Escolar Documentos
Profissional Documentos
Cultura Documentos
Internship Report
Declaration
We declare that this report is an original work of us and which is submitted in partial
fulfillment of the internship program in placement of practices during four months. This report
has not been submitted earlier either to these university or any other institute.
DECLARATION ......................................................................................................................... I
Page | ii
BDU/BiT/FECE
PROJECT ................................................................................................................................. 36
REFERENCE ........................................................................................................................... 42
Page | iii
BDU/BiT/FECE
List of figures
Figure 1. 1: The Over All Organizational Structure of EEP ...................................................... 4
Page | iv
BDU/BiT/FECE
List of Acronyms
EEPCO Ethiopian Electric Power Corporation
EEP Ethiopian Electric Power
GC Gregorian Calendar
GHz Giga Watt Hertz
KV Kilo Volt
HVAC High Voltage Alternating Current
VT Voltage Transformer
SF6 Sulfur Hexafluoride
I Current
Page | v
BDU/BiT/FECE
Executive Summery
Internship program is a very essential tool for higher college students to learn and develop
professional skills, and to get more knowledge in practical way on what they knew
theoretically at their colleges. With this regard, we have been working in Ethiopian Electric
Power, under North Western region office, Transmission Engineering Department
Supervision and Design sub department, which is responsible for supervising and monitoring
of substations, transmission lines technical performance and provide feasibility study report, in
Dangila from February 15 to June 15/06/2017 G.C. As we have been four months’ period of
internship program in this company, we have gained a lot of knowledge and professional skills.
In addition to this, we did various activities. Our main concern on this internship period was to
select a problem and provide a feasibility study report on over loaded substations and give
recommendations to solve the problems occurred on selected substations. In this report, we
tried to complete all requirements requested and expected from us. Generally, our
internship period on EEP was great and was useful and it helped us to get experiences that
will be very important to our professions, develop technical and inter personal skills, and
strengthen our social and professional links. Mainly this internship period lets our reasoning,
Page | vi
BDU/BiT/FECE
Chapter One
Background of EEP
1.1 History of EEP
Electric power was introduced to Ethiopia in the late 19th century, during the regime of
Minilik. The first generator was given to Atse Minilik around the 1898 to give light to the
palace. In addition to the use of generator, Atse Minilik constructed the first Hydro Power Plant
on Akaki River in the year 1912 in order to supply power to small factories that had been
established in Addis Ababa. Consequently, the power supply that had been limited to small
factories, the palace and it was extended to the public places and major roads in the vicinity of
the palace. During this temporary occupation, the Italian company called Coneil overtook the
generation and distribution of electric power. The company installed generators at different
places and extended the power supply to the major towns. After the Italian were driven out
from Ethiopia in the year1941, an organization called Enemy Property Administration
was established and took overalong with other activities the generation and distribution of
power to the public. In the year1948, an organization that had been vested with the enemy
property was evolved to an organization called Shewa Electric Power. This also with limited
capacity, managed to increase the power supply not only in Shewa but also other administrative
regions. In light of its function,its name was changed “Ethiopian Electric Light and Power” in
the 1955. Soon after itsestablishment, the supervision and management of the organization was
vested in the Board of Directors appointed by the government. After eight months of its
establishment the Ethiopia Electric light and power was transformed to the “Ethiopian Electric
Light and power Authority”. The authority was engaged in the business of producing,
transmitting, distributing and selling of electric energy to the people of Ethiopia and carry on
any other lawful business incidentals or appropriate which is calculated directly or indirectly to
promote the interest of the authority or to enhance the value of its properties. At that time the
annual electricity production capacity of the authority was 35 GHz while the number of
customer was 12,500. One of the major changes in the economic sector was the transformation
of centralized command economy to the free market driven economy in the 1987.In order to
accommodate the new changes in the environment, the Ethiopia Electric light and Power
Authority was transformed to the Ethiopian Electric Power Corporation (EEPCo) in 1997 as
public enterprise was established for indefinite duration by regulation No.18/1997, and
conferred with the power Authority. The purpose of the corporation is to engage in the Page | 1
BDU/BiT/FECE
business of producing, transmitting, distributing and selling electric energy in accordance with
economic and social development policies and priorities of the government and to carry on any
other related activities that would enable it achieve its purpose. Currently the annual electricity
production capacity of the corporation is about 3112 GWH and number of customer 1.1
million. The corporation has been increasing the number of customers by more than 15%
annually, but this does not mean that the corporation has met demand for electric power.
EEPCo is required to think and work strategically to meet the power supply need of the socio-
economy development of country. The corporation has two electric power supplying systems:
The Interconnected System (ICS) and Self Contained System (SCS). The main energy source
of ICS is hydropower plant, and for the SCS mini-hydro and a number of isolated diesels
power generators allocated in various areas of the country are the energy sources. EEPCo is a
government owned corporation and it has two organizations one of this, EEP which is
responsible for the generation, transmission service of electric energy throughout
Ethiopia. The second organization is Ethiopian Electric Utility (EEU) which is responsible for
distributing and selling power to customers. However, Dangila substation is installed in 1976
E.C, which is found in North West region of Amhara.
Page | 2
BDU/BiT/FECE
In line with directives and policy guidelines issued by the Ministry of Finance and Economic
Development, to sell and pledge bonds and to negotiate and sign loan agreements with local
and international financial sources;
? To undertake any other related activities necessary for the attainment of its purposes.
EEP produces electric power from hydropower, diesel, geothermal, wind, solar, natural gas,
biomass and coal plants that provides the service of selling the electric power to its customers
mainly the Ethiopian people for house hold uses, factories, and the nearby countries like
Kenya, Sudan, and Djibouti.
Ethiopia is focusing on the development of the huge hydro potential it possesses in the Eastern
African Region. To get the required economy of scale to develop the big hydropower sites in
Ethiopia, it is compulsory to seek foreign demands for export purposes, especially, neighboring
countries of Sudan, Egypt, Djibouti, Yemen, Kenya, Eritrea, and Somalia. There are current
and potential interconnections. Ethiopia-Sudan (Current Interconnections)
Currently, Ethiopia is supplying 100MW of power to Sudan A link of double circuit 230 KV
with transfer capacity of about 400 MW is Constructed. The link starts from Bahir Dar Page | 3
BDU/BiT/FECE
substation passing through Gondar and Shehedi substations in Ethiopia and ends at Gedaref
substation in Sudan with a total length of 296 km(from Shehedi to gedarif) . Ethiopia-Djibouti
(Current Interconnections) Currently, Ethiopia is supplying 60MW of power to Djibouti a link
of Double circuit 230 KV with transfer capacity of about 400 MW is Construct .The link starts
from Dire Dawa substation in Ethiopia and ends at PK-12 substation in Djibouti with a total
length of 283 km. Ethiopia-Kenya (Potential Interconnections) the export will, possibly, be
based on firm energy. The link may start from Gilgel Gibe-III power plant and passes through
Mega substation in Ethiopia and ends at the towns of Nairobi or Eldorate in Kenya. The link
from Gilgel Gibe-III to Mega will be double circuit 400 KV HVAC. HVDC link of at least 500
KV with transfer capacity of about 600 MW is anticipated from Mega substation to Kenya
(Nairobi or Eldorate).
Page | 4
BDU/BiT/FECE
EEP is responsible for generating, transmitting, distributing and selling of electric energy
throughout the country. To fulfill this company, use a wide and interconnected work flow
therefore by using different mechanism power will be generated and this will be transmitted
and will be distributed for customers. We must consider this all system is interconnected by a
system which is called load dispatch center (LDC).
Ethiopia is a country endowed with abundant, natural recourses such as Hydro power;
Geothermal, natural gas, solar and wind energy etc. that could generate surplus electricity.
Among these only Hydro powers potential of the country is estimated to be up to 45,000 MW.
Since almost all the listed resources not yet tapped the prevailing energy source
that constitutes about 94.1 is biomass. The rest are petroleum 5.2% and electricity 0.8%.
Supply system: - The Ethiopian electric power corporation (EEP) is a sole electricity power
supplier in the country. The corporation has two electric energy supply system. These are the
interconnected system (ICS) and the self-contained system (SCS). The main energy source of
ICS is hydro and also the SCS are mini hydrous and diesel power generators allocated in
various areas of the country. For the record, most diesel power Generators are becoming out
of service because they are too much costly with little amount of power.
Inter Connected System (ICS): - The ICS consists of 12 hydro, 11 diesel standbys, one
geothermal and two wind from power plants with installed capacity of 1939.6MW, 112.3MW,
7.30MW and 81MW respectively which brought a total of 2140.2MW.
Page | 5
BDU/BiT/FECE
Self-Contained System (SCS): - The SCS consists of three small hydro and several diesel
power plants. Generation in this System is mainly by diesel power plants having an aggregate
capacity of 26.80MW.The contribution from the small hydro power plants is only 6.15MW.
2008/09 - 12 55 30 23 120
2009/10 - 12 55 30 23 120
2010/11 2 14 56 30 23 123
2011/12 5 17 57 30 23 127
Page | 6
BDU/BiT/FECE
1.5.3 Distribution
Power distribution is both ICS and SCS is effected at primary voltage of 33, and
15KV.Consisting entirely of 3-phases, 3-wire feeders and is stepped down to a utilization
voltage of 380\220 (3-phase, 4-wire) using 3-phase transformers to customer’s level.
Page | 7
BDU/BiT/FECE
Page | 8
BDU/BiT/FECE
Chapter Two
Bahir Dar Institute of Technology targeted this internship program can enable Engineering
students at their faculty to relate their theoretical knowledges gained from their department to
practical knowledge, and develop their profession skills.
design sub department and he gave us paper that have been submitted to the supervision office
Page | 9
BDU/BiT/FECE
with best wishes. Finally we met Mr.Giwon, manager of the supervision office at Dangila
substation, he welcomed us with full of kindness and explained what we will work on the
internship period and informed us that we will be with his office for the next four months and
introduces us to Mr. Fekadie, Mr. Serawdink and other stuff members and we start our intern
with eager on February 15. But to get this placement in the company it was tedious we were
spending a lot of times come and backs.
Dangila substation receives power from one incoming line. This incoming line is Gordema
substation (main supply from beles), so receives 66KV. The incoming 66KV stepped down
into 66/33kv, 66/15kv (feeders). Gordema substation (No: 2 substation in Bahir Dar) receives
power mainly from two generations, Tis -sat and Tana Beles 132kv and 400kv respectively. In
addition to this the substation can be received or send through Alamata and Mota lines. Hence,
Gordema substation can be considered as ring system. Ring system is a system that can be
received and sent. In substation 400kv from beles step down into national grid (230kv) and
then distributes into the outgoing lines, these are Gonder-1,Gonder-2,Alamata,Mota and 400kv
into markos,66kv into Bahir Dar No:1 substation and Dangla as well as 33kv into Adet. Since
Ethiopian Electric Power Corporation, EEP is associated with generation, transmission and
distribution system. In fact that after the power is generated; it has to be distributed to the
customers through high voltage transmission lines. But it is impossible to provide the
generated power from generation station directly to the customer due to different reasons. The
first and main reason is voltage drop, because the voltage drop will be high when the
transmission line becomes longer and longer. So that substations have a great role to solve the
occurrence of this problem. Since most of distributions’ fault are occurred due to over loading
and due to lacking of ability of transmission lines to carry the required power when they are
designed and constructed. So, we selected this work section to solve such problems. As a
result, customers such as residents, companies, real estates, factories and interconnected
countries can get enough and suitable power.
Page | 10
BDU/BiT/FECE
Aluminum is the most common conductor metal for overhead transmission than copper, due to
its lower cost and lighter in weight properties, and its abundant whereas copper is limited.
Most common Al conductors are
? All-Aluminum Conductor, AAC.
? All-Aluminum-Alloy Conductor, AAAC.
? Aluminum Conductor Alloy Reinforced, ACAR.
? Aluminum Conductor Steel Reinforced, ACSR.
From those Al conductors, Aluminum Conductor Steel Reinforced, ACSR, is the most
common conductor type, which consists of layers of Al strands surrounding a central core of
steel strands. Stranded conductors are easier to manufacture, since larger conductor size can be
obtained by simply adding successive layers of strands. Stranded conductors are also easier to
handle and more flexible than solid conductors, especially in large size. The use of steel
strands gives ACSR conductors a high strength to weight ratio, and for the purpose of heat
dissipation, overhead lines are bare (no insulator cover).EHV lines often have more than one
conductor per phase, these conductors are called a bundle. Bundle conductors have a lower
electric field strength of the conductor surfaces, thereby controlling corona. They also have a
smaller series reactance.
b. Insulators
Insulators provide electrical insulation between live conductors and earthed structures under
operating and over voltage conditions. Insulators are mainly made of either glazed, porcelain,
or toughened glass.
• Pin type
• Suspension type
• Shackle insulator
Page | 11
BDU/BiT/FECE
Pin type insulators are used for transmission and distribution of electric power at voltages up
to 33 KV. Beyond operating voltage of 33 KV, the pin type insulators become too bulky and
hence uneconomical.
For high voltages (greater than 33 KV), it is mostly used suspension type insulators shown in
figure below, which consists of a number of porcelain discs connected in series by metal links
in the form of a string.
greater tension. In order to relive the line of excessive tension, strain insulators are used. For
Page | 12
BDU/BiT/FECE
low voltage lines (less than 11 KV), shackle insulators are used as strain insulators. However,
for high voltage transmission lines, strain insulators consist of assembly of suspension
insulators as shown in figure below.
Insulators for transmission lines above 33KV are suspension type insulator, which consists of
discs, typically porcelain. The standard discs have a 10-inch (0.254-m) diameter, 5.75 inch
(0.146-m) spacing between centers of adjacent discs, and mechanical strength of 7500 Kg. The
number of insulator discs in a string increases with line voltage. Other types of discs include
larger units with higher mechanical strength and fog insulators for use in contaminated
areas.
Support Structures
Transmission lines employ a variety of support structures. Support structures are arranged
either in a triangular configuration to reduce tower height or in a vertical configuration to
reduce tower width. Shield Wires Shield wires located above phase conductors protect the
phase conductors against lightning. They are usually high or extreme high strength steel,
ACSR with much smaller cross section than phase conductors. The number and location of the
shield wires are selected so that almost all lightning strokes terminate on the shield wires than
on the phase conductors. Shield wires are grounded to the tower. As such, when
lightning strike shields wires, it flows harmlessly to ground, provided that the tower
impedance and tower footing resistance are small.
Page | 14
BDU/BiT/FECE
Transmission Substations
Page | 15
BDU/BiT/FECE
If protection fails or is absent lightning that strikes the electrical system introduces thousands
of kilo volts that may damage the transmission lines, and can also cause severe damage to
Transformers and other electrical or electronic devices. Lightning-produced extreme voltage
Spikes in incoming power lines can damage electrical home appliances.
Transformer
Transformer is generally a four-terminal device that can transform an AC input voltage into a
relatively higher or lower AC output voltage. A transformer usually consists of two closely
coupled coils that are designed to transfer energy between its winding circuits. A typical
transformer has two or more coils that share a common laminated iron core. One of the coils is
referred to as the primary (containing NP turns), while the other coil is called secondary
(containing NS turns). Primary coils are defined as those coils whose current is driven by an
external alternating-current source, whereas secondary coils are defined as those coils whose
voltage is induced by the varying magnetic field produced by the primary coil.
Transformer Cooling System and Methods
The main source of heat generation in transformer is its copper loss or loss and core loss.
Although there are other factors contribute heat in transformer such as hysteresis & eddy
current losses but contribution of loss dominates them. If this heat is not dissipated properly,
the temperature of the transformer will rise continually which may cause damages in paper
insulation and liquid insulation medium of transformer. So, it is essential to control the
temperature with in permissible limit to ensure the long life of transformer by reducing
thermal degradation of its insulation system. In electrical power transformer, we use external
transformer cooling system to accelerate the dissipation rate of heat of transformer. There are
different transformers cooling methods available for transformer.
Page | 16
BDU/BiT/FECE
level is detected by a float converted in to rotary motion by gear and transmitted to the external
pointer through magnet. If the indicator tilted downward then the oil should change. Oil
temperature indicator is also shows the heating up of transformer.
Winding temperature indictor: - The temperature of winding is measured and determined
indirectly. The temperature difference between the winding and coolant is the actual current in
the winding. The transformer secondary current is proportional to the current transformer
winding. The secondary current feeds a heating resistor in thermometer and so produces a
display reading of transformer load. Generally, when the loss is happened on the winding, the
heat has been developed; transformer becomes heated up and because of thermostat starts
rotating for cooling the transformer.
ONAN Cooling of Transformer
This is the simplest transformer cooling system. The full form of ONAN is "Oil Natural Air
Natural". Here natural convectional flow of hot oil is utilized for cooling. In convectional
circulation of oil, the hot oil flows to the upper portion of the transformer tank and the vacant
Place is occupied by cold oil. This hot oil which comes to upper side will dissipate heat in the
Atmosphere by natural conduction, convection & radiation in air and will become cold. In this
Way the oil in the transformer tank continually circulate when the transformer put into load.
As the rate of dissipation of heat in air depends upon dissipating surface of the oil tank, it is
essential to increase the effective surface area of the tank. So, additional dissipating surface in
the form of tubes or radiators connected to the transformer tank. This is known as radiator of
transformer or radiator.
Page | 17
BDU/BiT/FECE
Page | 18
BDU/BiT/FECE
Conservator
Conservator tank, where fitted should be assembled with its pipe work, etc. making sure that
Skated joints are oil tight and the pipe work is clean and free from moisture. The mechanism of
the float type oil gauge inside the conservator is locked to prevent damage during transit. After
placing the conservator in position, it should be released by turning the locking bolt in the
direction indicated on the plate. While feeling the conservator with transformer oil, it should
be ensured that the oil filled up to the level indicated by the oil gauge on the
conservator. On the oil gauge’s dial, there is an indication of temperature, this tells the
prescribed level of oil in the conservator at that temperature. For example, if temperature is
30°C. But during actual oil filling in conservator tank, we should commensurate with the oil
temperature at that time.
The function of conservator tank is giving the space to the oil expanded during the ambient
temperature rises. When transformer is loaded and ambient temperature rises, the volume of oil
inside transformer increases. A conservator tank of transformer provides adequate space to this
expanded transformer oil. It also acts as a reservoir for transformer insulating oil.
Silica Gel
Silica gel breather always comes as loose item. The plastic plug sealing on the top of the
breather should be removed and fitted to the associated pipe work. The oil cup at the bottom of
the breather should be removed, filled with transformer oil to the level indicated on it and then
re fitted to the position. Thus, the silica gel is prevented from absorbing moisture from
atmosphere. When the oil becomes depreciate the silica gel color becomes change from pink to
the blue this indicates the oil should be changed and silica gel itself changed into new.
Page | 19
BDU/BiT/FECE
Page | 20
BDU/BiT/FECE
Auxiliary Transformer
Auxiliary transformer is types of transformer which gives service only the compound of the
Substations. Auxiliary transformer is used to supply low voltage for AC power system inside
substation such as lighting, air conditioners and other AC supply system and DC power
system such as protection relays, batteries.
Earthing Transformer
Earthing transformer is used stabilize an external earth fault on the delta side of star -delta
power transformer. In cases where the neutral point of three phase system is not accessible like
the system connected to the delta connected side of an electrical power transformer, an
artificial neutral point may be created with help of a zigzag connected earthing transformer. In
normal condition of the system, the voltage across the winding of the earthing transformer is
1/√3 times of rated per phase voltage of the system. But when single line to ground fault
occurs on any phase of the system, zero sequence component of the earth fault current flows in
the earth and returns to the electrical power system by way of earth star point of the earthing
transformer. The rated voltage of an earthing or grounding transformer is the line to line
voltage on which it is intended to be used. Current rating of this transformer is the maximum
neutral current in Amperes that the transformer is designed to carry in fault condition
for a specific time. Generally,the time interval, for which transformer designed to carry the
maximum fault current through it safely, is taken as 30 second.
Instrument transformers
Instrument transformers are high accuracy class electrical devices used to isolate or transform
voltage or current levels. The most common usage of instrument transformers is to operate
instruments or metering from high voltage or high current circuits, safely isolating secondary
Control circuitry from the high voltages or currents. The primary winding of the transformer is
connected to the high voltage or high current circuit, and the meter or relay is connected to the
secondary circuit. The two types of instrument transformers are discussed below.
Current transformer
A current transformer works on the same principle as that of a simple transformer however it
Steps down the high current into a low level so that the range can be measured. In some
current transformers, extra cores are provided. This is done to prevent the faulty currents i.e.
the over currents, earth faults, differential protections. The extra cores of a C.T. gets saturated
as soon as the faulty currents starts flowing and thereby does not harm the main core of the
transformer and the ammeter connected. The C.T. is always connected in the line carrying Page
| 21
BDU/BiT/FECE
current. It first steps down the current to measurable form and further gives this current to the
ammeter.
A potential transformer (or voltage transformer) is used to reduce high-voltages to values that
Can be remotely monitored with ordinary voltmeters, or to provide inputs to protective relays.
It also electrically-isolates meters/relays from the high-voltage systems. They are mutual
transformers which work on the same principle as any other step-down transformer i.e. a
voltage applied to the primary winding results in a lower voltage induced into its secondary.
Page | 22
BDU/BiT/FECE
Power transformer
Power transformer is a device that is used to convert inbound electricity or voltage to a higher
or lower value in order to accommodate the current flow needed for specific purposes. Power
transformers are a normal component in the power grids of many nations, making it possible to
regulate the transfer of power to residences and commercial building without overloading the
circuit in those structures. From this perspective, the transformer can also be viewed as a safety
feature that reduces some of the risk associated with utilizing electrical current in those
settings. The two main functions of a power transformer are to transfer electrical current from
a source to a destination, and to regulate the voltage of that current before it reaches the
intended destination. In Dangila substation there three power transformers.
1. Power transformer one 15kv
2. power transformer two 15kv
3. Power transformer three 33kv
Page | 23
BDU/BiT/FECE
A tap changer is a device fitted to power transformers for regulation of the output voltage to
required levels. This is normally achieved by changing the ratios of the transformers on the
system by altering the number of turns in one winding of the appropriate transformer/s. Supply
authorities are under obligation to their customers to maintain the supply voltage between
certain limits. Tap changers can be on load or off load. On load tap changers generally consist
of a diverter switch and a selector switch operating as a unit to effect transfer current from one
voltage tap to the next. On load tap changers were introduced to power transformers as a
means of on load voltage control.
Page | 24
BDU/BiT/FECE
A switching device which can be opened or closed only under no current condition it provides
isolation of a circuit for maintenance. A disconnector, disconnect switch or isolator switch is
used to ensure that an electrical circuit is completely de-energized for service or maintenance.
High-voltage isolation switches are used in electrical substations to allow isolation of
apparatus such as circuit breakers, transformers and transmission lines, for
maintenance. The disconnector is usually not intended for normal control of the circuit, but
only for safety isolation. Disconnector can be operated either manually or automatically
(motorized disconnector). Unlike load break switches and circuit breaker, disconnectors lack a
mechanism for suppression of electric arc, which occurs when conductors carrying high
currents are electrically interrupted. Thus, they are off load devices, intended to be opened only
after current has been interrupted by some other control device. Safety regulations of the utility
must prevent any attempt to open the disconnector while it supplies a circuit. Standards in
some countries for safety may require either local motor isolators or lockable overloads (which
can bepadlocked). Substation class group operated air disconnect switches can be
defined quite simply as mechanical devices which conduct electrical current and provide an
open point in a circuit for isolation of one of the following devices: circuit breaker, circuit Page
| 25
BDU/BiT/FECE
switcher, power transformer, capacitor bank, or other. The most important functions that
disconnect switches must perform are: -
a. To open and close reliably when called upon to do so,
b. To carry current continuously without overheating
Depending upon the position in power system, the isolators can be categorized as
1. Bus side isolator: - the isolator is directly connected with main bus
2. Line side isolator: - the isolator is situated at line side of any feeder
Electrical Circuit Breaker is a switching device which can be operated manually as well as
automatically for controlling and protection of electrical power system respectively. It is a
device capable of making, breaking and electric circuit under normal and abnormal conditions
such as short circuits. The circuit breaker can protect the circuit from a high current short
circuit and through its thermal trip it can protect the circuit from overload condition. Working
Principle of Circuit Breaker,the circuit breaker mainly consists of fixed contacts and moving
contacts. In normal "on" condition of circuit breaker, these two contacts are physically
connected to each other due to applied mechanical pressure on the moving contacts. There is
an arrangement stored potential energy in the operating mechanism of circuit breaker which is
realized if switching signal given to the breaker.
Page | 26
BDU/BiT/FECE
•Low-oil content circuit breakers: - which operate with minimum amount of oil used
only for arc extinction.
•Bulk oil breakers: - these types of breaker use a large quantity of oil used for arc
extinguishing and insulating the current conducting part.
Page | 27
BDU/BiT/FECE
The function of relays is to discriminate between normal operation and fault conditions. The
OC relay has an operating coil, which is connected to the CT secondary winding, and a set of
contacts. When / I’/ exceeds a specified “pick up” value, the operating coil causes the
normally open contacts to close. When the relay contacts close, the trip coil of the circuit
breaker is energized, which then causes the circuit breaker to open. Note that the circuit
breaker doesn’t open until its operating coil is energized, either manually or by relay
operation. Based on information from instrument transformers, a decision is made and
“relayed” to the trip coil of the breaker, which opens the power circuit-hence the name relay.
Page | 28
BDU/BiT/FECE
The CT secondary I’ is the input to the over current relay operating coil. Instantaneous over
current relays respond to the magnitude of their input current. If the current magnitude I=/I’/
exceeds a specified adjustable current magnitude Ip, called the pickup current, then the relay
contacts close “ instantaneously ” to energize the circuit breaker trip coil. If I’ is less than the
pickup current Ip, then the relay contacts remain open, blocking the trip coil. Time-delay over
current relay also respond to the magnitude of their input current, but with an intentional time
delay. The time delay depends on the magnitude of the relay input current. If I’ is a large
multiple of the pickup current Ip, then the relay operates (or trips) after a small-time delay.
Differential Relay
Is a current operated relay that responds to the difference between two or more current above a
set value. Differential relays are commonly used for protecting generators, buses, and
transformers. And there are many relays used in a transmission substation. Such as: -
? Over voltage relay
? Under voltage relay
? Power relay
? Directional relay
? Thermal relay
? Auxiliary relay…etc.
Page | 29
BDU/BiT/FECE
normal conditions and neglecting internal losses, the power entering a protection zone must
be equal to the power leaving that protected zone. Any difference in these quantities
indicates a fault within the protected zone. Because of its simplicity and selectivity,
differential protection is the most common form of equipment protection. Over current
Protection:- his is a protection which mainly used as a back-up protection for transmission
lines and transformers and main protection for distribution lines. It mainly analyzes the
current on the system and act when the current is above the setting value. In substations,
there are various panels such as protective panels, measuring panels, SCADA system,
Central unit panel, AC panel and DC panels as well as batteries. But SCADA system is not
available in Dangila substation because of its establishment time (it is not modern).
Substations control room has following functions.
1. Protection
2. Metering
3. Communication with the neighbor substation and generation
4. Controlling
5. Monitoring and operating
6. Tap-Changer control
7. Control of shunt reactor for voltage control in control panel
Generally, protection, Control, monitoring and operation are performed in the control room
automatically or manual. The control panels, Protection panels etc. are housed in the control
room building of the substation. The protection functions are performed automatically by
protective relaying system and the circuit breakers.
Page | 30
BDU/BiT/FECE
Figure 2. 18:Batteries
Page | 31
BDU/BiT/FECE
During our internship period, we have been performing different tasks in transmission and
distribution substations from being punctual, loyal, and attended every day to our office. The
other duties we have been performed is knowing how the working flow seems and
discovering all the equipment used in each substation we went with our supervisor. When we
have been working on Dangila substation, we read a primary design, and discovering the
arrangement of each equipment on the substation while the control room and how it is work
out. In general, we have been working on what we must know on all aspects, and that was very
useful and helping to our profession even for the future.
Page | 32
BDU/BiT/FECE
Chapter Three
Internship provides real world experience to those looking to explore or gain the relevant
knowledge and skills required to enter a particular career field. Internships are relatively short
term in nature with the primary focus on getting some on the job training and taking what’s
learned in the classroom and applying it to the real world. An experience should enhance a
student’s academic career and personal development.
Current transformer. If 400KV is generated from the generation station the voltage
transformer should read 66KV and the current transformer should read 5A, because
66KV is set by5A. But if it is greater or less than the given voltage there is a problem
either at the transmission line or the generation station.
? How to control all substation equipment automatically in control room.
? How to control all substation equipment manually and
? Substation rehabilitation.
solutions, types and uses of major equipments that we have never seen, and mainly the Page |
33
BDU/BiT/FECE
concepts of the courses that we have learnt in class especially power system, installation,
electrical machine, energy conversion and rural electrification and modern control. We have
been thought so many things beyond the course we have taken during our four-year program.
Among these theoretical skills: -
? Understand how the formulas do work and when to use them.
? We understand how transformers do work
? Understand transformer loses like eddy current loose and core loose
? Realize transformer cooling mechanisms.
? How the corona effects occur.
? How to solve problems.
? How to do feasibility study.
Leading a team or an organization holds the most basic and key place of profession, hence
requires well trained person. We have learned a good leading skill from our supervisor and all
be responsible and trusted. The engineers that we work together Some of the leader ship skills
that we have performed are: -
o To share our problems openly and get the team involved in solutions whenever
there is a setback.
o As a leader to be clear, active by working, to have goals, mission and vision in
our ability.
o During our working time, always ready to show smiley face for the workers
and supervisor.
o Respecting differences of all team members.
o Listening and accepting the ideas of our supervisor.
o To recognize, tell and solve mistakes and problems.
Page | 34
BDU/BiT/FECE
• Responsibility and able to respond appropriately to any given situation without having to
be constantly monitored.
• Putting on work clothes, safety shoes and helmet before entering in to the construction
site or the substation.
• We try to adapt hard things at construction sites, like sun and dust.
• Self-motivation to solve problems and to create new ideas.
• Strong self-confidence
• Willingness to do what our profession asks to do without complain.
Page | 35
BDU/BiT/FECE
Chapter Four
Project
4.1 Upgrading Power Transformer of Dangila 66/ 33/15KV Substation
Rehabilitation In our four-month internship period we have been able to work a project. The
project selected by us at Dangila substation 66/15KV is Transformer Upgrading Project.
4.1.1 Introduction
Dangila Substation is under North Western region of Amhara with geographic reference
11.16N& 36.50N E where new and old housing developments around the substation with very
Small radius area exists. This substation was built by legislation Engineers 33 years ago, but it
was not maintained and upgraded until January 2017.Substation has incoming of 66KV from
Bahir Dare Substation No. 2, outgoing of 33KV to Arese Gimbha, Quancha-quakureta and
Shawora. This substation also has four 15KV outgoing line to different areas with overhead
distribution lines around the substation. This substation has two 6.3MVA transformers with
two winding. At the time, we went to observe the substation one additional transformer with
6.3MVA capacity is on test to parallel operate with the two existing transformers on the
substation.
4.3 Objective
• To minimize shaded hours and to strengthen the delivery of power to customers around
Dangila substation and nearby factories through rehabilitation of an existing 66/33/15KV
2x6.3 MVA transformers.
• To updating the substation since it is made 33 years from now.
• To fulfill the system demand supply imbalance that could be happened around Dangila
Substation.
4.4 Justification
To supply the growing demand of electricity reliably, new transformers should be addedand the
transmission line should be changed. It is expected that soon the demand for electric power
around Dangila substation will grow sharply. It is not possible to supply and satisfy the
demand with the only existing 66/33/15KV 2x6.3 MVA transformers due to its limited
capacity. Thus, to supply the factories and domestic customers, the substation should be
upgraded. Secondly to maintain the safety of the people around this substation the grounding
system should be reconstructed, the protection materials should be changed, its overall
materials should be replaced with recently updated materials, and the transmission line should
be free from any kind of contact with living house fences especially iron sheet fences.
4.5 Methodology
In this project, we have used an observation on the transformers, relays, and archives with both
primary and secondary data collection methods to gather data about the overall
substation. Primary data: This rehabilitation and upgrading project has prepared through
extensive use of primary data. It is collected from the group of people related to this
substation and professionals on the substation through the following primary data collection
methods;
a. Direct Interview: We have collected data from the substation officer, guards, and
supervisors
•Equipment and Other Painted Items: Thoroughly remove all loose paint, blisters, and scales
and paint as soon as possible.
•Galvanized Structures and Fences: The protective coating produced by the galvanizing
process is normally a long-lived coating; however, the coating will eventually fail and rust will
appear. For this reason, substations galvanized structures and fences needs to be painted at
least within 10 years depending on the substations environment. The fundamental goal of
reliability-centered maintenance is to preserve the function or operation of a system.
Page | 38
BDU/BiT/FECE
Specifically, the function that must be preserved for electric substations is the delivery of safe,
reliable electric power to customers. The concepts of reliability-centered maintenance that
have been used so effectively in other industries can be applied to electric substations in a
viable and effective maintenance approach that proactively addresses the challenges of
improving system reliability and controlling costs in an increasingly competitive energy
delivery market.
4.7 Electrical System Study of Dangila Substation
Based on the gathered data the peak loads on
From the above calculations we have seen that currently the substation is overloaded since
existing load capacity of the transformers is 405,375and375MW respectively but on these
three months the peak load is more than the average capacity of transformer on three months
I. e 385 MW therefore the substation is overloaded. Showing after one 6.3 MVA
transformers is added on the substation; 3 x6.3 MVA x0.8= 15.12 MW which is not
overloaded. Therefore adding one transformer on this substation is mandatory. Though the
transmission line can carry 15.12 MW load because the transmission line Power carrying
capacity is 66KV x 242.5A=.16.005MVA; where 242.5A is maximum capacity of the
transmission line. Therefore, three transformers work parallelly.
Page | 39
BDU/BiT/FECE
Chapter Five
Conclusion and Recommendation
5.1 Conclusion
Internship provides many benefits not only for interns, but also for hosting companies. Since the
interns could be parts of the employment, they could be an additional man power. And
accepting interns for internship could able to the company to get short-term support from
interns on many tasks. On our internship period, we knew what real world looks like and how
we could relate and practice our theoretical knowledge to the profession. Furthermore, it
helped us to improve our different skills such as leadership skills, inter communication skills,
industrial problem solving capability, and it was very helping even for the future. In the last
four months of our internship period in EEP company, we have been working on transmission
engineering department under supervision and design sub department, we have gained a hint
about substations, transmission, and each equipment of substations and how it be constructed
and how it operates. And this was very mandatory and helpful to relate our theoretical
knowledge with practical. In our stay of internship, we could have met many professions and
workers, engineers and this was very important and helping to get more knowledge and to
improve our practical skills and to understand work ethics.
Generally, our internship period was very interesting and we are satisfied in the program.And it
was successful on achieving its goal.
5.2 Recommendations
The rapid socio-economic growth and development of the Ethiopian economy needs sufficient
supply of Electrical Energy. Which means the EEP plays very great role on the development of
the country.
5.2.1 Recommendations for EEP
As we have clearly put the problems we observed on this internship period, we strongly
Recommend the EEP to:
? Upgrade substations based on their schedule.
? Upgrade substations based on feasibility studies.
? Rehabilitate aged substations, for instance. Dangila substation
? Maintain the safety of aged substations.
? Build substations based on the IEEE regulations. For example, the fences of the
substations have to be as the regulation states, the grounding cables should be
underground and the like.
Page | 40
BDU/BiT/FECE
? Implement safety rules. For instance, supply of safety shoes and clothes for substation
Operators and guards.
? Make the profile of the office with full data available.
? Make a contract deal with Ethiopian contractors for the construction of substations so
That it helps the country on many aspects.
? Upgrade the Ethiopian contractor’s capacity on building substations, transmission lines,
substations and the like on which first degree electrical engineering contractors can
perform.
? Punctuality should be accounted for all stuff of the office.
? Delaying of payment for intern students should be solved.
5.2.2 Recommendations for the Faculty
We would like to strongly recommend the faculty to:
• Announce the intern students, who their mentor is before the intern period starts,
so that the students can have a smooth relation with their mentor and the mentor
can give slight ideas what the intern’s working place looks like and on which area
the student should focus for project. As a result, students can be effective.
• The Collage should strengthen the relation with companies on which students are
being assigned on their internship period. W
5.2.3 Recommendation for the Industrial Linkage e
? Find the interns working industry around their home town.
? Pay the intern students money on time.
Page | 41
BDU/BiT/FECE
Reference
[1].Smith,Anthony M., Reliability Centered Maintenance, New York:McGraw-Hill,1993.ISBN
0-07-059046-X.”
[2]. Company manuals how to operate and the working principles of equipments.
[3]. B.L. Theraja, A.K. Theraja; “A textbook of electrical technology volume 2”
[4].IEEE std. C57.106,”Guide for Acceptance and Maintenance of insulating oil in
Equipment.”
[5]. V.K Mehta, R. Mehta; “principle of power system 2”
[6].IEEE std.P1266,”Trial-Use Guide for Evaluation and Development of Substation Life
Extension Programs.”
Page | 42