Escolar Documentos
Profissional Documentos
Cultura Documentos
INTRODUCTION
Manufacturing Plants are designed that would require a high amount of Investment to build
and to operate. The investment of the manufacturing plant should be estimated to be able to project
the profitability, breaking point, and return of investment. This chapter includes the economic
viability of manufacturing plant to be able to optimize the manufacturing design and the design
process. A preliminary assessment of the manufacturing plant was made in the chapter two of this
paper, as well as the market projection of the product and raw materials required. Class 3 and 4
estimates were conducted for the preliminary assessment. Class 3 and 4 estimates have an
inaccuracy range of 30% - 40% and the project definition is limited from 2% - 4%. The class
estimates were determined from the book Chemical Engineering Design by Towler. It was
determined that the return of investment for the manufacturing plant was 4 years.
This chapter will be providing a more accurate estimation of the investment since class 1
and 2 estimates will be provided for the equipment and prices of the raw materials and the products.
The fixed capital investment is the sum of cost of designing and constructing the plant, which
includes the outside battery limits (OSBL) and inside battery limits(ISBL) investments,
construction and engineering cost, and contingency charges, variable and fixed cost for the
production. The revenue of the manufacturing plant will be based on the production of raw
materials and as well as the savings from the recycling of waste and cooling water in order to
minimize the cost in the design process. After this chapter the economic viability of the Methyl
Isobutyl Ketone manufacturing plant will be determined. The Table 7.1 will include the
summarization of the ISBL, OSBL, engineering cost, and contingency charges. Table 7.2 will
include the Project cost (Variable and Fixed Cost of production) and the revenue.
Table 7
Fixed Capital Cost
FIXED CAPITAL INVESTMENT
Administrative Charges
Cooling Towers
Reboilers
Control Rooms
Price inflations
Table 7
Cost and Revenues
COSTS AND REVENUES
Labor
Maintenance
Property Taxes
Rent of Land
Wastewater Treatment
The plant will be operating for 8000 hours according to Towler & Sinnott (2013). This
would imply that the manufacturing plant will be operating for 334 days every year. Employees
will be given 15 days for sick leave and 15 days for vacation leave since it is mandated by the law.
Special non-working holidays such as Chinese New Year, Christmas Eve, and New Year be allotted
for plant maintenance. For other holidays without plant maintenance will still operate, given that
Price Quotations of equipment, raw materials, and products will be coming from
the different vendors. This could mean that the quotations would fall into the class 1
estimate. The vendors were e-mailed directly providing the specification sheets and system
drawing. The price quotations will be used as the basis since it will be purchased the same
year while the purchasing cost will be adjusted in order to account for the indirect costs
The method used for the cost calculation is the factorial method. Installation factors
also contributes to the total capital costs and is calculated by multiplying the total
purchased equipment costs by an appropriate factor. Since price quotations were provided
by the vendors, this method will fall into the class 3 estimate of the capital cost of the
manufacturing plant.
Ce = cost of equipment
Another cost that must be accounted is the freight costs, incurred from the transport
of shipments from port-to-port. This will be obtained using a freight rate calculator
available online at worldfreightrates.com. Lastly, duties and taxes imposed by the Bureau
of Customs, is the sum of the value added tax, import processing fee, and excise tax. The
rate of duty for steel to be used for industrial machinery and equipment, as per classification
of goods under AHTN, Section 104 of the Tariff and Customs Code of the Philippines
(TCCP), is 1% of the dutifiable or CIF value. The value added tax is calculated as 12% of
the Total Landed Cost or the sum of CIF value and Customs duty.
7.1.1Total Cost for Heat exchangers
The purchasing Cost of the Heat Exchangers were obtained via Aspen HYSIS V8.8
Exchanger Design ratings. The material used for the construction of the heat exchangers
are carbon steel and stainless steel. Table 7.4 shows the summation cost, and the adjusted
cost.
Table 7
Heat Exchangers purchasing cost
Equipment Area (m2) Price (PhP)
E-100` 18.7
207,376.00
E-102 480.1
5,532,644.00
E-103 355.5
3,564,028.00
E-200 213.7
2,686,320.00
E-201 195.3
2,531,048.00
E-202 169.6
2,334,072.00
E-203 427.6
4,785,092.00
E-300 4.5
100,360.00
E-301 6.4
115,284.00
E-302 3.4
91,156.00
Final Purchasing Cost
23,044,751.60
Cost with Installation Factor
73,743,205.12
Freight Cost
66,872.00
Total Cost
73,810,077.12
7.1.2 Total Cost for the Reboilers
The purchasing Cost of the reboilers were obtained via Aspen HYSIS V8.8
Exchanger Design ratings. The material used for the construction of the reboilers is carbon
steel and stainless steel. Table 7.5 shows the summation cost, and the adjusted cost.
Table 7
Reboilers purchasing cost
Equipment Area (m2) Price (PhP)
T-300 101.5
1,760,512.00
T-301 40.4
979,784.00
T-302 65.8
1,317,316.00
T-303 2.9
378,976.00
Final Purchasing Cost
4,658,417.40
Cost with Installation Factor
14,906,935.68
Freight Cost
66,872.00
Total Cost
14,973,807.68
7.1.3 Total Cost for the Condensers
The purchasing Cost of the Condensers were obtained via Aspen HYSIS V8.8
Exchanger Design ratings. The material used for the construction of the Condensers is
carbon steel and stainless steel. Table 7.5 shows the summation cost, and the adjusted cost.
Table 7
Condensers purchasing cost
Equipment Area (m2) Price (PhP)
T-300 7.5
559,780.00
T-301 3.1
401,960.00
T-302 3.6
495,612.00
T-303 2.2
67,600.00
Final Purchasing Cost
1,601,199.60
Cost with Installation Factor
5,123,838.72
Freight Cost
66,872.00
Total Cost
5,190,710.72
7.1.4 Total Cost for the Distillation Column
The purchasing Cost of the distillation column were obtained from the vendor,
Wuxi Nanquan Pharmaceutical Chemical Container Factory. The material used for the
construction of the distillation column is carbon steel and stainless steel. Table 6.5 shows
Table 7
Distillation column purchasing cost
Equipment Sieve Trays Price ($)
DC-1 36
11,840,400.00
DC-2 29
959,920.00
DC-3 27
904,280.00
DC-4 10
317,200.00
Final Purchasing Cost
14,021,800.00
Cost with Installation Factor
44,869,760.00
Freight Cost
66,872.00
Total Cost
44,936,632.00
7.1.5 Total Cost for the Compressors
The purchasing Cost of the compressors were obtained via Aspen HYSIS V8.8
Exchanger Design ratings. The material used for the construction of the compressors is
carbon steel and stainless steel. Table 6.5 shows the summation cost, and the adjusted cost.
Table 7
compressors purchasing cost
Equipment Power (kW) Price ($)
K-100 37739.02
81,865,992.00
K-U100 682.82
7,253,480.00
Final Purchasing Cost 1,713,836
The purchasing Cost of the pumps were obtained from Shanghai Kaiyuan Pump
Industry. The material used for the construction of the pumps is carbon steel and stainless
steel. Table 6.5 shows the summation cost, and the adjusted cost.
Table 7
Pumps purchasing cost
Equipment Power (hp) Price ($)
P-100 1
33,800.00
P-300 5
160,160.00
P-U100 3
121,680.00
P-U101 3
121,680.00
P-U200 3
121,680.00
P-U201 3
121,680.00
P-U300 7
183,560.00
PU-301 7
183,560.00
P-U302 7
183,560.00
P-U303 10
221,260.00
P-U400 7
183,560.00
P-U401 7
183,560.00
P-U402 7
183,560.00
P-U403 10
221,260.00
Final Purchasing Cost
2,224,560.00
Cost with Installation Factor
7,118,592.00
Freight Cost
66,872.00
Total Cost
7,185,464.00
The purchasing Cost of the storage tanks were obtained Taishan Group Taian Boao
International Trading Co., Ltd. The material used for the construction of the storage tanks
is carbon steel. Table 6.5 shows the summation cost, and the adjusted cost.
Table 7
Storage Tanks purchasing cost
Equipment Quantity Volume (m3) Price per unit Price (PhP)
(PhP/ unit)
Storage Tank)
2,886,000.00 86,580,000.00
DST (Diisobutyl 6 165.44
Ketone Storage
Tank)
3,046,680.00 18,280,080.00
MST1 (Methyl 6 189.28
Isobutyl Ketone
Storage Tank 1)
3,182,400.00 19,094,400.00
MST1 (Methyl 14 168.97
Isobutyl Ketone
Storage Tank 2)
3,614,000.00 50,596,000.00
Final Purchasing Cost
174,550,480.00
Cost with Installation Factor
558,561,536.00
Freight Cost
66,872.00
Total Cost
558,628,408.00
The purchasing Cost of the reactor were obtained from a quotation of a company
named Qingdao ShinDah Machinery Co., Ltd. The material of of construction is staineless
steel for the reactor. The purchasing price is listed in the table below:
Table 7
Reactor purchasing cost
Equipment Volume (m3) Price ($)
CRV-101
3,785,600.00
Final Purchasing Cost
3,785,600.00
Cost with Installation Factor
12,113,920.00
Freight Cost
66,872.00
Total Cost 12,180,792.00
The purchasing Cost of the reactor were obtained from a quotation of a company
stainless steel for the reactor. The purchasing price is listed in the table below:
Table 7
Separator purchasing cost
Equipment Volume (m3) Price ($)
V-300
1,690,000.00
Final Purchasing Cost
1,690,000.00
Cost with Installation Factor
5,408,000.00
Freight Cost
66,872.00
Total Cost
5,474,872.00
The purchasing Cost of the reactor were obtained from a quotation of a company
named PuyangZhongshi Group Co., Ltd.. The material of of construction is carbon steel
for the reactor. The purchasing price is listed in the table below:
Table 7
Decanter purchasing cost
Equipment Volume (m3) Price ($)
V-301
468,000.00
Final Purchasing Cost
468,000.00
Cost with Installation Factor
1,497,600.00
Freight Cost
66,872.00
Total Cost
1,564,472.00
7. 1.11 Total Cost for the Pipe
The purchasing Cost of the pipes were obtained from Torrent Engineering &
Equipment Inc. The following table contains the cost per length of specific pipe size.
Length (m) Material Material Stress (psig)
Stream Schedule Number Nominal pipe size fluid type Diameter(in) Diameter (m) Cost per length Cost ($)
288.81 CS 12885.3 AcetonefromSTR 40 2L 2.2 0.1 4.1 1184.121
6.22 CS 12885.3 S1-A 40 2L 2.2 0.1 4.1 25.502
12.84 CS 12885.3 S2-A 40 4G 4.3 0.1 8.4 107.856
17.28 CS 12885.3 S3-A 40 4G 4.3 0.1 8.4 145.152
65.15 AA 8585.3 S2-H 40 16 G 15.5 0.4 44.2 2879.63
37.39 AA 8585.3 S3 40 18 G 17.5 0.4 60.1 2247.139
10.9 SS 19985.3 S4 40 20 G 19.5 0.5 62.1 676.89
15.75 SS 19985.3 S5 40 20 G 19.5 0.5 62.1 978.075
25.43 SS 19985.3 S6 40 18 G 16.9 0.4 60.1 1528.343
26.13 SS 19985.3 S7 40 18 G 16.9 0.4 60.1 1570.413
15.47 SS 19985.3 S8 40 18 G 16.9 0.4 60.1 929.747
6.16 SS 19985.3 S9 40 18 G 16.9 0.4 60.1 370.216
75.19 SS 19985.3 RS1 40 16 G 15.5 0.4 44.2 3323.398
55.61 CS 12885.3 RS2 40 2G 2.2 0.1 4.1 228.001
Table 7
ISBL Capital Cost
Heat exchangers 73,810,077.12
Reboilers 287,957.84
Condensers 5,190,710.72
Compressors 285,249,182.40
Pumps 7,185,464.00
Reactor 12,180,792.00
Separator 5,474,872.00
Decanter 1,564,472.00
Pipes 12,770,924.40
The purchasing Cost of the cooling tower were obtained via Aspen HYSIS V8.8
Exchanger Design ratings. The material used for the construction of the cooling tower is
carbon steel. Table 7.9 shows the summation cost, and the adjusted cost.
Table 7
Cooling Tower purchasing cost
Equipment Capacity (m3/hr) Price (PhP)
The purchasing Cost of the fired heater were obtained via Aspen HYSIS V8.8
Exchanger Design ratings. The material used for the construction of the fired heater is
carbon steel. Table 7.9 shows the summation cost, and the adjusted cost.
Table 7
Fired heater purchasing cost
Equipment Capacity (m3/hr) Price (PhP)
estimation provided by Dr. Nolan Tolosa, where the amount of flow is used as a basis
for the cost estimation. He specified that for a daily cubic meter of flow, the cost is $
477.92.
Table 7
The materials for the construction of buildings, parking lots, and roads should also
be accounted. The different data gathered came from the Philippine Statistics Authority
and for the costing of the parking lots will be based on the E.P. Malto Asphalt Construction.
Table 7
Cost of Buildings per sq. m.
Type of Buildings Cost Per Square Meter (PhP/m2)
Table 7
Cost of Asphalt
Materials used for Parking Lots Cost (PhP) Per Square Meter
Asphalt 182
Table 7
Total Cost of Buildings
Facility Area (m2) Cost (PhP)
Administration 2500
38,156,300.00
Security 1 (Main) 240.3829
993,242.92
Security 2 252.0495
1,041,448.37
Wastewater Treatment Plant 600
5,328,648.00
Fire Station 562.4623
2,324,049.23
Delivery House 1 939.7878
718,110.65
Delivery House 2 939.7878
718,110.65
Warehouse 1404.211
5,802,087.52
Canteen 525.78
4,082,219.01
Clinic 75
582,309.00
Boiler House 375
2,911,545.00
Parking Lot 2400
436,800.00
Total 10814.46
63,094,870.35
The Safety of the Manufacturing plant is one of the top priority. A wall shall be
constructed in order to avoid outsiders to trespass in the manufacturing plant and for the
The transportation of the products will be carried by 12 ISUZU NHR Cab Chassis 71.
Table 7
Transportation Trucks
71
14,270,880.00
ISO tank (20 MT) 468,000.00 12
5,616,000.00
Total Cost
19,886,880.00
Table 7
OSBL capital cost summary
Facility/Equipment Cost
Facilities 63,094,870.35
Engineering costs
Engineering costs, also called home office charges or contractor charges, include the fees
of distinct design and different engineering services mandatory for a project. According to Towler
& Sinnott (2013), as a general rule of thumb, the engineering costs is 30% of ISBL plus OSBL
cost for smaller projects and 10% of ISBL plus OSBL cost for larger projects. This will be used
for the estimation of the total engineering costs for the plant.
As defined by Towler & Sinnott (2013), contingency charges are supplementary fee
charged by the Engineering, Procurement and Construction company to allow variation from the
cost estimate. It is also identified that a minimum contingency charge of 10% of ISBL plus OSBL
cost should be used on all projects. This will be used as an estimate for the contingency costs
Working Capital
Together with the fixed capital investments, the company needs to invest some capital for
daily plant operations. According to Towler & Sinnott (2013), a typical figure for petrochemical
The plant’s production will be consisting of the variable costs of the production and the
fixed costs of production. The variable costs of production include the raw materials consumed
in the process, utilities to support process, consumables and effluent disposal. On the other hand,
the fixed costs of production, includes the operating labor, supervision, wages, maintenance and
others. In addition, the revenues derived from the plant’s major products will be accounted in
this section.
The Raw materials needed in the Manufacturing plant are the Acetone and
Hydrogen. The Acetone will be coming from the A.P.C Chemicals and the hydrogen will
be provided by Linde on-site. The price of the Acetone is provided by the Table 7.15. since
the hydrogen will be provided by Linde on-site, the price will also include the equipment.
The inflation rate of Acetone and hydrogen according to the Philippine Statistics Authority
is 3.0%
Table 7
Acetone Price
Raw Material Flowrate Price (PhP) Cost per year (PhP)
Table 7
Acetone Cost 20 years
Year Turndown Capacity MTPY Price per MT Cost (PhP)
2021 50
24,000.00 32,136.00 771,264,000.00
2022 100
48,000.00 33,100.08 1,588,803,840.00
2023 100
48,000.00 34,093.08 1,636,467,955.20
2024 100
48,000.00 35,115.87 1,685,561,993.86
2025 100
48,000.00 36,169.35 1,736,128,853.67
2026 100
48,000.00 37,254.43 1,788,212,719.28
2027 100
48,000.00 38,372.06 1,841,859,100.86
2028 100
48,000.00 39,523.23 1,897,114,873.89
2029 100
48,000.00 40,708.92 1,954,028,320.10
2030 100
48,000.00 41,930.19 2,012,649,169.71
2031 100
48,000.00 43,188.10 2,073,028,644.80
2032 100
48,000.00 44,483.74 2,135,219,504.14
2033 100
48,000.00 45,818.25 2,199,276,089.27
2034 100
48,000.00 47,192.80 2,265,254,371.94
2035 100
48,000.00 48,608.58 2,333,212,003.10
2036 100
48,000.00 50,066.84 2,403,208,363.19
2037 100
48,000.00 51,568.85 2,475,304,614.09
2038 100
48,000.00 53,115.91 2,549,563,752.51
2039 100
48,000.00 54,709.39 2,626,050,665.09
2040 100
48,000.00 56,350.67 2,704,832,185.04
As for the On-site Hydrogen which will be supplied by ALLY HI-TECH Co. An
initial investment for the hydrogen plant and a monthly fee will be needed.
Table 7
Hydrogen Cost 20 years
On-Site Hydrogen Cost
2021 219,648.00
2022 219,648.00
2023 219,648.00
2024 219,648.00
2025 219,648.00
2026 219,648.00
2027 219,648.00
2028 219,648.00
2029 219,648.00
2030 219,648.00
2031 219,648.00
2032 219,648.00
2033 219,648.00
2034 219,648.00
2035 219,648.00
2036 219,648.00
2037 219,648.00
2038 219,648.00
2039 219,648.00
2040 219,648.00
Total Cost: 4,392,960.00
Total Cost with Investment: 75,031,320.00
7.7 Utilities
Utilities such as Reboilers and Cooling Towers will be used in the manufacturing plant in
order to minimize the cost and optimize the design process. The electricity and water used will also
be accounted as a utility.
The reboiler would require a fuel in order to produce steam in the design process. Propane
January 2017, the rate is 5.5561 PhP/kWh. Table shows the different power rate charge of
Table 7
PENELCO Electric Rates in Bataan
Rate Charges Residential Commercial Industrial
PhP/kWh 8.2746 6.9099 5.5561
Table 7
Power Requirement of Process
Equipment Power (kW)
Pump 59.68
Cooling Tower 83.0
Compressors 38,421.84
Total Power (kW)
38564.52
Total kWh/day
925548.48
Total kWh/year
309,133,192.3
Electric consumption
For boiler, warehouse and delivery houses, the standard electric consumption is
For wastewater treatment plant and parking lot, the electricity consumption is
based from number of LED bulbs installed in the respected area. 25 bulbs for
Wastewater treatment plant. These will cover the entire coverage area for
(Source: consumerenergysolutions.com)
For the buildings and offices such as Administration building, fire station,
category. In each building category, there will be varying usage rates, lightings,
https://www.riigiteataja.ee/en/eli/520102014002/consolide)
The electric consumption per area per year (kWh/m2 per year) will be then
multiplied to the respected area for the determination of kWh per year.
Table 7
Electricity consumption in buildings
Building Length Width Area Electricity Electricity
(kWh/m2/yr)
Security 1
29.82 7168.22
(Main) 20.03191 12 240.3829
Wastewater
Treatment - 2805.60
Plant 20 30 600
Delivery House
6.1 5732.71
1 35.4806 26.48737 939.7878
Delivery House
6.1 5732.71
2 35.4806 26.48737 939.7878
Table 7
Total Cost of Electricity
Year Turndown Buildings (₱) Process (₱) Electricity Cost
inflation rate
7.7.2 Fuel
Propane will be used as the fuel for the fired heater. As of December 2017, the
propane price is at PHP 24.975 per kilograms. Data is gathered from (indexmundi.com).
Table 7
Propane consumption per year
Raw Flow rate (kg/hr) kg/Year MT/Year PHP/kg PHP/yr
Material
C3H8 519.3127 4,162,810.603 4162.81 24.975 103,966,194.81
The table below shows the cost of propane consumption per year.
Table 7
Cost of Propane per year
Year Turndown Quantity Price (₱/kg) Fuel Cost(₱/year) with
7.7.3 Water
Water is being supplied by the Hermosa Water District which is used for water
Table 7
Makeup Water Requirement for in Cooling Process
Volume Flow (m3/hr) 92.27
Table 7
Make up Water Requirement in the Steam Generation Process
Volume Flow (m3/hr) 989.39
𝐿 1 𝑑𝑎𝑦 1 𝑚3
75.7082 ( )( )
𝑑𝑎𝑦 − 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒 24 ℎ𝑜𝑢𝑟𝑠 1000 𝐿
L
𝑊𝑎𝑡𝑒𝑟 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡 𝑓𝑜𝑟 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒𝑠 = 3.1545
ℎ𝑟 − 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒𝑠
For 8 shift employees per day,
𝑊𝑎𝑡𝑒𝑟 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟
L 8ℎ𝑟𝑠 1 𝑚3
= 3.1545 𝑥 𝑥 203 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒𝑠 𝑥 334 𝑑𝑎𝑦𝑠 𝑥
ℎ𝑟 − 𝑒𝑚𝑝𝑙𝑜𝑦𝑒𝑒𝑠 1 𝑑𝑎𝑦 1000 𝐿
= 1711.05 𝑚3 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟
Table 7
Consumed Water for domestic and process uses per Year
Year Turndown Cubic meter used in Cubic meter used for
support employees’ daily functions PLDT is operating in towns of Pilar, Limay, Orani,
Hermosa, Dinalupihan, Abucay and Balanga City of Bataan. The cost for Monthly rental
Table 7
Monthly Rental Rates of Telecommunication
Particulars Cost (₱)
PLDT Fibrbiz 100 25,000
PLDT Plan600 600
The table below shows the total cost of telecommunication (landline and
data/internet connection) consumed by the plant in monthly and annual basis. The burst
speed is up tp 200 Mbps. Monthly fee is Php 6,000. Landline is PHP 600 per month.
Table 7
Total Landline& Data/Internet Cost per year
Year Turndown Capacity Bundle Cost (₱) Installation Annual Cost (₱)
Cost (₱)
The table below shows the summary of the total utilities consumed in a yearly basis.
Table 7
Total cost of utilities per year
Year Turndown Capacity Total (₱)
2021 50%
984,954,618.80
2022 100%
2,030,722,906.33
2023 100%
2,095,087,084.22
2024 100%
2,161,491,606.55
2025 100%
2,230,001,152.24
2026 100%
2,300,682,450.52
2027 100%
2,373,604,345.96
2028 100%
2,448,837,865.49
2029 100%
2,526,456,287.59
2030 100%
2,606,535,213.65
2031 100%
2,689,152,641.70
2032 100%
2,774,389,042.19
2033 100%
2,862,327,436.59
2034 100%
2,953,053,478.10
2035 100%
3,046,655,535.11
2036 100%
3,143,224,777.33
2037 100%
3,242,855,264.53
2038 100%
3,345,644,038.18
2039 100%
3,451,691,215.95
2040 100%
3,561,100,089.25
Consumables
The catalyst needed for the production of MIBK is Palladium catalyst which
will be supplied by Yurui(Shanghai) Chemical Co., Ltd, Ruiyuan Group. The needed
Table 7
Cost of Catalyst per year
Year Turndown MTPY Price per MT Cost (PhP)
Capacity
2021 50
3.069 52,000.00 159,588.00
2022 100
3.069 53,560.00 164,375.64
2023 100
3.069 55,166.80 169,306.91
2024 100
3.069 56,821.80 174,386.12
2025 100
3.069 58,526.46 179,617.70
2026 100
3.069 60,282.25 185,006.23
2027 100
3.069 62,090.72 190,556.42
2028 100
3.069 63,953.44 196,273.11
2029 100
3.069 65,872.04 202,161.30
2030 100
3.069 67,848.21 208,226.14
2031 100
3.069 69,883.65 214,472.93
2032 100
3.069 71,980.16 220,907.11
2033 100
3.069 74,139.57 227,534.33
2034 100
3.069 76,363.75 234,360.36
2035 100
3.069 78,654.67 241,391.17
2036 100
3.069 81,014.31 248,632.90
2037 100
3.069 83,444.73 256,091.89
2038 100
3.069 85,948.08 263,774.65
2039 100
3.069 88,526.52 271,687.89
2040 100
3.069 91,182.31 279,838.52
Table 7
Annual Transportation Cost
Target Trucks Price of Distance Fuel used Weekly Annual
Market used per fuel per per Km Cost Transportation
week L
Manila 14 44.98 107.5 0.3 20,308.00 967,070
Table 7
Annual Shipping Fee
Source Destination Shipping Fee (PhP) Annual Shipping Fee
(PhP)
The Salary of the employees of the MIKCo. manufacturing plant is based from the average
monthly salary of employees in the Philippines. This was based from the Payscale Human Capital
Philippines. The Withholding tax was based on the TRAIN Tax law implemented on the year 2018.
Benefits were based on the common benefits given by the companies which includes the PAGIBIG,
Health Insurance, Performance Bonus, Transportation Benefits etc. The 13-month pay is a required
Table 7
Employee Salaries
Employee Salary in Pesos
Position Basic Salary Benefits 13 Month Total Monthly (PhP)
Yearly (PhP) (PhP) (PhP)
CEO
6,040,236.00 206,936.00 503,353.00 6,750,525.00
Plant Director
4,266,180.00 101,949.00 355,515.00 4,723,644.00
Production
Manager 634,848.00 8,510.00 52,904.00 696,262.00
Production
Assistant 180,000.00 417.00 15,000.00 195,417.00
Quality Assurance
Manager 613,320.00 10,027.00 51,110.00 674,457.00
Quality Assurance
Analyst 248,268.00 2,546.00 20,689.00 271,503.00
Maintenance
Supervisor 386,076.00 8,333.00 32,173.00 426,582.00
Maintenance
Personnel 167,436.00 6,264.00 13,953.00 187,653.00
Research and
Development
Manager 914,748.00 25,760.00 76,229.00 1,016,737.00
Research and
Development
Analyst 224,400.00 4,542.00 18,700.00 247,642.00
Human resource
526,428.00 8,281.00 43,869.00 578,578.00
Safety Officer
303,792.00 6,383.00 25,313.00 335,488.00
Security
181,200.00 1,949.00 15,100.00 198,249.00
Medical
596,784.00 20,000.00 49,732.00 666,516.00
Sales and
Marketing
Manager 669,492.00 17,173.00 55,791.00 742,456.00
Sales
Representative 187,644.00 60,000.00 15,637.00 263,281.00
Logistics
880,836.00 14,795.00 73,403.00 969,034.00
Corporate
accounts Manager 491,496.00 11,923.00 40,958.00 544,377.00
Since, the manufacturing plant will be operating 24 hours a day, there will be 3 shifts for
the production team and 1 shift for the administration. In Table 7.18, shows the total number of
Table 7
Total Number of Employees
No. of Employees per Shift Total No. of Employees
CEO
1 1
Plant Director
4 4
Production Manager
1 4
Production Assistant
25 100
Quality Assurance
Manager
1 4
Quality Assurance
Analyst
3 12
Maintenance Supervisor
1 4
Maintenance Personnel
8 32
Research and
Development Manager
1 1
Research and
Development Analyst
3 3
Human resource
3 3
Safety Officer
1 1
Security
5 20
Medical
2 8
Sales and Marketing
Manager
1 1
Sales Representative
3 3
Logistics
1 1
Corporate accounts
Manager
1 1
TOTAL 65
203
Table 7 Shows the annual net labor cost of the employees. The employees will be given a
2021
77,812,640.00
2022
79,368,892.80
2023
80,956,270.66
2024
82,575,396.07
2025
84,226,903.99
2026
85,911,442.07
2027
87,629,670.91
2028
89,382,264.33
2029
91,169,909.62
2030
92,993,307.81
2031
94,853,173.97
2032
96,750,237.44
2033
98,685,242.19
2034
100,658,947.04
2035
102,672,125.98
2036
104,725,568.50
2037
106,820,079.87
2038
108,956,481.46
2039
111,135,611.09
2040
113,358,323.32
Land Cost
The manufacturing plant will be located in Hermosa Ecozone Industrial Park (HEIP) in the
province of Bataan. The land cost in HEIP is PHP 4,000 per sq. m. Since the manufacturing plant
Table 7
Total Land Cost
Year Land Area Land Cost Per Year
2021 90000
18,000,000
2022 90000
18,000,000
2023 90000
18,000,000
2024 90000
18,000,000
2025 90000
18,000,000
2026 90000
18,000,000
2027 90000
18,000,000
2028 90000
18,000,000
2029 90000
18,000,000
2030 90000
18,000,000
2031 90000
18,000,000
2032 90000
18,000,000
2033 90000
18,000,000
2034 90000
18,000,000
2035 90000
18,000,000
2036 90000
18,000,000
2037 90000
18,000,000
2038 90000
18,000,000
2039 90000
18,000,000
2040 90000
18,000,000
Total
360,000,000.00
Depreciation Cost
The depreciation cost will be calculated using the straight-line method and the
declining balance method. The end life of 20 years will be assumed to have a zero-market
value.
Assumptions:
Table 7
Depreciation in 20 Years
Declining
The Fixed Capital Cost will be the sum of the Depreciation Cost and the Land Cost.
Table 7
Annual Fixed Cost
Year Land Cost Depreciation Cost Fixed Cost
Quality Control and Laboratory Cost = 20% of Operating Labor (Silla, 2003)
Every industry should establish the following government permits and licenses, that should
be paid and accomplish before the business operates. Table --. Summarizes all the required permits
and licenses.
Table 7
Permits and Licenses
Permits and Licenses Cost (PHP)
Business Permit 0
Location Clearance 6,000.00
Fire Permit 0
(PhilHealth)
Reservation
TIN
(PhilHealth)
Cost (PHP)
Permits and licenses
Permits for starting a business 93,385
permits
Total 1,652,886
Annual Revenue
The Revenue of the MIKCo. manufacturing plant will be coming from the two products:
Table 7
Revenue Per Year
Products Mass of Product per Price of Product per Revenue per year
year (MTPY) MT
2021 50
15,290.00 111,280.00 1,701,693,760.00
2022 100
30,584.00 114,618.40 3,505,489,145.60
2023 100
30,584.00 118,056.95 3,610,653,819.97
2024 100
30,584.00 121,598.66 3,718,973,434.57
2025 100
30,584.00 125,246.62 3,830,542,637.60
2026 100
30,584.00 129,004.02 3,945,458,916.73
2027 100
30,584.00 132,874.14 4,063,822,684.23
2028 100
30,584.00 136,860.36 4,185,737,364.76
2029 100
30,584.00 140,966.17 4,311,309,485.70
2030 100
30,584.00 145,195.16 4,440,648,770.28
2031 100
30,584.00 149,551.01 4,573,868,233.38
2032 100
30,584.00 154,037.55 4,711,084,280.38
2033 100
30,584.00 158,658.67 4,852,416,808.80
2034 100
30,584.00 163,418.43 4,997,989,313.06
2035 100
30,584.00 168,320.98 5,147,928,992.45
2036 100
30,584.00 173,370.61 5,302,366,862.23
2037 100
30,584.00 178,571.73 5,461,437,868.09
2038 100
30,584.00 183,928.88 5,625,281,004.14
2039 100
30,584.00 189,446.75 5,794,039,434.26
2040 100
30,584.00 195,130.15 5,967,860,617.29
Table 7
Revenue of DIBK with Inflation
Year Turndown Capacity MTPY Price per MT Cost (PhP)
2021 50
3,891.30 151,320.00 2,064,986,186.99
2022 100
7,782.40 155,859.60 2,064,986,186.99
2023 100
7,782.40 160,535.39 2,064,986,186.99
2024 100
7,782.40 165,351.45 2,064,986,186.99
2025 100
7,782.40 170,311.99 2,064,986,186.99
2026 100
7,782.40 175,421.35 2,064,986,186.99
2027 100
7,782.40 180,683.99 2,064,986,186.99
2028 100
7,782.40 186,104.51 2,064,986,186.99
2029 100
7,782.40 191,687.65 2,064,986,186.99
2030 100
7,782.40 197,438.28 2,064,986,186.99
2031 100
7,782.40 203,361.43 2,064,986,186.99
2032 100
7,782.40 209,462.27 2,064,986,186.99
2033 100
7,782.40 215,746.14 2,064,986,186.99
2034 100
7,782.40 222,218.52 2,064,986,186.99
2035 100
7,782.40 228,885.08 2,064,986,186.99
2036 100
7,782.40 235,751.63 2,064,986,186.99
2037 100
7,782.40 242,824.18 2,064,986,186.99
2038 100
7,782.40 250,108.90 2,064,986,186.99
2039 100
7,782.40 257,612.17 2,064,986,186.99
2040 100
7,782.40 265,340.54 2,064,986,186.99
Interest
The Loan will be coming from the Bank of Commerce. According to Engr. Conrad
Monterola the manufacturing plant will be borrowing 50 percent of the total capital. The total
capital includes the ISBL, OSBL, Engineering Cost, Contingency Charges, Working Capital, Water
Initial Investment, and Start-up Cost. The Interest of the Bank of Commerce is 7% and will be paid
within 10 years.
Table.
Loan Amount in Million
Total Capital PhP 4,841,529,284.86
Annuity Calculation
𝑖(1 + 𝑖)𝑛
𝐴=𝑃( )
(1 + 𝑖)𝑛 − 1
0.07(1 + 0.07)10
𝐴 = 2,420,764,642.43 ( )
(1 + 0.07)10 − 1
𝐴 = 𝑃ℎ𝑃 344,662,424.5
Cash Flow Analysis Summary: