Local Authorities
1 Letter Letter 1 25/Mar/12
Permission
Minutes Of Utilities
5 MOM 13 1/Feb/13
Meeting availability
Doors and
Shop Drawing
9 SDF 2 Windows Shop 29/Apr/12
reviews Drawing
Authorities
1 28/Mar/12 Letter 1 - 1 20
Permissions
Site Delivery
2 20/Mar/12 Letter 2 - 1 10
Delay
New Pumps
3 15/Apr/12 MAR-20-1 5
Submittal
Delay of MAR
4 15/May/12 MAR 4-1 20
response
Delay of Utilities
5 5/Feb/13 MOM-13-1 Milestone
availability
Safe Door
6 1/Sep/12 MOM 9-1 60
Supplying Delay
Response from
7 29/Mar/12 RFI No.3-1 10
Consultant
Remove Fixed
8 5/Feb/13 RFI-6-1 20
Lighting Fixture
New Door
9 30/Apr/12 SDF 2-1 5
Submittal
Submit new
11 19/Mar/13 SWI 2_1 material for 3
approved
Local Authorities
Letter 1 FS 0
Permission
Changing Pumps
Mar-20 FS 0 MAR-20-2
specs by client
Late Response
Mar-04 FS 0
Lighting Fixture
Utilities
MOM 13 FS 0
availability
Safe Door
MOM 9 FS 0
Delivery
New Pumps
New Pumps Approval 3 MAR-20-1 FS
Submittal
Response from
Dewatering 10 RFI No.3-1 FS
Consultant
Remove Fixed
Modify Cables and conducts 20 RFI-6-1 FS
Lighting Fixture
New Door
New Door Approval 3 SDF 2-1 Submittal
Submit new
Approved New Material 3 SWI 2_1 material for SS
approved
Dewatering FS 0
LIGHTING FIXTURES&
A2250 47 MAR-4-1
SWITCHS Procurement
LIGHTING FIXTURES&
0801EL0005 60 RFI-6-2
SWITCHS & OUTLETS
Authorities FS 0
Permissions
Site Delivery FS 0
Delay
New Pumps FS 0
Procurement
Consultant FS 0
Safe Door FS 0
Supplying Delay
Soil replacement FS 0
Modify Cables FS 0
and conducts
Door FS 0
Procurement
Material
Procurement FS 0
order for new
material
Material FS 0
Procurement
Delay of Utilities
14 MOM-13-1 FS 0
availability
Delay of Utilities
MOM-13-1 FS 0
availability
This event will delay the project because ,these instructions from the client to hold excavation is after the
planned date of Excavation.
Reference to the approved project time schedule ,this event will delay the project start from (10-March
2012) to (20-March 2012)
This event will delay the project because it will take several months to procure these pumps as they will be
imported.
Reference to the approved project time schedule this event will delay the project , because the consultant
late response with 27 delays days .Response date (12-May 2012) instead of (15-Apr-2012) this will delay the
whole process of procurement and executing of these fixtures.
Reference to the approved project time schedule this event will delay the project , because any delay in
Utilities availability will delay the "Testing & Commissioning" Work Package .Also Utilities availability was
planned to start on (21-Mar-2013) not (1-July-2013).
Reference to the approved project time schedule this event will delay the project because , Safe Door has a
Milestone with fixed date on the baseline schedule. The client delayed this date by (60) days
The actual condition of the underground water differs from the contractual foundation report therefore the
contractor has the right to claim for time and money.
Reference to the approved project time schedule this event will delay the project because ,the contractor
raised the problem before the activity planned start date, however, the consultant late reply (after 8
months) will cause rework for the contractor.
changing the door from local to imported will take longer time to procure which give the right contractor to
claim EOT.
Reference to the approved project time schedule this event will delay the project because ,the client
instructed the contractor to change the installation method after starting the activity. This instruction will
hold the work until submitting new method statement, procure the material and remove the fixed marble
Reference to the approved project time schedule this event will delay the project because , the client
requested to change the color code on "15-Mar-2013" and the contactor painting material procurement
finish date "20-Oct-2012" , So the contactor has right to claim about the time needed for new material
procurement.