PERIODO : 1/23/2017 - 1/29/2017

CONTRATISTA : COAM CONTRATISTAS S.A.C. AVANCE ANTERIOR = 37.95%


PROYECTO :CONJUNTO RESIDENCIAL ALBRECHT II Inicio: 3/1/2016 AVANCE ACTUAL = 1.38%
PROPIETARIO :COAM CONTRATISTAS S.A.C. Fin: 3/1/2018 AVANCE ACUMULADO = 39.33%

Item Descripción Und. BASE CONTRACTUAL ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO TOTAL
Metrado Precio S/. Parcial S/. Metrado Parcial % Metrado Parcial % Metrado Parcial %
01 OBRAS PROVISIONALES 208,211.49
01.01 GRUA PLUMA glb 1.00 188,042.00 188,042.00 1.00 188,042.00 100% - - 0.00% 1.00 188,042.00 100.00%
01.02 FLUIDO ELECTRICO PARA LA OBRA glb 1.00 20,169.49 20,169.49 0.70 14,118.64 70% - - 0.00% 0.70 14,118.64 70.00%
02 OBRAS PRELIMINARES 10,428.95
02.01 TRAZO, NIVELACION Y REPLANTEO m2 1,865.00 0.23 428.95 1,000.00 230.00 54% - - 0.00% 1,000.00 230.00 53.62%
02.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPO, MAQUINARIAS Y HERRAMIENTAS PARA LA OBRA glb 1.00 10,000.00 10,000.00 0.50 5,000.00 50% - - 0.00% 0.50 5,000.00 50.00%
03 MANO DE OBRA 3,572,813.56
03.01 MANO DE OBRA CIVIL glb 1.00 3,572,813.56 3,572,813.56 0.29 1,030,327.97 29% 0.01 40,015.51 1.12% 0.30 1,070,343.49 29.96%
04 MOVIMIENTO DE TIERRAS 129,479.20
04.01 EXCAVACION CON MAQUINARIA PARA CIMIENTOS DE SOTANO, ASCENSORES Y CISTERNA m3 11,492.00 1.55 17,812.60 11,492.00 17,812.60 100% - - 0.00% 11,492.00 17,812.60 100.00%
04.02 RELLENO CONTROLADO BAJO PLATEA DE CIMENTACION EN CAPAS DE 0.20 CM m3 2,490.00 22.68 56,473.20 2,440.00 55,339.20 98% - - 0.00% 2,440.00 55,339.20 97.99%
04.03 NIVELACION Y COMPACTACION DEL TERRENO NORMAL m2 1,880.00 0.93 1,748.40 1,830.00 1,701.90 97% - - 0.00% 1,830.00 1,701.90 97.34%
04.04 ELIMINACION DE MATERIAL ACARREADO C/MAQUINARIA m3 15,270.00 3.50 53,445.00 15,170.00 53,095.00 99% - - 0.00% 15,170.00 53,095.00 99.35%
05 OBRAS DE CONCRETO SIMPLE 117,475.29
05.01 CONCRETO CALZADURAS MEZCLA 1:10 + 30% P.G. m3 1,690.50 68.58 115,934.49 1,690.50 115,934.49 100% - - 0.00% 1,690.50 115,934.49 100.00%
05.02 ENCOFRADO Y DESENCOFRADO DE CALZADURAS m2 1,440.00 1.07 1,540.80 1,440.00 1,540.80 100% - - 0.00% 1,440.00 1,540.80 100.00%
06 OBRAS DE CONCRETO ARMADO 5,022,998.92
06.01 PLATEA DE CIMENTACION 382,337.23
06.01.01 CONCRETO PREMEZCLADO f'c=245 kg/cm2 TIPO MS H67 A4"-6" INC. BOMBA EN PLATEA DE CIMENTACION m3 1,053.18 255.23 268,803.13 1,053.18 268,803.13 100% - - 0.00% 1,053.18 268,803.13 100.00%
06.01.02 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN PLATEA DE CIMENTACION kg 58,522.73 1.94 113,534.10 58,522.73 113,534.10 100% - - 0.00% 58,522.73 113,534.10 100.00%
06.02 VIGA DE CIMENTACION 321,214.19
06.02.01 CONCRETO PREMEZCLADO f'c=245 kg/cm2 TIPO MS H67 A4"-6" INC. BOMBA EN VIGAS DE CIMENTACION m3 811.94 255.23 207,231.45 811.94 207,231.45 100% - - 0.00% 811.94 207,231.45 100.00%
06.02.02 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION m2 200.00 1.07 214.00 200.00 214.00 100% - - 0.00% 200.00 214.00 100.00%
06.02.03 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN VIGAS DE CIMENTACION kg 58,643.68 1.94 113,768.74 58,643.68 113,768.74 100% - - 0.00% 58,643.68 113,768.74 100.00%
06.03 PLACAS 1,459,411.92 - 0%

06.03.01 CONCRETO PREMEZCLADO f'c=280 kg/cm2 TIPO MS H67 A4"-6" NO INC. BOMBA EN PLACAS m3 875.93 250.77 219,656.97 773.40 193,945.52 88% 15.00 3,761.55 1.71% 788.40 197,707.07 90.01%
06.03.02 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A6"-8" NO INC. BOMBA EN PLACAS m3 848.48 233.35 197,992.81 478.00 111,541.30 56% 34.50 8,050.58 4.07% 512.50 119,591.88 60.40%
06.03.03 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A8"-10" NO INC. BOMBA EN PLACAS m3 547.18 262.58 143,678.52 395.00 103,719.10 72% 37.00 9,715.46 6.76% 432.00 113,434.56 78.95%
06.03.04 ENCOFRADO Y DESENCOFRADO DE PLACAS m2 18,014.15 1.19 21,436.84 10,944.84 13,024.36 61% 1,000.00 1,190.00 5.55% 11,944.84 14,214.36 66.31%
06.03.05 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN PLACAS kg 442,219.79 1.94 857,906.39 198,028.87 384,176.01 45% 3,500.00 6,790.00 0.79% 201,528.87 390,966.01 45.57%
06.03.06 JUNTA SISMICA e=25cm m2 492.52 38.05 18,740.39 339.63 12,922.77 69% 10.00 380.50 2.03% 349.63 13,303.27 70.99%
06.04 VIGAS 1,369,993.26

06.04.01 CONCRETO PREMEZCLADO f'c=245 kg/cm2 TIPO MS H67 A4"-6" NO INC. BOMBA EN VIGAS m3 872.41 239.23 208,706.64 872.41 208,706.64 100% - - 0.00% 872.41 208,706.64 100.00%
06.04.02 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A6"-8" NO INC. BOMBA EN VIGAS m3 998.54 233.35 233,009.31 873.00 203,714.55 87% 27.00 6,300.45 2.70% 900.00 210,015.00 90.13%
06.04.03 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A8"-10" NO INC. BOMBA EN VIGAS m3 582.65 262.58 152,992.24 300.00 78,774.00 51% 50.00 13,129.00 8.58% 350.00 91,903.00 60.07%
06.04.04 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 13,524.52 1.19 16,094.18 11,495.84 13,680.05 85% 405.74 482.83 3.00% 11,901.58 14,162.88 88.00%
06.04.05 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN VIGAS kg 391,335.51 1.94 759,190.89 332,635.18 645,312.26 85% 11,740.07 22,775.73 3.00% 344,375.25 668,087.98 88.00%
06.05 LOSAS ALIGERADAS 1,359,772.51
06.05.01 CONCRETO PREMEZCLADO f'c=245 kg/cm2 TIPO MS H67 A4"-6" NO INC. BOMBA EN LOSAS ALIGERADAS m3 566.84 239.23 135,605.13 566.84 135,605.13 100% - - 0.00% 566.84 135,605.13 100.00%
06.05.02 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A6"-8" NO INC. BOMBA EN LOSAS ALIGERADAS m3 611.43 233.35 142,677.19 531.00 123,908.85 87% 34.00 7,933.90 5.56% 565.00 131,842.75 92.41%
06.05.03 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A8"-10" NO INC. BOMBA EN LOSAS ALIGERADAS m3 317.70 262.58 83,421.67 160.00 42,012.80 50% 40.00 10,503.20 12.59% 200.00 52,516.00 62.95%
06.05.04 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA m2 20,282.59 0.48 9,735.64 17,000.00 8,160.00 84% 1,000.00 480.00 4.93% 18,000.00 8,640.00 88.75%
06.05.05 VIGUETAS PREFABRICADAS Y BOVEDILLAS m2 20,282.59 42.80 868,094.85 17,000.00 727,600.00 84% 1,000.00 42,800.00 4.93% 18,000.00 770,400.00 88.75%
06.05.06 MALLA PREFABRICADA COMO ACERO DE TEMPERATURA R-80 und 1,650.00 29.93 49,384.50 1,400.00 41,902.00 85% 80.00 2,394.40 4.85% 1,480.00 44,296.40 89.70%
06.05.07 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN LOSA ALIGERADA kg 36,522.44 1.94 70,853.53 31,005.00 60,149.70 85% 1,795.00 3,482.30 4.91% 32,800.00 63,632.00 89.81%
06.06 MURO DE CONTENCION 64,877.53
06.06.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A4"-6" NO INC. BOMBA EN MURO DE CONTENCION m3 171.34 235.52 40,354.00 171.34 40,354.00 100% - - 0.00% 171.34 40,354.00 100.00%
06.06.02 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCION m2 755.30 1.19 898.81 755.30 898.81 100% - - 0.00% 755.30 898.81 100.00%
06.06.03 ACERO DE REFUERZO f'y=4200 kg/cm2 GRADO 60 EN MURO DE CONTENCION kg 11,871.72 1.99 23,624.72 11,871.72 23,624.72 100% - - 0.00% 11,871.72 23,624.72 100.00%
06.07 RAMPAS 23,683.35
06.07.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A4"-6" NO INC. BOMBA EN RAMPAS m3 37.80 235.52 8,902.66 14.00 3,297.28 37% - - 0.00% 14.00 3,297.28 37.04%
06.07.02 ENCOFRADO Y DESENCOFRADO DE RAMPAS m2 6.30 1.07 6.74 1.80 1.93 29% - - 0.00% 1.80 1.93 28.58%
06.07.03 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN RAMPAS kg 7,615.44 1.94 14,773.95 2,820.00 5,470.80 37% - - 0.00% 2,820.00 5,470.80 37.03%
06.08 ESCALERAS 41,708.93
06.08.01 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A4"-6" NO INC. BOMBA EN ESCALERAS m3 33.48 235.52 7,885.21 33.48 7,885.21 100% - - 0.00% 33.48 7,885.21 100.00%
06.08.02 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A6"-8" NO INC. BOMBA EN ESCALERAS m3 39.06 233.35 9,114.65 29.00 6,767.15 74% 3.00 700.05 7.68% 32.00 7,467.20 81.93%
06.08.03 CONCRETO PREMEZCLADO f'c=210 kg/cm2 TIPO MS H67 A8"-10" NO INC. BOMBA EN ESCALERAS m3 39.80 262.58 10,450.68 22.00 5,776.76 55% 6.00 1,575.48 15.08% 28.00 7,352.24 70.35%
06.08.04 ENCOFRADO Y DESENCOFRADO DE ESCALERAS m2 634.89 1.19 755.52 462.44 550.31 73% 22.00 26.18 3.47% 484.44 576.49 76.30%
06.08.05 ACERO CORRUGADO f'y=4200 kg/cm2 GRADO 60 EN ESCALERAS kg 6,960.24 1.94 13,502.87 4,567.22 8,860.40 66% 490.00 950.60 7.04% 5,057.22 9,811.00 72.66%
01 ALBAÑILERIA 167,812.63
01.01 MUROS DE LADRILLO DE CONCRETO VIBRADO DE 9x19x39 JUNTAS DE 1.5 cm. m2 9,605.76 17.47 167,812.63 7,700.00 134,519.00 80% 300.00 5,241.00 3.12% 8,000.00 139,760.00 83.28%
02 REVOQUES Y ENLUCIDOS 833,507.87
02.01 SOLAQUEO DE MUROS INTERIORES m2 51,685.56 1.21 62,539.53 3,020.00 3,654.20 6% 100.00 121.00 0.19% 3,120.00 3,775.20 6.04%
02.02 TARRAJEO MUROS INTERIORES m2 19,876.75 3.49 69,369.86 - - 0% - - 0.00% - - 0.00%
02.03 TARRAJEO DE CIELORASO m2 1,515.00 3.84 5,817.60 - - 0% - - 0.00% - - 0.00%
02.04 TARRAJEO FONDO DE ESCALERA MORTERO 1:5 m2 424.00 3.84 1,628.16 - - 0% - - 0.00% - - 0.00%
02.05 TARRAJEO IMPERMEABILIZADO EN CISTERNA m2 182.60 7.83 1,429.76 182.60 1,429.76 100% - - 0.00% 182.60 1,429.76 100.00%
02.06 TARRAJEO MUROS EXTERIORES Y DUCTOS m2 10,514.25 3.84 40,374.72 - - 0% - - 0.00% - - 0.00%
02.07 PAPEL COLOMURAL m2 41,445.25 15.74 652,348.24 - - 0% - - 0.00% - - 0.00%
03 PISOS Y PAVIMENTOS 653,718.21
03.01 PISO CON IMPERMEABILIZANTE EN CISTERNA 50 mm m2 102.13 12.87 1,314.41 102.13 1,314.41 100% - - 0.00% 102.13 1,314.41 100.00%
03.02 PISO DE CEMENTO PULIDO EN CISTERNA DE 50 mm m2 31.00 7.54 233.74 - - 0% - - 0.00% - - 0.00%
03.03 CONTRAPISO DE 40 mm m2 14,663.50 6.67 97,805.55 3,250.00 21,677.50 22% - - 0.00% 3,250.00 21,677.50 22.16%
03.04 PISO DE CEMENTO PULIDO EN VESTIBULO PREVIO A ESCALERAS Y OTROS m2 4,082.92 7.54 30,785.22 - - 0% - - 0.00% - - 0.00%
03.05 PISO DE PORCELANATO DE 60 x 60 cm m2 2,523.15 42.84 108,091.75 324.00 13,880.16 13% - - 0.00% 324.00 13,880.16 12.84%
03.06 PISO DE CERAMICA GRIS 45 x 45 cm m2 1,628.03 38.48 62,646.59 216.00 8,311.68 13% - - 0.00% 216.00 8,311.68 13.27%
03.07 PISO DE MADERA LAMINADA DE 7 mm m2 11,781.00 29.95 352,840.95 50.00 1,497.50 0% - - 0.00% 50.00 1,497.50 0.42%
04 ZOCALOS Y CONTRAZOCALOS 326,759.83
04.01 CONTRAZOCALOS 82,718.90
04.01.01 CONTRAZOCALO DE PORCELANATO DE 60 x 60 cm h=7.50 cm. m 2,468.49 4.25 10,491.08 - - 0% - - 0.00% - - 0.00%
04.01.02 CONTRAZOCALO DE MADERA LAMINADA m 14,954.00 4.83 72,227.82 60.00 289.80 0% - - 0.00% 60.00 289.80 0.40%
04.02 ZOCALOS 244,040.93
04.02.01 ZOCALO DE CERAMICA 45 x 45 cm m2 6,342.02 38.48 244,040.93 360.00 13,852.80 6% - - 0.00% 360.00 13,852.80 5.68%
05 COBERTURAS 13,847.41
05.01 COBERTURA CON LADRILLO PASTELERO DE 24 x 24 x 3 cm m2 776.20 17.84 13,847.41 - - 0% - - 0.00% - - 0.00%
06 MESADAS Y OTROS 240,282.25
06.01 MESADA DE GRANITO und 221.00 1,087.25 240,282.25 1.00 1,087.25 0% - - 0.00% 1.00 1,087.25 0.45%
07 CARPINTERIA DE MADERA 470,937.68
07.01 PUERTA PRINCIPAL DE MADERA DE 2.00 x 2.10 metros und 1.00 769.65 769.65 - - 0% - - 0.00% - - 0.00%
07.02 PUERTA DE VIDRIO DE 1.60 x 2.10 metros incluye accesorios de colocacion und 4.00 124.30 497.20 - - 0% - - 0.00% - - 0.00%
07.03 PUERTAS DE MADERA PARA INGRESO DE SERVICIO DE 0.97 x 2.10 metros und 2.00 373.28 746.56 - - 0% - - 0.00% - - 0.00%
07.04 PUERTA CONTRAFUEGO VESTIBULO DE 1.00 x 2.10 metros und 35.00 650.00 22,750.00 - - 0% - - 0.00% - - 0.00%
07.05 PUERTA CONTRAFUEGO ESCALERA DE EVACUACION DE 1.00 x 2.10 metros und 35.00 650.00 22,750.00 - - 0% - - 0.00% - - 0.00%
07.06 PUERTA DE MADERA IDE 0.90 x 2.10 M und 221.00 603.91 133,464.11 1.00 603.91 0% - - 0.00% 1.00 603.91 0.45%
07.07 PUERTA CONTRAPLACADA DE 0.75 x 2.10 M und 454.00 263.84 119,783.36 2.00 527.68 0% - - 0.00% 2.00 527.68 0.44%
07.08 PUERTA CONTRAPLACADA DE 0.90 x 2.10 M und 645.00 263.84 170,176.80 3.00 791.52 0% - - 0.00% 3.00 791.52 0.47%
08 CARPINTERIA METALICA 150,333.23
08.01 BARANDA DE ESCALERAS TUB DE 2" DE ACERO m 185.00 80.00 14,800.00 10.00 800.00 5% - - 0.00% 10.00 800.00 5.41%
08.02 PUERTA METALICA PARA INGRESO DE BANCO DE MEDIDORES INCLUYE BISAGRAS und 1.00 1,016.95 1,016.95 - - 0% - - 0.00% - - 0.00%
08.03 PORTONES METALICOS SECCIONABLES m2 45.00 350.00 15,750.00 - - 0% - - 0.00% - - 0.00%
08.04 BARANDA DE ACERO INOXIDABLE PARA BALCONES m 500.49 237.30 118,766.28 - - 0% - - 0.00% - - 0.00%
09 VIDRIOS Y CRISTALES 124,173.64
09.01 VENTANAS 96,053.28
09.01.01 VENTANA DE TEMPLADO DE 6MM m2 1,676.03 57.31 96,053.28 25.00 1,432.75 1% - - 0.00% 25.00 1,432.75 1.49%
09.02 MAMPARAS 28,120.36
09.02.01 MAMPARAS DE VIDRIO TEMPLADO DE 8MM m2 408.37 68.86 28,120.36 3.40 234.12 1% - - 0.00% 3.40 234.12 0.83%
10 PINTURA 481,552.97
10.01 ESCARCHADO FINO DE CIELO RASO m2 20,956.65 10.50 220,044.83 3,744.00 39,312.00 18% - - 0.00% 3,744.00 39,312.00 17.87%
10.02 PINTURA LATEX EN MUROS EXTERIORES m2 10,514.25 7.96 83,693.43 - - 0% - - 0.00% - - 0.00%
10.03 PINTURA LATEX EN INTERIORES m2 30,870.61 5.76 177,814.71 130.00 748.80 0% 1,146.00 6,600.96 3.71% 1,276.00 7,349.76 4.13%
11 APARATOS SANITARIOS Y ACCESORIOS 203,475.35
11.01 INODORO KARSON VINCINY BLANCO und 445.00 204.84 91,153.80 2.00 409.68 0% - - 0.00% 2.00 409.68 0.45%
11.02 LAVATORIO BALI BLANCO KARSON CON PEDESTAL BOLANO BLANCO D'ACQUA und 446.00 62.82 28,017.72 2.00 125.64 0% - - 0.00% 2.00 125.64 0.45%
11.03 URINARIO NACIONAL MODELO CADET und 2.00 574.29 1,148.58 - - 0% - - 0.00% - - 0.00%
11.04 LAVATORIO TACANDINA 90x50 cm (COCINA) und 221.00 165.25 36,520.25 1.00 165.25 0% - - 0.00% 1.00 165.25 0.45%
11.05 LAVARROPA DE FIBRA 53X45X28 (LAVANDERIA) und 221.00 60.00 13,260.00 1.00 60.00 0% - - 0.00% 1.00 60.00 0.45%
11.06 COLOCACION DE APARATOS SANITARIOS und 1,335.00 25.00 33,375.00 6.00 150.00 0% - - 0.00% 6.00 150.00 0.45%
12 GRIFERIAS 107,929.77
12.01 GRIFERIA MEZCLADORA DE DUCHA und 442.00 86.26 38,126.92 2.00 172.52 0% - - 0.00% 2.00 172.52 0.45%
12.02 GRIFERIA SIMPLE PARA LAVATORIO und 442.00 56.37 24,915.54 2.00 112.74 0% - - 0.00% 2.00 112.74 0.45%
12.03 LLAVE TREBOL DE 1/2" COCINA AL MUEBLE und 221.00 71.60 15,823.60 1.00 71.60 0% - - 0.00% 1.00 71.60 0.45%
12.04 CAÑO DE JARDIN 1/2" ITAP und 221.00 21.51 4,753.71 1.00 21.51 0% - - 0.00% 1.00 21.51 0.45%
12.05 COLOCACION DE GRIFERIAS (AGUA FRIA/CALIENTE) und 442.00 25.00 11,050.00 2.00 50.00 0% - - 0.00% 2.00 50.00 0.45%
12.06 COLOCACION DE GRIFERIAS (AGUA FRIA) und 884.00 15.00 13,260.00 4.00 60.00 0% - - 0.00% 4.00 60.00 0.45%
13 VARIOS 1,978.06
13.01 NUMERACION DE DEPARTAMENTOS und 221.00 5.00 1,105.00 - - 0% - - 0.00% - - 0.00%
13.02 NUMERACION DE BLOQUES DE EDIFICIOS und 2.00 5.00 10.00 - - 0% - - 0.00% - - 0.00%
13.03 NUMERACION DEL PROYECTO und 1.00 5.00 5.00 - - 0% - - 0.00% - - 0.00%
13.04 MURETE DE DUCHA und 454.00 1.89 858.06 - - 0% 100.00 189.00 22.03% 100.00 189.00 22.03%
14 EQUIPAMIENTO 716,313.57
14.01 SUMINISTRO E INSTALACION DE ASCENSORES glb 1.00 716,313.57 716,313.57 - - 0% - - 0.00% - - 0.00%
23 SISTEMA DE DESAGUE 203,774.29
23.01 REDES DE DISTRIBUCION 122,641.96
23.01.01 ACCESORIOS DE INSTALACION PARA TUBERIA COLGADA DE TECHO glb 1.00 743.17 743.17 - - 0% - - 0.00% - - 0.00%
23.01.02 TUBERIA DE PVC SAL DE 8'' m 63.25 29.95 1,894.34 - - 0% - - 0.00% - - 0.00%
23.01.03 TUBERIA DE PVC SAL DE 6'' m 138.71 20.40 2,829.68 - - 0% - - 0.00% - - 0.00%
23.01.04 TUBERIA DE PVC SAL DE 4'' m 2,390.30 19.22 45,941.57 807.00 15,510.54 34% 143.00 2,748.46 5.98% 950.00 18,259.00 39.74%
23.01.05 TUBERIA DE PVC SAL DE 3'' m 1,100.00 23.31 25,641.00 783.00 18,251.73 71% 17.00 396.27 1.55% 800.00 18,648.00 72.73%
23.01.06 TUBERIA DE PVC SAL DE 2'' m 3,712.72 12.28 45,592.20 950.00 11,666.00 26% 550.00 6,754.00 14.81% 1,500.00 18,420.00 40.40%
23.02 CAJAS DE REGISTRO 318.93
23.02.01 CAJAS DE REGISTRO DE DESAGUE 24" x 24" und 3.00 106.31 318.93 - - 0% - - 0.00% - - 0.00%
23.03 SALIDAS 80,813.40
23.03.01 SALIDA DESAGUE DE 4" pto 445.00 44.21 19,673.45 288.00 12,732.48 65% 32.00 1,414.72 7.19% 320.00 14,147.20 71.91%
23.03.02 SALIDA DESAGUE DE 2" pto 1,321.00 19.75 26,089.75 864.00 17,064.00 65% 26.00 513.50 1.97% 890.00 17,577.50 67.37%
23.03.03 SALIDA DE VENTILACION DE 3'' pto 66.00 12.23 807.18 - - 0% - - 0.00% - - 0.00%
23.03.04 REGISTRO DE BRONCE ROSCADO DE PISO DE 8'' und 2.00 69.30 138.60 - - 0% - - 0.00% - - 0.00%
23.03.05 REGISTRO DE BRONCE ROSCADO DE PISO DE 6'' und 2.00 52.35 104.70 - - 0% - - 0.00% - - 0.00%
23.03.06 REGISTRO DE BRONCE ROSCADO DE PISO DE 4'' und 469.00 25.23 11,832.87 - - 0% - - 0.00% - - 0.00%
23.03.07 REGISTRO DE BRONCE ROSCADO DE PISO DE 3'' und 403.00 18.45 7,435.35 - - 0% - - 0.00% - - 0.00%
23.03.08 SUMIDERO DE PVC DE 2" und 1,150.00 12.81 14,731.50 - - 0% - - 0.00% - - 0.00%
24 SISTEMA DE AGUA FRIA 210,550.71
24.01 SALIDAS DE AGUA 69,964.18
24.01.01 SALIDA DE AGUA FRIA 1/2" pto 2,431.00 28.78 69,964.18 594.00 17,095.32 24% - - 0.00% 594.00 17,095.32 24.43%
24.02 REDES DE DISTRIBUCION 41,640.33
24.02.01 TUBERIA PVC CLASE 10 P/AGUA FRIA 1/2'' m 7,440.00 4.36 32,438.40 1,134.00 4,944.24 15% - - 0.00% 1,134.00 4,944.24 15.24%
24.02.02 TUBERIA PVC CLASE 10 P/AGUA FRIA 3/4'' m 50.60 4.65 235.29 - - 0% - - 0.00% - - 0.00%
24.02.03 TUBERIA PVC CLASE 10 P/AGUA FRIA 1 1/2'' m 44.11 9.50 419.05 - - 0% - - 0.00% - - 0.00%
24.02.04 TUBERIA PVC CLASE 10 P/AGUA FRIA 2 1/2'' m 81.40 12.45 1,013.43 - - 0% - - 0.00% - - 0.00%
24.02.05 TUBERIA PVC CLASE 10 P/AGUA FRIA 3'' m 371.69 20.27 7,534.16 - - 0% - - 0.00% - - 0.00%
24.03 RED DE IMPULSION Y BAJADA 11,626.22
24.03.01 TUBERIA PVC CLASE 10 P/AGUA FRIA 1/2'' m 210.11 4.36 916.08 - - 0% - - 0.00% - - 0.00%
24.03.02 TUBERIA PVC CLASE 10 P/AGUA FRIA 3/4'' m 59.40 4.65 276.21 - - 0% - - 0.00% - - 0.00%
24.03.03 TUBERIA PVC CLASE 10 P/AGUA FRIA 1'' m 445.50 6.75 3,007.13 - - 0% - - 0.00% - - 0.00%
24.03.04 TUBERIA PVC CLASE 10 P/AGUA FRIA 2 1/2'' m 450.00 12.45 5,602.50 - - 0% - - 0.00% - - 0.00%
24.03.05 TUBERIA PVC CLASE 10 P/AGUA FRIA 3'' m 90.00 20.27 1,824.30 - - 0% - - 0.00% - - 0.00%
24.04 ACCESORIOS DEL SISTEMA DE IMPULSION
24.05 VALVULAS 76,527.15
24.05.01 VALVULA REDUCTORA DE PRESION DE 3" und 12.00 252.55 3,030.60 - - 0% - - 0.00% - - 0.00%
24.05.02 VALVULA REDUCTORA DE PRESION DE 2 1/2" und 3.00 229.25 687.75 - - 0% - - 0.00% - - 0.00%
24.05.03 VALVULA COMPUERTA DE 1/2" und 1,319.00 55.20 72,808.80 216.00 11,923.20 16% - - 0.00% 216.00 11,923.20 16.38%
24.06 MEDIDORES DE AGUA 10,792.83
24.06.01 MEDIDOR DE AGUA 1/2'' und 221.00 48.59 10,738.39 - - 0% - - 0.00% - - 0.00%
24.06.02 MEDIDOR DE AGUA 3/4'' und 1.00 54.44 54.44 - - 0% - - 0.00% - - 0.00%
25 SISTEMA DE AGUA CALIENTE 66,736.07
25.01 SALIDAS DE AGUA CALIENTE 22,807.20
25.01.01 SALIDA DE AGUA CALIENTE C- PVC 1/2" pto 884.00 25.80 22,807.20 162.00 4,179.60 18% - - 0.00% 162.00 4,179.60 18.33%
25.02 REDES DE DISTRIBUCION 7,331.27
25.02.01 TUBERIA DE AGUA CALIENTE C-PVC 1/2" m 1,215.80 6.03 7,331.27 918.00 5,535.54 76% - - 0.00% 918.00 5,535.54 75.51%
25.03 VALVULAS 36,597.60
25.03.01 VALVULA COMPUERTA DE 1/2" und 663.00 55.20 36,597.60 162.00 8,942.40 24% - - 0.00% 162.00 8,942.40 24.43%
26 EQUIPAMIENTO DE CUARTO DE MAQUINAS 122,400.00
26.01 EQUIPAMIENTO PARA EL SISTEMA DE AGUA DOMESTICA glb 1.00 122,400.00 122,400.00 - - 0% - - 0.00% - - 0.00%
27 SISTEMA CONTRA INCENDIO 225,000.00
27.01 SUBCONTRATO DE SUMINISTRO E INSTALACION DE REDES CONTRA INCENDIO glb 1.00 225,000.00 225,000.00 - - 0% - - 0.00% - - 0.00%
28 SALIDAS DE DISTRIBUCION 440,876.26
28.01 SALIDA PARA CENTRO DE LUZ pto 3,433.00 38.58 132,445.14 525.60 20,277.65 15% 43.60 1,682.09 1.27% 569.20 21,959.74 16.58%
28.02 SALIDA DE TOMACORRIENTE MONOFASICO DOBLE CON BORNE PUESTA A TIERRA EN PARED h=0.40m/1.10m. pto 3,794.00 42.29 160,448.26 1,053.00 44,531.37 28% 83.70 3,539.67 2.21% 1,136.70 48,071.04 29.96%
28.03 SALIDA DE TOMACORRIENTE MONOFASICO SIMPLE CON BORNE PUESTA A TIERRA EN PARED h=1.80m PARA pto 303.00 85.29 25,842.87 - - 0% - - 0.00% - - 0.00%
28.04 SALIDA
SALIDADEDE
EMERGENCIA
TOMACORRIENTE MONOFASICO PARA BAÑO A PRUEBA DE AGUA CON BORNE PUESTA A TIERRA pto 436.00 42.29 18,438.44 - - 0% - - 0.00% - - 0.00%
28.05 SALIDA PARA INTERRUPTORES SIMPLES pto 1,544.00 32.00 49,408.00 - - 0% - - 0.00% - - 0.00%
28.06 SALIDA PARA INTERRUPTORES DOBLES pto 95.00 37.80 3,591.00 - - 0% - - 0.00% - - 0.00%
28.07 SALIDA PARA INTERRUPTORES TRIPLES pto 3.00 43.30 129.90 - - 0% - - 0.00% - - 0.00%
28.08 SALIDA PARA INTERRUPTORES CONMUTACION SIMPLE pto 1,273.00 37.30 47,482.90 - - 0% - - 0.00% - - 0.00%
28.09 SALIDA PARA INTERRUPTORES CONMUTACION DOBLE pto 33.00 45.70 1,508.10 - - 0% - - 0.00% - - 0.00%
28.10 SALIDA PARA BOMBA DE AGUA pto 35.00 45.19 1,581.65 - - 0% - - 0.00% - - 0.00%
29 ALIMENTADORES ELECTRICOS 234,955.32
29.01 CABLE N2XOH 2x6 mm² +1x6 mm² m 857.00 8.12 6,958.84 - - 0% - - 0.00% - - 0.00%
29.02 CABLE N2XOH 2x10 mm² +1x6 mm² m 13,613.00 11.30 153,826.90 - - 0% - - 0.00% - - 0.00%
29.03 CABLE N2XOH 2x16 mm² +1x6 mm² m 4,178.00 16.77 70,065.06 - - 0% - - 0.00% - - 0.00%
29.04 CABLE N2XOH 3-1x25 +1x25 mm² (N) + 1x16 mm² m 99.00 29.40 2,910.60 - - 0% - - 0.00% - - 0.00%
29.05 CABLE N2XOH 3-1x35 +1x25 mm² (N) + 1x16 mm² m 32.00 37.31 1,193.92 - - 0% - - 0.00% - - 0.00%
30 CAJAS DE PASE ESPECIAL 9,679.13
30.01 CAJA F°G° 100 x 100 x 55 mm und 54.00 14.95 807.30 - - 0% - - 0.00% - - 0.00%
30.02 CAJA F°G° 150 x 150 x 75 mm und 31.00 17.50 542.50 - - 0% - - 0.00% - - 0.00%
30.03 CAJA F°G° 200 x 200 x 100 mm und 127.00 21.75 2,762.25 - - 0% - - 0.00% - - 0.00%
n 30.04 CAJA F°G° 250 x 250 x 100 mm und 80.00 30.80 2,464.00 - - 0% - - 0.00% - - 0.00%
30.05 CAJA F°G° 300 x 300 x 150 mm und 66.00 36.44 2,405.04 - - 0% - - 0.00% - - 0.00%
30.06 CAJA F°G° 400 x 400 x 200 mm und 3.00 44.98 134.94 - - 0% - - 0.00% - - 0.00%
30.07 CAJA F°G° 450 x 450 x 200 mm und 6.00 49.25 295.50 - - 0% - - 0.00% - - 0.00%
30.08 CAJA F°G° 500 x 500 x 250 mm und 5.00 53.52 267.60 - - 0% - - 0.00% - - 0.00%
31 TABLERO DE DISTRIBUCION 76,540.00
31.01 TABLERO T-SG1 und 1.00 1,760.00 1,760.00 - - 0% - - 0.00% - - 0.00%
31.02 TABLERO T-SG2 und 1.00 995.00 995.00 - - 0% - - 0.00% - - 0.00%
31.03 TABLERO T-SG3 und 1.00 835.00 835.00 - - 0% - - 0.00% - - 0.00%
31.04 TABLERO T-SG1.1, T-SG2.1, T-SG3.1, und 1.00 240.00 240.00 - - 0% - - 0.00% - - 0.00%
31.05 TABLERO T-SG1.2 und 1.00 148.00 148.00 - - 0% - - 0.00% - - 0.00%
31.06 TABLERO T-SG1.3 und 1.00 121.00 121.00 - - 0% - - 0.00% - - 0.00%
31.07 TABLERO T-SG2.2 und 1.00 284.00 284.00 - - 0% - - 0.00% - - 0.00%
31.08 TABLERO T-SG2.3 und 1.00 220.00 220.00 - - 0% - - 0.00% - - 0.00%
31.09 TABLERO DE DISTRIBUCION T-101 a T-104 und 202.00 307.00 62,014.00 2.00 614.00 1% - - 0.00% 2.00 614.00 0.99%
31.10 TABLERO DE DISTRIBUCION T-1601 a T-1605 und 5.00 307.00 1,535.00 - - 0% - - 0.00% - - 0.00%
31.11 TABLERO DE DISTRIBUCION T-1606 a T-1609 und 5.00 307.00 1,535.00 - - 0% - - 0.00% - - 0.00%
31.12 SUB TABLERO DE DISTRIBUCION ST-1601 a ST-1604 und 4.00 307.00 1,228.00 - - 0% - - 0.00% - - 0.00%
31.13 SUB TABLERO DE DISTRIBUCION ST-1605 und 1.00 280.00 280.00 - - 0% - - 0.00% - - 0.00%
31.14 TABLERO DE DISTRIBUCION T-1701 a T-1704 und 4.00 307.00 1,228.00 - - 0% - - 0.00% - - 0.00%
31.15 TABLERO DE DISTRIBUCION T-1801 a T-1804 und 4.00 307.00 1,228.00 - - 0% - - 0.00% - - 0.00%
31.16 SUB TABLERO T-B und 1.00 2,889.00 2,889.00 - - 0% - - 0.00% - - 0.00%
32 COMUNICADORES 74,453.46
32.01 SALIDA PARA TELEFONO pto 442.00 26.64 11,774.88 101.00 2,690.64 23% - - 0.00% 101.00 2,690.64 22.85%
32.02 SALIDA PARA TV-CABLE pto 884.00 26.64 23,549.76 202.00 5,381.28 23% - - 0.00% 202.00 5,381.28 22.85%
32.03 SALIDA PARA INTERCOMUNICADOR und 221.00 26.22 5,794.62 50.50 1,324.11 23% - - 0.00% 50.50 1,324.11 22.85%
32.04 SISTEMA DE INTERCOMUNICADORES glb 1.00 33,334.20 33,334.20 - - 0% - - 0.00% - - 0.00%
33 MONTANTES Y ACOMETIDA (TUBERIA) 133,871.41
33.01 TUBERIA PVC-SEL ELECTRICA DE 50 mm m 130.00 4.24 551.20 - - 0% - - 0.00% - - 0.00%
33.02 TUBERIA PVC-SEL ELECTRICA DE 25 mm m 34,896.27 2.69 93,870.97 - - 0% - - 0.00% - - 0.00%
33.03 TUBERIA PVC-SEL ELECTRICA DE 20 mm m 16,858.65 2.34 39,449.24 - - 0% - - 0.00% - - 0.00%
34 SISTEMA DE POZO DE TIERRA 7,849.00
34.01 POZO DE TIERRA und 9.00 686.00 6,174.00 - - 0% - - 0.00% - - 0.00%
34.02 CONDUCTOR DESNUDO 25 mm2 m 35.00 25.00 875.00 - - 0% - - 0.00% - - 0.00%
34.03 CONDUCTOR DESNUDO 10 mm2 m 80.00 10.00 800.00 - - 0% - - 0.00% - - 0.00%
35 BANCO DE MEDIDORES 3,150.00
35.01 BANCO DE MEDIDORES glb 1.00 3,150.00 3,150.00 - - 0% - - 0.00% - - 0.00%
36 SISTEMA CONTRA INCENDIO 1,092.00
36.01 DETECTORES DE HUMO CON ALAMRMA A BATERIA und 56.00 19.50 1,092.00 - - 0% - - 0.00% - - 0.00%
37 SISTEMA MECANICO DE IMPULSION Y EXTRACCION DE AIRE 46,013.64
37.01 EXTRACTOR DE AIRE DE 4" und 479.00 88.58 42,429.82 - - 0% - - 0.00% - - 0.00%
37.02 INYECTOR DE AIRE DE 6" und 37.00 96.86 3,583.82 - - 0% - - 0.00% - - 0.00%
COSTO DIRECTO 15,410,971.17 5,849,064.30 38% 212,638.38 1.38% 6,061,702.68 39.33%