ID Task  Task Name Duration Start Qtr 2, 2017 Qtr 3, 2017

Mode Apr May Jun Jul Aug


1 CRUDE OIL METERING INSTALLATION PROJECT  66 days Mon 4/3/17
‐BONNY TERMINAL
2 CRUDE OIL METERING INSTALLATION PROJECT  53 days? Mon 4/3/17
‐BONNY TERMINAL
3 MATERIAL COLLECTION FROM SPDC YARD 4 days Thu 4/20/17 LOGISTICS
4  DETAIL SITE VISIT 2 days Wed 4/12/17 PROJECT ENGINEER,QA/QC LEAD,1 FITTER,1 FORMAN
5 WPS APPROVAL 12 days Mon 4/3/17 QA/QC LEAD
6 PREQUALIFICATION OF WELDERS AND PROCEDURE 8 days Tue 4/18/17 8 WELDERS,2 FITTERS
7 SHOP FABRICATION OF 24 " SCH 80 (7 JOINTS) 5 days Thu 4/27/17 4 WELDERS,2  HELPERS,2 FITTER
8 SHOP FABRICATION OF 24 " SCH 20 (29 JOINTS) 7 days Tue 5/2/17 4 WELDERS,2 FITTERS,2 HELPERS
9 SHOP FABRICATION OF 2 " SCH 40 (48 JOINTS) 3 days Tue 5/9/17 4 WELDERS,2 FITTERS,2 LABOUR
10 TYPE 2 SUPPORT FABRICATION ( 5 NOS) 3 days Fri 5/19/17 2 WELDERS,2 FITTERS
11 PWHT FOR 24 " SCH 80 7 JOINTS 4 days Wed 5/3/17 2 NDT 
12 PREPARATION OF STIFFNERS AND BASE PLATES 4 days Wed 5/17/17 2 FITTER
13 RADIOGRAPHIC TEST FOR TOTAL (JOINTS 84) 10 days Sun 5/7/17 2NDT
14 MPI STRUCTURAL JOINTS 1 day Sat 4/22/17 2NDT
15 FLUSHING OF 24 " LINE 1 day Fri 5/19/17 2 TECHNICIANS,2  HELPERS
16 FLUSHING OF 2 " LINE 1 day Fri 5/19/17 2 TECHNICIANS,2  HELPERS
17 HYDRO TEST OF 24 " LINE SCH 80 2 days Sat 5/20/17 2 NDT ,2 TECHNICIANS
18 HYDROTEST OF 24 " LINE SCH 20 2 days Mon 5/22/17 2 TECHNICIANS,2NDT
19 HYDRO TEST OF 2 " LINE SCH 40 1 day Mon 4/24/17 2 HELPERS,2 TECHNICIANS
20 PAINTING AND BLASTING 1ST & 2ND COAT 2 days Wed 5/24/17 2 PAINTERS,2  HELPERS
21 TRANSPORTATION OF SPOOLS AND STRUCTURES TO  3 days Fri 5/26/17 LOGISTICS
SITE
22
23 SITE WORKS 46 days Fri 4/28/17
24 SITE WORKS 46 days Fri 4/28/17 HSE
25 MOBILIZATION 3 days Wed 5/17/17
26 EQUIPMENT AND MATERIAL PREMOB 2 days Sat 5/20/17 LOGISTICS
27 SITE PREPARATION/DECOMMISION OF F& G  2 days Mon 5/22/17 1 FORMAN,4 HELPER,PROJECT ENGINEER
DETECTORS
28 TRANSPORT MATERIALS TO SITE 3 days Tue 5/23/17 LOGISTICS
29 PTW 1 day Mon 5/22/17 PROJECT ENGINEER
30 INSTALLATION OF TEMPORAL FIELD LIGHTINING &  1 day Tue 5/23/17 2 HELPERS,ELECTRICAL TECH 1,ELECTRICAL TECH 2
FIELD TENT OFFICE
31 SITE DEWATERING 1 day Wed 5/24/17 1 FORMAN,2  HELPERS
32 EXCAVATION OF TYPE 1 FOUNDATION 12NOS 2 days Thu 5/25/17 4 HELPER
33 BLINDING OF TYPE 1 FOUNDATION 3 days Mon 5/29/17 2MASON,4 HELPER
34 FORM WORK PREPARATION FOR TYPE 1 FOUNDATION 2 days Thu 6/1/17 2  HELPERS,2 CAPERNTER

35 CASTING OF TYPE 1 FOUNDATION 7 days Mon 6/5/17 2  HELPERS,2MASON


36 REMOVING OF FORM WORK 1 day Thu 6/15/17 2  HELPERS,2 CAPERNTER
37 EXCAVATION OF TYPE 3 FOUNDATION ( 8 NOS) 2 days Mon 6/12/17 1 FORMAN,4 HELPER
38 BLINDING OF TYPE 3 FOUNDATION 2 days Thu 6/15/17 2 HELPERS,2MASON
39 FORM WORK PREPARATION FOR TYPE 3 FOUNDATION 2 days Fri 6/16/17 2  HELPERS,2 CAPERNTER

40 CASTING OF TYPE 3 FOUNDATION 5 days Wed 6/21/17 2MASON,4 HELPER


41 REMOVING OF FORM WORK 1 day Wed 6/28/17 2 CAPERNTER,2 HELPERS
42 DRILLING ANCHOR HOLES FOR TYPE 2 FOUNDATION 2 days Thu 6/29/17 1 FORMAN,1 OPERATOR,2  HELPERS
43 CASTING OF TYPE 2 FOUNDATION 3 days Thu 6/29/17 2MASON,4 HELPER
44 PREPARATION OF CABLE TRENCH AND PRECAST 2 days Thu 6/15/17 1 FORMAN,4 HELPER,ELECTRICAL TECH 1,ELECTRICAL TECH 2
45 EXCAVATION OF LIGHTING POLE FOUNDATION (7NOS) 2 days Mon 7/3/17 4 HELPER,1 FORMAN

46 BLINDING OF LIGHTING FOUNDATION 2 days Tue 7/4/17 2  HELPERS,2MASON


47 FORM WORK PREPARATION FOR LIGHTING POLE  2 days Mon 7/10/17 2 CAPERNTER,2 HELPERS
FOUNDATION
48 CASTING OF LIGHTING POLE FOUNDATION 4 days Mon 7/10/17 2MASON,1 OPERATOR,4SKILLED LABOUR
49 E & I  ACTIVITIES 20 days Tue 6/6/17 ELECTRICAL TECH 1,ELECTRICAL TECH 2,2  HELPERS
50 INSTRUMENTATION/AUTOMATION (INTECH) 10 days Thu 6/15/17
51 TIE‐IN OF 24 " INLET LINE TO SKID 5 days Wed 7/5/17 2 FITTER,4 HELPER
52 TIE‐IN OF 24 " OUT LINE TO SKID 5 days Tue 7/11/17 2 FITTER,4 HELPER
53 TIE‐IN OF 2 " DRAIN LINE 6 days Tue 7/18/17 2 FITTER,2 HELPERS
54 CONNECTION OF DRAIN TO PIT 2 days Wed 7/26/17 2 FITTERS,1 WELDER
55 INSTALLATION OF BASE PLATES ,STIFFNERS AND BEAMS2 days Fri 6/16/17 2  HELPERS,2 FITTERS

56 PAINTING AND BLASTING FINAL COAT 2 days Thu 7/20/17 2 HELPERS,2 PAINTERS

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish‐only


Project: CRUDE METRING INSTALL
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Fri 5/12/17
Milestone External Tasks Inactive Milestone Duration‐only Start‐only Progress

Page 1