EXECUTION TECHNOLOGY REPORT

EARTHWORKS

Report created by:

Žarko Janjić, Master of Science in Civil Engineering.

Licence no: 310 М961 14


CONTENTS

CONTENTS ................................................................................................................ Error! Bookmark not defined.


GENERAL ................................................................................................................... Error! Bookmark not defined.
Licence and certificate.......................................................................................... Error! Bookmark not defined.
1 GENERAL INFORMATION ABOUT THE FACILITY ............................................................................................... 8
2 CATEGORIZATION OF EARTHWORKS................................................................................................................ 8
3 REMOVAL OF HUMUS AND POOR QUALITY MATERIAL ................................................................................... 8
4 EXCAVATION OF SOIL ....................................................................................................................................... 9
5 STABILIZATION OF ROAD BED BOTTOM ......................................................................................................... 11
6 BACKFILLING ................................................................................................................................................... 11
7 SUBGRADE SURVEY ........................................................................................................................................ 13
8 SURVEY OF COMPRESSION BELOW THE FOUNDATION ................................................................................. 13
9 DENSITY OF GRAVEL LAYERS ......................................................................................................................... 13
10 HUMUS LAYING ........................................................................................................................................... 14
11 TRANSPORT OF MATERIAL .......................................................................................................................... 14
GENERAL

Licence and certificate

Translation:
Chamber of Engineers of Serbia

LICENCE

for responsible designer

Pursuant to Law on (design) planning and construction and the Articles of Association of the Chamber
of Engineers of Serbia

it is hereby established that

Žarko M. Janjić

Master of civil engineering

LIB 05078064304

is a responsible designer

for civil, building and other construction works

Number of licence: 310 M961 14

In Belgrade, January 23, 2014 President of the Chamber

Milovan Glavonjić,
Bachelor of civil engineering
No: 12-02/27128
Belgrade, 04.08.2017.

Pursuant to Article 75 of the Articles of Association of the Chamber of Engineers of Serbia (“Official
Gazette of RS” no. 88/05 and 16/09), at the personal request of a member of the Chamber, the
Chamber of Engineers of Serbia is issuing this

CERTIFICATE

which certifies that Žarko M. Janjić, master of civil engineering


licence number 310 M961 15

for responsible designer for civil, building and other construction works
is a member of the Chamber of Engineers of Serbia on the day of issuing of this certificate, that he
has settled his obligation to pay a membership fee to the Chamber in the period before 15.08.2018,
as well as that there was no decision by the Court of Honour to rescind his licence

President of the Chamber of Engineers of Serbia

Prof. Dr Milisav Damnjanović, Doctor of science of architecture


1 GENERAL INFORMATION ABOUT THE FACILITY

The location of the wind farm complex (power transformer station TS 33/220kV and substation 220
kV) is located on parcel no. 4949, 4950, Cadastre Municipality Debeljača. The total estimated area of
the complex is 2.14 ha.

The complex of the power transformer station is connected to the local road in three locations, two
connections belong to cadastre parcel 4949 (width of connecting streets is 6.00 m each) while one of
them is located at parcel 4950 (width of the connecting street is also 6.00 m).

The complex also contains two parking areas with 6 parking spaces (parcel 4949) and 4 parking
spaces (parcel 4950).

2 CATEGORIZATION OF EARTHWORKS

All earthworks which will be performed during the construction of the Kovačica Wind Farm can be
categorized in the following manner:

 Removal of humus and poor quality material


 Excavation of soil:
o machine
o manual
 Stabilization of road bed bottom
 Backfilling:
o soil
o sand
o gravel
 Humus laying
 Transport of earthen material and loose material
o internal
o external

3 REMOVAL OF HUMUS AND POOR QUALITY MATERIAL

The work includes surface excavation of humus material in bulk excavation, according to project
details, with transport or pushing of materials using machines into a landfill on the side, in space
which is owned by the investor, for later construction. The average width of the layer which shall be
removed is 30cm. All works must be performed in accordance with the project, i.e. SRPS.U.Е1.010.

The surface excavation should be performed everywhere where it is necessary in order to prepare
the road bed – foundation soil and subgrade. All excavated material is to be deposited outside of the
surface of construction works, so that it can later be used and accessed without disturbance.

The removal of humus is performed with a treaded bulldozer (of the type) “TG 140 F/P 304 A”, with
blade capacity of 2.3-3.6 m3, and the ability to push soil up to 20m. From there, the humus will be
loaded onto trucks with a “JSV” Excavator, blade capacity 1.8 m3, and then transported to the local
landfill within the investor’s parcel to be disposed.

Below is a table displaying the position where humus removal will be performed, along with the
quantity.

Position quantity
Power control building 144.0 m3
Well cabin 3.0 m3
Relay cabin 18 m3
Access road, transport road and plateau 5,444.8 m3
Management building 110.0 m3
table 1

4 EXCAVATION OF SOIL

The works include bulk excavation of all types of earthen materials defined by the project, as well as
transportation, i.e. pushing of excavated material into embankments, landfills, or to general use
landfills, according to the purpose for which the material will be used during the performance of
works.

All excavation should be performed according to profile, described levels, inclination according to the
project, having in mind all necessary characteristics of the specific uses of excavated material, in
accordance with these technical specification and SRSPS.U.Е1.010.

During the performance of excavation, protection measures for full occupational safety shall be
implemented, as well as all necessary security for existing buildings and communications.
The excavation performance schedule shall be organized so that no “gaps” will form, in which water
would accumulate in the event of rain.

Machine excavation of soil of II and III category is performed with the combined machine – Excavator
“JSV” with blade capacity of 1.8 м3. Soil is deposited to the side, or is transported by trucks to a
temporary earthen material landfill within the investor’s parcel, a location where it will not obstruct
construction, or is transported to the location ordered by Supervision.

The maximum depth of the excavation is 2.9 m, and the level of groundwater is at more than 7.0m
below ground level.

The excavation banks are secured through the construction of bank slopes and, as required,
additional support, horizontal and vertical, and beams of wood and metal.

Below is a table displaying the excavation positions and their quantities.

Position quantity
Cable canals 393.0 м3
Fence and gate foundations 6.0 м3
Lightning rods and candelabra foundation 5.2 м3
Diesel generator plate 5,444.79 м3
Firewall foundation 70.0 м3
Drainage well 20.0 м3
Self-supported cable line foundation 21.47 м3
Power control building 450.0 м3
Well cabin 10.0 м3
Relay cabin 15.0 м3
AB plate of the diesel generator 5.2 м3
Foundations for Portals P1 and P2 393.3 м3
Substation foundation 476.0 м3
Lightning rod foundation 24.5 м3
Septic tank 60.0 м3
Drinking water reservoir 250.0 м3
Management building P 410.0м3
Table 2

Machine excavation of the canal for sewer and water pipes, for laying cables, is performed with the
combined machine “KRAMER 516” which possess blades of different dimensions and capacities.
Usable material from the excavation will be deposited in the immediate range of the excavation, for
the purposes of reuse during filling.

The table displays the positions in which the row for setting sewer and water pipes, and for laying
cables will be set, as well as their quantities.

Position Quantity

Oil sewer 58.0 м3


Water network substation 220 80 м'
kV
Hydrant network 210.0 м3
Grounding 1340.0 м3
External lighting 400.0 м3
Table 3

The bulk excavation will be performed on positions displayed in Table 4. The excavation banks are
secured through the construction of bank slopes and, as required, additional support, horizontal and
vertical, and beams of wood and metal.

 Maximum permitted slope inclination (surface of the slope) for digging of embankments with
an excavator without support for the banks, cannot exceed the following inclination:

- well secured solid material


- slope - (slope surface) maximum 3:1 (horizontal distance of 1m, with 3m of vertical change )
- for loose – bulk material:
slope - (slope surface) maximum 1:1 (horizontal distance of 1m, with 1m of vertical change)
Maximum excavation depth is 5.1m, and the level of groundwater is more than 7m below ground
level.

Below is a table displaying positions where bulk excavation will be performed and its quantity

Position Quantity
Drainage well 20.0 м3
Foundations and bed of the 675.0 м3
transformer
Construction of the foundation pit 600 м2
Table 4

5 STABILIZATION OF ROAD BED BOTTOM

Before the start of the works, it is necessary to examine the road bed bottom, determine the
composition and density of it, and select one of the following road bet bottom processing methods:

- If the material fulfils set requirements, the road bed is processed mechanically.

The road bed material will first be excavated with a “New Holland” type grader, and after planning it
shall be compacted with a smooth roller of the type "HAM HD 90" or grid roller of the type "BOMAG"
.

-If the required consolidation of the road bed cannot be achieved due to great compressibility of
autochthon soil, the geo-mechanical improvement of the road bed up to the depth of 30cm will be
carried out by adding sand or gravel material, until compaction with grid rollers and vibro rollers
results in a load bearing capacity of Мс=15 MN/м2 (plate Ø30cm), expressed using the
compressibility modulus

The table below displays positions in which stabilization of the road bed bottom will be performed.

Position quantity
Lightning rod 41.0 м3
Transformer bed and foundation 432.0 м3
Firewall 30.0 м3
Plateau 18,149.0м2
table 5

6 BACKFILLING

These works include backfilling, spreading, coarse or fine planning, wetting and compressing material
using adequate mechanical means, - Bulldozer for spreading, grader for paving, grid for compression,
everything in accordance with the dimensions and levels from the project
The construction works for the earthen material embankment includes backfilling of soil from the
deposit, spreading, wetting or drying as necessary, smoothing , compressing according to regulation,
and inspection.

The construction of the backfill is performed in accordance with profiles, levels and inclinations of the
project. The embankment will be constructed in layers with width up to 30cm, with a slope for
drainage. The compression of the embankment will be performed with vibrating equipment or static
rollers, until achieving the required density levels.

For backfilling purposes, soil from the deposit will be used, as per the geo-mechanical report, or the
survey results submitted by an accredited laboratory.

Density control for the processed layers will be performed with a test circular plate with radius d=30
cm, for which the minimum values are:

- for embankments with height over 2m, for layers under 2m below the plane of the lower layer:

 for coherent soil, a compressibility modulus of МС= 35 МPа is required


 survey at 1000m2

Below is a table displaying positions in which backfilling with compression will be performed, as well
as their quantities.

Position Quantity
Transformer bed and foundation 90.0 м3
Firewall 42.0 м3
Grease trap, sewer and drainage well 378.0 м3
Self-supporting cable line beam 6.7 м3
Well cabin 7.0 м3
Relay cabin 7.0 м3
AB plate of the diesel generator 0.7 м3
Foundation for portals P1 and P2 83.0 м3
Foundation and support of substation 371.0 м3
Septic tank 50.0 м3
Hydrant network 166.0 м3
Drinking water reservoir 150.0 м3
Management building P 250.0 м3
Table 6

Backfilling of sand and gravel is performed with a combined machine "KRAMER 516" which can be
equipped with blades of different dimensions and capacities, below canalization and water pipes,
below the hydrant network, in order to construct a protective buffer layer and secure them against
falls.
7 SUBGRADE SURVEY

After the geo-mechanical report has been created for the deposit and which contains a Proctor
compaction test, it is not necessary to perform it again.

Quality control of materials for construction is performed according to regulation:

Sampling shall be performed at 1000-2000 m2


SRPS.U.B1.010 - Sampling
SRPS.U.B1.012 - Determining the moisture of soil
SRPS.U.B1.014 - Determining the specific weight of soil
SRPS.U.B1.016 -Determining the volume weight of soil
SRPS.U.B1.018 - Determining the granulation composition
SRPS.U.B1.020 - Determining consistency limits
SRPS.U.B1.024 - Inflammable and organic matter content
SRPS.U.B1.038 - Determining the optimal water content
Control of subgrade compression is performed with a testing circular plate with a radius of d=30 cm
at 500m2, with the minimum required value:
* compressibility modulus МS = 35 MPa.

8 SURVEY OF COMPRESSION BELOW THE FOUNDATION

The SURVEY OF COMPRESSION BELOW THE FOUNDATION will be performed with a test circular plate
with a radius of d =30 cm for slab on grade foundations, at 100 m2, for spot footing, each fifth, with
the minimum required value:
* compressibility modulus 20 MPa in accordance with SRPS.U.B1.046.

9 DENSITY OF GRAVEL LAYERS

The quality of the material itself will be certified by adequate certificates.

Control of density of subgrade shall be performed with a circular test plate with a radius of d=30 cm
at 500m2, with the minimum required values:

 for gravel 0-63, compressibility modulus 40 MPa in accordance with SRPS.U.B1.046.


 for gravel 0-31, compressibility modulus 50 MPa in accordance with SRPS.U.B1.046.
10 HUMUS LAYING

The works include humus laying on plain surfaces, slopes and embankments, with necessary grass
planting, in layers of 15-30cm. Humus laying shall be performed with humus which was previously
removed from the way and deposited into piles. If the humus at the landfill is dry, it should be spread
and wetted during filling. After spreading and smoothing the humus layer, it shall be lightly
compressed.

In the event that there is not enough humus on the location, it will be either transported from a
storage or from a location determined by the supervisory authority.

Below is a table displaying positions where humus laying will be performed as well as the quantities.

Position quantity
Plateau 13,970.0 м2
Horticulture 6,200.0 м3
Table 7

11 TRANSPORT OF MATERIAL

The entire transport of material (humus, soil categories II and III, gravel, sand) shall be performed
with Man 26-280 DFK, 3 - way, load capacity 15,700.00 kg and Mercedes Actros 26-36 K 6x4, 3 - way,
load capacity 14,200.00 kg.