PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014

Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Wadi Aba See
Seela 204 25-Jan-18 19-Sep-18 19-Sep
General 204 25-Jan-18 19-Sep-18 19-Sep
A1000 Starting 0 25-Jan-18 Starting
A1005 RO & Excavation Permit 45 25-Jan-18 18-Mar-18 -18 18-Mar-18
A1010 Finishing 0 19-Sep-18 Finishin
Line No 01,
01 Dia. 400mm, Chainage from 0+000 to 1+304 56 21-Jun-18 25-Aug-18 25-Aug-18, Line
A1020 Setting Out 3 21-Jun-18 24-Jun-18 21-Jun-18 24-Jun-18
A1030 Safety Arrangment 10 25-Jun-18 05-Jul-18 25-Jun-18 05-Jul-18
A1040 Excavation - Trail pits 32 25-Jun-18 31-Jul-18 25-Jun-18 31-Jul-18
A1050 Leveling & Bedding 11 09-Jul-18 21-Jul-18 09-Jul-18 21-Jul-18
A1060 Dry Swabbing, Pipe Laying , Alignment, Heatsherinkable Joints & Peel off Test 18 12-Jul-18 01-Aug-18 12-Jul-18 01-Aug-18
A1070 Surrounding & Thrush Blocks 12 24-Jul-18 06-Aug-18 24-Jul-18 06-Aug-18
A1080 1st Layer Backfilling 4 07-Aug-18 11-Aug-18 07-Aug-18 11-Aug-18
A1090 2nd Layer Backfilling 4 12-Aug-18 15-Aug-18 12-Aug-18 15-Aug-18
A1100 3rd Layer Backfilling 4 16-Aug-18 20-Aug-18 16-Aug-18 20-Aug-18
A1110 Final Layer Backfilling 4 21-Aug-18 25-Aug-18 21-Aug-18 25-Aug-18
Line No 02
02, Dia. 400mm, Chainage from 0+000 to 0+037 41 28-Jul-18 12-Sep-18 12-Sep-1
A1140 Setting Out 1 28-Jul-18 28-Jul-18 28-Jul-18 28-Jul-18
A1150 Safety Arrangment 2 29-Jul-18 30-Jul-18 29-Jul-18 30-Jul-18
A1160 Excavation - Trail pits 5 31-Jul-18 05-Aug-18 31-Jul-18 05-Aug-18
A1170 Leveling & Bedding 2 14-Aug-18 15-Aug-18 14-Aug-18 15-Aug-18
A1180 Dry Swabbing, Pipe Laying , Alignment, Heatsherinkable Joints & Peel off Test 4 21-Aug-18 25-Aug-18 21-Aug-18 25-Aug-18
A1190 Surrounding & Thrush blocks 2 30-Aug-18 01-Sep-18 30-Aug-18 01-Sep-18
A1200 1st Layer Backfilling 2 04-Sep-18 05-Sep-18 04-Sep-18 05-Sep-18
A1210 2nd Layer Backfilling 2 06-Sep-18 08-Sep-18 06-Sep-18 08-Sep-18
A1220 3rd Layer Backfilling 2 09-Sep-18 10-Sep-18 09-Sep-18 10-Sep-18
A1230 Final Layer Backfilling 2 11-Sep-18 12-Sep-18 11-Sep-18 12-Sep-1
Line No 03
03, Dia. 400mm, Chainage from 0+000 to 1+373 81 19-Mar-18 20-Jun-18 20-Jun-18, Line No 03, Dia. 400mm, Cha
A1260 Setting Out 3 19-Mar-18 21-Mar-18 19-Mar-18 21-Mar-18
A1270 Safety Arrangment 15 22-Mar-18 08-Apr-18 22-Mar-18 08-Apr-18
A1280 Excavation - Trail pits 43 25-Mar-18 13-May-18 25-Mar-18 13-May-18
A1290 Leveling & Bedding 33 08-Apr-18 15-May-18 08-Apr-18 15-May-18
A1300 Dry Swabbing, Pipe Laying , Alignment, Heatsherinkable Joints & Peel off Test 38 11-Apr-18 24-May-18 11-Apr-18 24-May-18
A1310 Surrounding 32 22-Apr-18 28-May-18 22-Apr-18 28-May-18
A1320 1st Layer Backfilling 5 29-May-18 03-Jun-18 29-May-18 03-Jun-18
A1330 2nd Layer Backfilling 5 04-Jun-18 09-Jun-18 04-Jun-18 09-Jun-18
A1340 3rd Layer Backfilling 5 10-Jun-18 14-Jun-18 10-Jun-18 14-Jun-18
A1350 Final Layer Backfilling 5 16-Jun-18 20-Jun-18 16-Jun-18 20-Jun-18
Line No 04,
04 Dia.400mm, Chainage from 0+000 to 0+035 37 08-May-18 19-Jun-18 19-Jun-18, Line No 04, Dia.400mm, Chai
A1560 Setting Out 1 08-May-18 08-May-18 08-May-18 08-May-18
A1570 Safety Arrangment 2 09-May-18 10-May-18 09-May-18 10-May-18
A1580 Excavation - Trail pits 4 12-May-18 15-May-18 12-May-18 15-May-18
A1590 Leveling & Bedding 2 26-May-18 27-May-18 26-May-18 27-May-18
A1600 Dry Swabbing, Pipe Laying , Alignment, Heatsherinkable Joints & Peel off Test 3 29-May-18 31-May-18 29-May-18 31-May-18

Remaining Level of Effort Actual Work Critical Remaining ... Page 1 of 7 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014
Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A1610 Surrounding 2 09-Jun-18 10-Jun-18 09-Jun-18 10-Jun-18
A1620 1st Layer Backfilling 2 11-Jun-18 12-Jun-18 11-Jun-18 12-Jun-18
A1630 2nd Layer Backfilling 2 13-Jun-18 14-Jun-18 13-Jun-18 14-Jun-18
A1640 3rd Layer Backfilling 2 16-Jun-18 17-Jun-18 16-Jun-18 17-Jun-18
A1650 Final Layer Backfilling 2 18-Jun-18 19-Jun-18 18-Jun-18 19-Jun-18
Line No 05
05, Dia. 400mm, Chainage from 0+000 to 1+059 81 12-May-18 13-Aug-18 13-Aug-18, Line No 0
A1670 Setting Out 4 12-May-18 15-May-18 12-May-18 15-May-18
A1680 Safety Arrangment 19 16-May-18 06-Jun-18 16-May-18 06-Jun-18
A1690 Excavation - Trail pits 33 19-May-18 25-Jun-18 19-May-18 25-Jun-18
A1700 Leveling & Bedding 24 02-Jun-18 28-Jun-18 02-Jun-18 28-Jun-18
A1710 Pipe Laying , Alignment, Heatsherinkable Joints & Peel off Test 26 05-Jun-18 04-Jul-18 05-Jun-18 04-Jul-18
A1720 Surrounding & Thrush Blocks 23 16-Jun-18 11-Jul-18 16-Jun-18 11-Jul-18
A1730 1st Layer Backfilling 7 12-Jul-18 19-Jul-18 12-Jul-18 19-Jul-18
A1740 2nd Layer Backfilling 7 21-Jul-18 28-Jul-18 21-Jul-18 28-Jul-18
A1750 3rd Layer Backfilling 7 29-Jul-18 05-Aug-18 29-Jul-18 05-Aug-18
A1760 Final Layer Backfilling 7 06-Aug-18 13-Aug-18 06-Aug-18 13-Aug-18
Line No 06
06, Dia. 300mm, Chainage from 0+000 to 0+624 60 19-Mar-18 27-May-18 27-May-18, Line No 06, Dia. 300mm, Chainage fro
A1780 Setting Out 3 19-Mar-18 21-Mar-18 19-Mar-18 21-Mar-18
A1790 Safety Arrangment 12 22-Mar-18 04-Apr-18 22-Mar-18 04-Apr-18
A1800 Excavation - Trail pits 18 25-Mar-18 14-Apr-18 25-Mar-18 14-Apr-18
A1810 Leveling & Bedding 15 08-Apr-18 24-Apr-18 08-Apr-18 24-Apr-18
A1820 Pipe Laying , Alignment, Heatsherinkable Joints & Peel off Test 18 12-Apr-18 02-May-18 12-Apr-18 02-May-18
A1830 Surrounding 14 23-Apr-18 08-May-18 23-Apr-18 08-May-18
A1840 1st Layer Backfilling 4 09-May-18 13-May-18 09-May-18 13-May-18
A1850 2nd Layer Backfilling 4 14-May-18 17-May-18 14-May-18 17-May-18
A1860 3rd Layer Backfilling 4 19-May-18 22-May-18 19-May-18 22-May-18
A1870 Final Layer Backfilling 4 23-May-18 27-May-18 23-May-18 27-May-18
Chamber Construction
C 154 19-Mar-18 13-Sep-18 13-Sep-1
Line No 01 - AV Chamber at 0+005 34 01-Jul-18 08-Aug-18 08-Aug-18, Line No 01
A207 Excavation 4 01-Jul-18 04-Jul-18 01-Jul-18 04-Jul-18
A208 Leveling & Blinding 3 05-Jul-18 08-Jul-18 05-Jul-18 08-Jul-18
A209 Water Proffing ,Screeding, Shuttering & R/F for Base 5 09-Jul-18 14-Jul-18 09-Jul-18 14-Jul-18
A210 Concrete Pouring for Base 1 15-Jul-18 15-Jul-18 15-Jul-18 15-Jul-18
A211 Installation of Fittings 2 16-Jul-18 17-Jul-18 16-Jul-18 17-Jul-18
A212 R/F & Shuttering for Wall 5 18-Jul-18 23-Jul-18 18-Jul-18 23-Jul-18
A213 Concrete Pouring for Wall 1 24-Jul-18 24-Jul-18 24-Jul-18 24-Jul-18
A214 De shuttering & Curing the wall 2 25-Jul-18 26-Jul-18 25-Jul-18 26-Jul-18
A215 Surface leveling & primer 3 28-Jul-18 30-Jul-18 28-Jul-18 30-Jul-18
A216 Water Proffing for Wall 6 28-Jul-18 02-Aug-18 28-Jul-18 02-Aug-18
A217 R/F, Shuttering & Pouring for Cover Slab 5 25-Jul-18 30-Jul-18 25-Jul-18 30-Jul-18
A218 Chamber Backfilling Layer by Layer 9 28-Jul-18 06-Aug-18 28-Jul-18 06-Aug-18
A219 Inside Painding & replace the Coverslab top of chamber 2 07-Aug-18 08-Aug-18 07-Aug-18 08-Aug-18
Line No 01 - WO Chamber at 0+605 34 12-Jul-18 20-Aug-18 20-Aug-18, Line N
A220 Excavation 4 12-Jul-18 16-Jul-18 12-Jul-18 16-Jul-18

Remaining Level of Effort Actual Work Critical Remaining ... Page 2 of 7 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014
Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A221 Leveling & Blinding 3 17-Jul-18 19-Jul-18 17-Jul-18 19-Jul-18
A222 Water Proffing ,Screeding, Shuttering & R/F for Base 5 21-Jul-18 25-Jul-18 21-Jul-18 25-Jul-18
A223 Concrete Pouring for Base 1 26-Jul-18 26-Jul-18 26-Jul-18 26-Jul-18
A224 Installation of Fittings 2 28-Jul-18 29-Jul-18 28-Jul-18 29-Jul-18
A225 R/F & Shuttering for Wall 5 30-Jul-18 04-Aug-18 30-Jul-18 04-Aug-18
A226 Concrete Pouring for Wall 1 05-Aug-18 05-Aug-18 05-Aug-18 05-Aug-18
A227 De shuttering & Curing the wall 2 06-Aug-18 07-Aug-18 06-Aug-18 07-Aug-18
A228 Surface leveling & primer 3 08-Aug-18 11-Aug-18 08-Aug-18 11-Aug-18
A229 Water Proffing for Wall 6 08-Aug-18 14-Aug-18 08-Aug-18 14-Aug-18
A230 R/F, Shuttering & Pouring for Cover Slab 5 06-Aug-18 11-Aug-18 06-Aug-18 11-Aug-18
A231 Chamber Backfilling Layer by Layer 9 08-Aug-18 18-Aug-18 08-Aug-18 18-Aug-18
A232 Inside Painding & replace the Coverslab top of chamber 2 19-Aug-18 20-Aug-18 19-Aug-18 20-Aug-18
Line No 01- 3BV +01AV Combain Chamber at 1+225 34 28-Jul-18 04-Sep-18 04-Sep-18, L
A233 Excavation 4 28-Jul-18 31-Jul-18 28-Jul-18 31-Jul-18
A234 Leveling & Blinding 3 01-Aug-18 04-Aug-18 01-Aug-18 04-Aug-18
A235 Water Proffing ,Screeding, Shuttering & R/F for Base 5 05-Aug-18 09-Aug-18 05-Aug-18 09-Aug-18
A236 Concrete Pouring for Base 1 11-Aug-18 11-Aug-18 11-Aug-18 11-Aug-18
A237 Installation of Fittings 2 12-Aug-18 13-Aug-18 12-Aug-18 13-Aug-18
A238 R/F & Shuttering for Wall 5 14-Aug-18 19-Aug-18 14-Aug-18 19-Aug-18
A239 Concrete Pouring for Wall 1 20-Aug-18 20-Aug-18 20-Aug-18 20-Aug-18
A240 De shuttering & Curing the wall 2 21-Aug-18 22-Aug-18 21-Aug-18 22-Aug-18
A241 Surface leveling & primer 3 23-Aug-18 26-Aug-18 23-Aug-18 26-Aug-18
A242 Water Proffing for Wall 6 23-Aug-18 29-Aug-18 23-Aug-18 29-Aug-18
A243 R/F, Shuttering & Pouring for Cover Slab 5 21-Aug-18 26-Aug-18 21-Aug-18 26-Aug-18
A244 Chamber Backfilling Layer by Layer 9 23-Aug-18 02-Sep-18 23-Aug-18 02-Sep-18
A245 Inside Painding & replace the Coverslab top of chamber 2 03-Sep-18 04-Sep-18 03-Sep-18 04-Sep-18
Line No 01- 3BV Combain Chamber at 1+300 34 01-Aug-18 09-Sep-18 09-Sep-18
A246 Excavation 4 01-Aug-18 05-Aug-18 01-Aug-18 05-Aug-18
A247 Leveling & Blinding 3 06-Aug-18 08-Aug-18 06-Aug-18 08-Aug-18
A248 Water Proffing ,Screeding, Shuttering & R/F for Base 5 09-Aug-18 14-Aug-18 09-Aug-18 14-Aug-18
A249 Concrete Pouring for Base 1 15-Aug-18 15-Aug-18 15-Aug-18 15-Aug-18
A250 Installation of Fittings 2 16-Aug-18 18-Aug-18 16-Aug-18 18-Aug-18
A251 R/F & Shuttering for Wall 5 19-Aug-18 23-Aug-18 19-Aug-18 23-Aug-18
A252 Concrete Pouring for Wall 1 25-Aug-18 25-Aug-18 25-Aug-18 25-Aug-18
A253 De shuttering & Curing the wall 2 26-Aug-18 27-Aug-18 26-Aug-18 27-Aug-18
A254 Surface leveling & primer 3 28-Aug-18 30-Aug-18 28-Aug-18 30-Aug-18
A255 Water Proffing for Wall 6 28-Aug-18 03-Sep-18 28-Aug-18 03-Sep-18
A256 R/F, Shuttering & Pouring for Cover Slab 5 26-Aug-18 30-Aug-18 26-Aug-18 30-Aug-18
A257 Chamber Backfilling Layer by Layer 9 28-Aug-18 06-Sep-18 28-Aug-18 06-Sep-18
A258 Inside Painding & replace the Coverslab top of chamber 2 08-Sep-18 09-Sep-18 08-Sep-18 09-Sep-18
Line No 02- 3BV Combain Chamber at 0+037 34 06-Aug-18 13-Sep-18 13-Sep-1
A259 Excavation 4 06-Aug-18 09-Aug-18 06-Aug-18 09-Aug-18
A260 Leveling & Blinding 3 11-Aug-18 13-Aug-18 11-Aug-18 13-Aug-18
A261 Water Proffing ,Screeding, Shuttering & R/F for Base 5 14-Aug-18 19-Aug-18 14-Aug-18 19-Aug-18

Remaining Level of Effort Actual Work Critical Remaining ... Page 3 of 7 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014
Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A262 Concrete Pouring for Base 1 20-Aug-18 20-Aug-18 20-Aug-18 20-Aug-18
A263 Installation of Fittings 2 21-Aug-18 22-Aug-18 21-Aug-18 22-Aug-18
A264 R/F & Shuttering for Wall 5 23-Aug-18 28-Aug-18 23-Aug-18 28-Aug-18
A265 Concrete Pouring for Wall 1 29-Aug-18 29-Aug-18 29-Aug-18 29-Aug-18
A266 De shuttering & Curing the wall 2 30-Aug-18 01-Sep-18 30-Aug-18 01-Sep-18
A267 Surface leveling & primer 3 02-Sep-18 04-Sep-18 02-Sep-18 04-Sep-18
A268 Water Proffing for Wall 6 02-Sep-18 08-Sep-18 02-Sep-18 08-Sep-18
A269 R/F, Shuttering & Pouring for Cover Slab 5 30-Aug-18 04-Sep-18 30-Aug-18 04-Sep-18
A270 Chamber Backfilling Layer by Layer 9 02-Sep-18 11-Sep-18 02-Sep-18 11-Sep-18
A271 Inside Painding & replace the Coverslab top of chamber 2 12-Sep-18 13-Sep-18 12-Sep-18 13-Sep-1
Line No 03 - AV Chamber at 0+005 34 19-Mar-18 26-Apr-18 26-Apr-18, Line No 03 - AV Chamber at 0+005
A272 Excavation 4 19-Mar-18 22-Mar-18 19-Mar-18 22-Mar-18
A273 Leveling & Blinding 3 24-Mar-18 26-Mar-18 24-Mar-18 26-Mar-18
A274 Water Proffing ,Screeding, Shuttering & R/F for Base 5 27-Mar-18 01-Apr-18 27-Mar-18 01-Apr-18
A275 Concrete Pouring for Base 1 02-Apr-18 02-Apr-18 02-Apr-18 02-Apr-18
A276 Installation of Fittings 2 03-Apr-18 04-Apr-18 03-Apr-18 04-Apr-18
A277 R/F & Shuttering for Wall 5 05-Apr-18 10-Apr-18 05-Apr-18 10-Apr-18
A278 Concrete Pouring for Wall 1 11-Apr-18 11-Apr-18 11-Apr-18 11-Apr-18
A279 De shuttering & Curing the wall 2 12-Apr-18 14-Apr-18 12-Apr-18 14-Apr-18
A280 Surface leveling & primer 3 15-Apr-18 17-Apr-18 15-Apr-18 17-Apr-18
A281 Water Proffing for Wall 6 15-Apr-18 21-Apr-18 15-Apr-18 21-Apr-18
A282 R/F, Shuttering & Pouring for Cover Slab 5 12-Apr-18 17-Apr-18 12-Apr-18 17-Apr-18
A283 Chamber Backfilling Layer by Layer 9 15-Apr-18 24-Apr-18 15-Apr-18 24-Apr-18
A284 Inside Painding & replace the Coverslab top of chamber 2 25-Apr-18 26-Apr-18 25-Apr-18 26-Apr-18
Line No 03- WO chamber at 1+315 34 14-May-18 21-Jun-18 21-Jun-18, Line No 03- WO chamber at
A389 Excavation 4 14-May-18 17-May-18 14-May-18 17-May-18
A390 Leveling & Blinding 3 19-May-18 21-May-18 19-May-18 21-May-18
A391 Water Proffing ,Screeding, Shuttering & R/F for Base 5 22-May-18 27-May-18 22-May-18 27-May-18
A392 Concrete Pouring for Base 1 28-May-18 28-May-18 28-May-18 28-May-18
A393 Installation of Fittings 2 29-May-18 30-May-18 29-May-18 30-May-18
A394 R/F & Shuttering for Wall 5 31-May-18 05-Jun-18 31-May-18 05-Jun-18
A395 Concrete Pouring for Wall 1 06-Jun-18 06-Jun-18 06-Jun-18 06-Jun-18
A396 De shuttering & Curing the wall 2 07-Jun-18 09-Jun-18 07-Jun-18 09-Jun-18
A397 Surface leveling & primer 3 10-Jun-18 12-Jun-18 10-Jun-18 12-Jun-18
A398 Water Proffing for Wall 6 10-Jun-18 16-Jun-18 10-Jun-18 16-Jun-18
A399 R/F, Shuttering & Pouring for Cover Slab 5 07-Jun-18 12-Jun-18 07-Jun-18 12-Jun-18
A400 Chamber Backfilling Layer by Layer 9 10-Jun-18 19-Jun-18 10-Jun-18 19-Jun-18
A401 Inside Painding & replace the Coverslab top of chamber 2 20-Jun-18 21-Jun-18 20-Jun-18 21-Jun-18
Line No 03- 2BV +01SV Combain Chamber at 1+320 34 19-May-18 26-Jun-18 26-Jun-18, Line No 03- 2BV +01SV Co
A376 Excavation 4 19-May-18 22-May-18 19-May-18 22-May-18
A377 Leveling & Blinding 3 23-May-18 26-May-18 23-May-18 26-May-18
A378 Water Proffing ,Screeding, Shuttering & R/F for Base 5 27-May-18 31-May-18 27-May-18 31-May-18
A379 Concrete Pouring for Base 1 02-Jun-18 02-Jun-18 02-Jun-18 02-Jun-18
A380 Installation of Fittings 2 03-Jun-18 04-Jun-18 03-Jun-18 04-Jun-18

Remaining Level of Effort Actual Work Critical Remaining ... Page 4 of 7 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014
Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A381 R/F & Shuttering for Wall 5 05-Jun-18 10-Jun-18 05-Jun-18 10-Jun-18
A382 Concrete Pouring for Wall 1 11-Jun-18 11-Jun-18 11-Jun-18 11-Jun-18
A383 De shuttering & Curing the wall 2 12-Jun-18 13-Jun-18 12-Jun-18 13-Jun-18
A384 Surface leveling & primer 3 14-Jun-18 17-Jun-18 14-Jun-18 17-Jun-18
A385 Water Proffing for Wall 6 14-Jun-18 20-Jun-18 14-Jun-18 20-Jun-18
A386 R/F, Shuttering & Pouring for Cover Slab 5 12-Jun-18 17-Jun-18 12-Jun-18 17-Jun-18
A387 Chamber Backfilling Layer by Layer 9 14-Jun-18 24-Jun-18 14-Jun-18 24-Jun-18
A388 Inside Painding & replace the Coverslab top of chamber 2 25-Jun-18 26-Jun-18 25-Jun-18 26-Jun-18
Line No 03- 3BV Combain Chamber at 1+370 34 23-May-18 01-Jul-18 01-Jul-18, Line No 03- 3BV Combain
A363 Excavation 4 23-May-18 27-May-18 23-May-18 27-May-18
A364 Leveling & Blinding 3 28-May-18 30-May-18 28-May-18 30-May-18
A365 Water Proffing ,Screeding, Shuttering & R/F for Base 5 31-May-18 05-Jun-18 31-May-18 05-Jun-18
A366 Concrete Pouring for Base 1 06-Jun-18 06-Jun-18 06-Jun-18 06-Jun-18
A367 Installation of Fittings 2 07-Jun-18 09-Jun-18 07-Jun-18 09-Jun-18
A368 R/F & Shuttering for Wall 5 10-Jun-18 14-Jun-18 10-Jun-18 14-Jun-18
A369 Concrete Pouring for Wall 1 16-Jun-18 16-Jun-18 16-Jun-18 16-Jun-18
A370 De shuttering & Curing the wall 2 17-Jun-18 18-Jun-18 17-Jun-18 18-Jun-18
A371 Surface leveling & primer 3 19-Jun-18 21-Jun-18 19-Jun-18 21-Jun-18
A372 Water Proffing for Wall 6 19-Jun-18 25-Jun-18 19-Jun-18 25-Jun-18
A373 R/F, Shuttering & Pouring for Cover Slab 5 17-Jun-18 21-Jun-18 17-Jun-18 21-Jun-18
A374 Chamber Backfilling Layer by Layer 9 19-Jun-18 28-Jun-18 19-Jun-18 28-Jun-18
A375 Inside Painding & replace the Coverslab top of chamber 2 30-Jun-18 01-Jul-18 30-Jun-18 01-Jul-18
Line No 04- 3BV+1AV Combain Chamber at 0+037 , L05 , 0+005 34 16-May-18 24-Jun-18 24-Jun-18, Line No 04- 3BV+1AV Com
A350 Excavation 4 16-May-18 20-May-18 16-May-18 20-May-18
A351 Leveling & Blinding 3 21-May-18 23-May-18 21-May-18 23-May-18
A352 Water Proffing ,Screeding, Shuttering & R/F for Base 5 24-May-18 29-May-18 24-May-18 29-May-18
A353 Concrete Pouring for Base 1 30-May-18 30-May-18 30-May-18 30-May-18
A354 Installation of Fittings 2 31-May-18 02-Jun-18 31-May-18 02-Jun-18
A355 R/F & Shuttering for Wall 5 03-Jun-18 07-Jun-18 03-Jun-18 07-Jun-18
A356 Concrete Pouring for Wall 1 09-Jun-18 09-Jun-18 09-Jun-18 09-Jun-18
A357 De shuttering & Curing the wall 2 10-Jun-18 11-Jun-18 10-Jun-18 11-Jun-18
A358 Surface leveling & primer 3 12-Jun-18 14-Jun-18 12-Jun-18 14-Jun-18
A359 Water Proffing for Wall 6 12-Jun-18 18-Jun-18 12-Jun-18 18-Jun-18
A360 R/F, Shuttering & Pouring for Cover Slab 5 10-Jun-18 14-Jun-18 10-Jun-18 14-Jun-18
A361 Chamber Backfilling Layer by Layer 9 12-Jun-18 21-Jun-18 12-Jun-18 21-Jun-18
A362 Inside Painding & replace the Coverslab top of chamber 2 23-Jun-18 24-Jun-18 23-Jun-18 24-Jun-18
Line No 05- WO chamber at 0+995 34 21-Jun-18 30-Jul-18 30-Jul-18, Line No 05- WO
A337 Excavation 4 21-Jun-18 25-Jun-18 21-Jun-18 25-Jun-18
A338 Leveling & Blinding 3 26-Jun-18 28-Jun-18 26-Jun-18 28-Jun-18
A339 Water Proffing ,Screeding, Shuttering & R/F for Base 5 30-Jun-18 04-Jul-18 30-Jun-18 04-Jul-18
A340 Concrete Pouring for Base 1 05-Jul-18 05-Jul-18 05-Jul-18 05-Jul-18
A341 Installation of Fittings 2 07-Jul-18 08-Jul-18 07-Jul-18 08-Jul-18
A342 R/F & Shuttering for Wall 5 09-Jul-18 14-Jul-18 09-Jul-18 14-Jul-18
A343 Concrete Pouring for Wall 1 15-Jul-18 15-Jul-18 15-Jul-18 15-Jul-18

Remaining Level of Effort Actual Work Critical Remaining ... Page 5 of 7 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014
Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A344 De shuttering & Curing the wall 2 16-Jul-18 17-Jul-18 16-Jul-18 17-Jul-18
A345 Surface leveling & primer 3 18-Jul-18 21-Jul-18 18-Jul-18 21-Jul-18
A346 Water Proffing for Wall 6 18-Jul-18 24-Jul-18 18-Jul-18 24-Jul-18
A347 R/F, Shuttering & Pouring for Cover Slab 5 16-Jul-18 21-Jul-18 16-Jul-18 21-Jul-18
A348 Chamber Backfilling Layer by Layer 9 18-Jul-18 28-Jul-18 18-Jul-18 28-Jul-18
A349 Inside Painding & replace the Coverslab top of chamber 2 29-Jul-18 30-Jul-18 29-Jul-18 30-Jul-18
Line No 05- 2BV +01SV Combain Chamber at 1+005 34 26-Jun-18 04-Aug-18 04-Aug-18, Line No 05-
A324 Excavation 4 26-Jun-18 30-Jun-18 26-Jun-18 30-Jun-18
A325 Leveling & Blinding 3 01-Jul-18 03-Jul-18 01-Jul-18 03-Jul-18
A326 Water Proffing ,Screeding, Shuttering & R/F for Base 5 04-Jul-18 09-Jul-18 04-Jul-18 09-Jul-18
A327 Concrete Pouring for Base 1 10-Jul-18 10-Jul-18 10-Jul-18 10-Jul-18
A328 Installation of Fittings 2 11-Jul-18 12-Jul-18 11-Jul-18 12-Jul-18
A329 R/F & Shuttering for Wall 5 14-Jul-18 18-Jul-18 14-Jul-18 18-Jul-18
A330 Concrete Pouring for Wall 1 19-Jul-18 19-Jul-18 19-Jul-18 19-Jul-18
A331 De shuttering & Curing the wall 2 21-Jul-18 22-Jul-18 21-Jul-18 22-Jul-18
A332 Surface leveling & primer 3 23-Jul-18 25-Jul-18 23-Jul-18 25-Jul-18
A333 Water Proffing for Wall 6 23-Jul-18 29-Jul-18 23-Jul-18 29-Jul-18
A334 R/F, Shuttering & Pouring for Cover Slab 5 21-Jul-18 25-Jul-18 21-Jul-18 25-Jul-18
A335 Chamber Backfilling Layer by Layer 9 23-Jul-18 01-Aug-18 23-Jul-18 01-Aug-18
A336 Inside Painding & replace the Coverslab top of chamber 2 02-Aug-18 04-Aug-18 02-Aug-18 04-Aug-18
Line No 05- 3BV Combain Chamber at 1+055 34 01-Jul-18 08-Aug-18 08-Aug-18, Line No 05
A311 Excavation 4 01-Jul-18 04-Jul-18 01-Jul-18 04-Jul-18
A312 Leveling & Blinding 3 05-Jul-18 08-Jul-18 05-Jul-18 08-Jul-18
A313 Water Proffing ,Screeding, Shuttering & R/F for Base 5 09-Jul-18 14-Jul-18 09-Jul-18 14-Jul-18
A314 Concrete Pouring for Base 1 15-Jul-18 15-Jul-18 15-Jul-18 15-Jul-18
A315 Installation of Fittings 2 16-Jul-18 17-Jul-18 16-Jul-18 17-Jul-18
A316 R/F & Shuttering for Wall 5 18-Jul-18 23-Jul-18 18-Jul-18 23-Jul-18
A317 Concrete Pouring for Wall 1 24-Jul-18 24-Jul-18 24-Jul-18 24-Jul-18
A318 De shuttering & Curing the wall 2 25-Jul-18 26-Jul-18 25-Jul-18 26-Jul-18
A319 Surface leveling & primer 3 28-Jul-18 30-Jul-18 28-Jul-18 30-Jul-18
A320 Water Proffing for Wall 6 28-Jul-18 02-Aug-18 28-Jul-18 02-Aug-18
A321 R/F, Shuttering & Pouring for Cover Slab 5 25-Jul-18 30-Jul-18 25-Jul-18 30-Jul-18
A322 Chamber Backfilling Layer by Layer 9 28-Jul-18 06-Aug-18 28-Jul-18 06-Aug-18
A323 Inside Painding & replace the Coverslab top of chamber 2 07-Aug-18 08-Aug-18 07-Aug-18 08-Aug-18
Line No 06- 3SV Combain Chamber at 0+005 34 25-Mar-18 02-May-18 02-May-18, Line No 06- 3SV Combain Chamber at 0+005
A298 Excavation 4 25-Mar-18 28-Mar-18 25-Mar-18 28-Mar-18
A299 Leveling & Blinding 3 29-Mar-18 01-Apr-18 29-Mar-18 01-Apr-18
A300 Water Proffing ,Screeding, Shuttering & R/F for Base 5 02-Apr-18 07-Apr-18 02-Apr-18 07-Apr-18
A301 Concrete Pouring for Base 1 08-Apr-18 08-Apr-18 08-Apr-18 08-Apr-18
A302 Installation of Fittings 2 09-Apr-18 10-Apr-18 09-Apr-18 10-Apr-18
A303 R/F & Shuttering for Wall 5 11-Apr-18 16-Apr-18 11-Apr-18 16-Apr-18
A304 Concrete Pouring for Wall 1 17-Apr-18 17-Apr-18 17-Apr-18 17-Apr-18
A305 De shuttering & Curing the wall 2 18-Apr-18 19-Apr-18 18-Apr-18 19-Apr-18
A306 Surface leveling & primer 3 21-Apr-18 23-Apr-18 21-Apr-18 23-Apr-18

Remaining Level of Effort Actual Work Critical Remaining ... Page 6 of 7 TASK filter: All Activities
Actual Level of Effort Remaining Work Milestone © Oracle Corporation
PROJECT NAME :- EXTENSION OF DISTRIBUTION NETWORK (PHASE 6): PACKAGE E, GTC 644E/2014
Execution Plan for Wadi Aba Seela

Activity ID Activity Name Original Start Finish 2018


Duration
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
A307 Water Proffing for Wall 6 21-Apr-18 26-Apr-18 21-Apr-18 26-Apr-18
A308 R/F, Shuttering & Pouring for Cover Slab 5 18-Apr-18 23-Apr-18 18-Apr-18 23-Apr-18
A309 Chamber Backfilling Layer by Layer 9 21-Apr-18 30-Apr-18 21-Apr-18 30-Apr-18
A310 Inside Painding & replace the Coverslab top of chamber 2 01-May-18 02-May-18 01-May-18 02-May-18
Line No 06- 2SV Combain Chamber at 0+624 34 15-Apr-18 23-May-18 23-May-18, Line No 06- 2SV Combain Chamber at
A285 Excavation 4 15-Apr-18 18-Apr-18 15-Apr-18 18-Apr-18
A286 Leveling & Blinding 3 19-Apr-18 22-Apr-18 19-Apr-18 22-Apr-18
A287 Water Proffing ,Screeding, Shuttering & R/F for Base 5 23-Apr-18 28-Apr-18 23-Apr-18 28-Apr-18
A288 Concrete Pouring for Base 1 29-Apr-18 29-Apr-18 29-Apr-18 29-Apr-18
A289 Installation of Fittings / shutdown 2 30-Apr-18 01-May-18 30-Apr-18 01-May-18
A290 R/F & Shuttering for Wall 5 02-May-18 07-May-18 02-May-18 07-May-18
A291 Concrete Pouring for Wall 1 08-May-18 08-May-18 08-May-18 08-May-18
A292 De shuttering & Curing the wall 2 09-May-18 10-May-18 09-May-18 10-May-18
A293 Surface leveling & primer 3 12-May-18 14-May-18 12-May-18 14-May-18
A294 Water Proffing for Wall 6 12-May-18 17-May-18 12-May-18 17-May-18
A295 R/F, Shuttering & Pouring for Cover Slab 5 09-May-18 14-May-18 09-May-18 14-May-18
A296 Chamber Backfilling Layer by Layer 9 12-May-18 21-May-18 12-May-18 21-May-18
A297 Inside Painding & replace the Coverslab top of chamber 2 22-May-18 23-May-18 22-May-18 23-May-18
Testing & C
Commission 103 23-May-18 19-Sep-18 19-Sep
9 Bar Test
Te 97 23-May-18 12-Sep-18 12-Sep-1
A204 Line No 01 & 02 2 11-Sep-18 12-Sep-18 11-Sep-18 12-Sep-1
A205 Line No 03,04 & 05 3 07-Aug-18 09-Aug-18 07-Aug-18 09-Aug-18
A206 Line No 06 3 23-May-18 26-May-18 23-May-18 26-May-18
Sterilization & Water Sample
Steriliza 5 15-Sep-18 19-Sep-18 19-Sep
A155 Flushing & Water Sample collection 5 15-Sep-18 19-Sep-18 15-Sep-18 19-Sep