1 A - 1 100 2 2 1
2 B A 3 250 2 2 4
3 C A 5 450 1 4 5
4 D A 2 350 4 3 2
5 E BC 4 200 2 3 4
6 F BC 6 600 4 3 2
7 G BC 2 100 3 4 1
8 H E 3 300 2 3 3
9 I DG 4 400 1 2 1
Total 2750
% Diario
% Comulativo
Diagrama de Barras
No. Actividade actividade antecessoras Durasaun Custo Trab Mat Eq
1 A - 1 100 2 2 1
2 B A 3 250 3 2 4
3 C A 5 450 1 4 5
4 D A 2 350 4 3 2
5 E BC 4 200 2 3 4
6 F BC 6 600 4 3 2
7 G BC 2 100 3 4 1
8 H E 3 300 2 3 3
9 I DG 4 400 1 2 1
Total 2750
TRABALHADOR
MATERIAL
EQUIPAMENTOS
Diagrama de Barras
Pesso
1 2 3 4 5 6 7 8 9 10 11 12 13
3.6 3.6
9.1 3.03 3.0303 3.0303
16.4 3.273 3.2727 3.2727 3.273 3.273
12.7 6.364 6.3636
7.3 1.8182 1.818 1.818 1.818
21.8 3.6364 3.636 3.636 3.636 3.636 3.636
3.6 1.8182 1.818
10.9 3.636 3.636 3.636
14.5 3.636 3.636 3.636 3.636
100.0
3.6 12.7 12.7 6.3 3.3 3.3 7.3 7.3 9.1 9.1 10.9 10.9 3.6
3.6 16.3 29.0 35.3 38.5 41.8 49.1 56.4 65.5 74.5 85.5 96.4 100.0
Diagrama de Barras
Pesso
1 2 3 4 5 6 7 8 9 10 11 12 13
3.6 2/2/1
9.1 2/2/4 2/2/4 2/2/4
16.4 1/4/5 1/4/5 1/4/5 1/4/5 1/4/5
12.7 4/3/2 4/3/2
7.3 2/3/4 2/3/4 2/3/4 2/3/4
21.8 4/3/2 4/3/2 4/3/2 4/3/2 4/3/2 4/3/2
3.6 3/4/1 3/4/1
10.9 2/3/3 2/3/3 2/3/3
14.5 1/2/1 1/2/1 1/2/1 1/2/1
100.0
2.0 8.0 8.0 4.0 1.0 1.0 9.0 9.0 6.0 6.0 7.0 7.0 2.0
2 9 9 6 4 4 10 10 6 6 8 8 3
1.0 11.0 11.0 9.0 5.0 5.0 7.0 7.0 6.0 6.0 6.0 6.0 3.0
% COMULATIVO DE RECURSOS
12.0
10.0
8.0
6.0
4.0
2.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13
TRABALHADOR MATERIAL EQUIPAMENTOS
6.0
4.0
2.0
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13
TRABALHADOR MATERIAL EQUIPAMENTOS