Escolar Documentos
Profissional Documentos
Cultura Documentos
Attachment 8
Environmental Protection Plan
ENVIRONMENTAL PROTECTION PLAN
FOR THE PROPOSED
2016 METER STATIONS AND LATERALS
ABANDONMENT PROGRAM
December 2016
678527
Prepared for
TABLE OF CONTENTS
Page
1.0 INTRODUCTION.............................................................................................................................. 1
2.0 PURPOSE ........................................................................................................................................ 3
3.0 ENVIRONMENTAL PROTECTION PLAN ORGANIZATION .......................................................... 4
3.1 Organization ........................................................................................................................ 4
3.2 Environmental Setting ......................................................................................................... 5
3.3 Extent and Limits of the Environmental Protection Plan ..................................................... 5
4.0 ENVIRONMENTAL COMPLIANCE ................................................................................................. 6
5.0 NOTIFICATION TO CONCERNED PARTIES ............................................................................... 10
6.0 PRE-ABANDONMENT MEASURES ............................................................................................. 11
7.0 PROJECT-SPECIFIC ENVIRONMENTAL PROTECTION MEASURES ...................................... 12
8.0 METER STATION AND PIPELINE ABANDONMENT ................................................................... 21
8.1 General Environmental Protection Measures ................................................................... 21
8.2 Right-of-Way and Access Preparation, Topsoil/Strippings Salvage and Grading ............ 26
8.3 Watercourse Crossings ..................................................................................................... 29
8.4 Pipeline and Facility Abandonment Activities (Excavating, Cutting, Capping and
Welding) ............................................................................................................................ 32
8.5 Backfill ............................................................................................................................... 34
8.6 Clean-Up and Reclamation ............................................................................................... 35
9.0 RECLAMATION AND MONITORING ............................................................................................ 38
10.0 REFERENCES............................................................................................................................... 39
LIST OF APPENDICES
Appendix 1A Emergency Contacts ......................................................................................................1A-1
Appendix 1B Contacts .........................................................................................................................1B-1
Appendix 1C Approvals/Permits Potentially Required For Abandonment ......................................... 1C-1
Appendix 1D Typical Drawings ........................................................................................................... 1D-1
Appendix 1E Contingency Plans .........................................................................................................1E-1
Appendix 1F Management Plans ........................................................................................................ 1F-1
Appendix 1G Caribou And General Wildlife Observation Forms ........................................................ 1G-1
LIST OF TABLES
Table 1 Details for the 2016 Meter Stations and Laterals Abandonment Program ......................... 1
Table 2 Pipeline Segment Crossing Locations at Paved Public Roads .......................................... 2
Table 3 Site-Specific Mitigation Measures ..................................................................................... 12
Page i
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
1.0 INTRODUCTION
This Environmental Protection Plan (EPP) outlines environmental protection measures to avoid or
minimize potential effects during the physical abandonment, remediation and reclamation phases of
the 2016 Meter Stations and Laterals Abandonment Program (the Project), proposed by NOVA
Gas Transmission Ltd. (the Company), a wholly owned subsidiary of TransCanada PipeLines
Limited (TransCanada). This EPP is being filed in support of the Project.
segmenting, plating, and filling the pipeline in place at 2 highway crossings (Table 2);
To minimize disturbance, existing access and rights-of-way (RoWs) will be used, where possible. Physical
abandonment activities will take place within the existing RoW. No work is planned to be conducted
instream or within the riparian area of any watercourse or wetland. The abandonment activities will be
carried out in accordance with Canadian Standards Association Z662-15: Oil and Gas Pipeline Systems
(CSA Z662-15) and the National Energy Board (NEB) Onshore Pipeline Regulations (OPR).
TABLE 1
DETAILS FOR THE 2016 METER STATIONS AND LATERALS ABANDONMENT PROGRAM
Page 1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 1 Cont’d
Meter Station Legal
Description
Length of Pipeline Valve Site Legal Pipeline Abandoned
Component Name Lateral(s) and Loops(s) Description In Place or Full Removal
Sharrow South No. 2 Receipt Meter Station and Lateral (Sharrow 0.18 km of NPS 4 NE 10-020-02 W4M In place
South No. 2) NE 10-020-02 W4M
Steele Lake Receipt Meter Station and Lateral (Steele Lake) 5.1 km of NPS 8 NW 34-065-24 W4M In place
NE 14-066-24 W4M
Thornbury West Meter Station and Lateral (Thornbury West) 0.15 km of NPS 6 SW 28-079-14 W4M Full removal
SW-28-079-14 W4M
TABLE 2
The EPP is written in abandonment specification format and should be read in conjunction with
Project-specific environmental documents. This EPP provides Project-related environmental protection
measures and commitments to be considered during the detailed engineering design, and carried out
during the abandonment, reclamation and monitoring phases of the Project.
professional experience.
Subject to regulatory approval, physical abandonment activities are scheduled to commence in Q3 2017
with a target completion date of Q1 2018. Clean-up and initial post removal reclamation of disturbed
portions of the Project footprint will be conducted following physical abandonment activities, or as soon as
weather, ground or seasonal conditions allow. The Company anticipates that the window for physical
abandonment activities will be approximately 10 to 14 days at each site.
Page 2
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
2.0 PURPOSE
The purpose of the EPP is to describe the environmental protection measures and commitments to be
carried out by the Company, its Contractor(s) and subcontractor(s) during the abandonment activities for
the Project to avoid or minimize potential environmental effects of the Project. The EPP includes both
general and site-specific environmental protection measures which have been developed and refined
over time based on past project experience, input from aboriginal communities, landowners, stakeholders
and regulators during consultation, and reflect current industry best management practices where they
are applicable to Project activities.
Following completion of the physical abandonment phase, this EPP will be used as a guide during the
reclamation and monitoring phases.
Page 3
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
3.1 Organization
The EPP provides Project-related environmental protection measures and commitments to be carried out
during abandonment activities for the Project. A large portion of environmental protection measures are
standard practice for all TransCanada projects. Additional Project-specific environmental protection
measures are identified in Section 7.0 of the EPP.
Environmental protection measures are identified under the headings below in accordance with the
typical progression of abandonment activities.
The EPP is intended to provide the Company and its Contractor(s) and subcontractor(s) personnel with
an understanding of the general environmental setting of the Project, extent and limitations of the EPP,
specific or unique mitigation measures for the Project, and general environmental protection measures or
industry best management practices that are typically applied and that generally reflect the sequence of
meter station and pipeline segment abandonment.
Sections 1 to 3 outlines the purpose and organization of the EPP, summarizes the environmental setting
and context with respect to geographic location, and identifies where information can be found in the
EPP.
Section 4 "Environmental Compliance" provides information about the tools and process to facilitate
compliance with all regulatory approvals, permits, commitments and specific requirements of the EPP.
Section 8 "Meter Station and Pipeline Abandonment" outlines the environmental protection measures
associated with general meter station and pipeline abandonment activities, RoW and access preparation,
areas of potential environmental concern and topsoil handling, strippings salvage, grading, excavating,
cutting, capping, welding, backfill and reclamation activities stated in Section 8.5 that will be executed
during abandonment activities.
Section 9 "Reclamation and Monitoring" outlines activities to take place once physical abandonment and
reclamation activities have been completed to evaluate the success of reclamation activities, compliance
with commitments and the stability of the disturbed lands.
Appendices to the EPP include drawings, Project contacts, contingency plans, management plans and a
wildlife observation template to support the specific environmental protection measures identified in the
EPP and provide guidance to decision making processes should conditions arise that require
implementation of contingency measures.
Page 4
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Indefinite terms may be included in some environmental protection measures in order to provide the
Company with the flexibility needed during abandonment and reclamation phases to accommodate
unique situational circumstances where general environmental protection measures must be refined or
site-specific environmental protection measures applied as part of the adaptive management process.
Page 5
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objectives
The objectives of these environmental protection measures are to ensure that:
processes are in place that allow the Company, its authorized representative,
Contractor(s) and subcontractor(s) to access Project environmental information to aid
in decision making at the field level; and
Specific Measures
Page 6
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 7
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 8
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Change Management
During the course of abandonment activities, it may be necessary to modify or create new procedures to
address site conditions not anticipated in the EPP. This procedure outlines the process to be followed.
Page 9
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objectives
The objectives of these environmental protection measures are to ensure:
interruptions to other land use activities are minimized during the abandonment
activities;
Specific Measures
Contacts Measures
Federal, Provincial Inform all responsible federal and provincial resource agencies and
and Municipal interested municipal officials of the Project developments, as warranted.
Agencies
Landowners and Notify all directly affected landowners and lessees of the intended Project
Lessees schedule, at least 15 days before the start of those abandonment activities to
prevent or reduce impacts to their operations or activities.
Review affected landowner requests as they appear on the landowner line list
or as they arise in the field to ensure conformance with the environmental
commitments.
Aboriginal Provide directly affected Aboriginal communities with the proposed
Communities abandonment activities schedule and Project maps.
Trappers Notify directly affected registered trappers of the proposed abandonment
activities schedule, at least 2 weeks prior to beginning abandonment
activities.
Page 10
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objectives
The objectives of these environmental protection measures are to ensure:
all known above or below ground hazards are identified prior to abandonment
(e.g., building materials and surface staining);
all resources are properly identified and marked in the field before the initiation of
ground disturbance to avoid or minimize potential Project effects;
the Project sites are properly delineated to prevent inadvertent trespass; and
all access to and from the work sites are properly marked to maintain safety and
environmental compliance.
Specific Measures
Page 11
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objectives
The objectives of these environmental protection measures are to:
ensure the identification and protection of biophysical and cultural resources identified
in Project-specific environmental documents; and
Table 3 summarizes the unique site-specific mitigation measures required on the Project.
TABLE 3
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Coleman
Wildlife Coleman KWBZ December 15 to Avoid abandonment The Coleman pipeline will be
Facilities April 30 activities within the KWBZ cleaned and fully removed.
between December 15 and
April 30.
In the event abandonment
activities occur within the
recommended restricted
activity period (RAP)
(December 15 to April 30),
consult with AEP and
develop a KWBZ plan.
Migratory Birds April 19 to August 11 Avoid abandonment --
activities during the primary
nesting period.
In the event abandonment
activities occur within the
primary nesting period for
migratory birds, a
non-intrusive area search
for evidence of nesting
within 7 days of starting
abandonment activities may
be conducted if warranted,
based on the Breeding Bird
Nest Management Plan
(Appendix 1F).
Page 12
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Wildlife See above See above See above In the event an active nest is See above
(cont’d) found, it will be subject to
site-specific mitigation
measures (e.g., protective
buffer and/or non-intrusive
monitoring until the nest is
no longer active) according
to the Wildlife Species of
Concern Discovery
Contingency Plan
(Appendix 1E).
Vegetation Length of Rare plants -- Refer to Section 8.1 and A search of the Alberta
pipeline follow mitigation measures Conservation Information
for abandonment activities Management System (ACIMS)
related to clearing and identified western larch potentially
vegetation. located near the pipeline, onion
grass potentially located within
900 m of the pipeline and
aspen/thimbleberry forest
potentially located within 700 m of
the pipeline.
Coleman is located within the
species distribution of Limber Pine
and Whitebark Pine.
All activities will be constrained to
the previously disturbed ROW.
Enchant
Wetlands 11-03-014- A seasonal marsh is -- Refer to Section 8.1 and the The Enchant pipelines will be
17 W4M located east of the side Wet Soils Contingency Plan cleaned and fully removed, except
valve to identify mitigation where they cross underneath an
measures for abandonment irrigation canal.
activities in/near wetlands. The pipelines underneath the
Watercourses 13-35-013- Pipeline crosses one No RAP Refer to Section 8.1 and 8.3 irrigation canal will be cleaned,
17 W4M mapped Class D and follow mitigation filled with concrete and abandoned
watercourse measures for abandonment in place.
04-02-014- Pipeline crosses one No RAP activities in/near No instream or riparian area
17 W4M mapped, Class D watercourses. disturbance is planned for
irrigation canal Abandon in place the Enchant.
portion of pipeline
underneath the irrigation
canal.
Wildlife Enchant Migratory Birds April 21 to August 13 Refer to Migratory Bird Agricultural land use in the area
Facilities mitigation measures for has resulted in highly modified
Coleman in Table 3. habitat that is poor or unsuitable
for nesting migratory birds.
Sharp-Tailed Grouse 500 m setback from Avoid activities within the Agricultural land use in the area
Survey Area active sharp-tailed sharp-tailed grouse survey has resulted in highly modified
grouse leks is area between March 15 and habitat.
recommended from June 15.
March 15 to June 15 In the event abandonment
activities occur during this
time, conduct a survey for
leks within 500 m of the
work site. If an active lek is
found, consult with AEP to
determine if work can
proceed during the lekking
period.
Page 13
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Wildlife See above Sensitive Raptor 1,000 m setback from Avoid activities within the The breeding period for some
(cont’d) Range (prairie falcon, active sensitive raptor sensitive raptor range raptor species at risk begins as
golden eagle, and nests is recommended between March 1 and early as March 1 (e.g., ferruginous
ferruginous hawk) from March 1 to August 31. hawk).
August 31 In the event abandonment
activities occur during the
raptor nesting period, the
need for a nest survey will
be evaluated by a wildlife
biologist and determined by
land cover types and
potential for nesting raptors
within 500 m of the work
site.
Burrowing Owl Range 500 m setback from Avoid abandonment Agricultural land use in the area
active burrowing owl activities during the nesting has resulted in highly modified
burrows is period within a burrowing habitat that is unsuitable for
recommended from owl range from April 1 to nesting burrowing owls.
April 1 to August 15 August 15.
In the event abandonment
activities occur within the
nesting period, conduct a
survey for burrows within
500 m of the work site. If an
active burrow is found,
consult with AEP to
determine if work can
proceed during the nesting
period.
Grew Lake
Wildlife Grew Lake West Side of the February 15 to July 15 Avoid abandonment activity The Grew Lake pipeline will be
Facilities Athabasca River within the sensitive timing cleaned and abandoned in place.
(WSAR) Caribou window for caribou AEP recommends a timing
Range (February 15 to July 15). restriction of February 15 to
An early in/early out July 15 within caribou range to
approach will be reduce impacts to pregnant cows
implemented since wet and their calves. Exceptions
conditions necessitate include activities that are initiated
access under frozen prior to February 15; activities
conditions. accessed using Class V routes or
In the event abandonment activities within 100 m of an
activities are planned within all-weather road. Work can
the sensitive timing window continue until adverse ground
for caribou, consult with conditions are encountered
AEP and follow provincial (AER 2013).
and federal regulations for
work within the sensitive
timing window.
Submit a Caribou Protection
Plan to AEP on or before
October 15, 2017 for
activities at the Grew Lake
Facilities. Follow the
mitigation measures
outlined in the Caribou
Protection Plan.
Migratory Birds May 2 to August 10 Refer to Migratory Bird Abandonment activities are
mitigation measures for scheduled under frozen
Coleman in Table 3. conditions.
Page 14
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Grew Lake East
Wetland 15-30-090- The meter station is -- Refer to Section 8.1 and the The Grew Lake East pipeline will
19 W4M surrounded by a bog Wet Soils Contingency Plan be cleaned and abandoned in
complex. to identify mitigation place.
The pipeline crosses measures for abandonment Abandonment activities are
numerous bogs, fens activities in/near wetlands. scheduled under frozen
and swamps. The Refer to Section 8.4 to conditions.
majority of the route identify mitigation measures There are no wetlands within 30 m
crosses wetlands. for excavation water. of the surface disturbance
activities planned at the side valve.
All activities will be constrained to
the previously disturbed ROW.
Watercourses 03-31-090- The pipeline crosses -- Refer to Section 8.1 and 8.3 The Grew Lake East RoW will be
19 W4M one unmapped, and follow mitigation used to access the meter station,
Class C watercourse measures for abandonment which will require the installation of
05-25-090- The pipeline crosses April 16 to July 15 activities in/near temporary crossing structures (i.e.,
20 W4M one mapped, Class C watercourses. ice and snowfill bridges).
watercourse There are no fish-bearing
watercourses within 30 m of the
surface disturbance activities
planned at the meter station or
side valve.
Other than the temporary crossing
structures at watercourse or
wetland crossings along the RoW,
no instream or riparian area
disturbance is planned for Grew
Lake East.
Wildlife Grew Lake WSAR Caribou Range February 15 to July 15 Refer to Caribou mitigation --
East measures for Grew Lake in
Facilities Table 3.
Migratory Birds May 2 to August 10 Refer to Migratory Bird
mitigation measures for
Coleman in Table 3.
Hotchkiss
Wetlands Length of The pipelines crosses -- Refer to Section 8.1 and the The Hotchkiss pipelines will be
pipelines several fens, bogs and Wet Soils Contingency Plan cleaned and abandoned in place.
swamps. to identify mitigation No instream or riparian area
measures for abandonment disturbance is planned for
activities in/near wetlands. Hotchkiss.
Watercourses 10/11-34- The pipelines crosses -- Refer to Section 8.1 and 8.3 There are no fish-bearing
093-1 W6M five unmapped, and follow mitigation watercourses within 30 m of the
09-33-093- Class C watercourses measures for abandonment surface disturbance activities
01 W6M activities in/near planned at the meter stations or
watercourses. side valve sites.
06-33-093-
01 W6M
08-32-093-
01 W6M
11-30-093-
01 W6M
Wildlife Hotchkiss Migratory Birds May 2 to August 10 Refer to Migratory Bird Abandonment activities are
Facilities mitigation measures for scheduled under frozen conditions
Coleman in Table 3. outside of the migratory bird
nesting period.
Page 15
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Wildlife See above Grizzly Bear and 200-750 m setback from Use existing access. Abandonment activities are
(cont’d) Special Access Zone active dens between Implement the Wildlife scheduled under frozen
October 1 and April 30 Species of Concern conditions.
Discovery Contingency Plan The Hotchkiss meter station is
(Appendix 1E) if grizzly bear located adjacent to operational
activity is observed in facilities. Abandonment activities
proximity to the work site. at the Hotchkiss meter station will
not substantially alter the existing
level of disturbance.
Abandonment activities at the side
valve location will be short duration
and constrained to the existing
RoW.
Hotchkiss East
Wetlands 03-01-094- A potential swamp is -- Refer to Section 8.1 and the Hotchkiss East pipeline will be
02 W6M located east of the side Wet Soils Contingency Plan cleaned and abandoned in place.
valve. to identify mitigation All activities will be constrained to
The pipeline crosses measures for abandonment the previously disturbed ROW.
several wetlands activities in/near wetlands.
(marsh, swamp and Refer to Section 8.4 to
fen). identify mitigation measures
for excavation water.
Watercourses 03-01-094- The pipeline crosses April 16 to July 15 Refer to Section 8.1 and 8.3 The Hotchkiss East RoW will be
02 W6M one unmapped, Class and follow mitigation used to access the meter station,
C watercourse measures for abandonment which will require the installation of
activities in/near temporary crossing structures (i.e.,
watercourses. ice and snowfill bridges).
There are no fish-bearing
watercourses within 30 m of the
surface disturbance activities
planned at the meter station or
side valve.
Other than the temporary crossing
structures at watercourse or
wetland crossings along the RoW,
no instream or riparian area
disturbance is planned for
Hotchkiss East.
There are no fish-bearing
watercourses within 30 m of the
surface disturbance activities
planned at meter stations or side
valve sites.
Wildlife Hotchkiss Migratory Birds May 2 to August 10 Refer to Migratory Bird Abandonment activities are
East mitigation measures for scheduled under frozen
Facilities Coleman in Table 3. conditions.
Grizzly Bear 200-750 m setback from Refer to Grizzly Bear Abandonment activities are
dens between October 1 mitigation measures for scheduled under frozen
and April 30 Hotchkiss in Table 3. conditions.
The Hotchkiss East meter station
is located adjacent to operational
facilities.
Abandonment activities at the
Hotchkiss East meter station will
not substantially alter the existing
level of disturbance.
Abandonment activities at the side
valve location will be short duration
and contained to existing RoW.
Page 16
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Mastin Lake
Wildlife Mastin Lake Migratory Birds May 2 to August 10 Refer to Migratory Bird The Mastin Lake pipeline will be
Facilities mitigation measures for cleaned and removed.
Coleman in Table 3. A search of the FWMIS online
database revealed an occurrence
of sharp-tailed grouse within 1 km
of the meter station site or
associated pipeline. The site is not
located in provincially identified
Sharp-tailed Grouse Survey Area.
Meanook
Wetlands Length of The pipeline crosses -- Refer to Section 8.1 and the The Meanook pipeline will be
pipeline several fens and Wet Soils Contingency Plan cleaned and abandoned in place.
swamps. to identify mitigation No instream or riparian area
measures for abandonment disturbance is planned for
activities in/near wetlands. Meanook.
Watercourses 02-25-063- The pipeline crosses April 16 to July 15 Refer to Section 8.1 and 8.3
22 W4M Pine Creek (mapped, and follow mitigation
15/16-21- Class C, fish-bearing) measures for abandonment
064-21 W4M at two locations activities in/near
03-05-064- The pipeline crosses watercourses.
21 W4M seven unmapped,
15-05-064- Class C watercourses
21 W4M
14-16-064-
21 W4M
06-21-064-
21 W4M
10-34-064-
21 W4M
01-03-064-
21- W4M
01-11-065-
02 W4M
Wildlife 2.3 km of KWBZ January 15 to April 30 Avoid abandonment The Meanook pipeline will be
pipeline from activities within the KWBZ cleaned and abandoned in place.
SW 21-064- recommended RAP from No abandonment activities within
21 W4M to January 15 to April 30. or access through the KWBZ is
NW 09-064- In the event that planned.
21 W4M. abandonment activities
occur during the
recommended RAP
(January 15 to April 30),
consult with AEP to develop
a KWBZ plan.
See above Migratory Birds May 2 to August 10 Refer to Migratory Bird --
mitigation measures for
Coleman in Table 3.
Rambling Creek East
Wildlife Rambling Chinchaga Caribou February 15 to July 15 Refer to Caribou mitigation --
Creek East Range measures for Grew Lake in
Facilities Table 3.
Migratory Birds May 2 to August 10 Refer to Migratory Bird
mitigation measures for
Coleman in Table 3.
Page 17
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Sharrow South No. 2
Wildlife 16-10-020- Ord’s Kangaroo Rat November 1 to May 31 Avoid abandonment The Sharrow South No. 2 pipeline
02 W4M Range activities during the Ord’s will be cleaned and abandoned in
kangaroo rat recommended place.
RAP (November 1 to Native prairie in the area supports
May 31). sensitive species habitat.
In the event abandonment Abandonment activities are
activities are scheduled to scheduled for Fall 2017.
occur during the RAP, The FWMIS online database
consult with AEP to resulted in the following
determine if pre-construction occurrences within 1 km of the
surveys are recommended meter station site: sharp-tailed
(mid-June to early grouse, olive-backed pocket
September) to document mouse, Ord's kangaroo rat,
occurrence of Ord’s pronghorn, Baird's sparrow,
kangaroo rat den sites. Brewer's sparrow, grasshopper
If habitat for Ord’s kangaroo sparrow, long-billed curlew,
rat is confirmed or likely to Sprague's pipit, upland sandpiper,
occur, consult with AEP to Great Plains toad, plains
develop mitigation for spadefoot and prairie rattlesnake.
abandonment activities
during the active period
(between June 1 and
October 31), such as
exclusion fencing,
monitoring and/or moving
animals outside the area of
activities (with appropriate
permits in place).
Implement the Wildlife
Species of Concern
Discovery Contingency Plan
(Appendix 1E) in the event
that Ord’s kangaroo rat or
their dens are discovered
prior to or during
abandonment activities.
Sharp-Tailed Grouse 500 m setback from Refer to Sharp-Tailed
Survey Area active sharp-tailed Grouse Survey Area
grouse leks from March mitigation measures for
15 to June 15 Enchant in Table 3.
16-10-020- Sensitive Snake Range Snake rookery: 200 m Provide snake awareness
02 W4M setback between training for Contractors.
March 15 and If snakes are identified at
October 31; setback the site, implement the
reduced to 50 m for low Wildlife Species of Concern
and medium impact Discovery Contingency Plan
activities between (Appendix 1E). Mitigation
November 1 and may include implementing a
March 14 protective buffer and timing
Snake hibernacula: restrictions, exclusion
500 m setback year- fencing, snake relocation or
round vehicle and speed
restrictions.
Page 18
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Wildlife See above Sensitive Raptor 1,000 m setback from Refer to Sensitive Raptor
(cont’d) Range (prairie falcon, active sensitive raptor Range mitigation measures
golden eagle, and nests from March 15 to for Enchant in Table 3.
ferruginous hawk) July 15
Burrowing Owl Range 500 m setback from Refer to Enchant burrowing
active burrowing owl owl mitigation measures in
burrows from April 1 to Table 3.
August 15.
Sensitive Amphibian Year-round: Activities Avoid abandonment There are no non-permanent
Range shall not occur within activities within 100 m of a seasonal wetlands within 100 m of
100 m of a non-permanent seasonal the surface disturbance activities
non-permanent wetland. planned for Sharrow South No. 2.
seasonal wetland in Implement the Wildlife No instream or riparian area
areas identified as Species of Concern disturbance is planned for Sharrow
Sensitive Amphibian Discovery Contingency Plan South No. 2.
Ranges, unless (Appendix 1E) in the event
otherwise approved by that amphibians are
AEP. observed prior to or during
abandonment activities.
Migratory Birds April 21 to August 13 Refer to Coleman Migratory
Bird mitigation measures in
Table 3.
Vegetation 16-10-020- Rare Plants: slender -- Refer to Section 8.1 for A search of ACIMS identified
02 W4M mouse ear cress, tiny general rare plant mitigation slender mouse ear cress, tiny
cryptantha, sandhills measures. cryptantha and sandhills cinquefoil
cinquefoil potentially located within 1 km of
the pipeline. Pipeline will be
abandoned in place with limited
excavations occurring at the meter
station and side valve and
contained within existing RoW.
Steele Lake
Wetlands Length of The pipeline crosses -- Refer to Section 8.1 and the The Steele Lake pipeline will be
pipeline numerous wetlands Wet Soils Contingency Plan cleaned and abandoned in place.
(fens, swamps) to identify mitigation No instream or riparian area
measures for abandonment disturbance is planned for Steele
activities in/near wetlands. Lake.
Watercourses 03/02-03- The pipeline crosses April 16 to July 15 Refer to Section 8.1 and 8.3 Abandonment activities are
066-24 W4M three unmapped, Class and follow mitigation scheduled for June 2017.
13-02-066- C watercourses measures for abandonment
24 W4M activities in/near
watercourses.
16-14-066-
24 W4M
Wildlife Steele Lake Migratory Birds May 2 to August 10 Refer to Coleman Migratory Abandonment activities are
Facilities Bird mitigation measures in scheduled for June 2017. Habitat
Table 3. in the area is suitable migratory
bird habitat. Migratory bird
mitigation is applicable if
abandonment activities occur from
May 2 to August 10.
Thornbury West
Wetlands 05-28-079- Small -- Refer to Section 8.1 and the The Thornbury West pipeline will
14 W4M wetland/waterbody Wet Soils Contingency Plan be cleaned and fully removed.
located approximately to identify mitigation
>10 m to the west of measures for abandonment
Thornbury West. activities in/near wetlands.
Page 19
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE 3 Cont’d
Timing Windows
and/or Regulatory Description of Occurrence/ Other
Feature Location Issues Guidelines Mitigation Comments
Wildlife 05-28-079- Potential Amphibian May 1 to September 30 Avoid abandonment Suitable habitat for amphibians
14 W4M Habitat activities during the active may be present at the small
toad season within potential wetland and adjacent uplands.
breeding and foraging Abide by timing restrictions, MBCA
habitat. and SARA.
Thornbury East Side of Athabasca February 15 to July 15 Refer to Caribou mitigation --
West River Caribou Range measures for Grew Lake in
Facilities (Egg-Pony herd) Table 3.
Migratory Birds May 2 to August 10 Refer to Migratory Bird The FWMIS online database
mitigation measures for identified the following
Coleman in Table 3. occurrences within 1 km of the
meter station and associated
pipeline: American kestrel, barred
owl and least flycatcher.
Page 20
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objectives
The objective of these environmental protection measures is to:
avoid and minimize the potential environmental effects associated with general
abandonment activities.
Specific Measures
Page 21
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 22
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 23
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 24
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 25
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objective
The objectives of these mitigation measures are to:
minimize effects to soil capability, surface drainage patterns, land use and wildlife
habitat;
Specific Measures
Page 26
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 27
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 28
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objectives
The objectives of these environmental protection measures are to:
comply with the fisheries protection provisions of the Fisheries Act and its supporting
Fisheries Protection Policy by applying DFO’s Measures to Avoid Causing Harm to
Fish and Fish Habitat;
Page 29
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 30
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 31
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objective
The objectives of these mitigation measures are to:
Specific Measures
Page 32
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 33
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
8.5 Backfill
Introduction
The following mitigation measures will be implemented during backfill operations.
Objective
The objectives of these environmental protection measures are to:
ensure that excavated materials from the trench and excavation are replaced and
properly compacted; and
Specific Measures
Page 34
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Objective
The objectives of these mitigation measures are to:
effectively use reclamation techniques that prevent topsoil/surface material loss from
wind and water erosion;
establish a vegetative cover compatible with surrounding vegetation and land uses;
comply with approval conditions, including permits and landowner commitments; and
maintain equivalent land capability, ensuring the ability of the land to support various
land uses and equivalent land capability following abandonment.
Specific Measures
Page 35
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 36
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 37
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Process
Reclamation monitoring for the Project will follow the principles of the Company’s post construction
monitoring program which ensures compliance with specific reclamation performance expectations and
applicable regulatory requirements. Mitigation methods will be based on the principle that success of land
reclamation is measured against adjacent representative site conditions while taking into consideration
the status of reclamation at the time of assessment.
Preliminary assessments of disturbed areas are conducted during the most appropriate time of the
season, which depends on the various biophysical resources and their growth stage or life cycle. This is
usually in the spring/summer and involves identifying deficiencies and proposing recommendations for
corrective actions.
The reclamation monitoring program will utilize principles of the Draft 2001 Reclamation Assessment
Criteria for Pipelines (Alberta Environment 2001) and may entail other specifically-designed evaluation
criteria, depending on the concerns and issues that were highlighted through Project-specific
environmental documents, or encountered during the abandonment activities. The monitoring program
includes measurable parameters that will be recorded and compared to representative control areas to
measure reclamation success.
Areas that do not meet equivalent land capability for items such as landscape features, vegetation
establishment, soils and reclamation success will be identified and records will be maintained for remedial
measures implemented, the success of these measures and to ensure that outstanding issues are
investigated and resolved.
Page 38
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
10.0 REFERENCES
Alberta Energy Regulator. 2013. Integrated Standards and Guidelines – Enhanced Approval Process.
December 1, 2013. 84 pp.
Alberta Environment (AENV). 2001. Reclamation Assessment Criteria for Pipelines, 2001 Draft. Available
at: https://extranet.gov.ab.ca/env/infocentre/info/library/6883.pdf.
CAPP, CEPA and CGA (Canadian Association of Petroleum Producers, Canadian Energy Pipeline
Association, and Canadian Gas Association). 2012. Pipeline associated watercourse crossings,
4th Edition. Prepared by TERA Environmental Consultants. Calgary, AB. 217 pp.
CSA (Canadian Standards Association). 2015. CSA Z662-15: Oil and Gas Pipeline Systems.
CH2M HILL Energy Canada, Ltd. 2015. Caribou Protection Plan for the Proposed NOVA Gas
Transmission Ltd. Operations and Maintenance Activities Lower Athabasca Operations Area.
Prepared for NOVA Gas Transmission Ltd.
Environment Canada. 1994. Migratory Birds Convention Act. Available at: http://laws-
lois.justice.gc.ca/eng/acts/M-7.01/.
Fisheries and Oceans Canada. 1995. Freshwater Intake End-of-Pipe Fish Screen Guideline. Available at:
http://www.dfo-mpo.gc.ca/Library/223669.pdf.
Fisheries and Oceans Canada 2013. Measures to Avoid Causing Harm to Fish and Fish Habitat. Date
Modified: 2013-11-25. Available at: http://www.dfo-mpo.gc.ca/pnw-ppe/measures-mesures/index-
eng.html.
Government of Alberta. 2000. Historical Resources Act. Chapter H-9. Current as of June 12, 2013.
Available at: http://www.qp.alberta.ca/documents/Acts/h09.pdf.
Government of Canada. 2002. Species at Risk Act. S.C. 2002, c.29. Assented to 2002-12-12. Available
at: http://laws-lois.justice.gc.ca/eng/acts/S-15.3/index.html.
Page 39
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1A
EMERGENCY CONTACTS
RCMP
Ambulance 911
Fire 911
1-800-222-6514 (24-hour)
AEP Emergency/Complaint Hotline (24 hours)
or 7378 (Telus Mobile)
1-888-888-4567
STARS Emergency Link Centre
or *4567 (Cell Phone)
Page 1A-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1B
CONTACTS
Page 1B-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 1B-2
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1C
Other
N/A
_____________________________
For more information, see Environmental Operating Practices for the Upstream Petroleum Industry Alberta
Operations - Pipelines Volume by the Canadian Association of Petroleum Producers.
AC = Alberta Culture
AT = Alberta Transportation
CTY = City
FMA = Forest Management Agreement
LFD = Public Lands and Forests Division, Alberta Environment and Sustainable Resource
Development
MD = Municipal District
NEB = National Energy Board
RS = Regional Services, Alberta Environment
WM = Water Management, Regional Services, Alberta Environment
Page 1C-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1D
TYPICAL DRAWINGS
Page 1D-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 1D-2
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1E
CONTINGENCY PLANS
Page 1E-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE OF CONTENTS
Page
1.0 RELEASE CONTINGENCY PLAN .............................................................................................1E-3
2.0 ADVERSE WEATHER CONTINGENCY PLAN ..........................................................................1E-7
3.0 WET SOILS CONTINGENCY PLAN ..........................................................................................1E-8
4.0 FIRE SUPPRESSION CONTINGENCY PLAN ...........................................................................1E-9
5.0 SOIL EROSION CONTINGENCY PLAN ..................................................................................1E-11
6.0 SOIL HANDLING CONTINGENCY PLAN ................................................................................1E-12
7.0 PLANT SPECIES AND ECOLOGICAL COMMUNITIES OF CONCERN DISCOVERY
CONTINGENCY PLAN .............................................................................................................1E-13
8.0 WILDLIFE SPECIES OF CONCERN DISCOVERY CONTINGENCY PLAN ...........................1E-14
9.0 HERITAGE RESOURCE DISCOVERY CONTINGENCY PLAN ..............................................1E-16
Page 1E-2
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Introduction
During construction, an accidental release incident (i.e., spill) has the potential to occur. The majority of
releases on a construction project are categorized as small or low impact releases (spot spill). Depending
upon the location, substance and quantity of the release, the release incident may be reportable to
applicable federal and/or provincial authorities. The following contingency plan identifies the appropriate
measures required to be employed.
If an accidental release does occur, measures to control, contain, recover and clean up the release are to
be implemented in a timely manner to minimize the potential for adverse environmental and human health
effects. The effective containment of a release onto land or into a waterbody or watercourse depends on
a variety of factors including: the composition of the release material, duration and extent of the release in
addition to ground cover, topography, hydrogeology, solubility of the material, viscosity of the liquid, water
currents, soil permeability, climatic, seasonal and local weather conditions of the release site.
If a Contractor specific Release Response Plan (or equivalent) is required, the plan will be reviewed by a
Company Representative to ensure that the Contractor Release Response Plan is in alignment and
meets the requirements of the Company’s Release Contingency Plan.
1. Appropriate release containment (spill kits) and recovery equipment and materials will be maintained
at all work sites, in accordance with the Chemical and Waste Management Plan (Appendix 1F).
2. Specific instructions regarding applicable notifications and appropriate response actions to be taken
in the event of a release will be included in project orientations.
3. The first person on the scene will take immediate action to control the scene as identified in the
Company reviewed Contractor Release Response Plan (or equivalent) or the Company’s Release
Contingency Plan.
4. Ensure release is reported to the Environmental Inspector or designate.
5. The Release Report Form (below) or other equivalent form shall be used to document the details of
the release. Do not wait for all the details to fill-in and provide the form to the Company.
6. When notified of a release of any type, a Company Representative will:
• determine if the release is reportable as per applicable provincial and/or federal regulations (refer
to Appendix A of the TransCanada Release and Spill Response Operating Procedure);
• refer to the Emergency Reporting Contacts (Appendix 1A); and
• notify the appropriate responsible regulatory agency if the release incident is reportable as soon
as practical and within 24 hours of detection.
7. The Environmental Advisor or designate will document the incident in the TransCanada EHSM
Incident Management system within 24 hours of the incident;
8. Where applicable, prepare a detailed reclamation plan and follow-up reports that may be required by
regulations or information request.
Page 1E-3
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
1. The first person on the scene will take immediate action to control the scene as identified in the
Contractor Release Response Plan and will notify both the Contractor and a Company
Representative of the nature of the release incident;
2. When notified of a hazardous materials release, the Contractor will immediately ensure that:
• action is taken to control potential danger to human life including the appointment of an Onsite
Safety Supervisor;
• the necessary equipment is mobilized and measures are implemented immediately to control and
contain the release; and
• all resources are made available to contain and safely recover the release.
Page 1E-4
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
1. Recover the released materials from the containment area using equipment suitable to the nature and
extent of the release;
2. Deploy booms, skimmers, sorbent pads or a functionally equivalent containment structure to contain
releases in or near a watercourse or waterbody;
3. Recover spilled product;
4. Cleanup the release and containment areas. Consult with a qualified remediation specialist and/or
Company Representative, where required; and
5. Dispose of containment materials, and contaminated soil, vegetation and water at an approved
facility.
Page 1E-5
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Land Use:
(dd/mm/yy) (hr:min):
Date: __________________
Page 1E-6
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Where adverse weather conditions and activities have the potential to cause adverse environmental
effects, the Environmental Inspector(s) or Designate will suspend that phase of the operation until
weather conditions abate or effective mitigation procedures have been implemented. The following
represents mitigation measures that may be applied. Specific environmental mitigation is subjective and
dependent upon specific right-of-way conditions and the Project schedule.
The following table outlines mitigation measures that allow for the continuation of activities and reduce
potential adverse environmental effects.
WIND EROSION
Mitigation Options to Consider
1 Uniformly apply mulch or tackifier to topsoil/strippings piles and/or other areas affected by wind erosion.
2 Water identified areas when activities or sufficient winds have created the potential for topsoil/strippings erosion.
3 Apply straw to topsoil/strippings and/or other areas where winds have created the potential for soil erosion. Straw sources are subject to landowner or
regulatory approval and must be approved by the Environmental Inspector(s) or Designate. When clean straw is unavailable, seeding a clean,
unpalatable annual crop at half the normal rate is acceptable.
WATER EROSION
Temporary Berms/Silt Fence
1 Temporary berms, silt fence and/or other appropriate mitigation measures (e.g., wattles and erosion control matting) will be implemented along the
trench crown, surface material piles and/or other areas where the potential for water erosion has been identified.
2 To prevent ponding and/or erosion, cross right-of-way drainage will be maintained. Appropriate measures (e.g., sumps and pumping excess water) to
prevent deleterious material from entering a watercourse will be implemented, when and where required.
Facility Maintenance/Stabilization
1 During adverse weather conditions, NGTL will direct the Contractor to reduce unnecessary traffic and the number of vehicles on the right-of-way. Better
planning of activities will be required by the Contractor to either tighten up or spread out the work crews as warranted (e.g., close proximity of ditching,
lower-in and backfill operations). To reduce effects, a one trip in, one trip out philosophy will be implemented for all right-of-way access.
2 Traffic will be restricted to the right-of-way. The appropriate regulatory agency will need to approve any off right-of-way activities.
3 The traffic pattern on the right-of-way will be changed to avoid repeated driving in the same areas.
4 Under adverse weather conditions, the Contractor will be required to back-blade the right-of-way during and at the end of the day. Back-blading of the
right-of-way fills in tire tracks, thereby assisting in the prevention of water erosion and re-establishing a firm, working right-of-way surface.
5 Under adverse weather conditions, topsoil/surface material and/or subsoil may be stripped and placed at the edge of the right-of-way if approved by the
Environmental Inspector(s) or Designate. Topsoil, surface material and/or subsoil will be redistributed evenly across the right-of-way during clean-up.
6 Under spring thaw conditions and/or where identified by NGTL, and in consultation with the appropriate regulatory representatives, vehicle watercourse
crossing techniques may be modified and/or replaced with other appropriate crossing techniques.
7 When available and practical, tracked equipment may be required for specific activities.
8 Work in highly sensitive areas may be stopped and shifted to less sensitive areas.
9 If all mitigation fails, Project activities may be suspended until adverse weather conditions abate, thereby incurring a schedule delay. Project shut-down
will be based upon discussions between the Construction Manager, Contractor, Environmental Advisor and the appropriate regulatory agencies.
Recommencement of work must be authorized by the Construction Manager in consultation with the Environmental Inspector(s) or Designate prior to
restart.
Page 1E-7
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Soils are considered to be excessively wet when the planned activity could cause unacceptable damage
to soils either due to rutting by traffic through the surface layer into the subsoil, soil structure damage
during soil handling or compaction and associated pulverization of surface material due to heavy traffic.
In order to minimize terrain disturbance and soil structure damage through rutting or compaction due to
wet soil conditions, construction alternatives will be employed, as necessary, in the event of excessively
wet soils. The contingency measures listed below will be implemented individually or in combination, as
necessary, based on site-specific conditions.
1. Restrict construction traffic, where feasible, to equipment with low-ground-pressure tires or wide pad
tracks.
2. Postpone construction until evening or early morning when the ground is frozen.
3. Install biodegradable geotextile, swamp mats, rig mats, access mats or corduroy if approved by the
applicable regulatory agency, or equivalent, in problem areas.
4. Under frozen conditions, employ frost inducement measures such as snow packing or plowing to
increase the load-bearing capacity of thawed ground.
5. Suspend timber skidding operations or implement other measures (e.g., use tarps or plastic sheeting)
if the potential exists for salvageable timber to be damaged through contact with wet soils.
6. Suspend construction until soils dry out or freeze.
Page 1E-8
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
1. Commence fire suppression measures immediately upon detection of fire provided that fire conditions
allow personnel to safely proceed under the direction of the Fire Boss.
2. Personnel working on the Project must report the location of the fire as well as the size of the fire and
wind direction to the Fire Boss immediately.
3. The Fire Boss or the NGTL Designate will report wildfires and relevant information to NGTL’s
Environmental Advisor, Construction Manager, AEP’s Public Lands and Forest divisions, municipal
Bylaw Officers and applicable local fire departments. Reporting to provincial authorities must be
completed immediately. Refer to the Fire Report Form for guidance when reporting fires to regulatory
agencies.
4. The Fire Boss will deploy firefighting equipment and crew to clear fire breaks or extinguish the fire
directly if possible. All equipment and personnel shall be made available to control the fire. The effort
of fire control will be limited, if warranted, due to safety issues and will take into consideration fire
conditions, safety, fitness of personnel and equipment availability.
5. Fire Boss will inspect the fire site as soon as possible and take charge of directing suppression
measures until relieved of this duty by the applicable provincial authority or until conditions become
unsafe.
6. The Fire Boss will deploy additional crew and machinery as needed, and NGTL will request the
assistance of AEP’s Public Lands and Forest divisions, the local fire department and applicable
municipal government if Contractor resources are inadequate (see the contact list and phone
numbers below). Fire suppression measures shall continue until the fire is extinguished or until
otherwise notified by applicable regulatory agency.
7. Moveable material, particularly explosive or flammable materials, vehicles, etc., will be promptly
moved to a safe location whenever there is a possibility of being endangered by fire.
8. The Fire Boss will ensure that all burning embers are extinguished and will monitor the burn area for
smouldering material. Employ infrared scanning equipment to detect any hot spots.
Page 1E-9
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
General
Date and Time of Fire or Discovery:
Source (if known):
Location of Fire
LSD ______ of section _____ Township _____ Range _____ W _____ Mer.
Easting _______________; Northing __________________ UTM Zone ____; KP _____
Site Information
Fire is burning in the:
ground
bush (timber type)
agricultural land
Other
Any people at the fire? Yes _____ No _____ Don’t know _____
Is property threatened? Yes _____ No _____ Don’t know _____
Is road access available? Yes _____ No _____ Don’t know _____
Is water readily available? Yes _____ No _____ Don’t know _____
Any other observations?
(e.g., lightning, recreation, vehicles)
Smoke Information
When unable to see fire, only smoke visible:
Colour: light grey _______ Column: intermittent _______
medium grey _______ scattered _______
dark grey _______ light _______
black _______ heavy _______
Page 1E-10
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
This table provides a list of control options to be implemented as appropriate. Similar procedures should
be followed during the operational phase.
Page 1E-11
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 1E-12
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
• the relative rarity of the plant or ecological community (regionally, nationally, etc.);
• the growth habit and propagation strategy of the plant or ecological community; and
The suite of mitigation options that may be implemented includes the following:
• narrow down the proposed area of disturbance and protect the site using snow fencing
as well as signage;
• temporarily cover the site with snow (given the season), geotextile pads, flex net,
swamp mats or equivalent;
• propagate rare plants or specific portions of rare ecological communities via vegetative
or reproductive means (e.g., harvesting of seed from the Footprint or adjacent area,
salvaging and transplanting portions of sod and surrounding vegetation, or collecting of
cuttings); or
An addendum will be published to outline appropriate mitigation for the discovered rare plant or ecological
community within the Project Footprint.
Page 1E-13
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
• the timing of construction versus the timing constraints for the species; and
The suite of mitigation options that may be implemented includes the following:
• narrow down the proposed area of disturbance and protect the site using snow fencing
as well as signage;
In the event that a discovery is made during supplemental wildlife surveys, the appropriate mitigation will
be outlined in an addendum.
1. Suspend work immediately in the vicinity of any newly discovered wildlife species of concern or their
site-specific habitat. Work at that location may not resume until the measures below are taken.
2. Notify the Environmental Inspector(s) or Designate, who will notify the Construction Manager.
Page 1E-14
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
3. The Environmental Inspector(s) or Designate will assess the discovery and either allow construction
to be resumed or, in the event of a confirmed or potential discovery, proceed by notifying:
• applicable government agencies (e.g., provincial regulator, Environment Canada) as required
(Appendix B); and
• NGTL’s Wildlife Resource Specialist.
4. NGTL’s Wildlife Resource Specialist may deem it necessary to visit the site to develop an appropriate
mitigation plan in consultation with NGTL’s Environmental Advisor. The mitigation measures available
include those listed above.
Page 1E-15
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
In the event that heritage resources are discovered during construction, follow the measures outlined
below.
1. Suspend work immediately in the vicinity of any newly discovered archaeological, palaeontological,
historical or Traditional Land Use site. Work at that location may not resume until the measures below
are taken.
2. Notify the Environmental Inspector(s) or Designate, who will notify the Construction Manager.
3. The Environmental Inspector(s) or Designate will provide an initial review of possible archaeological,
palaeontological and historical remains, and either allow construction to resume or, in the event of a
confirmed or potential discovery, proceed by notifying:
• NGTL’s Heritage Resource Specialist; and
• applicable regulatory agencies (e.g., ACT) (see Appendix B) as required.
4. NGTL’s Heritage Resource Specialist may deem it necessary to visit the site and will, regardless of
whether a site visit is required, develop an appropriate mitigation plan in consultation with NGTL’s
Environmental Advisor and, if necessary, the appropriate regulatory agency.
Page 1E-16
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1F
MANAGEMENT PLANS
Page 1F-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
TABLE OF CONTENTS
Page
1.0 WASTE MANAGEMENT PLAN FOR ABANDONMENT ACTIVITIES ....................................... 1F-3
1.1 Waste Management ....................................................................................................... 1F-3
1.2 Sampling ........................................................................................................................ 1F-3
1.3 Contaminants ................................................................................................................. 1F-3
1.3.1 Soil .................................................................................................................... 1F-3
1.3.2 Concrete ............................................................................................................ 1F-4
1.3.3 Piping, Vessels, Valves and Equipment ........................................................... 1F-4
1.3.4 Liquid and Sludge ............................................................................................. 1F-4
1.3.5 Water Management .......................................................................................... 1F-4
1.4 Salvage and Waste Management Areas ....................................................................... 1F-5
1.4.1 PCB Materials ................................................................................................... 1F-5
1.5 Transportation ................................................................................................................ 1F-5
1.6 Documentation ............................................................................................................... 1F-5
1.7 Applicable Environmental Quality Guidelines ................................................................ 1F-5
2.0 CHEMICAL AND WASTE MANAGEMENT PLAN ...................................................................... 1F-6
2.1 Purpose .......................................................................................................................... 1F-6
2.2 Guiding Principles .......................................................................................................... 1F-6
2.2.1 Application......................................................................................................... 1F-6
2.2.2 Description of Wastes and Chemicals .............................................................. 1F-6
2.2.3 Mitigative Measures .......................................................................................... 1F-8
3.0 TRAFFIC CONTROL MANAGEMENT PLAN ........................................................................... 1F-11
3.1 Purpose ........................................................................................................................ 1F-11
3.2 Preconstruction ............................................................................................................ 1F-11
3.3 Construction ................................................................................................................. 1F-11
3.4 Post-Construction......................................................................................................... 1F-12
4.0 HYDROVAC SLURRY HANDLING MANAGEMENT PLAN ..................................................... 1F-13
4.1 Purpose ........................................................................................................................ 1F-13
4.2 Pre-Excavation Contamination Risk Screening ........................................................... 1F-13
4.3 Contamination Not Suspected/Non-Contaminated Slurry ........................................... 1F-13
4.4 Contaminated/Suspected Contaminated ..................................................................... 1F-14
4.5 Additional Requirements .............................................................................................. 1F-14
5.0 BREEDING BIRD AND NEST MANAGEMENT PLAN ............................................................. 1F-16
5.1 Regulations, Guidelines, and Codes of Practice ......................................................... 1F-16
5.1.1 Federal ............................................................................................................ 1F-16
5.1.2 Provincial and Territorial ................................................................................. 1F-16
5.1.3 Guidelines and Codes of Practices ................................................................. 1F-17
5.2 Breeding Bird and Nest Management .......................................................................... 1F-17
5.2.1 Breeding Bird General Mitigation and Management ....................................... 1F-17
LIST OF FIGURES
Figure 1 Migratory Bird Nesting Zones in Canada ..................................................................... 1F-18
Figure 2 Primary Nesting Periods by Nesting Zones and Broad Habitat Types ........................ 1F-19
Figure 3 Breeding Bird Nest Search .......................................................................................... 1F-20
Page 1F-2
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Prior to the commencement of abandonment activities, the Site Hazard Assessment is provided to the
Contractor to identify site-specific anticipated waste streams. All identified waste streams are to be
tracked using a Waste Disposal Tracking List, provided by the Contractor.
The Waste Disposal Tracking List shall include intended disposal facilities and acceptance criteria for
potential wastes and associated Contaminants of Concern (COCs).
All removal, handling, containment, temporary storage, transportation, and disposal of salvage and
wastes will be conducted in accordance with applicable Federal and Provincial Regulations. Salvage and
wastes will be disposed off-site at approved and licensed disposal facilities.
1.2 Sampling
An Environmental Consultant shall be retained during the Program for the purpose of collecting samples
and interpreting analytical results to confirm the presence of potential COCs.
Sampling shall be conducted in accordance with the following TransCanada Operating Procedures
(TOPs):
Waste characterization sampling will be conducted on any salvage or wastes encountered to ensure that
COC concentrations are within acceptability limits for the intended disposal facilities identified in the
Waste Disposal Tracking List.
1.3 Contaminants
Pipeline and facility abandonment activities have the potential to encounter COCs associated with
equipment and infrastructure removed, such as asbestos, PCBs, Naturally Occurring Radioactive
Materials (NORMs), petroleum hydrocarbons or herbicides. To ensure the removal, handling,
containment, temporary storage, transportation, and disposal of contaminants are conducted in
accordance with applicable regulations, the following practices will be implemented.
1.3.1 Soil
Abandonment activities have the potential to encounter soils that contain COCs. The identification of
contaminated soils shall be conducted in accordance with the following TOP:
Removal, handling, stockpiling and disposal of contaminated soils on the Program will be completed on a
reactive basis.
Page 1F-3
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
In the event that potential contaminated soil is encountered based on visual and olfactory observation (as
determined by odour or discoloration) and/or historical environmental site assessment information, soil
sampling will be completed. Upon receipt and review of laboratory analytical data, subsequent activities
such as investigation and remediation will be completed, as required, prior to reclamation.
When removing, stockpiling, handling, loading, and transporting contaminated soils, no wind erosion/
blowing of materials will be permitted. If there is the potential for unacceptable blowing of materials
causing the migration of contaminants, then the Contractor will either reschedule the work or will
implement dust suppression (i.e., water mist, tackifier, etc.).
1.3.2 Concrete
There is potential that abandonment activities will encounter concrete that requires removal to complete
the scope of work. There is also potential that abandonment activities may unexpectedly encounter
concrete requiring removal. Concrete encountered may contain COCs.
Removal, handling and disposal of contaminated and non-contaminated concrete on the abandonment
project will be completed on a reactive, as-required basis.
The same process for contaminated soils applies to concrete. Verification samples will be collected, as
required, to ensure that no COCs remain following concrete removal, and waste characterization samples
will be collected to determine disposal requirements.
The Environmental Consultant will obtain representative samples from the interior of pipes, vessels or
valves removed (swab, sludge and/or grease if present) to be analyzed for PCBs. Samples will also be
collected from coating material to be analyzed for PCBs and asbestos, as necessary.
Upon removal of piping, valves, vessels, and equipment exposed to the gas flow, they will be checked for
the presence of NORMs. NORMs testing and analysis will be conducted in accordance with the following
TOP:
If sample results indicate the piping, vessels or valves are contaminated, they will be disposed of in
accordance with applicable Federal and Provincial Regulations and guidance from the Program
Environmental Resource.
Page 1F-4
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
If there is the potential for the water to be contaminated it will not be discharged unless sampling
indicates it is acceptable to do so. If sample results from the water indicate the presence of contaminants
above applicable guidelines, the water must either be disposed off-site or treated.
1.5 Transportation
Transportation of wastes encountered during the Program will comply with all applicable Federal and
Provincial Regulations, including the Transportation of Dangerous Goods Regulations and the
Interprovincial Movement of Hazardous Wastes Regulations.
1.6 Documentation
For all salvage and waste materials leaving sites, contaminated or not, a Waste Disposal Tracking List
shall be maintained by the Contractor. The Waste Disposal Tracking List shall document the type of
waste materials leaving the site, the quantity of materials leaving the site, the name of the shipper, the
name of the receiving facility, date of shipment, manifest or shipping document number, proof of receipt
by the receiver, and Certificates of Treatment or Destruction (if required).
Page 1F-5
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
2.1 Purpose
The Chemical and Waste Management Plan has been prepared to provide guidelines for dealing with the
generation of project waste, and to provide guidelines for dealing with the procurement, storing and
handling of hazardous materials and chemicals required for the Project.
This plan outlines specific measures to be followed by all Company employees and contractors involved
with the construction of the Project. The plan is designed to ensure that chemicals and wastes are
procured, handled, stored and disposed of in an environmentally responsible manner, thereby
maintaining ecological and cultural integrity. This plan will reduce the likelihood of an accidental release of
potentially hazardous waste products into the environment during construction.
This plan applies to all employees, contractors and consultants who conduct work on behalf of the
Company during construction of the Project. All employees, contractors and consultants will abide by all
federal, provincial and local requirements for the storage, handling, transport, disposal and release
reporting requirements of all products and waste materials that are potentially hazardous to human health
and the environment.
The Environmental Inspector is responsible for ensuring compliance with TransCanada’s Environmental
Guidelines and all applicable codes, regulations and industry standards for waste management and
handling chemicals. Where a discrepancy occurs, the most stringent requirements apply. In the event of a
release (i.e., spill), the Release Contingency Plan (see Appendix 1E of this EPP) will be implemented.
The Release Contingency Plan sets forth the lines of communication and procedures to follow in order to
facilitate containment and clean-up should a release occur.
• reasonable preventative measures will be taken to avoid the release of wastes and
hazardous materials into the environment;
• all waste and hazardous material releases will be reported to the Environmental
Inspector and to the appropriate authorities, if warranted;
• all waste and hazardous material releases will be cleaned up promptly and thoroughly;
and
• waste and hazardous materials will, to the extent feasible, be recycled, disposed of or
moved to an approved area as required.
2.2.1 Application
This Chemical and Waste Management Plan applies to the construction footprint, all staging areas,
construction yards and public roadways being used in association with the Project. Awareness of these
requirements will be integrated as appropriate into preconstruction training and orientations.
Page 1F-6
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Solid Nonhazardous Wastes – include garbage and debris generated through the activities of personnel
during construction and construction footprint reclamation. These wastes are nontoxic in nature and
include, but are not necessarily limited to:
• food wastes;
• grinder pads;
• wood;
• wire;
• metal strapping.
Industrial Wastes - include wastes and products generated or utilized during construction. These
materials may contain quantities of potentially toxic substances in the form of residues and include, but
are not necessarily limited to:
• used oils (engine oil, transmission/drive train oil, hydraulic/lube oil, gear oils, lubricating
greases);
• contaminated soil, vegetation and/or absorbents that may contain hydraulic fluid,
gasoline, diesel or lube oil;
• used solvents;
Potential Project related chemicals that are likely to be found on the construction sites include, but are not
necessarily limited to:
• batteries;
• cleaning products;
• lubricants (engine oil, transmission/drive train oil, hydraulic oil, gear oil, lubricating
grease);
Page 1F-7
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
General Measures
1. Construction yards and staging areas that are designated as an industrial waste or chemical storage
area will be selected and designed to:
• avoid wetlands, watercourses, sensitive vegetation, highly permeable soils, steep slopes and
water supply wells when feasible;
• prevent vehicle incidents by providing unobstructed access (for delivery, disposal and emergency
vehicles);
• provide safe storage areas, including secondary containment, for all chemical liquids and
hazardous wastes in accordance with applicable regulatory requirements; and
• provide unobstructed access/egress to/from emergency response materials and equipment.
2. All Project staff with waste management and hazardous materials responsibilities will be educated in
accordance with regulatory requirements specific to the Project. All personnel shall understand their
responsibilities for proper handling, identification, documentation and storage of wastes and
hazardous materials.
3. An appropriate number of portable toilets shall be made available to ensure each crew has ready
access to washroom facilities. The facilities will be serviced and cleaned regularly and will be
adequately secured. All site personnel are to use portable toilets as provided.
4. The Contractor shall register with the appropriate provincial government department with respect to
hazardous materials (to obtain a hazardous waste generator number or equivalent) and shall, at that
time, provide detailed manifest information regarding the location of the staging areas, the types of
waste that will be produced, and the transport vehicle that will be collecting the waste for disposal.
Release Prevention and Response Equipment
Page 1F-8
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
• hydrocarbon release containment (spill kit) complete with a minimum of 10 kg of sorbent material
for clean-up of small releases.
5. Equipment containing fuel or other hazardous materials or chemicals shall have a release
containment (spill kit) included with the unit. In the case of non-mobile equipment or equipment
stationed at a project location for an extended period of time, release containment shall be placed
adjacent to the location.
6. Sorbents, barrier materials (e.g., impermeable liners, etc.), shovels, a water boom, and 210 L storage
drums will be stockpiled at the contractor yards/staging areas to respond to small releases.
7. When working in or near (i.e., within 100m) of a watercourse or waterbody, release containment (spill
kits) shall include booms, sorbent pads or a functionally equivalent containment structure, and they
shall be onsite in the unlikely event of an accidental release of chemicals, hazardous materials or
waste.
Waste and Chemical Handling
1. Personnel who will be handling waste materials will possess valid WHMIS training.
2. All fuel truck drivers, and drivers transporting waste or chemicals will have current Transportation of
Dangerous Goods (TDG) certification.
3. During waste and chemical handling activities, employees and/or contractors will use appropriate
personal protective equipment to prevent any contact with material.
4. Procedures for safe loading and unloading of products will be followed
• service vehicles will be equipped with automatic shut-off valves;
• brakes will be set;
• the vehicle will be grounded if the product is flammable;
• the operator will observe loading and unloading activities at all times; and
• when complete, the operator will examine all outlets for leakage and take corrective action if
warranted.
Waste and Chemical Storage
1. An appropriate number of waste and recycling receptacles will be made available during the Project.
2. Designated industrial waste storage areas at a facility shall be designed to meet all applicable federal
and provincial regulations.
3. Hazardous materials will be stored in designated storage area(s). Short term hazardous material
storage on the right-of-way may be designated at the discretion of the Environmental Inspector, if
required for specific tasks.
4. Hazardous materials and industrial wastes will be stored greater than 100 m from a wetland,
watercourse or waterbody, where feasible.
5. Designated storage areas will be clearly identified and secured. Waste stored in any containers must
be clearly labelled to comply with TDG Act and WHMIS regulations.
6. Hazardous wastes will be separated by type.
7. Secondary containment may be required depending on the location, type, volume and duration of the
waste or chemical being stored. Secondary containment will be in accordance with applicable federal,
provincial and municipal requirements.
8. Containment devices will be constructed from suitable metallic or non-metallic materials capable of
containing the stored product. Liners used for secondary containment shall be placed and maintained
to ensure their effectiveness and intended use.
Page 1F-9
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
9. Secondary containment areas not protected from the elements will be monitored regularly to ensure
that ice, snow, or rainwater have not decreased the volumetric capacity for storage of a release to be
less than 110% of the aggregate storage volume of the containment area. Water accumulated within
a secondary containment structure may be removed if authorized by the Environmental Inspector. If
there is visible hydrocarbon sheen, the water will be collected for proper storage and disposal.
10. Containers and tanks will be closed when not in use. Drain valves will be locked to prevent accidental
or unauthorized releases.
11. Secured non-hazardous materials (i.e., skids, geotextiles, survey stakes etc.) that pose no threat to
the surrounding ecosystem will be neatly stockpiled in locations along the right-of-way for disposal.
The disposal frequency is dependent upon the type of material stockpiled and will be determined by
the Environmental Inspector.
12. The Contractor will visually inspect designated hazardous material and chemical storage areas and
aboveground tanks on a regular basis, as well as when fuel tanks are refilled. The Contractor shall
maintain inspection records in accordance with applicable federal, provincial and local requirements,
and upon request provide the inspection records to the Company. Identified problems or deficiencies
shall be corrected in a timely manner.
13. The Contractor will remove all secondary containment structures at the end of the construction phase,
and return the impoundment area to its original contours and appearance, including establishing
appropriate drainage patterns and vegetation cover.
Waste Disposal
1. All waste materials will be disposed of in accordance with federal and provincial legislation and
municipal/regional regulations as required.
2. Each construction site will be equipped with adequate garbage receptacles for solid non-hazardous
wastes and debris. These materials will be collected as required and disposed of at approved
locations. Food wastes will be stored in animal proof (bear-proof) containers and transported to an
appropriate landfill site.
3. Receptacles for industrial wastes generated during construction will be provided in order to keep
them segregated from non-hazardous waste. Used oil and oil filters will be placed in sealed
containers and delivered for disposal by a qualified service contractor.
4. Receptacles for recycling various products (e.g., paper and tin) will be available at Project
construction yards and camps and will be hauled to appropriate recycling depots.
5. Naturally Occurring Radioactive Materials (NORMs) will be transferred to approved locations by a
qualified contractor for final disposal.
6. Polychlorinated Biphenyl (PCB) treatment or disposal facilities must be pre-approved by the
Company. This includes third party waste brokers, consultants and contractors. PCB concentration
must be thoroughly characterized prior to special treatment or disposal.
Documentation and Record Keeping
1. Material Safety Data Sheets (MSDSs) will be available for each product stored at a particular
construction yard or staging area.
2. The contractor will maintain a record of the routine inspections performed on the industrial waste
storage area(s). The Contractor will furnish the Company construction office with any and all
inspection reports monthly.
3. Provincial manifest records will be reviewed by an authorized Company representative with current
TDG certification when waste is transferred from a temporary storage facility for transport to a final
disposal location.
4. The Environmental Inspector(s) will be provided with copies of waste manifests. Provincial manifest
records must be reconciled within six weeks of initial shipment date. Until notification that the waste
has been received at its final disposal location, the waste is the responsibility of the Company.
5. Copies of manifest records must be kept in a central location for a minimum of two years after the
waste has arrived at its final disposal location.
Page 1F-10
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
3.1 Purpose
The Traffic Control Management Plan provides guidelines for vehicular use on the construction footprint
and associated access roads. The intent is to minimize disturbance resulting from construction on these
lands, particularly in riparian areas and in areas of high erosion hazard. All vehicle and equipment
operators will adhere to the contingency measures for wet/thawed conditions outlined in the Wet Soils
Contingency Plan (see Appendix 1E of this EPP).
The plan objectives will be accomplished by minimizing the development of access routes, selecting
appropriate access routes that cause the least disturbance, managing traffic on these routes and
determining appropriate as-left treatment at the completion of the Project.
3.2 Preconstruction
The applicable provincial authorities will be notified of all access road upgrading requirements and the
Company will accommodate continued public access during construction whenever feasible.
1. To prevent inadvertent trespass, stake the approved construction footprint to clearly delineate all
boundaries.
2. All motorized vehicle traffic, including ATV, Argo and snowmobile traffic, will be confined to the
approved route, access roads or trails except where specifically authorized by the appropriate
authority.
3. Vehicle travel across wetlands and riparian areas should be reduced to the extent feasible.
The development and maintenance of access roads required prior to, or during construction, will adhere
to the relevant requirements set out in this EPP.
3.3 Construction
During construction, traffic will adhere to the following guidelines:
1. All Project personnel and other visitors to the right-of-way will participate in the Contractor orientation
program.
2. All access points to the construction footprint will be flagged and signed to discourage public use.
3. All vehicular traffic will be restricted to the approved and staked construction footprint.
4. Construction and inspection personnel and visitors to the construction footprint and other work sites
will receive instruction on locations suitable for parking vehicles and equipment.
5. The Company, Contractor and all subcontractor personnel will avoid areas that are fenced or staked
and abide by any restrictions on in/out privileges that are implemented in areas requiring special
protection.
6. The Company, Contractor and all subcontractor personnel will limit unnecessary travel on the
construction footprint during the course of the work.
Page 1F-11
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
7. Special measures such as the limiting of construction traffic or implementing of swamp mats or
matting may be warranted in areas with poorly-drained and organic soils (see the Wet Soils
Contingency Plan in Appendix 1E of this EPP).
8. Construction personnel will be transported between construction yards and the construction site by
multi-passenger vehicles to the extent practical, in order to minimize vehicle traffic.
9. Control measures may be put in place to ensure traffic adheres to special restrictions that are in effect
(e.g., narrowing of work space to limit impact on a species of concern).
10. The speed limit on the construction footprint will be designated by the Contractor. Speed limits may
be lowered under specific conditions such as areas with poor visibility, steep terrain or areas where
specific wildlife concerns have been identified.
11. All Project-related vehicles will follow applicable traffic, road-use and safety laws.
12. All vehicle traffic will avoid unnecessary wheel spin.
13. During non-frozen conditions, equipment travel, particularly that of heavy and/or tracked equipment,
will make use of the stripped and graded areas for travel and passing.
14. Stringing trucks require extra turning radius. Consequently, approaches to the right-of-way or existing
public roads will be wider when used for stringing trucks. Where turnarounds are required on the
right-of-way, extra space will be required on the travel side of the right-of-way. Previously disturbed
areas will be used for this purpose, when feasible. Stringing trucks will be limited to access roads
developed for their use. Turn around areas require approval by applicable government agencies.
3.4 Post-Construction
After construction is complete, restoration efforts will be initiated and traffic will adhere to the following
principles to ensure there is as little disturbance as practical.
1. All temporary construction access roads and shoo-flies will be reclaimed to preconstruction conditions
or restored as per this EPP. Newly created access points will be blocked unless otherwise directed by
the Company or the responsible regulatory agency.
2. Vehicle traffic will be minimized on newly seeded areas until ground cover is re-established.
3. Routine access to the construction footprint for operation, maintenance and monitoring activities will
be by way of pre-existing roads and trails wherever feasible. Where travel on the construction
footprint in the vicinity of important vegetation is required (e.g., during reclamation monitoring) foot
travel will be used whenever feasible. ATV/Argos will be used if necessary.
4. Efforts to control off-road vehicle use will be coordinated with the appropriate authorities and will
continue until the construction footprint has been satisfactorily reclaimed. Methods to control access
may include one or a combination of the following:
- posting of appropriate signage at all points of access;
- create a visual barrier to reduce line of sight;
- installation of locking gates and fencing; and/or
- installation of slash or rock barriers.
Page 1F-12
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
4.1 Purpose
To provide guidance regarding the management of hydrovac slurry during construction activities in a
manner that is protective of the environment and compliant with applicable regulations. This management
plan applies to all hydrovac slurry generated as a result of construction activities in Canada.
Selection of hydrovac slurry management methods is determined based on the presence or absence of
encountering contamination within the planned hydrovac excavation area. Contaminant risk screening
must include, at a minimum, the following: tasks:
1. Review historical information/records within the area(s) proposed for hydrovac excavation where
available.
2. Evaluate risk due to proximity of the planned excavation area to surface equipment.
• If the excavation area is located within a facility footprint (e.g., aboveground piping, valve
assemblies, meter stations, compressor stations, pump stations etc.), the slurry should be
considered potentially contaminated until analysis results prove otherwise. Refer to Section 3.4
Contaminated/Suspected Contaminated.
• If the excavation area is located outside of a facility footprint there is less risk in uncovering
contaminated soil.
3. Onsite inspection of the proposed excavation area will include olfactory and visual observation for
signs of contamination (e.g., odour, soil staining, impacted vegetation, sheen).
Upon completion of the risk screening, the Environmental Inspector (EI), or designate, should have
sufficient information to determine what will be encountered within the work area and designate the site
as ‘contamination not suspected’ or ‘contaminated/suspected contaminated.’
Hydrovac slurry from new disturbances is generally of mineral soil content and has a low risk of
contamination, therefore onsite disposal is the preferred method if subsidence is not a concern. The
disposal area must be in a location that has had the surface materials removed. If a soil berm is required
to contain slurry, soil material shall be of subsoil or an alternative material capable of containing the
slurry. This decision must be approved by the TransCanada Environmental Advisor or designated
environmental field representative.
Non-contaminated slurry can either be temporarily stored onsite in bermed containment (or in other
containers approved by the project) to ensure no uncontrolled surface run-off or release into the ground
or transported to an approved storage or disposal facility.
Non-contaminated slurry may be released into the hydrovac excavation if future subsidence of the site is
not a concern and the area is fenced until the tailings are dry.
Page 1F-13
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Non-contaminated slurry may be used as clean fill onsite only. Water from non-contaminated slurry can
be pumped on site or removed as non-contaminated, following approved dewatering and water
management practices.
If contaminants are suspected, do not remove the hydrovac slurry from the site. Arrangements should be
made to temporarily contain the slurry onsite in adequate structures pending analysis and final disposal
arrangements.
Contaminated slurry shall be kept separate from non-contaminated slurry. Ensure approved
transportation, temporary storage and disposal locations are in place prior to starting hydrovacing
activities.
Contaminated hydrovac slurry may be temporarily stored in bermed and/or lined impermeable
containment until a disposal location for the slurry has been determined. Contaminated hydrovac slurry
MUST NOT be allowed to drain onto or into the ground.
If temporary onsite storage is to be constructed (e.g., sump or bermed area) the surface materials must
be removed from the area. The area constructed must be able to contain slurry and prevent any off site
migration.
Hydrovac contractor may temporarily store slurry in their trucks or at a site that is designed to safely store
slurry. Use clean oilfield storage tank or metal slop bin for temporary storage if other more practical
storage options (i.e., temporary pits) are not desirable for the site.
The contractor will ensure that the EI has reviewed and approved a disposal site prior to starting
Hydrovac operation.
Salvage topsoil prior to hydrovac use in all areas with agricultural potential.
Wet hydrovac slurry cannot be sent to a landfill even if it is not contaminated with hazardous substances.
Wet hydrovac slurry can be disposed of by the hydrovac contractor to a licensed treatment or disposal
facility where accepted. Appropriate documentation must be provided to the Company to verify that
hydrovac slurry disposal is in accordance with regulatory requirements and to the satisfaction of the
Company
DO NOT pump hydrovac slurry water into a watercourse, waterbody or onto a landowner’s property, even
if the landowner has provided permission.
Page 1F-14
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Contaminated and potentially contaminated slurry needs special handling storage and disposal
requirements.
All hydrovac holes shall be adequately back filled with mineral soil or other materials as directed by the
owner of the facilities, to ensure settling of material does not pose a hazard for wildlife, livestock or the
general public.
Monitoring of the slurry for indications of contamination should be ongoing during the hydrovacing
activities.
Page 1F-15
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
5.1.1 Federal
There are legal obligations in Canada regarding the protection of migratory birds, as well as non-
migratory birds. The following regulations apply to the protection of birds in Canada:
The Migratory Birds Convention Act (MBCA) and the Migratory Birds Regulation (MBR) prohibit the
disturbance or destruction of migratory birds and their nests and eggs in Canada. “Migratory bird” is
defined by Section 2 of the MBCA, and generally includes most migratory species that are native or
naturally occurring in Canada (Environment Canada 2013a). The MBCA and MBR apply to all lands and
waters in Canada, regardless of ownership. Environment Canada is responsible for administering the
MBCA on behalf of the federal government.
Birds not covered by the MBCA include grouse, quail, pheasants, ptarmigan, hawks, owls, eagles,
falcons, cormorants, pelicans, crows, jays, kingfishers, and some species of blackbird. Although not
covered by the MBCA, Provincial setbacks or other protection may apply to these birds.
Some bird species, including migratory and non-migratory bird species are protected under the Species
at Risk Act (SARA). The Species at Risk Public Registry provides the current list of species protected
under SARA. It is prohibited to remove the nest of any threatened or endangered species at any time if
the species is likely to re-use that nest. Environment Canada is responsible for administering SARA.
• Wildlife Acts (Alberta, British Columbia, Manitoba, Northwest Territories, Nova Scotia,
Nunavut, Saskatchewan, Yukon);
Page 1F-16
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Provincial or territorial legislation may include year-round protection of inactive nests of some species,
and in some provinces or territories a permit may be authorized for the removal of an inactive nest of
some species. In some jurisdictions, legislation may include species-specific protection, or exemption
from protection (e.g., pest species that damage crops).
The following information sources were reviewed in the development of the BBNMP, and should be
referred to for additional detail in the development of project-specific BBNMPs:
• Draft Migratory Birds Convention Act: A Best Management Practice Developed for the
Canadian Energy Pipeline Association document prepared for the (CEPA 2013); and
• develop and implement appropriate preventative and mitigation measures to avoid the
risk of incidental take and to help maintain sustainable populations of birds.
TransCanada will use the regional nesting zones and nesting periods identified by Environment Canada
to identify the risk of incidental take of migratory birds in Canada (Figure 1). The primary nesting period is
the period when 10% or more of the species within a given nesting zone are expected to be breeding, as
interpreted from Environment Canada’s nesting calendars (Environment Canada 2014). The primary
nesting period is the period of time when risk of incidental take is substantially higher than at other times
of the year.
The nesting calendars provide nesting activity for migratory birds for three broad habitat types: wetland,
open field, and forest. Primary nesting periods for each nesting zone in Canada, by broad habitat type
and consolidated, are provided in Figure 2.
Page 1F-17
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 1F-18
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Figure 2 Primary Nesting Periods by Nesting Zones and Broad Habitat Types
Nesting Wetland Open Field Forest Consolidated Primary Nesting Period
Zone Start End Start End Start End Start End
A1 March 28 July 27 April 9 August 8 April 1 August 7 March 28 August 8
A1a March 29 July 25 April 10 August 10 April 5 August 7 March 29 August 10
A2 April 9 July 27 April 23 August 7 April 12 August 7 April 9 August 7
A3 April 16 July 29 May 2 August 8 May 1 August 7 April 16 August 8
A4 April 25 August 2 May 7 August 8 May 3 August 7 April 25 August 8
A5 April 29 August 2 May 7 August 8 May 3 August 7 April 29 August 8
B3 April 16 July 29 May 2 August 12 April 21 August 12 April 16 August 12
B4 April 26 July 30 May 5 August 15 April 25 August 12 April 26 August 15
B5 May 1 August 2 May 8 August 10 May 3 August 9 May 1 August 10
B6 May 5 August 2 May 10 August 5 May 7 August 7 May 5 August 7
B7 May 12 August 4 May 14 August 7 May 12 August 8 May 12 August 8
B8 May 15 August 7 May 16 August 10 May 15 August 8 May 15 August 10
B9 May 17 August 8 May 22 August 8 May 17 August 9 May 17 August 9
C1 April 3 August 12 April 16 August 11 April 9 August 11 April 3 August 11
C2 April 10 August 12 April 20 August 11 April 15 August 9 April 10 August 9
C3 April 15 August 2 April 25 August 13 April 21 August 11 April 15 August 13
C4 April 21 July 29 April 29 August 14 April 25 August 8 April 21 August 14
C5 April 27 July 29 May 7 August 14 May 1 August 8 April 27 August 14
C6 May 2 August 2 May 8 August 4 May 5 August 7 May 2 August 7
C7 May 7 August 4 May 13 August 2 May 9 August 7 May 7 August 7
C8 May 15 August 6 May 18 August 3 May 15 August 7 May 15 August 7
D3-4 April 20 July 28 May 27 July 29 May 23 August 7 April 20 August 7
D5 April 27 July 30 May 6 August 1 May 1 August 7 April 27 August 7
D6 May 7 August 3 May 15 August 4 May 10 August 7 May 7 August 7
D7 May 12 August 7 May 16 August 5 May 15 August 7 May 12 August 7
N8 May 22 August 7 May 22 August 7
N9 May 22 August 9 May 22 August 9
N10 May 30 August 7 May 30 August 7
Source: Environment Canada 2014
Potentially destructive or disruptive activities should be scheduled to occur outside of the nesting zone
primary nesting period, to the extent practical. However, avoidance of the primary nesting period must be
considered in a broader context and balanced with other environmental considerations (e.g., beneficial
timing for soil conservation, restricted activity periods for fish and other wildlife species in the project area,
etc.) Examples of where it may not be practical to avoid the primary nesting period include routine
maintenance of facilities for safe operation, emergency response, and geophysical, habitat, or climatic
constraints related to construction or maintenance activities.
In the event that clearing or construction activities cannot be avoided during the migratory bird nesting
period, non-intrusive methods should be used to conduct an area search for evidence of nesting within
seven days of activities that are scheduled to occur. The process to be followed in the event that a
migratory bird nest search is warranted is outlined in Figure 3.
In some circumstances, depending on the intensity of the activity to be conducted and the presence of
other mitigating factors (e.g., existing disturbance in the project area), a non-intrusive nest search
completed by a Wildlife Resource Specialist may not be warranted. A decision to modify the nest search
requirements will be made by the Environmental Advisor as well as the Project Manager and the
determination will be made following a risk assessment considering the intensity of proposed activity, land
use, and potential for incidental take.
Outside of the primary nesting period (i.e., when fewer than 10% of species in a nesting zone are
breeding), a search for migratory bird nests is generally not required, unless recommended on a project-
specific basis. Any discoveries of active or protected nests will be documented and mitigated through the
TransCanada Wildlife Species of Concern Discovery Contingency Plan. A Wildlife Resource Specialist
will be consulted for additional guidance as needed.
Page 1F-19
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Page 1F-20
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
APPENDIX 1G
Page 1G-1
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Observation:
Number of adult caribou observed (indicate male or female, if known):
Number of calves or young caribou observed:
Additional notes:
Habitat Type:
Recorded by:
Telephone:
Provide this information to NGTL’s Environmental Project Supervisor, who will submit this information to the AEP
Wildlife Biologist (see Appendix 1B) using a Fisheries and Wildlife Management Information System (FWMIS)
loadform.
Page 1G-2
NOVA Gas Transmission Ltd. Environmental Protection Plan
Proposed 2016 Meter Stations and December 2016/678527
Laterals Abandonment Program
Wildlife observations:
List wildlife species observations (provide species name, number of males, number of females, number of young and
any additional comments)
Habitat Description:
Recorded by:
Telephone:
Provide this information to NGTL’s Environmental Project Supervisor, who will submit this information to the AEP
Wildlife Biologist (see Appendix 1B) using a Fisheries and Wildlife Management Information System (FWMIS)
loadform.
Page 1G-3