Você está na página 1de 15

Table

of Contents
Section 1 – General Description ................................................................................................. 1 

Section 2 – Load Analysis ............................................................................................................ 1 

Section 3 – Voltage Drop Calculations ........................................................................................ 1 

Section 4 – Short Circuit Current Analysis .................................................................................. 1 

Section 5 – Arc Flash Hazard Analysis ......................................................................................... 2 

Section 6 – Power Company Correspondence ........................................................................... 2 

List of Appendices
Appendix A ‐ Load Analysis 
Appendix B ‐ Voltage Drop Calculations 
Appendix C ‐ Short Circuit Current Analysis 

Appendix D ‐ Arc Flash Hazard Analysis 

Appendix E ‐ Power Company Correspondence 
   

Page | i  
  Power Design Analysis Report ‐ 4/11/2016 
Section 1 – General Description 
The  purpose  of  this  report  is  to  document  the  conditions  of  location  of  data,  analysis, 
methodology  and  conclusions  reached  concerning  the  power  systems  designed  for  the  FTE 
Minneola  Interchange  ITS  project.  The  Power  Design  Analysis  Report  (PDAR)  includes:  Load 
Analysis, Voltage Drop calculations, Short Circuit Current Analysis, Arc Flash Hazard Analysis, and 
Power Service Coordination. 

Section 2 – Load Analysis 
The results of load analysis are provided in Appendix A as part of panelboard schedules given on 
the  ITS  contract  drawings.  The  results  are  summarized  in  panelboard  schedules  based  on 
connected  and  demand  loads.  The  total  loads  for  branch  and  main  feeder  circuits  in  terms  of 
amps are less than the branch and main circuit breaker current ratings.  

Section 3 – Voltage Drop Calculations 
Voltage drop calculations were conducted for a combination of feeder and branch circuits with 
the longest runs, highest loads, or worst case scenarios within the project limits. An acceptable 
voltage drop criteria of less than 5% is obtained for combination of branch and feeder circuits. 
The results of voltage drop calculations for the load centers are provided in the Appendix B. The 
conduits are properly sized to ensure the power conductors can be pulled from pull box to pull 
without complication and to meet NEC requirements.  

Section 4 – Short Circuit Current Analysis 
The  Short  Circuit  Current  Analysis  (SCCA)  performed  for  this  submittal  is  based  on  estimated 
available fault currents on the secondary sides of the local power company’s transformers. The 
analysis  was  performed  at  all  service  locations  designed  in  and  impacted  by  this  project.  ETAP 
Version  12.6.0  is  used  to  create  models  of  each  electrical  distribution  systems  from  the  utility 
service  transformer  through  the  load  center  to  the  first  branch  circuit  device.    Data  collected 
from  conversations  with  the  utility,  site  investigation,  record  documentation,  and  proposed 
design  are  used  to  best  model  the  electrical  systems.  All  calculated  results  will  be  included  in 
Appendix C. 

Power Design Analysis Report ‐ 4/11/2016  Page | 1  
 
Section 5 – Arc Flash Hazard Analysis 
Arc  Flash  Hazard  Analysis  (AFHA)  performed  for  this  submittal  is  based  on  estimated  available 
fault  currents  on  the  secondary  sides  of  the  local  power  company’s  transformers.  The  local 
power company is in process of providing information on their proposed transformers including 
available  fault  currents  and  all  short  circuit  current  calculations  will  be  updated  for  the  final 
submittal. The AFHA calculations will be performed using ETAP Version 12.6.0, and results will be 
based on the IEEE 1584 method which will be provided in Appendix D. The available short circuit 
current provided by the utility may be a worst case calculation assuming an infinite bus on the 
primary  and  the  lowest  possible  transformer  impedance  the  utility  would  ever  install.    As  the 
available  fault  currents  for  the  sites  investigated  will  not  exceed  25kA  the  tables  provided  in 
NFPA 70E are applicable for use in the Turnpike’s Employee Safety Program.  NFPA 70E (2012) 
Table  130.7(C)(15)(a)  Hazard/Risk  Category  provides  recommended  Personal  Protective 
Equipment (PPE) that, as a minimum, should be utilized for different types of tasks. Refer to the ITS
Power Service Details in the ITS plans for this project for Arc Flash Warning Label Information.

Section 6 – Power Company Correspondence 
AECOM  started  the  coordination  process  by  first  identifying  the  local  power  utility  company  in 
the  vicinity  of  the  project:  SECO.  Multiple  phone  conversations  with  the  power  company 
representatives  have  been  made  in  order  to  provide  them  with  a  detailed  description  of  the 
project,  discussing  the  project’s  power  requirements,  and  providing  them  with  the  appropriate 
information  to  establish  the  power  service  locations  and  requirements.  The  standard  operating 
voltage  for  the  proposed  ITS  is  120/240V,  single  phase,  3‐Wire  system.  See  Appendix  E  for 
the  service point letter from SECO, which contains the maximum available short circuit current. .

Power Design Analysis Report ‐ 4/11/2016  Page | 2  
APPENDIX A 

Load Analysis 

Power Design Analysis Report ‐ 4/11/2016 
APPENDIX B 

Voltage Drop Calculations 

Power Design Analysis Report ‐ 4/11/2016 
SINGLE PHASE CIRCUIT VOLTAGE DROP CALCULATIONS FOR MINNEOLA INTERCHANGE

PROJECT NAME: SR 91 FPID 433830-1-52-01


Vworking 240 OVERALL AMPS 5.78 VDROP% 0.10 VDROP 0.24
KVA 1.39
SAFETY
1
MARGIN

AMPS PER Overall DISTANCE CABLE Resistance


CKT # FROM NODE # STA TO NODE # STA INPUT WATTS VDROP
CABINET AMPS (FT) (AWG) 
Total Amp 5.78 VDROP 0.24
FD CKT TXFMR 0 METER 5.78 5.78 1386.02 107 2 0.04 0.24
SINGLE PHASE CIRCUIT VOLTAGE DROP CALCULATIONS FOR MINNEOLA INTERCHANGE
VDROP%
PROJECT NAME: SR 91 FPID 433830-1-52-01
SERVICE 0.10 VDROP
Vworking 240 OVERALL AMPS 5.78 FEEDER 3.15 FEEDER 7.56
KVA 1.39 TOTAL 3.25
SAFETY MARGIN 1

AMPS PER Overall INPUT FEEDER BRANCH BRANCH DISTANCE CABLE Resistance
CKT # FROM NODE # STA TO NODE # STA VDROP VDROP%
LOCATION AMPS WATTS WATTS DEVICE WATTS (FT) (AWG) 
Total Amp for CKT 1 5.78 FEEDER VDROP 7.56
CKT-1 METER AT 91-279.0-NB 243+00 CCTV/VDS-91-279.0-SB 6625+05 1.28 5.78 306.0 0.0 0 0.0 1330 6 1.31 7.54 3.14
CKT-1 CCTV/VDS-91-279.0-SB 6625+05 OUTLET NA 4.50 4.50 1080 0 0 0 5 6 0.00 0.02 0.01
APPENDIX C 

Short Circuit Current Analysis 

Power Design Analysis Report ‐ 4/11/2016 
One-Line Diagram - OLV1 (Short-Circuit Analysis)

100000000 MVAsc
Power

1330 ft
Network2 2-1/C 6

0.17
3 kA
(LL)
Transformer, 3 Wire .173 (LL)
25 kVA ITS Disconnect LN
5.5 0.24 kV
kA (
AB)
5.48 (AB) 20 A
meter
0.17
107 ft 0.24 kV 3 kA
(LL) .173 (LL)
3-1/C 2 ITS Disconnect LD
2.8
kA (
AB) 2.78 (AB) 0.24 kV
Main Disconnect LN
0.24 kV 5 ft
2-1/C 6
30 A

2.8
kA (
AB)
ITS XFMR
2.78 (AB) 1.5 kVA
Main Disconnect LD
0.24 kV

15 ft
10 ft
3-1/C 2 2-1/C 6
2.6 0.20
kA ( 6 kA
AB) 2.59 (AB) (LL) .206 (LL)
Panelboard LN ITS Cabinet Enclosure
0.24 kV 0.24 kV

Panelboard
1Ph-3W

page 1 13:19:41 Apr 26, 2016 Project File: ITS_Minneola_04-18-16


APPENDIX D 

Arc Flash Hazard Analysis 

Power Design Analysis Report ‐ 4/11/2016 
One-Line Diagram
One-Line Diagram -- OLV1
OLV1(Arc-Flash Analysis)
(Short-Circuit Analysis)

100000000 MVAsc
Power

1330 ft
Network2 2-1/C 6

Ia"
= .1
73 k
Transformer, 3 Wire A
25 kVA ITS Disconnect LN
Ia" 0.24 kV
= 3.
11 k Level 0
A FCT Not Determined 20 A
AFB = 1.41
meter IE = 1.06 @18"
Ia"
107 ft 0.24 kV = .1
73 FCT = 10.396
kA
3-1/C 2 ITS Disconnect LD
Ia"
= 1. 0.24 kV
86 k
A FCT Not Determined
Main Disconnect LN Level 0
AFB = 0.35
0.24 kV 5 ft IE = 0.07 @18"
2-1/C 6 FCT = 0.647
30 A

Ia"
= 1.
86 k
ITS XFMR
A 1.5 kVA
Main Disconnect LD
0.24 kV
Level 0
AFB = 0.38
15 ft IE = 0.08 @18"
FCT = 0.010 10 ft
3-1/C 2 2-1/C 6
Ia" Ia"
= 1. = .2
76 k 06 k
A A
Panelboard LN ITS Cabinet Enclosure
0.24 kV 0.24 kV
Level 0 Level 0
AFB = 0.36 AFB = 0.39
IE = 0.07 @18" IE = 0.08 @18"
FCT = 0.010 FCT = 0.667
Panelboard
1Ph-3W

page 1 13:26:20 Apr 26, 2016 Project File: ITS_Minneola_04-18-16


APPENDIX E 

Power Company Correspondence 

Power Design Analysis Report ‐ 4/11/2016 
Customer Name: NEW MINNEOLA TRNPIKE

Service Location: ACCT # 9603848901-


Site Name: URD/ TX #223659 – NEW PENDING
Person Requesting Information: OMNI COMMUNICATIONS ...
Inspecting Authority: LAKE COUNTY

Date: 03-25-2016

To Whom it May Concern:

The calculated maximum available short circuit current (SCA) requested at the point of
delivery for the above referenced service location is 5,482 amps at the secondary
terminals of the transformer. According to the plans submitted the site will be served by a
single 25 kva total, 1 phase, 120/240v URD/TX

Because of constant changes in our system due to load growth, the available short circuit
current could increase over time. Electrical protective equipment should therefore be
checked periodically to insure its adequacy. Sumter Electric Cooperative will furnish this
information any time on request.

If further information is desired, please contact your local Sumter Electric Cooperative
engineering representative.

Thank you,

Jerry Bolduc
Engineering
SECO ENERGY
Office (352) 569-9633
Fax (352) 793-2563
Cell (352) 274-2896

Você também pode gostar