ROW. 
Total 
Length   10652
Deletion of Area
Si. Mile  Total 
No stone Site/ Area  100 Dia 150 Dia 200 Dia 300 Dia 400 Dia 600 Dia 1200 Dia. Length Status 
1 Ghaleetha ‐ Part 02 4084 8326 12410
Letter Reff:‐ TW/6786/2016
 2 Wadi Al Ekresh & Al Slemiya Village
890 5800 5059 11749
 Gharrafat Al Rayyan‐70 (NDS‐
3
M‐02  16F‐BP001) 172 219 391 Transferred to Boom Contractor 
4 Gharafa North A  94 81 8 1357 1816 3356 TW/TWS/6311/2017
5 Heenath Al Seela 566 1902 3821 45 6334
6 Al Gharrafa North B 218 113 331
Total length (Meter) 266 1756 7928 14321 10255 45 0 34571