Escolar Documentos
Profissional Documentos
Cultura Documentos
INTRODUCTION
Two-phase flow piping which collects the fluid from several wellhead and
sends them to the separator;
The separator vessel;
The steam pipelines which take the steam from the separator to the power
plant;
The brine pipelines which take the separated brine from the vessel to a well
pad where the fluid is re- injected into several wells;
Miscellaneous cross-country piping includes the instrumental air lines, the
water- supply line and also the condensate line.
Two aspects of the design process of geothermal piping systems that must be
considered are the process of preparing the design and the deliverables. The scope
of this paper will be in the piping for the steam field and the process of preparing
the design divided in the following main categories: design criteria, produce
process flow diagram, define control philosophy, separator location, route
selection, dimension design, pressure design, load design, design codes and pipe
stress analysis.
The function of the piping engineering is to apply knowledge of fluid flow, stress
analysis, material properties, engineering judgement and convert the process
engineer’s specification into drawings and data from which materials can be
purchased, fabricated and assembled into piping systems which fulfil the
requirement of the process. this must be fulfilled at the minimum design cost
without sacrificing the quality and desired function, the piping system will operate
without physical failure or excessive pressure losses for the entire span of designed
plant life.
PLANT LAYOUT
A Process plant, which consist of the various different sections such as raw
material storage, intermediate and finished product storage, process units, control
rooms, Flare system, Raw material loading and uploading facilities, utilities
generation and distribution etc. should be arranged so as to follow the general route
of the raw material to process, to Intermediate/Finished product storage, to
dispatch. Generally block concept is prevalent for the plant layout where in the
entire plot area is divided into blocks. The size of the blocks depends upon the
facilities to be accommodated.
Process unit block shall be centrally located with straight approach from the
main gate.
The blocks shall be so arranged considering the prevalent wind direction that
flammable gases should not be carried by the wind on to source of ignition.
Utility blocks shall be located adjacent to unit blocks.
Flare shall be located upwind of process units so that the inflammable gas
from plant is not carried towards flare.
PIPING DESIGN
Design
Pipe routes
Aerial photographs and contour plan of the area are sufficient information to
identify a preliminary route for the pipes and suitable locations of the plant
components. The preliminary route is then inspected on site to check land owner,
houses, swamps, soil condition for foundations, anchors and expansion loops, hot
spots, slip risk, road crossing, watercourses, change in elevation, access. Using the
preliminary pipe route, an estimate of equivalent line length can be made. The
design flow and enthalpy are determined from the well data, and with this
information, the optimum diameter for the pipes can be known. Figure 3 shows a
contour plan of Berlín geothermal field. Stress analysis should be carried out for
the following load cases for compliance with the code requirement and support
load calculation. B31.1 requires that a pipeline shall be analyzed between anchors
for the effects of:
Expansion loops are the most commonly used in cross-country pipelines to handle
thermal expansion. On standard runs, L bends, Z bends, conventional 90 degree
elbow and V bends are the mostly used pipe configuration for the design. Z bends
can be very stable on downhill runs. Horizontal loops are very effective in
congested areas. Custom design based on following the natural configuration of the
terrain can be very effective on cross- country designs. Anchors shall be
strategically located to reduce the magnitude of the resultant load. This reduces the
size of the foundation. Typically, a cross- country pipe run without compensators
will require an anchor every 150 to 200 meters. The types of supports used are Y
stop, Guide, Line Stop, Constant Weight Support, Shock absorbers.
Reducing the number of pipe supports by spacing them as far apart as the
maximum pipe span is allowed. There should be a pipe support located near every
bend, as it reduces eccentric loading on the pipe and minimizes vertical vibration at
bends, especially in two- phase lines. Pipes are run close to the ground to reduce
overturning moment effect on the pipe support and anchors, which then reduce the
foundation size and hence the cost
Air piping shall have self draining provision at all low points for the collection of
condensate. Air traps shall be provided with isolation valves, balance lines and
drains to local collection points. Instrument air headers and manifolds shall not be
dead ended but supplied with blind flanges for cleaning and maintenance. All
branches and take-offs shall be from the top of the headers.
Steam piping shall be run to prevent pockets. Condensate shall be collected at low
points by using a standard steam trapping system. Drain points shall be from the
bottom of the header and steam take-offs from the top.
Utility stations
Utility stations shall be provided as required for air, water, steam/hot water and
nitrogen. Each station shall be numbered and located in the general working areas
at deck level. Freshwater, seawater and plant air systems shall be equipped with
hosereels. Nitrogen stations shall not be located inside enclosed areas. Nitrogen
hoses shall be installed if required (for reference, see L-003). Different types of
couplings shall be used for air and nitrogen.
Piping to pressure relief valve inlet shall be as short as possible. When relief valves
discharge to atmosphere, the elevation at the top of the discharge line shall
typically be 3000 mm above all adjacent equipment. This is to keep adjacent
equipment outside plume area. Discharge tail pipes shall have a drain hole at the
low point of the line. Relief valves discharging to a flare system shall be installed
so as to prevent liquid being trapped on the outlet side of the valve. All relief lines
and headers shall be designed to eliminate pockets, but if a relief valve must be
located at a lower elevation than the header, an automatically operated drain valve
shall be installed at the valve outlet and piped to a collecting vessel or closed drain.
Relief valve headers shall slope towards the knock-out drum, taking into account
anticipated deck deflection and platform tilt during operation. Pockets are to be
avoided, but where a pocket is unavoidable, some approved means of continuous
draining for the header shall be incorporated. Unless specifically noted on the
P&ID all branch connections on relief and blow down systems shall be at 90° to
the pipe run. Should there be a special requirement for a particular branch to enter
a header 45°, this shall be highlighted by process engineers on the P&ID.
METHODOLOGY
The piping layout) is modeled using CAESAR-II, the end of the pipe are rigidly
fixed using anchor and the input parameters listed in table are given, then the
analysis of layout is carried out with providing necessary supports, Then the input
temperature and pressure values are varied and their respective.
PARAMETERS VALUE
Material SS 316
Corrosion 0.1
LITERATURE REVIEW
Chapter-2
LITERATURE REVIEW
Mat´as Alvarado has given the basic ideas about the piping analysis software
CAESAR II. PSA is a complex engineering discipline which covers the design,
analysis and identification of piping problems by ensuring that weight, thermal,
and pressure stresses are at acceptable levels specified in engineering design
standards, problems such as thermal; deadweight analysis seismic analysis (static
or dynamic); wind load analysis; transient analysis; dynamic analysis about
exchanging data from CAESAR II.
SELECTION OF MATERIAL
STAINLESS STEEL
Introduction
Stainless steel belongs to the high alloy steel group. Chromium (Cr) is the element
the makes stainless steel stainless or corrosion resistant. the chromium combines
with oxygen and creates an invisible though impregnable Chromium oxide on the
surface. I t must contain at least 11.5% chromium, that is the content at which an
effective layer is formed that seals the surface against any further atmospheric
corrosion. Nickel (Ni) in excess of about 6% increases corrosion resistance slightly
and greatly improves mechanical properties. Small amounts of Molybdenum (Mo)
increase resistance to pitting type corrosion and general resistance to certain
corrosive media. Stainless steel alloy with molybdenum is referred to as acid
resistant. Molybdenum also improves high temperature strength.
Out of the wide range of standard wrought austenitic stainless steels several have
been used extensively for equipment operating at sub-zero temperatures which
may be as low as the boiling point of liquid helium (-269°C). As the temperature is
lowered the strength of these steels increases rapidly, whilst ductility and impact
toughness are maintained at a high level as temperatures approach absolute zero.
The steels are well suited for equipment handling liquid gases and for other liquids
where corrosion resistance is also required, e.g., the low-temperature processing of
foods and other products where product contamination must be held to a minimum.
The most widely used wrought stain-less steels for cryogenic service are the AISI
Types 304 and 304L, while Types 316, 316L, 321 and 347 are also used,
dependent upon the availability in the particular form or size required. For
temperatures below about -200°C the non-stabilized grades are generally preferred.
Data for each of these types are included in the present publication together with
summaries of the relevant European national specifications and steel designations.
Data for the corresponding casting grades are also given. Particular care should be
exercised in selecting appropriate grades of cast stainless steel for cryogenic.
STAINLESS STEEL SS316
Chemical composition:
ELEMENTS % LEVEL
C 0.08
Mn 2.0
Si 0.75
P 0.045
S 0.03
Cr 16
Mo 2-3
Ni 10-14
N 0.10
POWER PIPING
This Code prescribes requirements for the design, materials, fabrication, erection,
test, inspection, operation, and maintenance of piping systems. Piping as used in
this Code includes pipe, flanges, bolting, gaskets, valves, pressure-relieving valves/
devices, fittings, and the pressure containing portions of other piping components,
whether manufactured in accordance with Standards listed in specially designed. It
also includes hangers and supports and other equipment items necessary to prevent
overstressing the pressure containing components.
Background
This chapter is based on the 2007 edition of ASME B31.1, Power Piping Code. As
changes, some very significant, are made to the Code every year, the reader should
refer to the Code for any specific requirements. This chapter should be considered
to provide background information and not specific, current Code rules.
References herein to Sections I, II, III, V, VIII, and IX are references to Sections of
the ASME Boiler and Pressure Vessel Code. References to a Para. Are generally to
a paragraph in ASME B31.1 or to a paragraph in this book. The equations that are
numbered in this chapter use the same numbers as are used in ASME B31.1.
Equations that are not numbered are either not in ASME B31.1 or are not
numbered therein. Published references are listed at the end of each major section
of this chapter. Reference documents other than codes and standards are numbered.
Codes and standards, such as those provided by the ASME, API, AWWA, and
ASTM, are simply listed at the end of each reference section
History of B31.1
In 1926, the American Standards Institute initiated Project B31 to develop a piping
Code. The ASME was the sole administrative sponsor. The first publication of this
document, American Tentative Standard Code for Pressure Piping, occurred in
1935. From 1942 through 1955, the Code was published as the American Standard
Code for Pressure Piping, ASA B31.1. It consisted of separate sections for
different industries. These sections were split off, starting in 1955, with the Gas
Transmission and Distribution Piping Systems, ASA B31.8. ASA B31.3,
Petroleum Refinery Piping Code, was first published in 1959. A number of
separate documents have been prepared, most of which have been published. With
respect to the initials that appear in front of B31.1, these have been ASA, ANSI,
and ASME. It is currently correct to refer to the Code as ASME B31.1. The initial
designation ASA referred to the American Standards Association. This became the
United States of America Standards Institute and then the American National
Standards Institute (ANSI) between 1967 and 1969; thus, ASA was changed to
ANSI. In 1978, the Standards Committee was reorganized as a committee
operating under ASME procedures with ANSI accreditation. Therefore, the initials
ASME now appear in front of B31.1. These changes in acronyms have not changed
the committee structure or the Code itself.
Scope of B31.1
The ASME B31.1 Code was written with power piping in mind. It was intended to
cover the fuel gas and oil systems in the plant (downstream of the meters), central
and district heating systems, in addition to the water and steam systems in power
plants. The 1998 edition specifically listed systems that are included and those that
are excluded. However, the ASME B31 Standards Committee has directed that the
B31 Codes be revised to permit the Owner to select the piping code most
appropriate to their piping installation; this change is incorporated in the 1999
addenda. The Introduction to ASME B31.1 (as well as the Introductions to the
other B31 Codes) states the following: It is the Owner’s responsibility to select the
Code Section which most nearly applies to a proposed piping installation.
Primary Loads
These are typically steady or sustained types of loads such as internal fluid
pressure, external pressure, gravitational forces acting on the pipe such as weight
of pipe and fluid, forces due to relief or blow down pressure waves generated due
to water hammer effects. The last two loads are not necessarily sustained loads. All
these loads occur because of forces created and acting on the pipe. In fact, primary
loads have their origin in some force acting on the pipe causing tension,
compression, torsion etc. leading to normal and shear stresses.
Secondary Loads
Just as the primary loads have their origin in some forces; secondary loads are
caused by displacement of some kind. For example, the pipe connected to a storage
tank may be under load, if the tank nozzle to which it is connected moves down
due to tank settlement. Similarly, pipe connected to a vessel is pulled upwards
because the vessel nozzle moves up due to vessel expansion. Also, a pipe may
vibrate due to vibrations in the rotating equipment it is attached to. A pipe may
experience expansion or contraction once it is subjected to temperatures higher or
lower respectively as compared to temperature at which it was assembled. The
secondary loads are often cyclic, but not always. For example load due to tank
settlement is not cyclic. The load due to vessel nozzle movement during operation
Internal/External Pressure
A pipe used for transporting fluid would be under internal pressure load. A pipe
such as a jacketed pipe core or tubes in a Shell & Tube exchanger etc. may be
under net external pressure. Internal or external pressure induces stresses in the
axial as well as circumferential (Hoop’ s) directions. The pressure also induces
stresses in the radial direction.
Bending Load
A pipe can face sustained loads causing bending. The bending moment can be
related to normal and shear stresses. Pipe bending is caused mainly due to two
reasons: Uniform weight load and concentrated weight load. A pipe span supported
at two ends
PIPING SUPPORT
People around the world use pipe supports and restraints, in fact they spend
somewhere in the region of £250million on ‘engineered supports’ each year. When
people ask me what I do for a living, the usual response to my answer is ‘Oh, the
things you see in hospitals, colleges and large buildings.’ The next time you go to a
shopping mall or into a department store just peer through the suspended ceiling
and you will understand their answer. When I then explain that we support pipes
that operate at temperatures as high as 850o C and diameters large enough to walk
through they become very interested. Add a little spice by telling them that our
main market places are Asia and the Middle East and suddenly they want to know
much more about the subject. However, setting aside the images that these remarks
conjure up there are very real and practical reasons for companies and corporations
to spend such large sums of money on what for many appear to be just rods and
clamps. The majority of pipes that we support and restrain are actually long thin
pressure vessels operating at extreme pressures and temperatures.
PIPE HANGERS
To provide a general knowledge of the Pipe Supports Group, the market place, the
application and need for the product and the types of product and service offered.
Selection and Specification of Spring Hangers
The code ASME B 31.1 specifies under clause 321.1.1 the ay out and design of
piping and its supporting elements shall be directed toward preventing the
following:
Support locations are dependent on many considerations, such as pipe size, piping
configuration, the location of heavy Valves and fittings, and the structure that is
available for support. Following rules of thumb will help when doing the flexibility
analysis and operation and maintenance:
As much as possible, attach supports to straight pipe rather than elbows, other
fittings, Valves, flanges or instruments, but provide supports near instruments,
and other devices that are likely to be removed for maintenance.
Provide space for adding loops to piping near load sensitive equipment, e.g. in
pump suction lines.
Consider the need to add friction reducing slides between the piping and
support steel.
Support piping such that spools to be removed for equipment maintenace can
be removed without adding temporary supports.
Minimize the use of spring hangers
DETERMINATION OF LOADS AND MOVEMENTS
The anticipated movement at each support point dictates the basic type of support
required. Each type of support selected must be capable of accommodating
movements. It is a good practice to select first the most simple or basic rigid
support type and to add to the complexity only as conditions warrant. No
advantage will be realized in upgrading a support when a simpler, more
economical type can be shown to satisfy all the design requirements.
ANCHORS
A rigid support that restricts movement in all three orthogonal directions and all
three rotational directions. This usually is a welded stanchion that is welded or
bolted to steel or concrete. Two types of anchors exist: fixed and directional.
Fixed anchors are used in locations where all movement of a line must be
prevented. In piping terms this is called a fixed point. The most common way to
anchor a pipe is to weld the pipe directly to a support or structural member. If the
pipe to be anchored is insulated, first a pipe shoe is welded to the pipe and then the
shoe is welded to the steel structure. Directional anchors are used to force
movement to occur in one direction while preventing it from occuring in the
opposite direction. Directional anchors are used to direct a pipe's movement away
from buildings, structures, equipment etc. A vertical pipe support that incorporates
a rod. It may be a rigid, variable spring or constant support hanger. Hanger is a
term that often means quite different things to different people. Rod hangers or
pipe hangers attaches to the pipe by a U bolt, a clevis, a pipe clamp etc. to
structural steel above. The rod hanger provides support in the vertical direction and
allows limited motion in the horizontal direction. Adjustment in the vertical
direction can be accomplished by threads or a turnbuckle. See hanger rod image on
the right of this page.
GUIDES
When total restriction of pipe movement is not required, pipe guides are used. Pipe
guides confine movement along the pipe's lineal axis. In piping terms this is called
a sliding point. They are used primarily to maintain proper line spacing in a pipe
rack and they prevent lateral or side way movement. Unlike the pipe anchor which
is welded to the pipe and steel structure, the guide allows pipe to slide lengthwise
between two angle shapes. When the pipe is supported on shoes, the angle shapes
are positioned on either side of the shoe. For an image of guides see directional
anchor above.
HANGER
A helical coil that supports dead weight load. The support load changes as the
spring moves through its range at a specified spring rate. This support can be a
hanger above the pipe, or a floor support below the pipe. To prevent constraints in
the system, thermal expansion in the piping and other piping components must not
be hindered. The piping must therefore be supported in a correspondingly elastic
manner. To compensate for slight vertical displacements in the piping, spring
components are used as supports. The functioning of these components is based on
preset helical coil springs which exert a variable supporting load over the whole
range of movement corresponding to the given spring characteristics. Load
variations resulting from this are limited through corresponding specifications
based on stress calculations for the piping - this depends on the sensitivity of the
system.
DESIGN AND ANALYSIS
DESIGN AND ANALYSIS
APPLICATION
Steam power plant used in this project
Analysis the piping stress through the variation of the pipe material with respect
to pressure and temperature was optimized. As per the piping layout taken from the
ASME journal Chapter stress analysis of piping systems, number of hanger and
guide support used to reduced load. The results are compared for different loading
conditions and a suitable material is selected for the research of stainless steel
REFERENCES
C. Basavaraju, Senior Engineering Specialist, Bechtel Power Corporation.
Page (B.107–B.214).
Knowledge- Based Systems/ Knowl Inf Syst (2007) 12(2): Page (255–278).
between pipe supports using maximum bending stress theory, recent trends