Event Document Document Received

SN. Document Event Title


Ref. Date
Type

Local Authorities
1 Letter Letter 1 25/Mar/12
Permission

2 Letter Letter 2 Site Handing Over 20/Mar/12

Material Changing Pumps


3 Mar-20 15/Apr/12
Submittal specs by client

Material Late Response


4 Mar-04 12/May/12
Submittal Lighting Fixture

Minutes Of Utilities
5 MOM 13 1/Feb/13
Meeting availability

Minutes Of Safe Door


6 MOM 9 1/Sep/12
Meeting Delivery

Request For Under Ground


7 RFI 3 29/Mar/12
Information Water Level
Clash between
Request For
8 RFI 6 Lighting Unit and 1/Feb/13
Information Diffuser

Doors and
Shop Drawing
9 SDF 2 Windows Shop 29/Apr/12
reviews Drawing

Site Work Change Marble


10 SWI 1 20/Jan/13
Instruction Fixation

Site Work Change Painting


11 SWI 2 15/Mar/13
Instruction Color Code

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted
Supporting Supporting Letter New Activity New Activity New Activity
Letter No. Date ID (1) Name (1) (1) Duration

Authorities
1 28/Mar/12 Letter 1 - 1 20
Permissions

Site Delivery
2 20/Mar/12 Letter 2 - 1 10
Delay

New Pumps
3 15/Apr/12 MAR-20-1 5
Submittal

Delay of MAR
4 15/May/12 MAR 4-1 20
response

Delay of Utilities
5 5/Feb/13 MOM-13-1 Milestone
availability

Safe Door
6 1/Sep/12 MOM 9-1 60
Supplying Delay

Response from
7 29/Mar/12 RFI No.3-1 10
Consultant

Remove Fixed
8 5/Feb/13 RFI-6-1 20
Lighting Fixture

New Door
9 30/Apr/12 SDF 2-1 5
Submittal

Demolish all fixed


10 20/Jan/13 SWI1_1 3
marble

Submit new
11 19/Mar/13 SWI 2_1 material for 3
approved

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted
New Activity New Activity New Activity Impacted Impacted
(1) (1) (1) New Activity New Activity
Predecessor Predecessor Relationship (1) Lag ID (2)
Id Name type

Local Authorities
Letter 1 FS 0
Permission

Letter 2 Site Handing Over FS 0

Changing Pumps
Mar-20 FS 0 MAR-20-2
specs by client

Late Response
Mar-04 FS 0
Lighting Fixture

Utilities
MOM 13 FS 0
availability

Safe Door
MOM 9 FS 0
Delivery

RFI 3 RFI No.3 SS 0 RFI No.3-2

RFI 6 RFI-6 SS 0 RFI-6-2

SDF 2 SDF 2 SS 0 SDF 2-2

SWI 1 SWI 1 SS 0 SWI 1_2

SWI 2 SWI 2 SS 0 SWI 2_2

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted
Impacted New Activity New Activity New Activity
Impacted New Activity New Activity (2) (2) (2)
Name (2) (2) Duration Predecessor Predecessor Relationship
Id Name type

New Pumps
New Pumps Approval 3 MAR-20-1 FS
Submittal

Response from
Dewatering 10 RFI No.3-1 FS
Consultant

Remove Fixed
Modify Cables and conducts 20 RFI-6-1 FS
Lighting Fixture

New Door
New Door Approval 3 SDF 2-1 Submittal

Submit New Method Demolish all fixed


Statement for mechanical 3 SWI1_1 SS
marble
Fixation

Submit new
Approved New Material 3 SWI 2_1 material for SS
approved

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted
Impacted Impacted Impacted New Activity Impacted New Activity
New Activity New Activity New Activity (3)
Name (3)
(2) Lag ID (3) (3) Duration Predecessor
Id

0 MAR-20-3 New Pumps Procurement 180 MAR-20-2

0 RFI No.3-3 Soil replacement 7 RFI No.3-2

SDF 2-3 Door Procurement 280 SDF 2-2

Approved Method Statement


0 SWI1_3 3 SWI1_2
For Mechanical Fixation

0 SWI2 _3 Material Procurement 15 SWI 2_2

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted
New Activity Impacted
Impacted New Activity Impacted New
(3) New Activity
(3) Predecessor Name Relationship Activity (3) Lag ID (4)
type

New Pumps Approval FS 0

Dewatering FS 0

New Door Approval

Submit New Method


Statement for mechanical FS 0 SWI1_4
Fixation

Approved New Material FS 0

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted
Impacted Impacted New Activity Impacted New New Activity
New Activity New Activity (4) Activity (4) (4)
Name (4) (4) Duration Predecessor Predecessor Name Relationship
Id type

Material Approved Method


Procurement 7 SWI1_3 Statement For Mechanical FS
order for new Fixation
material

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted
Impacted
Impacted Impacted Existing
Impacted Existing Existing
New Activity Existing Activity (1)
Activity Name (1) Activity
(4) Lag Activity ID (1) Predecessor
Duration (1) Id

SUBz100020 Excavation Activity 6 Letter 1 - 1

SUBZ100010 Mobilization 25 Letter 2 - 1

INSTALLATION OF WATER &


0801MW0011 17 MAR-20-2
FIRE PUMPS

LIGHTING FIXTURES&
A2250 47 MAR-4-1
SWITCHS Procurement

Elevators TESTING AND


A2450 22 MOM-13-1
COMMISSIONING

Arch1070 Wall Preparation for Painting 21 MOM 9-1

COMPACTING WORKS UNDER


SUBZ100030 3 RFI No.3-3
THE P.C LAYER

LIGHTING FIXTURES&
0801EL0005 60 RFI-6-2
SWITCHS & OUTLETS

ARCH1150 WOODEN DOORS INSTALLING 14 SDF 2-3

MARBLE WORKS VIP SEC.


0 Arch1110 WALL'S CLADDING 20 SWI1_4
&FLOORING

A2290 Painting Site delivery date 15 SWI2 _3

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted
Existing Existing Impacted
Existing Impacted Existing
Activity (1) Activity (1) Existing
Activity (1) Activity Activity (2) Name
Predecessor Relationship ID (2)
Lag
Name type

Authorities FS 0
Permissions

Site Delivery FS 0
Delay

New Pumps FS 0
Procurement

Consultant FS 0

Delay of Utilities Finishes Touch up &


FS 0 Site10090
availability Commissioning

Safe Door FS 0
Supplying Delay

Soil replacement FS 0

Modify Cables FS 0
and conducts

Door FS 0
Procurement

Material
Procurement FS 0
order for new
material

Material FS 0
Procurement

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted
Impacted Impacted
Existing Existing Existing
Existing Existing
Activity (2) Activity (2) Activity (2)
Activity (2) Activity (2)
Predecessor Predecessor Relationship
Duration Lag
Id Name type

Delay of Utilities
14 MOM-13-1 FS 0
availability

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted
Impacted
Impacted Existing Existing
Impacted Existing Existing
Existing Activity (3) Activity (3)
Activity (3) Name Activity (3)
Activity (3) ID Predecessor Predecessor
Duration Id Name

MECHANICAL TESTING AND Delay of Utilities


SITE10100 23 MOM-13-1
COMMISSIONING availability

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted
Existing Impacted
Existing Impacted Existing Existing
Activity (3) Existing
Activity Lag Activity Activity (4) Name Activity (4)
Relationship (4) ID
(3) Duration
type

ELECTRICAL TESTING AND


FS 0 SITE10110 26
COMMISSIONING

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Impacted Impacted Impacted Impacted
Existing Existing Existing Existing
Activity (4) Activity (4) Activity (4) Activity (4)
Predecessor Predecessor Relationship Lag
Id Name type

Delay of Utilities
MOM-13-1 FS 0
availability

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Event Comment

This event will delay the project because ,these instructions from the client to hold excavation is after the
planned date of Excavation.

Reference to the approved project time schedule ,this event will delay the project start from (10-March
2012) to (20-March 2012)

This event will delay the project because it will take several months to procure these pumps as they will be
imported.

Reference to the approved project time schedule this event will delay the project , because the consultant
late response with 27 delays days .Response date (12-May 2012) instead of (15-Apr-2012) this will delay the
whole process of procurement and executing of these fixtures.

Reference to the approved project time schedule this event will delay the project , because any delay in
Utilities availability will delay the "Testing & Commissioning" Work Package .Also Utilities availability was
planned to start on (21-Mar-2013) not (1-July-2013).

Reference to the approved project time schedule this event will delay the project because , Safe Door has a
Milestone with fixed date on the baseline schedule. The client delayed this date by (60) days

The actual condition of the underground water differs from the contractual foundation report therefore the
contractor has the right to claim for time and money.
Reference to the approved project time schedule this event will delay the project because ,the contractor
raised the problem before the activity planned start date, however, the consultant late reply (after 8
months) will cause rework for the contractor.

changing the door from local to imported will take longer time to procure which give the right contractor to
claim EOT.

Reference to the approved project time schedule this event will delay the project because ,the client
instructed the contractor to change the installation method after starting the activity. This instruction will
hold the work until submitting new method statement, procure the material and remove the fixed marble

Reference to the approved project time schedule this event will delay the project because , the client
requested to change the color code on "15-Mar-2013" and the contactor painting material procurement
finish date "20-Oct-2012" , So the contactor has right to claim about the time needed for new material
procurement.

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/
Influence Event Total Screen shot
Schedule Delays Days

Schedule (1) 0 Event 1

Schedule (2) 17 Event 2

Schedule (3) 0 Event 3

Schedule (4) 0 Event 4

Schedule (5) 71 Event 5

Schedule (6) 1 Event 6

Schedule (7) 0 Event 7

Schedule (8) 44 Event 8

Schedule (9) 66 Event 9

Schedule (10) 26 Event 10

Schedule (11) 266 Event 11

Claims Management - Delay Analysis Workshop Link :


www.planningengineer.net/courses/claims-management-and-delays-
analysis-online-workshop/