Você está na página 1de 4

Planning for a turnaround

Without the efforts of professional craft planners and logistics professionals,


turnarounds will be a serious challenge

MIKE ASQUINI
T.A. Cook

R
efinery turnarounds project of this proportion. This load will affect the event’s cost
are massive events. For article will explain how to prop- and duration and make it very
organisations to be com- erly detail planning, schedul- difficult to maintain the already
petitive, they must be able to ing and overall management for challenging targets.
manage these maintenance the preparation of a successful Although there are many
overhaul projects and meet all turnaround. ways for an organisation to
safety, cost and duration tar- structure itself to perform
gets. Considering the quantity Phase 1: planning, site-wide a turnaround, one aspect is
of labour, and the materials and support, risk management non-negotiable: this is a site-
services a turnaround requires, Before actually executing work, wide event and must be sup-
coordination is a huge under- the right people need to plan ported by everyone. Without
taking, especially because all how they will do it. Setting this mindset, it is difficult to
of these resources add up to goals, developing strategies, accomplish the turnaround’s
significant sums of money. outlining tasks, and creating objectives. Once the goals
Beyond the financial pressures, a schedule are all important have been fully defined, man-
the logistics of predicting the aspects of planning and form agement must make sure that
costs for all of the scope, which the basis of overall turnaround everyone is aligned and under-
will include both known and development. The first step in stands all of the project’s objec-
unknown work, is particularly the process is to clearly define tives. In order to communicate
challenging. the turnaround’s objectives. all the details, management and
A successful turnaround exe- Only then will the scope of work decision-makers need to host
cution means that there are begin to take shape. Before the an informative meeting for all
absolutely no safety or environ- scope can be defined, let alone turnaround stakeholders. In this
mental setbacks, all cost and finalised, management must meeting, decision-makers need
duration targets are met and the decide what work will be done, to share all facets of the upcom-
affected units are guaranteed and what work will not be done, ing event. The areas of topic
to run at the expected rate as by creating a clearly defined set will include turnaround objec-
soon as the event ends until the of criteria. The question of what tives, project preparation sched-
beginning of the next scheduled should be included in the turn- ule, capital project integration,
turnaround. To reach that point, around’s scope should be min- sharing of lessons learned from
a site must have a strong prepa- imised at this stage by being as previous turnarounds, identi-
ration strategy in place. With the black and white and selective fying the core turnaround team
help of best practice techniques as possible. Any ambiguity will members and resource require-
and organisation requirements, lead to scope creep. This type of ments as well as initiating a
a site can control a maintenance spontaneous increase in work dynamic risk management pro-

www.digitalrefining.com/article/1001454 Revamps 2017 1


Consequences Probability
90–100% 60–90% 40–60% 10–40% 0–10%
A B C D E
Severity Health / Environ- Media Business TAR specific Possibility Possibility Possibility Not likely Practically
safety mental attention / impact of repeated of isolated of occurring to occur impossible
action by incidents incidents sometimes
authorities
1 Fatality(ies) / Potential signi- Significant Corporate Extends
(Severe) serious injury ficant, wide- public disrup- >$2M TAR duration
requiring med- spread long- tion; national >2 days
ical treatment
to members of
term adverse
effects; sus-
or international
media coverage
1A 1B 1C 1D 1E
public tained com-
plaints
2 Serious or lost- Potential local- Small public Business Extends
(Major) time injury / ised medium- disruption; $500k–$2M TAR duration
illness term adverse extended local <2 days 2A 2B 2C 2D 2E
effects; numer- media
ous complaints coverage
3 Restricted Potential One-time local Site Extends
(Serious) work or short-term media $100k–$500k unit critical
medical minor adverse coverage path 3A 3B 3C 3D 3E
treatment effects; public
complaints
4 First aid / Negligible or No media Other No impact on
(Significant) minor injury no adverse
effects
coverage <$100k unit critical
path
4A 4B 4C 4D 4E

Figure 1 An example of a risk matrix. The consequences are defined on the left, then measured against the probability of
a risk occurring

cess that remains in place until a turnaround’s success using a it thoroughly using the defined
the project officially closes. The risk matrix (see Figure 1). criteria. If proposed work meets
alignment meeting is the time The turnaround team starts the requirement, it is part of the
for employees to ask questions by minimising the risks with scope and if it does not meet the
and for management to provide the highest impact. Risks will be requirements staff should con-
answers. After this, the team added to and subtracted from sider scheduling it at a differ-
should be on the same page and the list based on the identifi- ent time, such as during routine
the overall site should be pre- cation of new risks, mitigation maintenance, as part of a capital
pared for the event. of existing risks, and changing project, during the next outage
The initiation of a risk man- conditions. Even though not (turnaround or otherwise), or
agement process is a key piece all risks can be managed, if the cancelling the work altogether.
of turnaround preparation. It turnaround team focuses work Any proposed work that does
needs to be mentioned that on the items with the highest not make the cut for inclusion in
risk management is dynamic; impact, the success of the project the turnaround still needs to be
it is forever changing. Risks can be maximised. dispositioned properly.
are inherent to all projects, but Beyond scope, there are other
fortunately they can be dealt Phase 2: scope management – preparatory activities during
with. If mitigating activities are definition and freeze this phase which are part of the
planned, risks are minimised At this point, the site should planning effort. One of these
(although not eliminated) as have all the turnaround’s objec- additional activities is coor-
much as possible. In most cases, tives defined, all personnel dination between the turna-
the list of identified risks can be aligned and the scope inclu- round team and procurement
lengthy. However, core turn- sion criterion finalised. The to identify long lead time items
around team members will next phase of the turnaround is based upon approved scope.
never have risk mitigation as selecting the actual work for Procurement will also be impor-
their only function. In order to the event. Developing the scope tant to help the site develop
efficiently and effectively man- is a rigorous process. Once the contracting strategies based on
age risk, we must rank the risks team identifies each piece of whether or not scope is clearly
and work on the ones that have work that could be added to defined. There are other fac-
the greatest potential impact on the scope, they must evaluate tors to consider when selecting

2 Revamps 2017 www.digitalrefining.com/article/1001454


a contracting strategy, but com- and the requirements to com- encounter at the job site.
pleteness of scope definition is a plete the work. Then, the plan- The job packages should pro-
governing factor. Besides organ- ner will only need to visit the job vide the craftspeople with
ising with procurement, the site and begin to develop a step- everything they need to per-
final piece to the puzzle at this by-step job plan. This detailed form the work safely, effi-
point is the development of a job plan is the first piece of the ciently and effectively. With a
first pass cost estimate. To form work package. The whole work job plan in hand, they should
the first pass cost estimate, the package comes about as the be able to arrive at the job site
team must have a fully devel- product of the planning phase. with the correct tools, materials,
oped idea of the upcoming work Each and every task on the and equipment to perform the
detail. Scope development is scope list will require a work identified work scope. At this
a prerequisite for detailed job package. That way, the person- point, there should be no prob-
planning. nel executing the work (usu- lem meeting quality control and
Finally, this phase is complete ally a contractor) can perform assurance requirements.
with the closure of scope devel- the assignments successfully
opment, also known as scope with little or no interjection from Phase 4: onboarding
freeze. This can happen only others. Of course, planning for a turna-
after all identified scope has Creating these work packages round includes much more than
been challenged. Inspections is a collaborative effort, but the detailed plans for each individ-
personnel will determine this site planner will take the reins. ual job. The site must be pre-
after thoroughly reviewing all Typically, the planner collects pared to accept the volumes of
the assets in the area where all the required information, craftspeople, administrative per-
the turnaround will be exe- which includes visiting the job sonnel, management, and all of
cuted. During these inspec- site to survey the work area and the support staff needed to exe-
tions, decision-makers will be determining what is required cute a turnaround. On oil, gas
able to consider poor perform- to complete the tasks. A check- and petrochemical sites, secu-
ing equipment or bad actors list is imperative to ensure the rity is a top concern. The site
prior to scope freeze. Once the planner surveys the site well, must be capable of screening
scope has been determined, the asks all the right questions, the mass of people coming to
team will be able to determine and comes up with a complete work to ensure the right people
an accurate high level cost esti- and thorough work package. are authorised to be there. This
mate. Additional scope may be During this first job site visit, massive undertaking can be
added, but it is only warranted the planner may take photos or done by site personnel or con-
by changing conditions. For any create sketches to help explain tracted out, but the bottom line
additional work, the same rigor- the task and the location. Then, is: everyone must be screened.
ous scope challenge is applied the step-by-step job plan can Management must verify a
and if the additional scope does begin to take shape. The plan variety of details, including
not meet the challenge, the item will include the craft disciplines background checks, security
must be properly dispositioned. required for each task along clearances, proof of permission
with an explanation. The details to work, drug testing, profes-
Phase 3: work packages of the work plan should include sional credentials, safety qual-
The next phase in the pro- any material, equipment or ifications, and more. Everyone
cess is planning and creating tool requirements for the task who is accepted to work on the
the detailed packages for all as well as any safety concerns, site will need a badge for iden-
work executed during the turn- such as exposure to harmful tification purposes. Site manage-
around. At this point, the fro- chemicals and any personal ment must organise onboarding
zen scope should be completely protective equipment required. for new personnel to under-
clear. Without this, the plan- After the planner creates the stand and follow all site rules
ner must ask questions in order detailed work package, he or and procedures. This is just one
to completely understand. A she is responsible for inform- element of mobilising a contrac-
well-written scope item should ing the craftspeople performing tor workforce.
define the symptoms observed the work as to what they may Prior to bringing the turna-

www.digitalrefining.com/article/1001454 Revamps 2017 3


round workforce on site, the movement between on-site and variety of lift capacities and
current site team must ham- off-site facilities, which may radiuses, without proper plan-
mer out all the details to sup- be via truck, trailer or railcar. ning, chaos will ensue.
port the temporary workforce On-site, there are multiple repair
increase. All questions will need areas, wash areas and decon- Conclusion
to be considered and answered. tamination areas, all of which The scenarios explained in this
For example, when a contrac- service a variety of customers article are just a taste of all the
tor comes on site, where does he and frequently have completely planning required to execute a
put his lunch box? Although the full schedules. Areas of the site successful turnaround. Without
question may be simple, a deci- that are often congested need to the efforts of professional craft
sion-maker must take it upon be taken care of. Another chal- planners and logistics profes-
himself to have an answer pre- lenge is test medium, which is sionals, turnarounds will be a
pared beforehand. Most sites are required to perform QC/QA serious challenge. Although
set up for process equipment, activities. The water required for these employees are invalua-
transferring operations person- this activity will not come about ble to the success of a turna-
nel, moving raw materials, and naturally. Expert planning is round, they often go unnoticed
finished goods. There is usually required to coordinate all of this. because they never turned
no protocol in place to support Arranging to send things a bolt or sparked a welding
large workforce fluctuations off-site and receive them back torch. However, as highlighted
as required for complex turna- on-site requires serious thought here, the work they do is nec-
round activities. The grounds and effort. One example of this essary and must be carried out
of the site must be able to house would be equipment that can- thoroughly and accurately if
the workforce. This includes not be moved off-site until it a site has any hope of stay-
providing building repair and is decontaminated – this takes ing on budget and on schedule.
maintenance (BRM) for man- coordination. In preparation for Imagine if during a turnaround
agement, administrative staff, a turnaround, site management event, a crane is in an area that
and other support staff, which must make sure to have the cor- cannot be accessed and the team
will require power, just as with rect amount of specialty equip- needs to wait for an extended
the work areas, but with differ- ment to work on different jobs, period of time. In this case, plan-
ent requirements. Turnaround and to plan and schedule their ning has not been done well or
decision-makers must consider use appropriately. One example at all. Although the prepara-
details such as eating facilities, of specialty equipment would tion process may be tedious, the
water for both cleaning and con- be coordinating bundle pull- most frustrating type of plan-
sumption, sanitary facilities, ers, which becomes even more ning is always poor planning.
comfort stations to protect from complicated if you are using Although this organisation does
heat and cold, and other hous- specialty pullers such as aerial not guarantee success, a lack of
ing concerns beforehand. bundle pullers. Organising large planning guarantees failure.
specialty equipment is key for
Phase 5: logistics a variety of reasons. Cranes, for
In addition to contractor and example, are set up and then Mike Asquini is a Project Manager with T.A.
Cook. While based in North America, he
workforce logistics, site man- left in anticipation of upcoming
has managed projects for refining leaders
agement must plan for the tech- work. However, sometimes just
in both the US and Canada. With 20 years
nical logistical challenges of a the presence of a crane creates a of consulting experience, he is currently
turnaround. One question might traffic nightmare. The site runs dedicated to asset intensive businesses
be: how do we transfer person- the risk of further complicat- in the refining and petrochemicals
nel, material, and equipment to ing already congested areas by industries. His work supports clients with
be exactly where we want them setting up equipment that will maintenance optimisation, turnaround,
when we need them? To answer not move in tight areas already. outage, shutdown optimisation and OEE
this, the site must coordinate Although cranes have a wide improvement.

4 Revamps 2017 www.digitalrefining.com/article/1001454

Você também pode gostar