Você está na página 1de 21

Compax installation

General information about


assembling and erection of a
Compax Cooler

Please note that some pictures in this presentation can vary in cooler size and form from
the ordered cooler in question. This presentation is only a supplement to the instruction
and assembly drawings.

For guidance only


Kiln outlet section
Kiln outlet section

Check kiln outlet sectors by


installing min. 3 pc. side by
side.
There shall be a small gab
between each sector

Cast sector

Control the sectors fit to the kiln


flange and don’t interfere among
them self

Kiln flange

For guidance only


Kiln outlet section with compax flange
Compax flange Before welding the compax flange
together; align the flange onto the
Kiln outlet. Look for match marking.
Check that the flange is faced correctly.

Look for match marking on the flange.


The flange normally come in 2-4 parts.
For guidance only
Compax flange aligned on kiln outlet

Check Flange
marking

For guidance only


Flange is horizontal positioned and aligned on a strong steel structure

Complete the flange welding


For guidance only
Intermediate shell

Align the intermediate


shell parts on the flange
according to the match
marking.
When the shell is
completely round on top,
middle and bottom
fully weld the shell from
both sides.

For guidance only


Innershell alignment

Align the innershell parts according to


the intermediate shell on the flange.
Check that spokeplate can be installed

Install and weld the guideplates for the


Stopblocks, 1-2 mm gab between plate
and stopblock.

Now remove the intermediate shell


so the innershell can be fully
welded.

Stopblock
For guidance only
Align the innershell inside the Intermediate shell

Align the innershell on the flange Check that the inner- and intermediate shell
according to the match marking. rails for the spokeplates are directly opposite.

Check the innershells Preinstall the stopblocks


roundness on top, and erect the side plates
middle and bottom. by tack welding.
If needed then install a Approx 1-2mm gab
spider / cross bracing between the side plates
and the stopblock.

Remove the intermediate shell and weld the shell from both sides.
Now remove the intermediate shell from the flange.
For guidance only
Outer shell
Install outer shell on the On the flange; it is
flange according to the important that the shell
match marking and bolt hole position is the
check that the spoke same as during the
plate rails are aligned to preassembly in the
the intermediate shell. workshop. As the two
flanges are normally
drilled together.

Install all bolts (nuts on


kiln flange side)

For guidance only


Outer shell

For guidance only


When the outer shell is finished welded
the intermediate shell is lifted back and
installed on the flange with the
Stopblocks.

Spoke plates between the outer and


intermediate shell are inserted

After the
intermediate shell
is installed can the
inner shell also be
installed.

For guidance only


Cassette installation

Before inserting the cassette the


cassette must be insulated with
hydraulic castable, see compax
refractory lining drawing.
For installation purpose it is important
that the castable is not above the
cassette frame.
The cassette are installed
according to the match marking

One cassette is delivered


without the overlapping Holes for cassette locks.
plate, this cassette is the Only tackweld the locks to
last to be installed the cassette

Overlapping plate
For guidance only
Intermediate stopblock is bolted to max
toque
Check that the stopblock has 100%
contact (no gap) with the cooler flange.

Inner shell stopblock is mounted as


well but after the bolt tensioning; the
block is tack welded to the flange.
Now remove these bolts again, as the
bolts must go through the kiln flange.

For guidance only


Rotary part

Close all holes, in all shells, used for the


insertion of the spoke plates.

Close the hole; by welding a plate on the back


side of the flange. (The front side must be plane
for the seal mounting)

Close the holes by welding a front plate on


Intermediate shell, front side

For guidance only


Shovel and rotary seal

Depending on the available lifting space.


Decide if the shovels and sealing should
be mounted on the ground or after the
cooler is mounted on the kiln

After bolting the shovels to the


shells; Weld the shovel to the
shell in front of the shovel ~8 cm

Rotary seal base with adjustable plate

For guidance only


Tunnel

Assemble the tunnel.


Make the tunnel lining according to refractory lining
drawing.
Install the 100mm insulation around the tunnel and
install and weld the covering stainless surrounding
plate.

For guidance only


Tunnel inside the rotary cooler

Align and secure the tunnel inside the


cassette.

Wood placed between tunnel


and cassette

For guidance only


Lifting of the rotary part and mounting on kiln flange

Check if the coolerflange is match marked with the kilnflange, if so; the kiln
position must be turned correct so the holes corresponds when the cooler is
mounted

For guidance only


Lifting of the rotary part and mounting on kiln flange

In some cases it can be an advantage to


install the bottom part of the stationary
shell, before mounting the rotary part.

Stationary shell; bottom part

For guidance only


For guidance only
Rotary part

• Fully weld the cassette locks and the last cassette over lapping plate.
• Install manholes (plate) in outershell
• Tension all bolts with torque, according to the assembly drawing. Due not tack weld
the nuts as all bolts must be torque again after the kiln have been running hot in
approx. 5 dayes.
• Install all remaining parts.

For guidance only

Você também pode gostar