Konsorsium PP – Betasurya ENGINEERING PROGRESS CALCULATION REPORT

Tatagraha
Jl. TB. Simatupang No. 57 Pasar Rebo Jakarta
PROYEK PLTGU TANJUNG UNCANG 100-120 MW
Telp. 021-840 3902 Fax. 021-840 3992
epc@pt-pp.com
BATAM

I. DETAIL ENGINEERING

WEIGHT FACTOR PROGRESS (%) CUMMULATIVE PROGRESS EARNED (%)


NO. DESCRIPTION Previous
LEVEL 2 LEVEL 3 LEVEL 4 This Week Cumulative LEVEL 2 LEVEL 3 LEVEL 4
Week
I.1. Design Basis 5.000% 5.000%
I.1.1 Design Basis Report 25.000% 25.000%
I.1.1.1 Design Basis Report 100.000% 100.000% 0.000% 100.000% 100.00%
I.1.2 Gas Turbine Generator 25.000% 25.000%
I.1.2.1 Gas Turbine Data 10.000% 100.000% 0.0000% 100.000% 10.000%
I.1.2.2 Typical Start and Trip Characteristics SGT-800 50 MW 10.000% 100.000% 0.0000% 100.000% 10.000%
I.1.2.3 Norminal Performance Data 10.000% 100.000% 0.0000% 100.000% 10.000%
I.1.2.4 Auxiliary Power Consumption at Different condition 10.000% 100.000% 0.0000% 100.000% 10.000%
I.1.2.5 Syatem Desciption -HVAC for battery module SAB 10.000% 100.000% 0.0000% 100.000% 10.000%
I.1.2.6 Specification for Gaseous Fuel 10.000% 100.000% 0.000% 100.000% 10.000%
I.1.2.7 Classification of Hazardous Area 10.000% 100.000% 0.000% 100.000% 10.000%
I.1.2.8 Surface Treatment 10.000% 100.000% 0.000% 100.000% 10.000%
I.1.2.9 Guidelines for Water and Steaam Quality 10.000% 100.000% 0.0000% 100.000% ` 10.000%
I.1.2.10 Nominal Sound Levels for Gas Turbine 10.000% 100.000% 0.0000% 100.000% 10.000%
I.1.3 Heat Recovery Steam Generator 25.000% 25.000%
I.1.3.1 HRSG System Description 100.000% 100.000% 0.000% 100.000% 100.00%
I.1.4 Steam Turbine Generator 25.000% 25.000%
I.1.4.1 Technical Description Siemens STG 100.000% 100.000% 0.000% 100.000% 100.00%
TOTAL DESIGN BASIS
I.2 Manufacture Design 45.000% 45.000%
I.2.1 Gas Turbine Generator 33.333% 33.333%
I.2.1.1 Customer Document List 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.2 Sub-Vendor List 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.3 Auxiliary System Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.4 Layout Unit Control Panel 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.5 E&C Module Internal Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.6 Foundation Design Requirements 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.7 SGT-800 Foundation 50 Hz embedded detail plate & fixtures 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.8 Foundation General Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.9 Foundation Loads Intensity 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.10 Foundation Loads Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.11 General Arrangement and Layout Drawings from Selling Phase 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.12 General Arrangement Drawing 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.13 Network Map (3 Sheet) 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.14 Removal and Service Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.15 Site Electrical Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.16 Turbine Foundation Design Requirements 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.17 Torsional and Lateral Analysis Report 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.18 Transport and lift gas turbine skid 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.19 Circuit Diagram 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.20 Communication Guideline (DCS) OPC 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.21 Control System Overview 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.22 Location and Delivery Limits 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.23 Delivery Limits (MV Electrical) 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.24 Earthing 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.25 Electrical Load List 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.26 Generator Relay Protection Setting List 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.27 Installation Data 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.28 Connection cable internal 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.29 Sequence Diagram 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.30 Signal Exchange List (HW) 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.31 Signal Transfer List (DCS) OPC 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.32 Single Line Diagram LV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.33 Single Line Diagram MV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.34 Perfomance test procedure 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.35 Correction Procedure for performance test 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.36 Commissioning Spare Parts List 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.37 Operation & Maintenance Manual - As Built 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.38 Operation & Maintenance Manual - As Designed 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.39 Procedure for emission guarantee test 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.40 List of Special Tools for maintence 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.41 Manufacturing Record Book 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.42 Project Quality Plan 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.43 Quality Control Plan 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.44 Surface Treatment 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.45 Normal Sound Level For Gas Turbine 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.46 Terminal Points Drawing 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.47 Terminal Points Exhaust 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.48 Classification of Hazardous Areas 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.49 Specification for Gaseous Fuels 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.50 Guidelines for Water and Steam Quality 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.51 Hazardous Area Layout 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.52 Sound measurement procedure 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.53 Instrument and Operating Air Consumption/Instrument and operating air system 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.54 Instrument List - Air Intake Filter System MBL 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.55 Instrument List - Compressor Washing System SDB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.56 Instrument List - Cooling and Sealing Air System MBH 10 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.57 Instrument List- Drying System Stationary MPS 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.58 Instrument List - Fire Detection and Extinguishing System SGJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.59 Instrument List - Gas Detection System SFY 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.60 Instrument List - Gas Fuel System MBP 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.61 Instrument List - Gas Turbine System MBA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.62 Instrument List - Gear System MBK 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.63 Instrument List - Generator System MKA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.64 Instrument List - Instrument Air System QFA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.65 Instrument List - Lube Oil System MBV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.66 Instrument List - Starting System MBJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.67 Instrument List - Ventilation System SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.68 Instrument List - Ventilation System GT- Enclosure SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.69 Lube Oil Specification 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.70 Mechanical Component List - Air Intake Filter System MBL 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.71 Mechanical Component List - Compressor Washing System SDB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.72 Mechanical Component List - Cooling and Sealing Air System MBH 10 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.73 Mechanical Component List - Drying System Stationary MPS 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.74 Mechanical Component List - Fire Detection and Extinguishing System SGJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.75 Mechanical Component List - Gas Fuel System MBP 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.76 Mechanical Component List - Gas Turbine System MBA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.77 Mechanical Component List - Gear System MBK 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.78 Mechanical Component List - Generator System MKA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.79 Mechanical Component List - HVAC for E&C Module SAC 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.80 Mechanical Component List - Instrument Air System QFA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.81 Mechanical Component List - Lube Oil System MBV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.82 Mechanical Component List - Pulsation Measurement System MBX 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.83 Mechanical Component List - Starting System MBJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.84 Mechanical Component List - HVAC for Battery Module SAB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.85 Mechanical Component List - Ventilation System SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.86 P&ID Air Intake Filter System MBL 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.87 P&ID Compressor Washing System SDB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.88 P&ID Cooling and Sealing Air System MBH 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.89 P&ID Drying System Stationary MPS 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.90 P&ID Fire Detection and Extinguishing System SGJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.91 P&ID Gas Detection System SFY 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.92 P&ID Gas Fuel System MBP 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.93 P&ID Gas Turbine System MBA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.94 P&ID Gear System MBK 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.95 P&ID Generator System MKA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.96 P&ID HVAC for E&C Module SAC 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.97 P&ID Instrument Air System QFA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.98 P&ID Legend for Symbols 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.99 P&ID Lube Oil System MBV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.100 P&ID Pulsation Measurement System MBX 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.101 P&ID Starting System MBJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.102 P&ID Ventilation System Battery Module SAB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.103 P&ID Ventilation System GT-Enclosure SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.104 Recommended Products for Compressor Cleaning 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.105 Setting List - Air Intake System MBL 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.106 Setting List - Compressor Washing System SDB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.107 Setting List - Cooling and Sealing Air System 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.108 Setting List - Drying System MPS 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.109 Setting List - Fire Detection and Extinguishing System SGJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.110 Setting List - Gas Detection System SFY 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.111 Setting List - Gas Fuel System MBP 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.112 Setting List - Gas Turbine System MBA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.113 Setting List - Gear System MBK 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.114 Setting List - Generator System MKA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.115 Setting List - HVAC for E&C Module SAC 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.116 Setting List - Instrument Air System QFA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.117 Setting List - Lube Oil System MBV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.118 Setting List - Starting System MBJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.119 Setting List - Ventilation System Battery Module SAB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.120 Setting List - HVAC for Battery Module SAB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.121 Setting List - Ventilation System GT-Enclosure SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.122 Setting List - Ventilation System SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.123 System Description - Air Intake Filter System MBL 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.124 System Description - Compressor Washing System SDB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.125 System Description - Control System CRB CWA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.126 System Description - Cooling and Sealing Air System MBH 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.127 System Description - Drying System Stationary MPS 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.128 System Description - Fire Detection and Extinguishing System SGJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.129 System Description - Gas Detection System SFY 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.130 System Description - Gas Fuel System MBP 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.131 System Description - Gas Turbine System MBA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.132 System Description - Gear System MBK 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.133 System Description - Generator System MKA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.134 System Description - HVAC for E&C Module SAC 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.135 System Description - Instrument Air System QFA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.136 System Description - Lube Oil System MBV 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.137 System Description - Protection System CAA 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.138 System Description - Pulsation Measurement System MBX 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.139 System Description - Starting System MBJ 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.140 System Description - Turbine Governing System CJP 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.141 System Description - Ventilation System Battery Module SAB 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.142 System Description - Ventilation System GT- Enclosure SAG 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.143 Technical Delivery Terms for Lube Oil 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.144 Utility Requirements 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.145 Packing List 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.146 GT Storage and Preservation 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.147 Shipping Information 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.148 EMBEDDED STEEL 01 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.149 EMBEDDED STEEL 02 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.150 EMBEDDED STEEL 03 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.151 EMBEDDED STEEL 04 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.152 EMBEDDED STEEL 05 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.153 EMBEDDED STEEL 06 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.154 EMBEDDED STEEL 07 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.155 EMBEDDED STEEL 08 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.156 EMBEDDED STEEL 09 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.157 EMBEDDED STEEL 10 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.158 EMBEDDED STEEL 11 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.159 EMBEDDED STEEL 12 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.160 EMBEDDED STEEL 13 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.161 EMBEDDED STEEL 14 0.633% 100.000% 0.000% 100.000% 0.633%
I.2.1.162 EMBEDDED STEEL 15 0.633% 100.000% 0.000% 100.000% 0.633%
TOTAL MANUFACTURE DESIGN - GTG 100.000%
I.2.2 Heat Recovery Steam Generator 33.333% 33.333%
I.2.2.1 Site conditions & utility data 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.2 General arrangement right and rear view 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.3 General arrangement left and front view 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.4 General arrangement top view 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.5 General arrangement isometric view 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.6 General arrangement top view AT EL+1.400 and top view AT EL+21.300 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.7 Purge volume calculation 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.8 Process flow diagram 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.9 Legend, Symbols and abbreviations 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.10 Legend, symbols and abbreviations 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.11 Legend, symbols and abbreviations 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.12 P&ID Economiser system(P&ID Economiser Pre-Heater system ) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.13 P&ID Economiser system 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.14 P&ID LP Boiler System 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.15 P&ID HP Boiler System 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.16 P&ID LP Superheater system 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.17 P&ID HP Superheater System 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.18 P&ID HRSG Drain & Vents 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.19 P&ID BlowDown System 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.20 FLue Gas System 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.21 P&ID HRSG Instrument Air Sytem 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.22 Pressure parts specification 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.23 HRSG system description - process description 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.24 Arrangement drawing blow down tank 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.25 General arrangement HP steam drum 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.26 Arrangement Internals HP steam drum 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.27 Transport drawing HP steam drum 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.28 Instructions for installation manhole gaskets HP and LP steamdrum 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.29 Outline of LP Drum 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.30 Platform support layout 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.31 General arrangement insulation - HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.32 Arrangement drawing inlet duct left side & right side view 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.33 Arrangement drawing inlet duct top & bottom view 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.34 Details inlet duct HRSG (1) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.35 Details inlet duct HRSG (2) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.36 Details inlet duct HRSG (3) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.37 Arrangement drawing SCR-Duct HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.38 Sections SCR-duct part 1 HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.39 Sections SCR-duct part 2 HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.40 Mainstack HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.41 Asembly drawing stack 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.42 Sub asembly 1 stack 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.43 Sub asembly 3 stack 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.44 Sub asembly 4 stack 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.45 Asembly Drawing platform stack 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.46 Basic of design steel structure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.47 Calculation foundation loads 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.48 Arrangement drawing staircase 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.49 Arrangement Drawing Topplatform at EL.+21.170 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.50 Arrangement drawing platform SCR-duct AT EL.+17.300 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.51 Arrangement drawing Escape route 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.52 Arrangement drawing platforms stack 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.53 Arrangement drawing platforms drums and manhole platforms 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.54 Arrangement Drawing Silencerframes 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.55 Typical details platforms, ladders,grating & stairs 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.56 Calculation anchor bolts and foot plates 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.57 Foundation & loading plan HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.58 Anchors and embedded parts HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.59 Foundation secodary steel supports and pipe supports HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.60 Stack template - details HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.61 MTO for stack template 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.62 Line List ( Grouped on P&ID & Sorted on KkS ) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.63 Piping Material Specification 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.64 Terminal point list 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.65 Preheater outlet line 01HAC20BR030 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.66 Preheater outlet line 01HAC20BR030 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.67 HRSG front sheet isometrics 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.68 HRSG fabrication tolerances piping 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.69 HRSG isometric legend standard 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.70 HRSG typical piping weld details 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.71 HRSG dimensions of welding ends 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.72 HRSG index sheet isometrics 1 of 2 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.73 HRSG index sheet insometrics 2 of 2 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.74 LP re-circulation line suction 01HAC20BR035 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.75 LP re-circulation line cv bypass 01HAC20BR040 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.76 LP re-circulation line discharge 01HAC20BR045 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.77 Preheater bypass line 01HAC20BR050 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.78 Preheater drain line 1 01HAC20BR410 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.79 Preheater drain line 2 01HAC20BR412 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.80 Preheater drain line 3 01HAC20BR414 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.81 Preheater drain line 4 01HAC20BR416 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.82 Preheater drain line 5 01HAC20BR418 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.83 Preheater drain line 6 01HAC20BR420 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.84 Preheater common drain line 01HAC20BR422 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.85 Preheater common drain line 01HAC20BR423 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.86 LP re-circulation suction drain 01HAC20BR430 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.87 LP re-circulation discharge drain 01HAC20BR432 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.88 Preheater outlet drain 01HAC20BR440 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.89 Preheater outlet drain line 01HAC20BR441 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.90 Preheater safety valve drain 01HAC20BR491 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.91 Preheater vent line 1 01HAC20BR501 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.92 Preheater vent line 2 01HAC20BR503 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.93 Preheater vent line 3 01HAC20BR505 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.94 Preheater vent line 4 01HAC20BR507 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.95 Preheater vent line 5 01HAC20BR509 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.96 Preheater vent line 6 01HAC20BR511 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.97 Preheater outlet vent 01HAC20BR513 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.98 Preheater common vent line 01HAC20BR515 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.99 Preheater common vent line 01HAC20BR516 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.100 HP eco 1 drain line 1 01HAC10BR401 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.101 HP eco 1 drain line 2 01HAC10BR403 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.102 HP eco 1 drain line 3 01HAC10BR405 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.103 HP eco 1 drain line 4 01HAC10BR410 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.104 HP eco 1 drain line 5 01HAC10BR413 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.105 HP eco 2 drain line 1 01HAC10BR436 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.106 Preheater outlet vent 01HAC20BR514 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.107 HP eco 2 drain line 2 01HAC10BR438 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.108 LP evap drain line 01HAD20BR403 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.109 HP eco 1 common drain line 01HAC10BR440 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.110 HP eco 2 common drain line 01HAC10BR441 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.111 LP intermittent BD line 01HAD20BR411 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.112 HP eco 1 vent line 1 01HAC10BR501 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.113 HP eco 1 vent line 2 01HAC10BR503 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.114 HP eco 1 vent line 3 01HAC10BR510 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.115 HP eco 1 vent line 4 01HAC10BR512 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.116 HP eco 1 outlet vent line 01HAC10BR520 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.117 HP eco 1 common vent line 01HAC10BR525 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.118 HP eco 1 common vent line 01HAC10BR526 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.119 HP eco 2 vent 01HAC10BR566 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.120 HP eco 2 vent line 01HAC10BR571 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.121 HP attemperator water line 01LAD10BR010 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.122 Pegging steam line 01HAD10BR040 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.123 LP dea instrument header 01HAD20BR040 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.124 LP evap drain line 01HAD20BR402 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.125 LP intermittent BD line 01HAD20BR410 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.126 LP dea safety valve drain line 01HAD20BR430 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.127 LP drain line level transmitter 01HAD20BR440 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.128 LP drain line level transmitter 01HAD20BR442 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.129 Drain line - silencer of LP dea safety valve 01HAD20BR491 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.130 LP dea blow off line 01HAD20BR501 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.131 LP sat steam common vent 01HAH20BR504 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.132 LP drum water sampling 01HAD20BR601 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.133 LP N2 supply line 01HAD20BR810 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.134 LP saturated steam line 1 vent 01HAH20BR501 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.135 LP steam sample line 01HAH20BR601 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.136 HP FW pump min. flow line 01LAB10BR051 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.137 HP evap drain line 01HAD10BR402 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.138 HP intermittent BD 01HAD10BR410 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.139 HP continuous BD line 01HAD10BR420 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.140 Drain HP drum safety valve 01HAD10BR430 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.141 HP drain line LG HAD10CL501 01HAD10BR440 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.142 HP drain line LG 01HAD10BR441 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.143 HP drain line LI HAD10CL004 01HAD10BR442 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.144 HP drain line LI 01HAD10BR443 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.145 HP drum instrument header 01HAD10BR490 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.146 Drain silencer HP drum safety valve 01HAD10BR491 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.147 Vent HP drum safety valve 01HAD10BR591 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.148 HP drum sample line 01HAD10BR601 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.149 HP boiler chemical dosing line 01HAD10BR802 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.150 HP N2 supply line 01HAD10BR810 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.151 HP saturated steam line 2 vent 01HAH10BR501 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.152 HP sat steam common vent 01HAH10BR504 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.153 HP saturated steam sample line 01HAH10BR601 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.154 LP superheater start-up drain line 01HAH20BR401 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.155 HP SH 2 start-up drain line 01HAH10BR410 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.156 HP SH 3 start-up drain line 01HAH10BR420 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.157 HP SH 4 start-up drain line 01HAH10BR430 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.158 HP steam vent line 1 01HAH10BR510 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.159 HP steam vent line 1 01HAH10BR512 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.160 HP steam vent line 2 01HAH10BR515 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.161 HP steam vent line 2 01HAH10BR517 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.162 HP attemperator water filter bypass 01LAD10BR011 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.163 HP attemperation watel line 01LAD10BR014 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.164 HP attemperation water drain line 01LAD10BR401 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.165 HP main steam start-up drain line 01HAH10BR443 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.166 LP steam start-up drain line 01HAH20BR412 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.167 Steam trap line 01HAN10BR420 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.168 Bypass line steam trap 01HAN10BR421 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.169 Blow down tank drain 01HAN10BR432 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.170 Drain line main stack 01HNE20BR410 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.171 Instument air 01QFB10BR001 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.172 Instrument air 01QFB10BR001 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.173 Instument air 01QFB10BR001 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.174 Instument air 01QFB10BR001 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.175 Instrument air 01QFB10Br001 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.176 Hook-up drawing HP-drum instruments 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.177 Hook-up drawing LP-drum instruments 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.178 Arrangement drawing tundish 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.179 MTO small bore pipe support steel 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.180 Valves and fittings list ( VALVE LIST (Sorted on KKS)) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.181 Hydrostatic Test Precedure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.182 Terminal connection diagram(s) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.183 Instrument process hoop-up diagrams 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.184 E&I location drawing plan view EL.+0.000 - + 3.000 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.185 E & I Location drawing plan view EL.+5.000 - +20.000 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.186 E & I location drawing plan view EL.+20.000 - +29.000 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.187 E & I location drawing side view looking west 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.188 E & I location drawing side view looking west 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.189 Functional control diagrams DCS-ESD 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.190 Calibration & Setting list (IO list) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.191 Instrument list 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.192 Instrument air consumers list 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.193 HRG Functional control description DCS-ESD 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.194 Start-up & Shut-down description 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.195 Electrical consumers list 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.196 Terminal connection diagram(s) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.197 Dimensions for lifting and transport,sea transport fixation - module 1 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.198 Transport dimensions and sea transport fixation - module 2 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.199 Lifting beam for jacking main steam line 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.200 Standard Boiler conservation specification 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.201 Erection manual 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.202 HRSG erection manual document index 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.203 HRSG erection tolerances 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.204 Pre operational conservation procedure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.205 Commissioning procedure and check lists 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.206 Boiler cleaning procedure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.207 Blow-out procedure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.208 Painting and Corrosion Prevention Specification 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.209 Project coating datasheet 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.210 Performance test procedure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.211 Operation and maintenance manual (Index) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.212 Boiler conservation Procedure 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.213 Operation and maintenance manual - Volume 1 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.214 Operation and maintenance manual - Volume 2 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.215 Operation and maintenance manual - Volume 3 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.216 Water chemistry Specification 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.217 Training manual 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.218 Inspection and Test plan HP drum (ITP HP DRUM) 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.219 Inspection and Test plan (ITP) Interconnection Piping 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.220 Inspection and Test plan (ITP) External piping HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.221 Inspection and Test plan (ITP) Header Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.222 Inspection and Test plan (ITP) Harp Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.223 Inspection and Test plan (ITP) Casing Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.224 Inspection and Test plan (ITP) Ducting Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.225 Inspection and Test plan (ITP) Stack and Duct Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.226 Inspection and Test plan (ITP) Main Steel structure Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.227 Inspection and Test plan (ITP) Secundary steel structure manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.228 Inspection and Test plan (ITP) Blow Down tank Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.229 Inspection and Test plan (ITP) LP integral deaerator Manufacturing HRSG 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.230 Inspection and Test plan (ITP)Finning 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.231 Instructions for cleanliness and Preservation 0.455% 100.000% 0.000% 100.000% 0.455%
I.2.2.232 Standard Specification For Pinting And Corrotion Prevention 0.455% 100.000% 0.000% 100.000% 0.455%
TOTAL MANUFACTURE DESIGN - HRSG 100.000%

I.2.3 Steam Turbine Generator 33.333% 33.333%


I.2.3.1 Supplier Document Index 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.2 Technical Description Siemens STG 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.3 Glan Steam Condenser And Specification Sheet 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.4 Inspection and Test Program 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.5 Quality Plan for Project Execution Phase 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.6 Condenser 2734 M2 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.7 P&I D - Steam Turbine 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.8 P&I D - Gland Steam System 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.9 P&I D - Drainage System 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.10 P&I D - Condenser System 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.11 P&I D - Main Condensate System 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.12 P&I D - Steam Jet Vacuum Pump 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.13 P&I D - Oil Supply Unit 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.14 P&I D - Lube Oil Consumer 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.15 P&I D - Graphical Symbol 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.16 P&I D - Graphical Symbol for Hydraulic and Pneumatic 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.17 Layout - Floor +0.000m 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.18 Layout Sections A-A 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.19 Layout Sections B-B 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.20 Data for Foundation Drawings 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.21 Data for Civil Design 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.22 Demands on Lay-down Surfaces 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.23 Allowable Forces and Moments on the Turbine Branches 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.24 Branches Displacements 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.25 Lube Oil Cooler (Sheet-4) 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.26 Control And Emergency Stop Flasps (Sheet-3) 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.27 Gearbox 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.28 Dimensional Sketches Of Delivered Equipment- Gear Box 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.29 Gland Steam Condenser and Tech Spesification Sheet 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.30 Dimensional Sketches Of Delivered Equipment- Condenser 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.31 Dimensional Sketches Of Delivered Equipment- Lube Oil Cooler 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.32 Dimensional Sketches Of Delivered Equipment- Lube Oil Unit 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.33 Dimensional Sketches Of Delivered Equipment- Vacuum Pump 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.34 Dimensional Sketches Of Delivered Equipment- Condensate Pumps 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.35 Lifting of Turbine Package 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.36 Draft of Color Shades 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.37 Painting Spesification 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.38 Information Data for Insulation of piping and equipment off skid 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.39 Steam Turbine Run Down During AC Black Out 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.40 Heat Balance Diagrams 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.41 Delivery Limit List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.42 Measuring Point List - Remote 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.43 Measuring Point List - Local 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.44 Measuring Point List - Acceptance Test 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.45 Setting List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.46 List of Electrical Consumers 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.47 List of Panels 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.48 Instrument List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.49 List of Electrical Consumers - Typical Consumers Wiring Diagram (Motor Control Diagrams) 1.205%
100.000% 0.000% 100.000% 1.205%
I.2.3.50 P&I D - Turbogenerator Measuring 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.51 P&I D - HP Control Oil Supply 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.52 P&I D - HP Control Oil Consumers 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.53 P&I D - HP Control Oil Consumers 2 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.54 Hook-Up Diagram 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.55 Control System Configuration 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.56 Turbine Protection Logical Diagram 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.57 Turbine Governing Diagram (Block Diagram of Turbine Control) 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.58 ALGORITHMS OF STG UNIT 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.59 Danger and Risk Analysis 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.60 General Description of DC Emergency Oil Pump Control 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.61 System Description for Steam Turbine and Auxiliary Equipment 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.62 Layout of MTB, Neutral and Line Cubicle 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.63 Signal Transfer List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.64 Circuit Diagrams 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.65 Equipment List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.66 Cable List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.67 I/O List (PLC Input-Output List) 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.68 GENERATOR PROTECTION PANEL BASIC DESIGN 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.69 GENERATOR SYNCHRONIZING & MEASURING PANEL BASIC DESIGN 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.70 GENERATOR EXCITATION PANEL BASIC DESIGN 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.71 DC STARTER EMERGENCY OIL PUMP BASIC DESIGN 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.72 Generator Technical Specification & Generator Curves 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.73 Outline Drawing & Generator 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.74 Dimesnional (Outline) Drawing Text 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.75 Generator Connection Circuit Diagram (Wiring) 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.76 Generator Rotor Withdrawal Procedure (Rotor removal and installation) 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.77 Excitation System Model IEEE Detail Design 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.78 Panels Layout 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.79 Single Line Diagram 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.80 Circuit Diagram of Panels 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.81 Generator Protection Tripping Matrix 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.82 Input / Output Signal List 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.83 Cable List Detail Design 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.84 Generator Protection Relay Setting 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.85 Single Line Diagram of MTB, Wiring Diagram of MTB (Generator MTB Wiring diagram) 1.205% 0.000%
100.000% 100.000% 1.205%
I.2.3.86 CUBICLE LAYOUTS ST1CJJ20 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.87 TERMINAL CHARTS ST1CJJ10 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.88 WIRING DIAGRAMS ST1CJJ10 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.89 EQUIPMENT LIST ST1CJJ10 1.205% 100.000% 0.000% 100.000% 1.205%
I.2.3.90 Cable List 1.205% 100.000% 0.000% 100.000% 1.205%

I.2.3.91 Single Line Diagram of MTB, Wiring Diagram of MTB (Generator MTB Wiring diagram) 1.205% 0.000%
100.000% 100.000% 1.205%
TOTAL MANUFACTURE DESIGN - STG
I.3 Mechanical BOP Design 20.000% 17.111%
I.3.1 Mechanical Drawing List 0.355% 100.000% 0.000% 100.000% 0.355%
I.3.2 Mechanical Symbol, code & abbreviation 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.3 Overall Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.4 Water Mass Balance Diagram 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.5 Heat & Mass Balance Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.6 Fuel Gas System Equipment Sizing Calculation 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.7 Fuel Gas System Piping & Instrument Diagram (P&ID) 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.8 Fuel Gas System Process flow diagram 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.9 Fuel Gas System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.10 Fuel Gas System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.11 Fuel Gas System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.12 Pipe Specification 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.13 Service and Instrument Air Compressor System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.14 Service and Instrument Air Compressor System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.15 Service and Instrument Air Compressor System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.16 Service and Instrument Air Compressor System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.17 Service and Instrument Air Compressor System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.18 Service and Instrument Air Compressor System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.19 Instrument air system process flow diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.19 Service air system process flow diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.20 Service and Instrument Air Compressor System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.21 Sea Water Intake System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.22 Sea Water Intake System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.23 Sea Water Intake System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.24 Sea Water Intake System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.25 Sea Water Intake System general arrangement 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.26 Sea Water Intake System General LAYOUT 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.27 Sea Water Intake System General Arrangement(Sheet-1) 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.28 Sea Water Intake System General Arrangement (Sheet-2) 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.28 Sea Water Intake System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.29 Sea Water Intake System Intake Channel Detail 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.30 Sea Water Intake System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.31 Chlorination System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.32 Chlorination Compressor System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.33 Chlorination System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.34 Chlorination System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.35 Chlorination System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.36 Chlorination System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.37 Potable Water System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.38 Service Water System Piping & instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.39 Nitrogen Purge System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.40 Nitrogen Purge System Process Flow Diagram (PFD) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.41 Closed Cooling System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.42 Closed Cooling System general arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.42 Cooling Water System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.43 Cooling Water System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.44 Boiler Feed System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.45 Boiler Feed System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.46 Sub Vendor List 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.47 Project Schedule 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.48 Organisation chart 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.49 Monthly Progress Report 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.50 MRB Index 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.52 Inspection and Test Plan 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.53 Inspection and Test Procedure 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.54 P & I Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.55 Process Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.56 Utility consumption list 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.57 Chemical Consumption list 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.58 Interface list 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.65 Oil And Waste Water Treatment System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.65 Process Datasheet For Centrifugal pumps 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.66 Process Datasheet For Dosing Pumps 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.67 Process Datasheet For Dosing Tanks 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.68 Process Datasheet For Turbo charger 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.69 Process Datasheet For RO Pressure tubes 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.70 Process Datasheet For RO Membranes 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.71 Process Datasheet For Tube settler media 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.72 Process Datasheet For Filter Media 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.73 Process Datasheet For Mixed bed resin 0.392%
80.000% 0.000% 80.000% 0.314%
I.3.74 Process Datasheet For Cartridge Filter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.75 Process Datasheet For Blowers 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.76 Process Datasheet For Static Mixer 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.77 Process Datasheet For Resin Trap 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.78 Process Datasheet For Tank Mixer 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.79 Equipment Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.80 Drain trench Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.81 Civil Outline Drawing For Lamell Clariffer Tank Foundation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.82 Civil Outline Drawing For SWRO Permeate Water Tanks Foundation (TK-105A/B) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.83 Civil outline Drawing for Demin water storage tanks foundation (TK-109A/B) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.84 Civil outline for Roughing and polishing filter system foundation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.85 Civil outline for SWRO system foundation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.86 Civil outline Drawing for BWRO system foundation 0.392% 80.000% 0.000% 80.000% 0.314%
Civil outline Drawing for MB system, Air blower, BWRO feed pump and regeneration pump
I.3.87 0.392%
foundation 80.000% 0.000% 80.000% 0.314%
I.3.88 Civil outline for Backwash pumps, potable pumps and MB feed pumps foundation 0.392% 80.000% 0.000% 80.000% 0.314%
Civil outline for backwash water tank, potable water tanks, Service water tanks and BWRO
I.3.89 0.392%
permeate tank foundation 80.000% 0.000% 80.000% 0.314%
I.3.90 Civil outline for Cleaning/flushing system and Dosing system foundation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.91 Electrical Room Layout And Civil Outline Detail Drawing. 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.92 Civil Plinth Locations & Drain Trench Layout For Water Treatment Plant 0.392%
80.000% 0.000% 80.000% 0.314%
I.3.93 Outline drawing for RO cleaning water tank-FRP 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.94 G.A Drawing for MB Vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.95 Strainer details for inlet Distributor of MB Vessel (MB-101A & MB101B) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.96 Middle Collector Details for MB Vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.97 Underdrain Strainer Details For MB Vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.98 Skid GA for SWRO System system 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.99 Skid piping isometric SWRO system-Duplex 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.100 Skid piping isometric SWRO system-uPVC 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.106 Plant piping layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.113 Inspection & Test Plan (Client's Comments On Our ITP For Water Treatment Plant & Mixed Bed Unit) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.122 Piping specification 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.123 Painting specification 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.124 Mechanical datasheet for media filter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.125 Instrument Index 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.126 I/O List 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.127 Electrical Load List. 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.128 Control Philosophy 0.392%
80.000% 0.000% 80.000% 0.314%
I.3.129 JB Termination Details 0.392%
80.000% 0.000% 80.000% 0.314%
I.3.130 Instrument Cable Schedule 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.131 Power Cable Schedule 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.132 Data Sheet for Pressure Gauge 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.133 Data Sheet for Pressure Switch 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.134 Data Sheet for Differential Pressure Transmitter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.135 Data Sheet for Differential Pressure Flow Transmitter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.136 Data Sheet for Orifice Plate 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.137 Data Sheet for Mag Flow Transmitter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.138 Data Sheet for Paddle wheel type flow transmitter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.139 Data Sheet for Float type Level switch 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.140 Data Sheet for Ultrasonic Level Transmitter 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.142 Data Sheet for pH Analyser 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.143 Data Sheet for ORP Analyser 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.146 Single Line Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.147 MCC Wiring(MCC GA + Wiring) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.148 PLC Panel Wiring Drawing (GA + Wiring) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.149 Instrument Hook up Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.150 Overall Cable Layout Drawing for Plant 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.153 SWRO Skid tray Layout Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.154 BWRO Skid tray Layout Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.155 MBE Skid tray Layout Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.156 Electrical Room Layout and Civil Outline Detail Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.157 Earthing Boss Layout Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.158 Closed Cooling System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.159 Closed Cooling System Heat & Mass Balance Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.160 Closed Cooling System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.161 Closed Cooling System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.162 Closed Cooling System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.163 Closed Cooling System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.163 Closed Cooling System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.164 FIN FAN COOLER GTG-1,GTG-2 AND STG 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.164 Cooling Water System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.165 Cooling Water System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.166 Cooling Water System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.167 Cooling Water System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.168 Cooling Water System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.169 Cooling Water System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.170 Cooling Water System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.170 Cooling Water System civil guide Drawing 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.171 001/WPS/SMAW R.1 & 001/PQR/SMAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.172 001/WPS/GTAW R.1 & 002/PQR/GTAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.173 005/WPS/GTAW R.0 & 005/PQR/GTAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.174 010/WPS/GTAW +SMAW R.0 & 010/PQR/GTAW + SMAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.175 011/WPS/GTAW +SMAW R.0 & 011/PQR/GTAW + SMAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.176 017/WPS/GTAW R.0 & 017/PQR/GTAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.177 021/WPS/GTAW+SMAW R.0 & 021/PQR/GTAW +SMAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.178 022/WPS/GTAW R.0 & 022/PQR/GTAW R.0 (Sheet 1 Of 6) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.171 HVAC System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.172 HVAC System Heat & Mass Balance Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.173 HVAC System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.174 HVAC System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.175 HVAC System Installation Layout for Electrical, Administration & Control Building 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.176 HVAC System Installation Layout for Steam Turbine Hall 0.392% 50.000% 0.000% 50.000% 0.196%
I.3.177 HVAC System Installation Layout for Workshop & Warehouse 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.178 HVAC System Installation Layout for Analyzer Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.179 HVAC System Installation Layout for BOP Water Treatment Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.180 HVAC System Installation Layout for Waste Water Treatment Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.181 HVAC System Installation Layout for Mosque 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.182 HVAC System Installation Layout for Guard House 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.183 Fire Protection System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.184 Fire Protection System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.185 Fire Protection System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.185 Fire Protection System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.186 Fire Protection System Installation Layout for 150 kV Switchyard Area 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.187 Fire Protection System Installation Layout for GSU Transformer Area 0.392% 50.000% 0.000% 50.000% 0.196%
I.3.188 Fire Protection System Installation Layout for Electrical, Administration & Control Building 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.189 Fire Protection System Installation Layout for Steam Turbine Hall 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.190 Fire Protection System Installation Layout for Workshop & Warehouse 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.191 Fire Protection System Installation Layout for Analyzer Building 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.192 Fire Protection System Installation Layout for BOP Area 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.193 Fire Protection System Installation Layout for Waste Water Treatment Building 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.194 Fire Protection System Installation Layout for Mosque 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.195 Fire Protection System Installation Layout for Guard House 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.196 Fire Alarm & Gas Detector Single Line Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.197 Fire Alarm & Gas Detector Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.198 Fire Alarm & Gas Detector Installation Layout for 150 kV Switchyard Area 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.199 Fire Alarm & Gas Detector Installation Layout for GSU Transformer Area 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.200 Fire Alarm & Gas Detector Installation Layout for Gas Turbine Area 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.201 Fire Alarm & Gas Detector Installation Layout for Gas Metering Station 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.202 Fire Alarm & Gas Detector Installation Layout for Electrical, Admnistration & Control Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.203 Fire Alarm & Gas Detector Installation Layout for Steam Turbine Hall 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.204 Fire Alarm & Gas Detector Installation Layout for Workshop & Warehouse 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.205 Fire Alarm & Gas Detector Installation Layout for Analyzer Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.206 Fire Alarm & Gas Detector Installation Layout for BOP Water Treatment Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.207 Fire Alarm & Gas Detector Installation Layout for Waste Water Treatment Building 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.208 Fire Alarm & Gas Detector Installation Layout for Mosque 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.209 Fire Alarm & Gas Detector Installation Layout for Guard House 0.392% 0.000% 0.000% 0.000% 0.000%
I.3.210 Boiler Feed System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.211 Boiler Feed System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.212 Boiler Feed System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.212 Boiler Feed System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.213 Boiler Feed System General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.214 Boiler Feed System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.215 Boiler Feed System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.216 Demin water system piping & instrument diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.217 Demin water system process flow diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.218 Demin water sizing calculations 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.224 Oily and Waste Water Treatment System Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.225 Oily and Waste Water Treatment System Oily and Waste Water PFD 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.226 Oily and Waste Water Treatment System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.227 Oily and Waste Water Treatment System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.228 Oily and Waste Water Treatment System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.229 Oily and Waste Water Treatment System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.230 Turbine Hall Overhead Crane Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.231 Workshop & Warehouse Overhead Crane Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.232 Sea Water Intake Pump House Gantry Crane Equipment Sizing Calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.233 Turbine Hall Overhead Crane General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.234 Turbine Hall Overhead Crane Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.235 Turbine Hall Overhead Crane Framing Plan 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.236 Workshop & Warehouse Overhead Crane General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.237 Workshop & Warehouse Overhead Crane Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.238 Workshop & Warehouse Overhead Crane Framing Plan 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.239 Sea Water Intake Pump House Gantry Crane General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.240 Sea Water Intake Pump House Gantry Crane Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.241 Sea Water Intake Pump House Gantry Crane Framing Plan 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.242 Sampling Rack System Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.243 Sampling Rack System P&ID 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.244 Sampling Rack System Wiring Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.245 Service And Instrument Air Compressor System Plan Layout. 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.246 Sea Water Intake System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.247 Potable System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.248 Service Water System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.249 Nitrogen Purge System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.250 Chemical Dosing System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.251 Fire Protection System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.252 Boiler Feed System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.253 Demin Water System Plant Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.254 Steam Interconnecting Pipe & Condensate Pipeline Heat & Mass Balance Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.255 Steam Interconnecting Pipe & Condensate Pipeline Process Flow diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.256 Steam Interconnecting Pipe & Condensate Pipeline Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.257 Steam Interconnecting Pipe & Condensate Pipeline Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.258 Steam Interconnecting Pipe & Condensate Pipeline Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.259 Condenser Steam Bypass System Process Flow Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.260 Condenser Steam Bypass System Heat & Mass Balance Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.261 Condenser Steam Bypass System Piping & Instrument Diagram (P&ID) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.262 Condenser Steam Bypass System Control Logic Diagram 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.263 Condenser Steam Bypass System Equipment Datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.264 Condenser Steam Bypass System Piping Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.265 Inspection & Test Plan 0.392% 100.000% 0.000% 100.000% 0.392%
I.3.266 Underdrain strainer details for MB Vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.267 Middle collector details for MB Vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.268 Strainer details for inlet distributor of MB Vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.269 GA Drawing for MB vessel 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.270 Bypass Exhaust System [2-Off] For Siemens Sgt-800 Gas Turbine General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.271 Bypass Exhaust System [2-Off] For Siemens Sgt-800 Gas Turbine General Arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.272 Bypass Exhaust System For Siemens Sgt-800 Gas Turbine Foundation Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.273 Bypass Exhaust System For Siemens Sgt-800 Gas Turbine Foundation Layout 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.274 PRDS Valve sizing calculation 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.275 PRDS Valve datasheet 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.276 PRDS Valve General arrangement 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.277 Natural gas pressure reduction & metering station general arrangement drawing (GAD) 0.392% 80.000% 0.000% 80.000% 0.314%
I.3.282 Diverter Function Test Procedure rev1 0.392% 80.000% 0.000% 80.000% 0.314%
TOTAL MECHANICAL BOP DESIGN 77.776%
I.4 Electrical BOP Design 20.000% 17.969%
I.4.1 Electrical Drawing List 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.2 Electrical Symbol, code & abbreviation 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.3 Overall Single Line Diagram 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.4 Overall Protection & Logic Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.5 Load List 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.6 Load Flow Analysis 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.7 Short Circuit Level Analysis 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.8 150 kV Switchyard Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.9 150 kV Switchyard Protection & Logic Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.10 150 kV Switchyard Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.11 150 kV Equipment Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.12 150 kV Switchyard Equipment General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.13 150 kV Switchyard Cable Trench Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.14 150 kV Substation Automation System Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.15 150 kV Switchyard Plan view 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.16 150 kV Switchyard Section View A-A 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.17 150 kV Switchyard Section View B-B 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.18 Technical Specification & Drawing of 150 kV Disconnector Switch W & W/O Earth Switch 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.19 Technical Specification & Drawing of 150 kV Current Transformer 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.20 Technical specification & Drawing of 150 kV Capacitor Voltage Transformer 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.21 Technical Specification & Drawing of 150 kV Lightning Arrester 0.578% 100.000% 0.000% 100.000% 0.578%
I.4.22 Busbar Identification 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.23 150 kV Switchyard -Safety Clearance Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.24 Support Of Disconnecting Switch (DS/DSE) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.25 Support Of Capacitive Voltage Transformer (CVT) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.26 Support Of Current Transformer (CT) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.27 Support Of Lighting Aresrer (LA) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.28 Support Of Cable Head (CH) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.29 Detail Drawing Fo Gantry Steet Sructure 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.30 Calculation Of Stee Structure 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.31 Clamp Drawing & Installation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.32 150 kV Switchyard -Ligthing Protection Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.33 GSU Transformer for GTG-1 & GTG-2 Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.34 GSU Transformer for GTG-1 & GTG-2 Protection & Logic Diagram 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.35 GSU Transformer for GTG-1 & GTG-2 Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.36 GSU Transformer for GTG-1 & GTG-2 General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.37 Other GSU Transformer for GTG-1 & GTG-2 Required Document / Drawing 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.38 GSU Transformer for STG Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.39 GSU Transformer for STG Protection & Logic Diagram 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.40 GSU Transformer for STG Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.41 GSU Transformer for STG General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.42 GCB for GTG-1 & GTG-2 Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.43 GCB for GTG-1 & GTG-2 Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.44 GCB for GTG-1 & GTG-2 Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.45 GCB for GTG-1 & GTG-2 General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.50 MV Switchgear Load List & Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.51 MV Switchgear Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.52 MV Switchgear Protection & Logic Diagram 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.53 MV Switchgear Load Flow Analysis 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.54 MV Switchgear Short Circuit Level Analysis 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.55 EBOP MV Switchgear 6,6 kV GA & SLD 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.56 MV Switchgear Plant Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.57 LV Switchgear Load List & Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.58 LV Switchgear Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.59 LV Switchgear Protection & Logic Diagram 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.60 LV Switchgear Load Flow Analysis 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.61 LV Switchgear Short Circuit Level Analysis 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.62 EBOP LV MCC 0.4 kV GA & SLD 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.63 EBOP Synchronizing panel G.A And SLD 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.64 EBOP Synchronizing Schematic 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.65 EBOP Generator Protection SLD & GA 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.63 LV Switchgear Plant Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.64 UAT & SST Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.65 UAT & SST Protection & Logic Diagram 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.66 UAT & SST Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.67 UAT & SST General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.68 UPS & DC System Equipment Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.69 UPS & DC System Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.70 UPS & DC System Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.71 UPS & DC System General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.72 EL+0.00m EAC building lighting calculation (cable cellar) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.73 el+2.60m EAC building lighting calcualation ( electrical room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.74 el+2.60m EAC building lighting calcualation ( enterance lobby room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.75 el+2.60m EAC building lighting calcualation (doctor room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.76 el+2.60m Eac building lighting calculation (battery room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.77 el+2.60m Eac building lighting calculation (emergency diesel generator room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.78 el+2.60m EAC building lighting calculation (transformer room no.1) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.79 el+2.60m EAC building lighting calculation (transformer room no.2) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.80 el+6.80m EAC building lighting calcualation (instrument panel room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.81 el+6.80m EAC building lighting calcualation (staff training room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.82 el+6.80m EAC building lighting calcualation (meeting room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.83 el+6.80m EAC building lighting calcualation (manager room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.84 el+6.80m EAC building lighting calcualation (locker room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.85 el+6.80m EAC building lighting calcualation (pray room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.86 el+6.80m EAC building lighting calcualation (pantry room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.87 el+6.80m EAC building lighting calcualation (administration room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.88 el+6.80m EAC building lighting calcualation (terrace garden) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.89 el+11.30m EAC building calculation (central control room) 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.90 el+11.30m EAC building calculation (terrace garden) 0.588% 80.000% 0.000% 80.000% 0.470%
I.4.91 Lighting layout for EAC building el+0.000mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.92 Lighiting single line diagram for EAC building EL+0.000mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.93 Receptacle layout for EAC building el+0.000mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.94 Receptacle single line diagram for EAC building EL+0.000mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.95 Lighting layout for EAC building el+2.600mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.96 Lighting single Line diagram for EAC building EL+2.600mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.97 Receptacle layout for EAC building el+2.600mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.98 Receptacle single line Diagram for EAC building el+2.600mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.99 Detail lighting panel (Lp-2) for EAC building EL+2.600mm part 1 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.100 Detail lighting panel (LP-2) for EAC building 2.600mm Part 2 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.101 Lighting layout for EAC building el+6.800mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.102 Lighting single line diagram for eac building el+6.800mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.103 Receptacle layout for EAC building EL+6.800mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.104 Receptacle single line diagram for EAC building el+6.800mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.105 Detail Lighting panel (Lp-2.1) for EAC building el+6.800mm Part 1 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.106 Detail Lighting panel (Lp-2.1) for EAC building el+6.800mm Part 2 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.107 Lighting layout for EAC building el+11.300mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.108 Lighting single line diagram for EAC building el+11.300mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.109 Receptacle layout for EAC building el+11.300mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.110 Receptacle single line diagram for EAC building el+11.300mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.111 Detail lighting panel (LP-2.2) for EAC building el+11.300mm 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.112 Lighting Lux & Receptacle Requirement Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.113 Lighting & Distribution Panel Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.114 Lighting Equipment Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.115 Lighting Distribution Panel General Arrangement 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.116 Lighting Installation Layout for Electrical, Administration & Control Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.117 Lighting Installation Layout for Steam Turbine Hall 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.118 Lighting Installation Layout for Workshop & Warehouse 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.119 Lighting Installation Layout for Analyzer Building 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.120 Lighting Installation Layout for BOP Water Treatment Building 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.121 Lighting Installation Layout for Waste Water Treatment Building 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.122 Lighting Installation Layout for Mosque 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.123 Lighting Installation Layout for Outdoor Siteplan 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.124 Lighting Installation Layout for Guard House 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.125 Road Lighting 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.126 Lightening & Grounding Requirement Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.127 Grounding Grid Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.128 Lightening & Grounding System Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.129 Lightening& Grounding Layout for GT-1 (General grounding layout for GTG and STG Area) 0.578%
80.000% 0.000% 80.000% 0.462%
I.4.130 Lightening & Grounding Layout for GT-2 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.131 Lightening & Grounding Layout for HRSG-1 & Auxiliary Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.132 Lightening & Grounding Layout for HRSG-2 & Auxiliary Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.133 Lightening & Grounding Layout for STG & Turbine Hall 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.134 Lightening & Grounding Layout for Electrical, Administration & Control Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.135 Lightening & Grounding Layout for 150 kV Switchyard Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.136 Lightening & Grounding Layout for GSU Transformer Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.137 Lightening & Grounding Layout for Unit Auxilliary Transformer Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.138 Lightening & Grounding Layout for Station Service Transformer Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.139 Lightening & Grounding Layout for Balance Of Plant Area 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.140 Emergency Diesel Generator Single Line Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.141 Emergency Diesel Generator Protection & Logic Diagram 0.578% 0.000% 0.000% 0.000% 0.000%
I.4.142 Emergency Diesel Generator Equipment Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.143 Emergency Diesel Generator General Arrangement 0.578% 0.000% 0.000% 0.000% 0.000%
I.4.144 Distributed Control System (DCS) Architecture Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.145 Distributed Control System (DCS) Technical Description 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.146 Distributed Control System (DCS) Control & Logic Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.147 Distributed Control System (DCS) I/O List 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.148 Emergency Shutdown Device (ESD) I/O List 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.149 Distributed Control System (DCS) Wiring Diagram 0.578% 50.000% 0.000% 50.000% 0.289%
I.4.150 Central Control Room (CCR) Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.151 Control Emmision Monitoring System (CEMS) Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.152 Control Emmision Monitoring System (CEMS) P&ID 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.153 Control Emmision Monitoring System (CEMS) Wiring Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.154 CCTV System Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.155 CCTV Equipment Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.156 CCTV Installation Layout for Electrical, Administration & Control Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.157 CCTV Installation Layout for Steam Turbine Hall 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.158 CCTV Installation Layout for Workshop & Warehouse 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.159 CCTV Installation Layout for Analyzer Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.160 CCTV Installation Layout for BOP Water Treatment Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.161 CCTV Installation Layout for Waste Water Treatment Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.163 CCTV Installation Layout for Outdoor Siteplan 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.164 CCTV Installation Layout for Guard House 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.165 PABX & Telecomunication System System Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.166 PABX & Telecomunication System Equipment Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
PABX & Telecomunication System Installation Layout for Electrical, Administration & Control
I.4.167 0.578% 80.000% 80.000% 0.462%
Building 0.000%
I.4.168 PABX & Telecomunication System Installation Layout for Steam Turbine Hall 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.169 PABX & Telecomunication System Installation Layout for Workshop & Warehouse 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.170 PABX & Telecomunication System Installation Layout for Analyzer Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.171 PABX & Telecomunication System Installation Layout for BOP Water Treatment Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.172 PABX & Telecomunication System Installation Layout for Waste Water Treatment Building 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.173 PABX & Telecomunication System Installation Layout for Guard House 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.174 Isolated Phase Busduct Schedule 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.175 Isolated Phase Busduct Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.176 Isolated Phase Busduct Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.177 Isolated Phase Busduct Installation Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.178 Non Segregated Phase Busduct Schedule 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.179 Non Segregated Phase Busduct Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.180 Non Segregated Phase Busduct Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.181 Non Segregated Phase Busduct Installation Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.182 MV Cable 6.6/7.2 kV Schedule 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.183 MV Cable 6.6/7.2 kV Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.184 MV Cable 6.6/7.2 kV Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.185 MV Cable 6.6/7.2 kV Installation Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.186 LV Cable 0.4/1 kV Schedule 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.187 LV Cable 0.4/1 kV Sizing Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.188 LV Cable 0.4/1 kV Datasheet 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.189 LV Cable 0.4/1 kV Installation Layout 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.190 Overall Cable Route Plan 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.191 CT Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.192 Grounding Calculation 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.193 Feeder Block Diagram 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.194 Substation Interlocking Principle 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.195 Control Functional Description 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.196 Protection Functional Description 0.578% 80.000% 0.000% 80.000% 0.462%
I.4.197 Cable Route Isometric Plan 0.578% 0.000% 0.000% 0.000% 0.000%
TOTAL ELECTRICAL BOP DESIGN 89.843%
I.5 Civil, Structural & Architechtural 10.000% 9.962%
I.5.1 Civil, Structural & Architect Drawing List 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.2 Civil, Structural & Architect Symbol, code & abbreviation 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.3 Final Report The Soil Resistivity Test 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.4 Final Report Soil Investigation 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.5 Final Report Hidrographic And Seawater Surveys 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.6 Final Report Concrete Mik Derain Pt.SRC 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.7 Master Plant Layout (Layout Master plant Overall) 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.8 Plant Layout Sea Water Intake (Sheet-01) 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.9 Master Plant Layout (Sheet-02) 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.10 Power Plant Layout (LAYOUT POWER PLANT) 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.11 Power Plant Layout 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.12 Power Plant Layout (A) (LAYOUT POWER PLANT (A)) 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.13 Site Plant Elevation Cross Section A-A (Sheet-1) 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.14 Site Plant Elevation Cross Section B-B (Sheet-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.15 Site Plant Elevation Cross Section C-C (Sheet-3) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.16 Site Plant Elevation Cross Section D-D (Sheet-4) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.17 Plant Site Grading 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.18 Design Calculation for Access Roads 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.19 Pant-Access Road 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.20 Access Road Typical Section & Elevation (Sheet-1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.21 Access Road Typical Section & Elevation (Sheet-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.22 Access Road Typical Section & Elevation (Sheet-3) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.23 Design Calculation for drainage system 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.24 Plant Drainage Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.25 Plant Drainage Layout (SHEET-1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.26 TYPICAL SECTION- Drainage SYSTEM (SHEET-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.27 150 kV Switchyard Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.28 150 kV Switchyard section details 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.29 150 kV Switchyard Cable Trench Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.30 150 kV Switchyard Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.31 150 kV Switchyard Drainage Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.32 150 kV Switchyard Slope Protection 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.33 Structural Design Calculation-of Foundation GTG Analysis 0.417% 100.000% 0.000% 100.000% 0.417%
Structural Design Calculation of gas turbine Ventilation outlet unit & CO2 Cabinet
I.5.34 0.417% 100.000%
(attachment "F") 0.000% 100.000% 0.417%
I.5.35 Structural Design Calculation of Turbine removal system area (attachment "I") 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.36 Structural Design Calculation of generator roror revision tool support (attachment "J") 0.417% 100.000% 0.000%
100.000% 0.417%
I.5.37 SGT-800 Foundation Layout Plan & Section 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.38 SGT-800 Foundation Section Detail & Embedded Details 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.39 Gas Turbine Foundation Layout (SGT-800 Foundation Section Embedded Details) 0.417% 80.000% 0.000% 80.000% 0.333%
Gas Turbine Anchor Bolt Layout (SGT-800 Foundation Layout Reinf.Plan At EL+0.300 &
I.5.40 0.417%
EL+0.500 Section (2 Sheet) 80.000% 0.000% 80.000% 0.333%
I.5.41 Gas Turbine Pipe & Cable Sleeve Layout (SGT-800 Foundation Layout Section (2 Sheet)) 0.417% 80.000% 0.000%
80.000% 0.333%
I.5.42 Gas Turbine Oil Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
Exhaust Gas Bypass Stack Load Calculation Analysis (Design calculation-Bypass Exhaust
I.5.43 0.417%
system) 80.000% 0.000% 80.000% 0.333%
Exhaust Gas Bypass Stack Foundation Layout (Foundation G.A Laout plan Tie Beam Elevation
I.5.44 0.417%
& section of bypass exhaust system BTWN HRSG-2 SGT-800/2 80.000% 0.000% 80.000% 0.333%
Exhaust Gas Bypass Stack Anchor Bolt Layout (Foundation G.A Layout Plan, Tie beam
I.5.45 0.417%
elevation & section of bypass Exhaust System BTWN. HRSG-1/SGT-800/1(2-sheet)
80.000% 0.000% 80.000% 0.333%
Exhaust Gas Bypass Stack Pipe & Cable Sleeve Layout (Foundation G.A Layout plan, Tie Beam
I.5.46 0.417%
Elevation & section of rotor tool support-1 SGT-800/1) 80.000% 0.000% 80.000% 0.333%
Exhaust Gas Bypass Stack Oil Pit Layout (Foundation G.A Layout plan, Tie Beam Elevation &
I.5.47 0.417%
section of rotor tool support-2 SGT-800/2) 80.000% 0.000% 80.000% 0.333%
I.5.48 Structural Design Calculation of Foundation –HRSG System 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.49 Design Calculation of Gas Turbine Ventilation outlet unit & CO2 Cabinet (attachment "F") 0.417% 80.000% 0.000%
80.000% 0.333%
I.5.50 HRSG-2 Foundation Layout Plan & R/F Detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.51 HRSG-1 Foundation Layout Plan & R/F Detail (Sheet-1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.52 HRSG-1 Foundation Layout Plan & R/F Detail (Sheet-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.53 HRSG Stack Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.54 HRSG-1 Pedestal Layout Plan & R/F Details 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.55 HRSG-1 Anchor Bolt Detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.56 HRSG-1 Grade Slab Plan & Detail(At0.00m Lvl) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.57 HRSG Oil Pit Layout (HRSG-1 Blowdown tank Foundation Layout Plan & R/F detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.58 Steam Turbine Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.59 Steam Turbine Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.60 Steam Turbine Embedded Plate Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.61 Steam Turbine Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.62 Steam Turbine Oil Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.63 GSU Transformer Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.64 GSU Transformer Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.65 GSU Transformer Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.66 GSU Transformer Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.67 GSU Transformer Oil Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.68 Control Room Foundation & Battery Foundation Layout Plan & R/F Detail of SGT-800/1 0.417%
80.000% 0.000% 80.000% 0.333%
I.5.69 Control Room Foundation & Battery Foundation Layout Plan & R/F Detail of SGT-800/2 0.417%
80.000% 0.000% 80.000% 0.333%
I.5.70 SGT-1 800 Lubrication oil Cooler Foundation Layout Plant & RF detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.71 SGT-2 800 Lubrication oil Cooler Foundation Layout Plant & RF detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.72 Emergency Diesel Generator Oil Pit Layout 0.417% 0.000% 0.000% 0.000% 0.000%
I.5.73 Auxilliary & Station Service Transformer Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.74 Auxilliary & Station Service Transformer Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.75 Auxilliary & Station Service Transformer Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.76 Auxilliary & Station Service Transformer Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.77 Auxilliary & Station Service Transformer Oil Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.78 Fuel Gas Booster Compressor & Metering System Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.79 Fuel Gas Booster Compressor & Metering System Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.80 Fuel Gas Booster Compressor & Metering System Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.81 Fuel Gas Booster Compressor & Metering System Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.82 Fuel Gas Booster Compressor & Metering System Oil Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.83 Air Compressor & Bottle Rack Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.84 Air Compressor & Bottle Rack Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.85 Air Compressor & Bottle Rack Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.86 Air Compressor & Bottle Rack Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.87 Air Compressor & Bottle Rack Drain Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.88 Sea Water Intake Pump & Chlorination Equipment Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.89 Sea Water Intake G.A Detail Of Foundation Plant Section 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.90 Sea Water Intake R/F Detail Of Foundation Plant 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.91 Sea Water Intake Column Layout Plant & Schedule 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.92 Sea Water Intake Pump & Chlorination Equipment Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.93 Sea Water Intake Pump & Chlorination Equipment Drain Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.94 Water Treatment Pump & Tank Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.95 Water Treatment Pump & Tank Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.96 Water Treatment Pump & Tank Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.97 Water Treatment Pump & Tank Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.98 Water Treatment Pump & Tank Drain Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.99 Cooling System Pump Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.100 Cooling System Pump Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.101 Cooling System Pump Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.102 Cooling System Pump Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.103 Cooling System Pump Drain Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.104 Cooling Tower Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.105 Cooling Tower Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.106 Cooling Tower Wash Basin Design 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.107 Cooling Tower Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.108 Cooling Tower Drain Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.109 Fire Pump & Tank Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.110 Fire Pump & Tank Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.111 Fire Pump & Tank Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.112 Fire Pump & Tank Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.114 Boiler Feed Pump Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.115 Boiler Feed Pump Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.116 Boiler Feed Pump Anchor Bolt Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.117 Boiler Feed Pump Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.118 Boiler Feed Pump Oil Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.119 Oily & Waste Water Equipment Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.120 Oily & Waste Water Equipment Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.121 Oily & Waste Water Equipment Pipe & Cable Sleeve Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.122 Oily & Waste Water Equipment Collecting Pit Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.123 Electrical, Administration & Control Building Detail of Retaining wall 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.124 Electrical, Administration & Control Building Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.125 Electrical, Administration & Control Building Cable Trench Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.126 Workshop & Warehouse Foundation and pedestal layout detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.127 Workshop & Warehouse G.A and R/F Detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.128 Analyzer Building Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.129 Analyzer Building Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.130 BOP Water Treatment Building Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.131 BOP Water Treatment Building Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.132 Mosque Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.133 Mosque Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.134 Guard House Load Calculation Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.135 Guard House Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.136 HRSG-2 Blowdown Tank Foundation Layout Plan & R/F Detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.137 SGT-800/1 CO2 Cabiinet & Gas Turbine Ventilation Outlet Foundation Layout Plan & R/F detail 0.417%
80.000% 0.000% 80.000% 0.333%
I.5.138 SGT-800/1 CO2 Foundation Layout Plan & RF detail of turbine removal area 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.139 Pipe and Cable Rack Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.140 Workshop & Warehouse Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.141 Workshop & Warehouse Roof 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.142 Workshop & Warehouse Framing Elevation (2-Sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.143 Workshop & Warehouse Framing Elevation Detail (2-Sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.144 Workshop & Warehouse waremesh Partition detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.145 Emergency Diesel Generator Shelter Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.146 Cooling Water Circulating Pump Shelter Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.147 Gas Booster Compressor Shelter Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.148 Gas Metering & Regulating Shelter Layout 0.417% 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Load Calculation & Structural Analysis(Design
I.5.149 0.417%
Calculation Electrical, Administration & Control Building) 80.000% 0.000% 80.000% 0.333%
I.5.150 Electrical, Administration & Control Building Column Layout & Column Schedule (2 Sheet) 0.417%
80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Plinth Beam G.A & R/F Detail AT (EL-
I.5.151 0.417%
0.150M)Level (2 Sheet) 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Reinforcement Plan (electrical ,administration &
I.5.152 0.417%
control building stair detail (4 sheet) 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building First Floor (Electrical Room ) G.A & R.F Detail AT
I.5.153 0.417%
2.6M Level (4 Sheet) 80.000% 0.000% 80.000% 0.333%
I.5.154 Electrical, Administration & Control Building G.A & R.F Detail AT 5.0M Level 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.155 Electrical, Administration & Control Building stair detail (4 sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.156 Electrical, Administration & Control Building Plumbing Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.157 Steam Turbine Hall Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.158 Steam Turbine Hall Column Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.159 Steam Turbine Hall Steel Framing Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.160 Steam Turbine Hall Reinforcement Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.161 Steam Turbine Hall Concrete Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.162 Steam Turbine Hall Plumbing Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.163 Analyzer Building Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.164 Analyzer Building Column Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.165 Analyzer Building Steel Framing Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.166 Analyzer Building Reinforcement Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.168 BOP Water Treatment Building Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.169 BOP Water Treatment Building Column Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.170 BOP Water Treatment Building Steel Framing Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.171 BOP Water Treatment Building Reinforcement Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.172 BOP Water Treatment Building Concrete Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.173 Oily & Waste Water Treatment House Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.174 Oily & Waste Water Treatment House Column Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.175 Oily & Waste Water Treatment House Steel Framing Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.176 Oily & Waste Water Treatment House Reinforcement Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.177 Oily & Waste Water Treatment House Concrete Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.178 Mosque Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.179 Mosque Column Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.180 Plan, Section & elevation of mosque 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.181 Section Detail of Mosque 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.182 Floor Plan & Ceiling Plan Mosque 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.183 Door & Window Schedule of Mosque 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.184 Guard House Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
Guard House Column Layout (Guard House Foundation, Column schedule, G.A at Plinth beam
I.5.185 0.417%
Level R/F detail 80.000% 0.000% 80.000% 0.333%
I.5.186 Guard House Steel Framing Plan (Guard house G.A & R/F detail of Terrace level) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.187 Guard House Reinforcement Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.188 Guard House Concrete Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.189 Structural Design Calculation - Guard House 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.190 Structural Design Calculation-Sea Water Intake System 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.191 Sea Water Intake Channel Layout (Sea water intake G.A & R/F Detail of + 1.0 M LVL) 0.417%
80.000% 0.000% 80.000% 0.333%
I.5.192 Sea Water Intake System R/F OF Channel Section (Sheet-1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.193 Sea Water Intake System R/F OF Channel Section (sheet-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.194 Sea Water Intake Channel Pit Design Calculation 0.417% 80.000% 0.000% 80.000% 0.333%
Sea Water Pump House Load Calculation & Structural Analysis (sea water intake column
I.5.195 0.417%
Layout Plan & schedule) 80.000% 0.000% 80.000% 0.333%
I.5.196 Sea Water Intake G.A & Slab R/F Detail At 4.0m Level 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.197 Sea Water Intake G.A & Slab R/F Beam Elevation And Section 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.198 Sea Water Intake G.A & R/F Detail Of 7.0m & 10.0m 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.199 Sea Water Pump House Concrete Plan (Sea water intake Staircase detail) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.200 Sea water intake G.A & R/F Detail of +12.6 M Level 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.201 Sea water intake G.A & R/F detail of +10.0M Level 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.202 Sea Water Pond Capacity, Load Calculation & Structural Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.203 Sea Water Pond Retaining Wall Reinforcement 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.204 Sea Water Pond Foundation Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.205 Sea Water Pond Sleeve Layout (Sea Water Pond GA LAYOUT) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.206 Sea Water Pond Reinforcement Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.207 Sea Water Pond Concrete Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.208 Other Sea Water Pond Required Document / Drawing 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.209 SEA WATER POND GA LAYOUT & SECTION 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.210 SEA WATER POND SECTION DETAIL 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.211 SEA WATER POND CUTTING & FILLING SECTIONS 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.212 RF DETAIL for SEA WATER POND (2 SHEET ) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.213 SEA WATER POND WITH EXISTING COUNTOUR PLAN 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.214 SEA WATER POND CUTTING & FILLING SECTIONS 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.215 Electrical, Administration & Control Building Architecture Layout(Ground & First floor)Sheet-1 0.417%
80.000% 0.000% 80.000% 0.333%
I.5.216 Electrical, Administration & Control Building Architecture Layout(Ground & First floor)Sheet-2 0.417%
80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Architecture Layout(second floor & elevation
I.5.217 0.417%
)Sheet-1 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Architecture Layout(second floor & elevation
I.5.218 0.417%
)Sheet-2 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Architecture Layout(THIRD TERRACE FLOOR &
I.5.219 0.417%
SECTION )Sheet-1 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Architecture Layout(THIRD TERRACE FLOOR &
I.5.220 0.417%
SECTION )Sheet-2 80.000% 0.000% 80.000% 0.333%
Electrical, Administration & Control Building Architecture Layout(THIRD TERRACE FLOOR &
I.5.221 0.417%
SECTION )Sheet-3 80.000% 0.000% 80.000% 0.333%
I.5.222 Steam Turbine Hall Architecture Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.223 Analyzer Building Architecture Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.224 BOP Water Treatment Building Architecture Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.225 Oily & Waste Water Treatment House Architecture Layout 0.417% 50.000% 0.000% 50.000% 0.208%
I.5.226 Mosque Architecture Layout(PLANT ,SECTION & ELEVATION) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.227 Guard House Architecture Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.229 Sea Water Intake Architecture Layout (Sheet -1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.230 Sea Water Intake Architecture Layout (Sheet -2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.231 Sea Water Intake Architecture Layout (3 Sheet ) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.232 Building Painting & Coating Spesification 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.233 Pipe & Cable Rack Painting & Coating Spesification 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.234 Water Tank Painting & Coating Spesification 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.235 SGT-800 Earthing Point Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.236 Perimeter Wall Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.237 Slope Protection Layout 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.238 Plant Gravel Layout 0.417% 0.000% 0.000% 0.000% 0.000%
I.5.239 Plant Grass Layout 0.417% 0.000% 0.000% 0.000% 0.000%
I.5.240 Other Landscape Required Document & Drawing 0.417% 0.000% 0.000% 0.000% 0.000%
I.5.241 Design Calculation Electrical Room for WTP 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.242 Design Calculation-Electrical Room For WTP 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.243 Electrical room for WTP base plate & rafter plan and section (4sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.244 Architectural of electrical control room for WTP (2 sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.245 Electrical,Administration & Control Building G.A & R/F Detail Of +14.475m Lvl. 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.246 Electrical,Administration & Control Building MUMTY & WATER TANK G.A & R/F Detail 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.247 Workshop And Warehouse Floor Decking Arrangement At (+)3.7 M Lev 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.248 Workshop & Warehouse Framing Elevation (2-Sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.249 Structural Design Calculation-of Foundation GTG Analysis 0.417% 80.000% 0.000% 80.000% 0.333%
Structural Design Calculation of gas turbine Ventilation outlet unit & CO2 Cabinet
I.5.250 0.417%
(attachment "F") 80.000% 0.000% 80.000% 0.333%
I.5.251 Structural Design Calculation of Turbine removal system area (attachment "I") 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.252 Structural Design Calculation of generator roror revision tool support (attachment "J") 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.253 SGT-800 Foundation Layout R/F EMBEDDED DETAILS CABLE PIPES & DRAINAGE (sheet-3) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.254 GA & R/F DETAILS FOR BACKWASH,POTABLE & SERVICE WATER TANK & BWRO PERMEATE TANK 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.255 G.A & R/F DETAILS FOR BACKWASH ,POTABLE & SERVICE WATER TANK & BWRO Permeate Tank 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.256 G.A & R/F DETAIL FOR ROUGHING & POLISHING FILTER SYSTEM 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.257 G.A & R/F DETAIL FOR ROUGHING & POLISHING FILTER SYSTEM 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.258 G.A & R/F LAYOUT PLAN FOR SWRO PERMEATE & DENIN WATER TANKS FDN 0.417% 80.000% 0.000% 80.000% 0.333%
G.A & R/F Section Detail For SWRO Permeate & Denim Water Tanks FDN.(TK-150 A/B & TK-
I.5.259 0.417%
109 A/B) 80.000% 0.000% 80.000% 0.333%
I.5.260 Structural Design Calculation Of Foundation-Water Treatment Plant System 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.261 Key Plan Of Equipment Layout For Water Treatment Plant 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.262 SGT-1 800 Lubrication oil Cooler Foundation Layout Plant & RF detail 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.263 SGT-2 800 Lubrication oil Cooler Foundation Layout Plant & RF detail 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.264 SGT-800/1 CO2 Foundation Layout Plan & RF detail of turbine removal area 0.417% 100.000% 0.000% 100.000% 0.417%
I.5.265 SGT-800/2 CO2 Foundation Layout Plan & RF detail of turbine removal area 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.266 Steam turbine Generator R/F Detail Foundation Layout Plan at (EL- 5.3m & -3.20m Lvl) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.267 Steam turbine Generator R/F Detail Foundation Layout Plan at (EL -2.000 Lvl) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.268 Steam turbine Generator R/F Detail Foundation Layout Plan at (EL -0.0, 0.10 & 1.005,1.10m Lvl) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.269 Steam turbine generator R/F Detail of Foundation & section (Long) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.270 Steam turbine Generator R/F detail of Foundation section & pedestal details 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.271 Steam turbine Generator R/F detail of Foundation & pedestal details 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.272 Steam trubine generator Earthing Point Layout Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.273 Steam turbine generator with auxiliary EQT. Layout Plan 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.274 G.A Section Detail Of Retaining Wall For STG 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.275 R/F Section Detail Of Retaining Wall For STG 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.276 Plan & R/F Details Of SGT-800/1 Cable Trench 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.277 G.A & R/F.Detail For Bwro System Foundation 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.278 Sea Water Intake G.A Detail Of Foundation Plant Section 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.279 GA Details For Cleaning/Flushing System & Dosing System Foundation 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.280 R/F Details For Cleaning / Flushing System & Dosing System Foundation 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.281 G.A & R/F Detail At El.+1.40m Level Of Cleaning / Flushing System & Dosing System Foundation 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.282 GA & R/F DETAILS FOR BACKWASH,POTABLE & SERVICE WATER TANK & BWRO PERMEATE TANK 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.283 GA & R/F DETAILS FOR BACKWASH,POTABLE & SERVICE WATER TANK & BWRO PERMEATE TANK 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.284 G.A & R/F DETAILS FOR BACKWASH ,POTABLE & SERVICE WATER TANK & BWRO Permeate Tank 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.285 G.A & R/F DETAILS FOR BACKWASH ,POTABLE & SERVICE WATER TANK & BWRO Permeate Tank 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.286 G.A & R/F DETAIL FOR ROUGHING & POLISHING FILTER SYSTEM 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.287 G.A & R/F DETAIL FOR ROUGHING & POLISHING FILTER SYSTEM 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.288 G.A & R/F DETAIL FOR ROUGHING & POLISHING FILTER SYSTEM 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.289 G.A & R/F DETAIL FOR ROUGHING & POLISHING FILTER SYSTEM 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.290 G.A & R/F LAYOUT PLAN FOR SWRO PERMEATE & DENIN WATER TANKS FDN 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.291 Electrical room for WTP base plate & rafter plan and section (4sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.292 G.A & R/F LAYOUT PLAN FOR SWRO PERMEATE & DENIN WATER TANKS FDN 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.293 G.A & R/F Section Detail For SWRO Permeate & Denim Water Tanks FDN.(TK-150 A/B & TK-109 A/B) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.294 Structural Design Calculation-Boiler Feed Pump Foundation For HRSG-1 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.295 Structural Design Calculation-Boiler Feed Pump Foundation For HRSG-2 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.296 G.A For Foundation Of Boiller Feed Pump For (HRSG-1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.297 R.F For Foundation Of Boiller Feed Pump For (HRSG-1) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.298 G.A For Foundation Of Boiller Feed Pump For (HRSG-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.299 R.F For Foundation Of Boiller Feed Pump For (HRSG-2) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.292 Architectural of electrical control room for WTP (2 sheet) 0.417% 80.000% 0.000% 80.000% 0.333%
I.5.293 G.A & R/F LAYOUT PLAN FOR SWRO PERMEATE & DENIN WATER TANKS FDN 0.417% 80.000% 0.000% 80.000% 0.333%
TOTAL CIVIL, STRUCTURAL & ARCHITECHTURAL 99.625%